Draft Written Exam Sample plan (ES-401-1/2/3)
There was no Draft Written Exam Sample plan for the North Anna 2012-302 Exam (the Written Exam was waived).
ES-301 Administrative Topics Outline Form ES-301-1 Facility: North Anna Power Station Date of Examination: 12/17/2012.
Examination Level: SRO-I Operating Test Number:
Retake Administrative Topic (see Note)
Type Code*
Describe activity to be performed Conduct of Operations M, R G2.1.43 Calculate Estimated Critical Conditions (RO 4.1 / SRO 4.3)
Conduct of Operations M, R G2.1.18 Perform 1-LOG-20, ECCS Leakage Log (RO 3.6 / SRO 3.8)
Equipment Control N, R G2.2.20 Evaluate proposed troubleshooting activity and correctly apply the requirements of MA-AA-103.
Radiation Control M, R, P G2.3.7 Given an assignment in the RCA: Select the appropriate RWP Task, identify required dosimetry & alarm setpoints, and, using the appropriate survey maps, estimate total dose for performing the task.
Emergency Plan M, R G2.4.44 Determine Protective Action Recommendation (PAR) and update requirement (EPIP-1.06)
NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.
- Type Codes & Criteria:
(C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank (< 3 for ROs; < 4 for SROs & RO retakes)
(N)ew or (M)odified from bank (> 1)
(P)revious 2 exams (< 1; randomly selected)
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: _North Anna Power Station__
Date of Examination: __12/17/2012____
Exam Level : RO SRO-I SRO-U Operating Test No.:
Retake Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
Type Code*
Safety Function a) Makeup to Service Water Reservoir 076-A4.01, (RO 2.9 / SRO 2.9)
M, S 4(sec) b) Maintain stable plant conditions (No-tell, Unit on RHR, spurious SI, 1-AP-0.1) 006-A2.13 (RO 3.9 / SRO 4.2)
A, EN, L, N, S
3 c) Perform 1-PT-17.1, Control Rod Operability 001-A2.11, (RO 4.4 / SRO 4.7)
A, M, S 1
d) Place Excess Letdown in service 004-A4.06, (RO 3.6 / SRO 3.1)
D, S 2
e) Maintain Stable Plant Conditions (No-tell, N-44 failure, 1-AP-4.3) 015 - A2.02 (RO 3.1 / SRO 3.5)
A, M, S 7
f) Start RCP (No-tell, after start conditions degrade & require stopping RCPs )
003 - A1.09 (RO 2.8 / SRO 2.8)
A, L, M, S 4(pri) g) Raise PRT pressure by adding nitrogen 007 - A1.02 (RO 2.7 / SRO 2.9)
D, S, P 5
h) N/A N/A N/A In-Plant Systems@ (3 for RO; 3 for SRO-I; 3 or 2 for SRO-U) i)
Transfer Aux Monitoring Panel and Remote Monitoring Excore Neutron Flux Detectors to backup power.
067-AA2.16, (RO 3.3 / SRO 4.0)
D, E 6
j)
Trip reactor locally (2-FR-S.1) 029 - EA1.12 (RO 4.1 / SRO 4.0)
A, D, E, P 1
k) Align CC system for split operations (1-AP-15) 026 - AA2.03 (RO 2.6 / SRO 2.9)
D, E, R 8
All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path (C)ontrol room (D)irect from bank (E)mergency or abnormal in-plant (EN)gineered safety feature (L)ow-Power / Shutdown (N)ew or (M)odified from bank including 1(A)
(P)revious 2 exams (similar topic)
(R)CA (S)imulator 4-6 / 4-6 / 2-3
< 9 / < 8 / < 4
> 1 / > 1 / > 1
- / - / > 1 (control room system)
> 1 / > 1 / > 1
> 2 / > 2 / > 1
< 3 / < 3 / < 2 (randomly selected)
> 1 / > 1 / > 1