To:
Shea, Joseph W; 'Schrull, Edward Dustin'; 'tahess@tva.gov' Cc:
Dennig, Robert; Bettle, Jerome; Hamm, Matthew; Tate, Travis; Saba, Farideh; Quichocho, Jessie
Subject:
Accepted for review of one-time changge to TS 3.6.6 Completion for an Inoperable Containment Spray Train Under Exigent Circumstances to allow for pump repair - TAC MF-1875 By letter dated May 22, 2013 (ADAMS NO. ML13143A166), TVA submitted a license amendment request for Watts Bar Unit-1. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
If you have any questions, please contact me.
Andy Hon, PE Project Manager (Watts Bar Nuclear Unit-1)
Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 301-415-8480 OWFN 08E5 Mail Stop O8G-9a andrew.hon@nrc.gov