Other: GNRO-2013/00060, Entergys First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049), GNRO-2014/00011, Entergys Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses- with- Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), GNRO-2014/00060, Entergys Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, GNRO-2015/00004, Entergys Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mititgation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), ML14101A043, ML14101A087, ML14119A009, ML14260A130, ML14262A372, ML14262A397, ML14265A370, ML14265A384, ML14265A422, ML15085A227
|
MONTHYEARGNRO-2013/00060, Entergys First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2013-08-28028 August 2013 Entergys First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) Project stage: Other GNRO-2013/00012, Maximum Extended Load Line Limit Analysis Plus (Mellla+), License Amendment Request2013-09-25025 September 2013 Maximum Extended Load Line Limit Analysis Plus (Mellla+), License Amendment Request Project stage: Request ML13345A1822013-12-19019 December 2013 Supplemental Information Needed for Acceptance of Licensing Action, Request to Revise Technical Specification to Allow Operation in Expanded Maximum Extended Load Line Limit Analysis Plus (Mellla+) Domain Project stage: Acceptance Review ML13364A2862013-12-30030 December 2013 Maximum Extended Load Mine Limit Analysis Plus (Mella+) License Amendment Request-Responses to Requests for Supplemental Information Project stage: Supplement ML14023A5802014-01-23023 January 2014 NRR E-mail Capture - Acceptance Review of Grand Guld Nuclear Station License Amendment Request Regarding Maximum Extended Load Line Limit Analysis Plus Project stage: Acceptance Review ML14037A1492014-02-0606 February 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: RAI GNRO-2014/00011, Entergys Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses- with- Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-02-28028 February 2014 Entergys Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses- with- Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other GNRO-2014/00024, Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 2/6/20142014-03-10010 March 2014 Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 2/6/2014 Project stage: Response to RAI ML14080A2722014-03-18018 March 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: RAI ML14119A0092014-04-28028 April 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Audit Plan Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: Other ML14101A0432014-05-0808 May 2014 Request for Withholding from Public Disclosure - 12/19/2013 Affidavit Executed by L. Dolan, GE-Hitachi Nuclear Energy Americas LLC Related to Responses to Request for Supplemental Information Project stage: Other ML14101A0872014-05-0808 May 2014 Request for Withholding from Public Disclosure - 9/10/2013 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Nedc - 33612P, Revision 0 Project stage: Other ML14140A3012014-05-19019 May 2014 NRR E-mail Capture - Grand Gulf Nuclear Station, Unit 1, Request for Additional Information Regarding Maximum Load Line Limit Analysis Plus Project stage: RAI ML14211A1362014-07-30030 July 2014 NRR E-mail Capture - Grand Gulf Nuclear Station Request for Additional Information Regarding Maximun Extended Load Line Limit Plus Amendment Request Project stage: RAI GNRO-2014/00051, Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request Dated 7/2/20142014-08-14014 August 2014 Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request Dated 7/2/2014 Project stage: Response to RAI GNRO-2014/00045, Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/20142014-08-26026 August 2014 Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/2014 Project stage: Response to RAI GNRO-2014/00060, Entergys Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-08-26026 August 2014 Entergys Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other GNRO-2014/00064, Superseding Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 3/18/20142014-09-0404 September 2014 Superseding Response to Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 3/18/2014 Project stage: Response to RAI GNRO-2014/00052, Response to Electronic Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 7/29/20142014-09-10010 September 2014 Response to Electronic Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 7/29/2014 Project stage: Request ML14111A0582014-10-23023 October 2014 Request for Withholding from Public Disclosure - 3/4/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Enclosure to GNRO-2014/00024 Responses to Request for Additional Information Project stage: RAI ML14265A3702014-10-23023 October 2014 Request for Withholding from Public Disclosure - 7/1/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00064 Dated 9/4/14 Project stage: Other ML14265A3842014-10-23023 October 2014 Request for Withholding from Public Disclosure - 6/19/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00045 Dated 8/26/14 Project stage: Other ML14265A4222014-10-23023 October 2014 Request for Withholding from Public Disclosure - 6/25/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 3 to GNRO-2014/00045 Dated 8/26/14 Project stage: Other ML14262A3722014-11-12012 November 2014 Request for Withholding from Public Disclosure - 8/20/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00052 Dated 9/10/14 Project stage: Other ML14262A3972014-11-12012 November 2014 Request for Withholding from Public Disclosure - 7/22/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Enclosure 1 to GNRO-2014/00051 Dated 8/14/14 Project stage: Other ML14260A1302014-11-25025 November 2014 April 23-25, 2014, Audit Report Regarding Maximum Extended Load Line Limit Analysis Plus Amendment Including Minimum Stable Film Boiling Temperature and Quench Model Project stage: Other GNRO-2014/00083, Traversing Incore Probe (TIP) Comparisons TIP Comparisons for Current Operating Conditions in Support of the Grand Gulf Nuclear Station (GGNS) Maximum Extended Load Line Limit Analysis Plus (Mellla+) License Amendment Request2014-12-15015 December 2014 Traversing Incore Probe (TIP) Comparisons TIP Comparisons for Current Operating Conditions in Support of the Grand Gulf Nuclear Station (GGNS) Maximum Extended Load Line Limit Analysis Plus (Mellla+) License Amendment Request Project stage: Request GNRO-2014/00090, Correction to Typographical Error in Entergy Letter GNRO-2014/00053 Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using Consolidated Line Item Improvement.2015-01-0606 January 2015 Correction to Typographical Error in Entergy Letter GNRO-2014/00053 Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using Consolidated Line Item Improvement. Project stage: Request GNRO-2014/00088, Response to Item 20 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/20142015-01-20020 January 2015 Response to Item 20 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus Amendment Request, Dated 5/19/2014 Project stage: Request GNRO-2015/00003, Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus, Amendment Request, Dated 5/19/20142015-02-0909 February 2015 Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus, Amendment Request, Dated 5/19/2014 Project stage: Request GNRO-2015/00011, Supplement to License Amendment Request Application to Revise the Current Methodology from 0 EFPY Through the End of Extended Operations to a Single Fluence Method2015-02-18018 February 2015 Supplement to License Amendment Request Application to Revise the Current Methodology from 0 EFPY Through the End of Extended Operations to a Single Fluence Method Project stage: Supplement GNRO-2015/00013, Request to Convert Regulatory Commitments for Time Critical Operator Actions Listed in Letter GNRO-2015/00003, Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit2015-02-19019 February 2015 Request to Convert Regulatory Commitments for Time Critical Operator Actions Listed in Letter GNRO-2015/00003, Response to Item 25 Request for Additional Information Regarding Maximum Extended Load Line Limit Project stage: Request GNRO-2015/00004, Entergys Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mititgation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-19019 February 2015 Entergys Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mititgation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other GNRO-2015/00012, Response to License Amendment Request for Revision of Five Technical Specification Allowable Value Setpoints Request for Additional Information2015-03-0303 March 2015 Response to License Amendment Request for Revision of Five Technical Specification Allowable Value Setpoints Request for Additional Information Project stage: Request ML15040A1262015-03-19019 March 2015 Request for Withholding Information from Public Disclosure - 10/30/14 Affidavit Executed by James F. Harrison, GE-Hitachi Nuclear Energy Americas LLC, Related to Attachment 1 to GNRO-2014/00088 Dated 1/20/15 (TAC MF27 Project stage: Withholding Request Acceptance ML15085A2272015-04-14014 April 2015 October 15, 2014, Onsite Audit Report Regarding Maximum Extended Load Line Limit Analysis Plus Project stage: Other ML15040A0932015-06-24024 June 2015 Request for Withholding Information from Public Disclosure-10/12/14 Affidavit Executed by James F. Harrison, GE-Hitachi Nuclear Energy Amenricas LLC Related to Attachment 1 to GNRO-2014/00083 Dated 12/15/2014 (MF2798) Project stage: Withholding Request Acceptance GNRO-2015/00059, Submits Corrected Technical Specification Pages Regarding Maximum Extended Load Line Limit Plus License Amendment Request, Dated 9/25/20132015-08-14014 August 2015 Submits Corrected Technical Specification Pages Regarding Maximum Extended Load Line Limit Plus License Amendment Request, Dated 9/25/2013 Project stage: Request ML15229A2192015-08-31031 August 2015 Redacted, Issuance of Amendment Maximum Extended Load Line Limit Analysis Plus License Amendment Request Project stage: Approval 2014-05-08
[Table View] |
Text
~Entergy GNRO-2013/00060 August 28, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Entergy Operations, Inc.
P. O. Box 756 Port Gibson, MS 39150 Kevin J. Mulligan Site Vice President Grand Gulf Nuclear Station Tel. (601) 437-7500
SUBJECT:
Entergy's First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
Grand Gulf Nuclear Station, Unit 1 Docket No. 50-416 License No. NPF-29
REFERENCES:
1.
NRC Order Number EA-12-049, Order to Modify Licenses with Regard to Requirements for Mitigation Str~tegies for Beyond-Design-Basis External Events, dated March 12, 2012 (ML12054A735) 2.
Entergy Letter to NRC, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 27, 2013 (GNRO-2013/00015, ML13059A316)
Dear Sir or Madam:
On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission")
issued.an order (Reference 1) to.Entergy. Reference 1 was immediately effective and directs Entergy to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event.
Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan (Reference 2). The purpose of this letter is to provide the first six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementingthe requirements of Reference 1. The attached report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.
GNRO-2013/00060 Page 2 of 2 This letter contains no new regulatory commitments. Should you have any questions regarding this submittal, please contact Mr. Christopher R. Robinson, Licensing Manager, at (601) 437-7326.
I declare under penalty of perjury that the foregoing is true and correct; executed on August 28, 2013.
Sincerely,
~"'F------
KJM/slw
Attachment:
Grand Gulf Nuclear Station's First Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events cc:
U. S. Nuclear Regulatory Commission ATTN: Steven A. Reynolds Acting Regional Administrator, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 U. S. Nuclear Regulatory Commission Attn: Director, Office of Nuclear Reactor Regulation Washington, DC 20555-0001 U. S. Nuclear Regulatory Commission ATTN: Mr. Alan Wang, NRRlDORL Mail Stop OWFN/8 B1 Washington, DC 20555-0001 U. S. Nuclear Regulatory Commission ATTN: Jessica A. Kratchman Mail Stop OWFN/9 02 Washington, DC 20555-0001 NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150
Attachment to GNRO-2013/00060 Grand Gulf N~clear Station's First Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events
Attachment to GNRO-2013/00060 Page 1 of 3 Grand Gulf Nuclear Station's First Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with.Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events 1
Introduction Grand Gulf Nuclear Station (GGNS) developed an Overall Integrated Plan (Reference 1 in Section 8), documenting the divers~ and flexible strategies (FLEX), in response to Reference 2.
This attachment provides an update of milestone accomplishments since submittal of the Overall Integrated Plan, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
2 Milestone Accomplishments As of August 28,2013, the following milestone(s) have been completed:
Submit 6 Month Updates - Update 1 (August 2013).
3 Milestone Schedule Status The following provides an update to Attachment 2 of the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.
Validation:
Walk-through(s) or Demonstration(s): A target completion date has been added to the milestone listing for completion of the walk-through(s). The walk-through(s) will be completed during the FLEX modification implementation outage. This new milestone target date does not impact the Order implementation date.
Target Revised Milestone Completion Activity Target Date Status Completion Date Submit 60 Day Status 'Report Oct 2012 Complete N/A Submit Overall Integrated Plan Feb 2013 Complete N/A Submit 6 Month Updates:
Update 1 Aug 2013 Complete N/A Update 2 Feb 2014 Not Started No Change Update 3 Aug 2014 Not Started No Change Update 4 Feb 2015 Not Started No Change Update 5 Aug 2015 Not Started No Change Update 6 Feb 2016 Not Started No Change Update 7 Aug 2016 Not Started Deleted*
Perform Staffing Analysis Not Started No Change Modifications Develop Mods (Design Start)
May 2014 Not Started No Change
Attachment to GNRO-2013/00060 Page 2 of 3 Target Revised Activity Target Milestone Completion Status Completion Date Date Develop Strategies In Progress Nov 2014 Develop Mods (Design Complete)
Nov 2014 Not Started No Change Implementation Outage**
Mar 2016 Not Started No Change Implement Mods Dec 2016 Not Started Mar 2016 On-site FLEX Equipment Purchase In Progress No Change Procure In Progress No Change Off-site FLEX Equipment Develop Strategies / Contract with In Progress No Change RRC Procedures Issue GG FSGs Not Started No Change Create Maintenance Procedures Not Started No Change Procedure Changes Training Material Not Started No Change Complete Training Develop Training Plan Not Started No Change Implement Training Not Started No Change Validation / Demonstration Mar 2016 Not Started Submit Completion Report Dec 2016 Not Started Aug 2016
- Deleted due to Completion Report bemg submitted m August 2016.
- Full compliance since second refueling outage is before 12/31/2016.
4 Changes to Compliance Method There are no changes to the compliance method as documented in the Overall Integrated Plan (Reference 1).
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation GGNS expects to comply with the order implementation date and no relief/relaxation is required at this time.
6 Open Items from Overall Integrated Plan and Draft Safety Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan and the status of each item. The U.S. Nuclear Regulatory Commission (NRC) has not issued a draft safety evaluation for GGNS; therefore, there are no open items for the Draft Safety Evaluation identified at this time.
Overall Integrated Plan Open Item Status 1.
Structure, content and details of the Regional Not Started Response Center playbooks will be determined.
Attachment to GNRO-2013/00060 Page 3 of 3 7
Potential Draft Safety Evaluation Impacts There are no potential impacts to the Draft Safety Evaluation identified at this time.
8 References The following references support the updates to the Overall Integrated Plan described in this Attachment.
1.
"Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 27,2013 (GNRO-2013/00015, ML13059A316).
2.
NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012 (ML12054A735).