ML13071A340

From kanterella
Jump to navigation Jump to search

Review of the Physical Security Plan, Revision 5
ML13071A340
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/13/2013
From: Gratton C
Plant Licensing Branch II
To: Franke J
Florida Power Corp
Gratton, Chris
References
TAC ME9874
Download: ML13071A340 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 13,2013 Mr. Jon A Franke, Vice President Crystal River Nuclear Plant (NA2C)

ATTN: Supervisor, Licensing & Regulatory Programs 15760 W. Power Line Street Crystal River, Florida 34428-6708

SUBJECT:

CRYSTAL RIVER UNIT 3 NUCLEAR PLANT - REVIEW OF THE PHYSICAL SECURITY PLAN, REVISION 5 (TAC NO. ME9874)

Dear Mr. Franke:

By letter dated August 2, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12216A319), as supplemented December 10, 2012 (ADAMS Accession No. ML12353A093), Florida Power Corporation (the licensee) submitted the fleet physical security plan, security training and qualification plan, safeguards contingency plan, and independent spent fuel storage installation security program, revision 5. The enclosure to the letters contained safeguards information and was withheld from public disclosure.

The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the submittal to ensure compliance with Title 10 of the Code of Federal Regulations, Section 50.54{p )(2) and to ensure that the changes did not decrease the safeguards effectiveness of the NRC-approved security plans. The NRC staff has completed its review and has no further questions at this time. The NRC staff will close Task Activity Code ME9874.

If you have questions, you can contact me at 301-415-1055 or Christopher.Gratton@nrc.gov.

cr~J.d~(

Christopher Gratton, Senior Project Manager Plant Licensing Branch 1/-2 Division of Operating Reactor licenSing Office of Nuclear Reactor Regulation Docket No. 50-302 cc: Distribution via ListServ

March 13,2013 Mr. Jon A. Franke, Vice President Crystal River Nuclear Plant (NA2C)

ATTN: Supervisor, Licensing & Regulatory Programs 15760 W. Power Line Street Crystal River, Florida 34428-6708

SUBJECT:

CRYSTAL RIVER UNIT 3 NUCLEAR PLANT - REVIEW OF THE PHYSICAL SECURITY PLAN, REVISION 5 (TAC NO. ME9874)

Dear Mr. Franke:

By letter dated August 2, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12216A319), as supplemented December 10, 2012 (ADAMS Accession No. ML12353A093), Florida Power Corporation (the licensee) submitted the fleet physical security plan, security training and qualification plan, safeguards contingency plan, and independent spent fuel storage installation security program, revision 5. The enclosure to the letters contained safeguards information and was withheld from public disclosure.

The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the submittal to ensure compliance with Title 10 of the Code of Federal Regulations, Section 50.54(p)(2) and to ensure that the changes did not decrease the safeguards effectiveness of the NRC-approved security plans. The NRC staff has completed its review and has no further questions at this time. The NRC staff will close Task Activity Code ME9874.

If you have questions, you can contact me at 301-415-1055 or Christopher.Gratton@nrc.gov.

Sincerely, IRA!

Christopher Gratton, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-302 cc: Distribution via ListServ DISTRIBUTION:

PUBLIC LPL 2-2 R/F RidsNrrDorlLPL2-2 RidsNrrPMCrystal River RidsNrrLABClayton RidsOgcRp RidsAcrsAcnw_MailCTR RidsRgn2MailCenter RidsNsirDsp RCosta, NSIR ADAMS Accession No ML13071A340 OFFICE LPL2-2\PM LPL2-2\LA LPL2-2\BC LPL2-2\PM NAME CGratton BClayton JQuichocho CGratton DATE 3112/13 3/12/13 3113113 3/13/13 OFFICIAL RECORD COpy