Other: ML13365A264, ML14030A207, ML15110A051, ML15272A324, PNP 2012-092, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, PNP 2013-009, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), PNP 2013-064, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), PNP 2013-065, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), PNP 2014-011, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), PNP 2014-084, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), PNP 2014-085, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), PNP 2015-005, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), PNP 2015-007, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), PNP 2015-061, Fifth Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
|
MONTHYEARPNP 2012-092, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2012-10-25025 October 2012 Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Other PNP 2013-009, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-02-28028 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13183A4562013-07-0303 July 2013 Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 Project stage: Approval ML13200A3282013-07-18018 July 2013 NRR E-mail Capture - Palisades Nuclear Plant - Requests for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation Project stage: RAI PNP 2013-061, Response to Request for Additional Information for the Overall Integrated Plan in Response to the Commission Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2013-08-19019 August 2013 Response to Request for Additional Information for the Overall Integrated Plan in Response to the Commission Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI PNP 2013-065, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other PNP 2013-064, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13312A4232013-11-26026 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI ML14030A2072014-02-0606 February 2014 Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Palisades Nuclear Plant, TAC No.: MF0768 Project stage: Other ML13365A2642014-02-10010 February 2014 Interim Staff Evaluation Regarding Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Other PNP 2014-011, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-02-28028 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other PNP 2014-084, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other PNP 2014-085, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other PNP 2015-007, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other PNP 2015-005, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML15110A0512015-04-22022 April 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other PNP 2015-061, Fifth Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15272A3242015-10-13013 October 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other 2014-02-10
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 3, 2013 Vice President, Operations Entergy Nuclear Operations, Inc.
Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530
SUBJECT:
PALISADES NUCLEAR PLANT - ONLINE REFERENCE PORTAL FOR REVIEW OF MITIGATION STRATEGIES SUBMITTAL IN RESPONSE TO ORDER EA-12-049 (TAC NO. MF0768)
Dear Sir or Madam:
By letter dated February 28,2013, Entergy Nuclear Operations, Inc. (ENO, the licensee) submitted a response to Order EA-12-049 (Mitigation Strategies), for the Palisades Nuclear Plant (PNP).
To improve the efficiency of the Nuclear Regulatory Commission (NRC) review, the licensees' representatives and the NRC staff have discussed the use of an online reference portal that would allow the NRC staff and contractors limited read-only access to the basis documents and other reference materials cited in your submittal. The online reference portal would allow the NRC staff to audit the licensees' on-site documents that support the information in the submittal.
Documents that are necessary to support the NRC staff safety evaluation of the submittal will be identified by the NRC staff. The licensee will be formally requested to submit those documents on the NRC docket. Use of the online reference portal is acceptable as long as the following conditions are met:
- The online reference portal will be password-protected and passwords will be assigned to those directly involved in the review on a need-to-know basis;
- The online reference portal will be sufficiently secure to prevent staff from printing, saving, or downloading any documents; and
- Conditions of use of the online reference portal will be displayed on the log-in screen and will require concurrence by each user.
The NRC staff requests that the portal be populated, as a minimum, with the references included in the submittal such as drawings, procedures, and calculations. This will help to increase the effectiveness and timeliness of the NRC staff's review. The NRC requests that the portal be ready for access to the NRC staff, within two weeks of receipt of this letter.
Vice President, Operations
- 2 The conditions associated with the online reference portal must be maintained throughout the duration of the review process. Please provide written confirmation to the NRC stating that you agree to the terms and conditions set forth in this letter.
Should you have any questions regarding the Mitigation Strategies online reference portal,
. please contact Ms. Jessica Kratchman, Project Manager, at 301-415-5112, or via email at Jessica.Kratchman@nrc.gov. In addition, please e-mail Ms. Kratchman with the information that is needed to access the portal, such as username and password, after the portal is available for use.
Sincerely, Mahesh L. Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255 cc: Distribution via Listserv
Vice President, Operations
- 2 The conditions associated with the online reference portal must be maintained throughout the duration of the review process. Please provide written confirmation to the NRC stating that you agree to the terms and conditions set forth in this letter.
Should you have any questions regarding the Mitigation Strategies online reference portal, please contact Ms. Jessica Kratchman, Project Manager, at 301-415-5112, or via email at Jessica.Kratchman@nrc.gov. In addition, please e-mail Ms. Kratchman with the information that is needed to access the portal, such as username and password, after the portal is available for use.
Sincerely.
IRAI Tom Wengert for Mahesh L. Chawla, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255 cc: Distribution via Listserv DISTRI BUTION:
PUBLIC MMitchell, JLD LPL3-1 R/F JKratchman, JLD RidsNrrDorlLpl3-1 Resource JEvans, JLD RidsNrrPMPalisades Resource MKhanna, DORL RidsNrrLASRohrer Resource REnnis, DORL RidsAcrsAcnw_MailCTR Resource RidsRgn3MailCenter Resource ADAMS Accession No.:
OFFICE LP3-1/PM NAME MChawla fTWengert for 07/03/13 JLD/BC MMitchell roa for ILRegner for 07/03/13 LP3-1/BC RCarlson 07/03/13 OFFICIAL RECORD COpy