Mid Cycle Assessment Letter
ML13246A162
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 09/03/2013
From: Bartley J
NRC/RGN-II/DRP/RPB1
To: Capps S
Duke Energy Corp
References
IR-13-006
Download: ML13246A162 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 3, 2013 Mr. Steven D. Capps Site Vice President Duke Energy Corporation McGuire Nuclear Station MG01VP/12700 Hagers Ferry Road Huntersville, NC 28078

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR MCGUIRE NUCLEAR STATION UNIT 1 AND UNIT 2 (NRC INSPECTION REPORT 05000369/2013006 AND 05000370/2013006)

Dear Mr. Capps:

On August 13, 2013, the NRC completed its mid-cycle performance review of McGuire Nuclear Station Unit 1 and Unit 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2012, through June 30, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at McGuire Unit 1 and Unit 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low safety significance (Green),

and all PIs indicated that your performance was within the nominal, expected range (Green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2014.

Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the ROP baseline inspections, we will also conduct reactor operator licensing examinations. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.

S. Capps 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 404-997-4607 with any questions you have regarding this letter.

Sincerely,

/RA/

Jonathan H. Bartley, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket No.: 50-369, 50-370 License No.: NPF-9, NPF-17

Enclosure:

McGuire Inspection/Activity Plan (09/01/2013 - 12/31/2014) cc: Distribution via Listserv

_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE CWR /RA/ JHB /RA/

NAME CRapp JBartley DATE 08/21/2013 08/29/2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO S. Capps 3 Letter to Steven D. Capps from Jonathan H. Bartley dated September 3, 2013

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR MCGUIRE NUCLEAR STATION UNIT 1 AND UNIT 2 (NRC INSPECTION REPORT 05000369/2013006 AND 05000370/2013006)

DISTRIBUTION:

C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMMcGuire Resource Institute of Nuclear Power Operations (INPO)

ROP Reports

Page 1 of 2 McGuire 09/03/2013 08:04:13 Inspection / Activity Plan Report 22 09/01/2013 - 12/31/2014 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site MODS - PLANT MODIFICATIONS INSPECTION 3 1, 2 10/14/2013 10/18/2013 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1, 2 10/28/2013 11/01/2013 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications OL EXAM - INITIAL EXAM PREP 4 1 11/04/2013 11/08/2013 V23402 MCGUIRE/DECEMBER 2013 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM WEEK 1 5 1 12/02/2013 12/06/2013 V23402 MCGUIRE/DECEMBER 2013 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM WEEK 2 4 1 12/09/2013 12/13/2013 V23402 MCGUIRE/DECEMBER 2013 INITIAL EXAM AT POWER FACILITIES ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 03/31/2014 04/04/2014 IP 7111108P Inservice Inspection Activities - PWR SGISI - UNIT 2 SG IN-SERVICE INSPECTION 1 2 04/07/2014 04/11/2014 IP 7111108P Inservice Inspection Activities - PWR PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 4 1, 2 06/09/2014 06/13/2014 IP 71152B Problem Identification and Resolution 1, 2 06/23/2014 06/27/2014 IP 71152B Problem Identification and Resolution OL EXAM - REQUAL INSP 1 1, 2 06/23/2014 06/27/2014 IP 7111111B Licensed Operator Requalification Program OL EXAM - INITIAL LICENSE EXAM PREP 3 1 07/14/2014 07/18/2014 V23428 MCGUIRE/AUGUST 2014 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL LICENSE EXAM WEEK 1 3 1 08/11/2014 08/15/2014 V23428 MCGUIRE/AUGUST 2014 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL LICENSE EXAM WEEK 2 3 1 08/18/2014 08/22/2014 V23428 MCGUIRE/AUGUST 2014 INITIAL EXAM AT POWER FACILITIES EP - EP PROGRAM INSPECTION 1 1, 2 09/22/2014 09/26/2014 IP 7111402 Alert and Notification System Testing 1, 2 09/22/2014 09/26/2014 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 09/22/2014 09/26/2014 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 09/22/2014 09/26/2014 IP 71151 Performance Indicator Verification RP - RP OCCUPATIONAL BASELINE 3 1, 2 09/22/2014 09/26/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/22/2014 09/26/2014 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 09/22/2014 09/26/2014 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 McGuire 09/03/2013 08:04:13 Inspection / Activity Plan Report 22 09/01/2013 - 12/31/2014 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site RP - RP OCCUPATIONAL BASELINE 3 1, 2 09/22/2014 09/26/2014 IP 71124.04 Occupational Dose Assessment 1, 2 09/22/2014 09/26/2014 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 09/22/2014 09/26/2014 IP 71151 Performance Indicator Verification ISI - UNIT 1 IN-SERVICE INSPECTION 1 1 09/29/2014 10/03/2014 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL BASELINE WEEK2 2 1, 2 10/06/2014 10/10/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/06/2014 10/10/2014 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 10/06/2014 10/10/2014 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/06/2014 10/10/2014 IP 71124.04 Occupational Dose Assessment 1, 2 10/06/2014 10/10/2014 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 10/06/2014 10/10/2014 IP 71151 Performance Indicator Verification SGISI - UNIT 1 SG IN-SERVICE INSPECTION 1 1 10/06/2014 10/10/2014 IP 7111108P Inservice Inspection Activities - PWR Comments:

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure