Category:Letter
MONTHYEARML24302A2402024-10-28028 October 2024 CFR 21 Report 1-BY-BC-1-LV Battery Charger IR 05000338/20240032024-10-28028 October 2024 – Integrated Inspection Report 05000338-2024003 and 05000339-2024003 ML24302A2342024-10-23023 October 2024 Request for Project Number Related to Dominion Energy Services New Nuclear Program at North Anna Power Station ML24283A0392024-10-0909 October 2024 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.D ML24281A1372024-10-0707 October 2024 ISFSI - Submittal of Cask Registration for Spent Fuel Storage 05000338/LER-2024-001-01, Automatic Reactor Trip Due to Prni High Negative Rate2024-09-24024 September 2024 Automatic Reactor Trip Due to Prni High Negative Rate IR 05000338/20244202024-09-23023 September 2024 Security Baseline Inspection Report 05000338/2024420 and 05000339/2024420, Cover Letter ML24243A0872024-09-20020 September 2024 Response to EPA Comments Regarding the Final Site Specific Supplement to the Generic Eist for License Renewal North Anna Power Station, Units 1 and 2 IR 05000338/20244022024-09-17017 September 2024 Security Baseline Inspection Report 05000338/2024402 and 05000339/2024402 ML24215A2622024-08-28028 August 2024 Transmittal Letter for Subsequent Renewed License IR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) 05000339/LER-2024-001-01, Loss of Generator Field for 2J Eog During 2-PT-82.282024-08-20020 August 2024 Loss of Generator Field for 2J Eog During 2-PT-82.28 ML24234A0742024-08-15015 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-23-63, NEI 03-08 Needed Guidance: PWR Thermal Shield Flexure Inspection Requirements ML24221A1932024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Upper Mattaponi Tribe ML24221A1882024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Monacan Indian Nation ML24206A0052024-08-0808 August 2024 SLR Final EIS Letter to Achp ML24221A1842024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Nation, Oklahoma ML24221A1912024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Rappahannock Tribe, Inc ML24221A1942024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-United Keetoowah Band of Cherokee Indians in Oklahoma ML24221A1922024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Tuscarora Nation of New York ML24221A1852024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Tribe of Indians ML24221A1832024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Chickahominy Indian Tribe-Eastern Division ML24206A0062024-08-0808 August 2024 Notice of Availability of the Final Environmental Impact Statement for the North Anna Nuclear Power Station Unit Numbers 1 and 2 Subsequent License Renewal (Docket Numbers: 50-338 and 50-339) ML24163A3002024-08-0808 August 2024 Request for Relief Request N1-I5-NDE-007 Inservice Inspection Alternative ML24208A0142024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-Absentee-Shawnee Tribe of Indians of Oklahoma ML24221A1872024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Shawnee Tribe of Oklahoma ML24221A1862024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Band of Cherokee Indians ML24221A1812024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Catawba Indian Nation ML24221A1822024-08-0808 August 2024 Tribal Section 106 Letters - North Anna - Chickahominy Indian Tribe ML24221A1902024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Pamunkey Indian Tribe ML24221A1892024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Nansemond Indian Nation ML24241A0692024-08-0606 August 2024 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000338/20240022024-08-0202 August 2024 Integrated Inspection Report 05000338/2024002 and 05000339/2024002 ML24206A0432024-07-26026 July 2024 Feis - Letter to the Applicant 05000338/LER-2024-001, Automatic Reactor Trip Due to Prni High Negative Rate2024-07-25025 July 2024 Automatic Reactor Trip Due to Prni High Negative Rate ML24206A0902024-07-24024 July 2024 Owners Activity Report ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24165A1462024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 05000339/LER-2024-001, Loss of Generator Field for 2J EDG During 2-PT-82.282024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 IR 05000338/20240012024-05-10010 May 2024 Integrated Inspection Report 05000338/2024001 and 05000339/2024001 IR 05000338/20244032024-04-30030 April 2024 – Security Baseline Inspection Report 05000338-2024403 and 05000339-2024403 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24110A1502024-04-18018 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24110A1392024-04-18018 April 2024 Annual Environmental Operating Report ML24110A1462024-04-18018 April 2024 Independent Spent Fuel Storage Installation (Sfsi) - Annual Radiological Environmental Operating Report ML24087A0572024-04-16016 April 2024 Correction to Issuance of Amendment Nos. 296 and 279 ML24088A2692024-03-27027 March 2024 Core Operating Limits Report Cycle 31 Pattern Sos Revision 0 2024-09-24
[Table view] Category:License-Operator
MONTHYEARML22241A0262022-08-29029 August 2022 Exam Administrative Items (1) ML22241A0232022-08-29029 August 2022 Adams 2B Na Exam Administrative Items ML22214A0252022-08-0202 August 2022 NA-2022-6 RO as Given Written ML22214A0272022-08-0202 August 2022 NA-2022-6 SRO as Given Written ML22147A0162022-05-26026 May 2022 2022-301 Exam Approval Letter ML22125A1762022-05-0505 May 2022 Preparation and Scheduling of Operator Licensing. ML21313A2632021-11-0808 November 2021 301 Corporate Notification Letter (210-day Ltr) ML21111A3412021-04-16016 April 2021 March 2021 GFE ML21011A0082021-01-11011 January 2021 301-2B Normal Release - Exam Administrative Items ML21011A0552021-01-11011 January 2021 301 2A-3, Exam Administrative Items ML21011A0312021-01-11011 January 2021 301 2A-2 Exam Final Items ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML20156A3122020-06-0404 June 2020 Preparation and Scheduling of Operator Licensing Examinations ML19100A2012019-04-10010 April 2019 March 6, 2019, NRC Generic Fundamentals Examination Results for North Anna Power Station ML19045A3712019-02-12012 February 2019 March 2019 GFE Cover Letter Rii ML19018A0882019-01-17017 January 2019 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2019 IR 05000338/20183012018-08-29029 August 2018 05000338/2018301 and 05000339/2018301 Post Exam Comments ML18135A0842018-04-25025 April 2018 NRC Regulatory Issue Summary 2018-02 Preparation and Scheduling of Operator Licensing Examinations ML17331A7042017-11-21021 November 2017 Notification of Licensed Operator Initial Examination 05000338/2018301 and 05000339/2018301 ML17172A6922017-06-22022 June 2017 Section 1 - Draft Administrative Documents ML17172A7032017-06-21021 June 2017 Section 3 - North Anna 2016301 SRO Written Draft - Delay Release 2 Yrs ML17172A7012017-06-21021 June 2017 Section 2 - North Anna 2016301 RO Written Draft - Delay Release 2 Years ML17172A7112017-06-21021 June 2017 Section 5 - Draft Sim and in Plant JPMs ML17172A7272017-06-21021 June 2017 Section 14 - General Correspondence ML17172A7082017-06-21021 June 2017 Section 4 - North Anna 2016301 - Draft Simulator Scenarios ML17172A7262017-06-21021 June 2017 Section 12 - Final Administrative JPMs - North Anna Power Station ML17172A7202017-06-21021 June 2017 Section 10 - Final Simulator Scenarios - North Anna Power Station ML17172A7142017-06-21021 June 2017 Section 6 - Draft Administrative JPMs ML17172A7252017-06-21021 June 2017 Section 11 - Final Sim in Plant JPMs ML17172A7182017-06-21021 June 2017 Section 7 - Final Admin Docs - North Anna ML17142A2962017-05-17017 May 2017 Preparation and Scheduling of Operator Licensing Examinations ML17116A6362017-04-24024 April 2017 March 2017 - North Anna NRC Generic Fundamentals Examination Results ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML16214A3022016-08-0101 August 2016 05000338/2016301 and 05000339/2016301 Final RO Written Exam - Delay Release ML16214A3042016-08-0101 August 2016 0500033i8/2016301 and 05000339/20163001 Final SRO Written Exam - Delay Release ML16214A3012016-07-14014 July 2016 05000338/2016301 and 05000339/2016301 Post Exam Comments ML16173A1522016-06-16016 June 2016 Operator Licensing Written Examination Approval 050000338/2016301 and 050000339/2016301 ML15356A7592015-12-21021 December 2015 Notification of Licensed Operational Examination 05000338/2016301 and 05000339/2016301 IR 05000338/20163012015-12-21021 December 2015 Notification of Licensed Operational Examination 05000338/2016301 and 05000339/2016301 ML14233A5452014-08-21021 August 2014 Initial Exam 2014-301 Draft Simulator Scenarios ML14233A4602014-08-21021 August 2014 Inital Exam 2014-301 Draft RO Written Exam ML14233A4972014-08-21021 August 2014 Initial Exam 2014-301 Draft SRO Written Exam ML14234A0082014-08-21021 August 2014 Initial Exam 2014-301 Draft Simulator and in Plant JPMs ML14234A0102014-08-21021 August 2014 Initial Exam 2014-301 Draft Administrative JPMs ML14234A0132014-08-21021 August 2014 Initial Exam 2014-301 Final Administrative Documents ML14234A0152014-08-21021 August 2014 Initial Exam 2014-301 Final Simulator Scenarios ML14234A0182014-08-21021 August 2014 Initial Exam 2014-301 Final Simulator and in Plant JPMs ML14234A0192014-08-21021 August 2014 Initial Exam 2014-301 Final Administrative JPMs ML14234A0202014-08-21021 August 2014 Initial Exam 2014-301 Post Exam Comments ML14234A0222014-08-21021 August 2014 Initial Exam 2014-301 General Correspondence 2022-08-29
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML22241A0232022-08-29029 August 2022 Adams 2B Na Exam Administrative Items ML22241A0262022-08-29029 August 2022 Exam Administrative Items (1) ML22214A0252022-08-0202 August 2022 NA-2022-6 RO as Given Written ML22214A0272022-08-0202 August 2022 NA-2022-6 SRO as Given Written ML22147A0162022-05-26026 May 2022 2022-301 Exam Approval Letter ML22125A1762022-05-0505 May 2022 Preparation and Scheduling of Operator Licensing. ML21313A2632021-11-0808 November 2021 301 Corporate Notification Letter (210-day Ltr) ML21011A0312021-01-11011 January 2021 301 2A-2 Exam Final Items ML21011A0552021-01-11011 January 2021 301 2A-3, Exam Administrative Items ML21011A0082021-01-11011 January 2021 301-2B Normal Release - Exam Administrative Items ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML20156A3122020-06-0404 June 2020 Preparation and Scheduling of Operator Licensing Examinations ML19100A2012019-04-10010 April 2019 March 6, 2019, NRC Generic Fundamentals Examination Results for North Anna Power Station IR 05000338/20183012018-08-29029 August 2018 05000338/2018301 and 05000339/2018301 Post Exam Comments ML18135A0842018-04-25025 April 2018 NRC Regulatory Issue Summary 2018-02 Preparation and Scheduling of Operator Licensing Examinations ML17331A7042017-11-21021 November 2017 Notification of Licensed Operator Initial Examination 05000338/2018301 and 05000339/2018301 ML17172A6922017-06-22022 June 2017 Section 1 - Draft Administrative Documents ML17172A7202017-06-21021 June 2017 Section 10 - Final Simulator Scenarios - North Anna Power Station ML17172A7182017-06-21021 June 2017 Section 7 - Final Admin Docs - North Anna ML17172A7252017-06-21021 June 2017 Section 11 - Final Sim in Plant JPMs ML17172A7142017-06-21021 June 2017 Section 6 - Draft Administrative JPMs ML17172A7262017-06-21021 June 2017 Section 12 - Final Administrative JPMs - North Anna Power Station ML17172A7012017-06-21021 June 2017 Section 2 - North Anna 2016301 RO Written Draft - Delay Release 2 Years ML17172A7272017-06-21021 June 2017 Section 14 - General Correspondence ML17172A7082017-06-21021 June 2017 Section 4 - North Anna 2016301 - Draft Simulator Scenarios ML17172A7032017-06-21021 June 2017 Section 3 - North Anna 2016301 SRO Written Draft - Delay Release 2 Yrs ML17172A7112017-06-21021 June 2017 Section 5 - Draft Sim and in Plant JPMs ML17142A2962017-05-17017 May 2017 Preparation and Scheduling of Operator Licensing Examinations ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML16214A3022016-08-0101 August 2016 05000338/2016301 and 05000339/2016301 Final RO Written Exam - Delay Release ML16214A3042016-08-0101 August 2016 0500033i8/2016301 and 05000339/20163001 Final SRO Written Exam - Delay Release ML16214A3012016-07-14014 July 2016 05000338/2016301 and 05000339/2016301 Post Exam Comments ML16173A1522016-06-16016 June 2016 Operator Licensing Written Examination Approval 050000338/2016301 and 050000339/2016301 IR 05000338/20163012015-12-21021 December 2015 Notification of Licensed Operational Examination 05000338/2016301 and 05000339/2016301 ML15356A7592015-12-21021 December 2015 Notification of Licensed Operational Examination 05000338/2016301 and 05000339/2016301 ML14234A0202014-08-21021 August 2014 Initial Exam 2014-301 Post Exam Comments ML14234A0232014-08-21021 August 2014 Initial Exam 2014-301 Other Documents for Retention ML14233A4602014-08-21021 August 2014 Inital Exam 2014-301 Draft RO Written Exam ML14233A4972014-08-21021 August 2014 Initial Exam 2014-301 Draft SRO Written Exam ML14234A0082014-08-21021 August 2014 Initial Exam 2014-301 Draft Simulator and in Plant JPMs ML14234A0222014-08-21021 August 2014 Initial Exam 2014-301 General Correspondence ML14234A0102014-08-21021 August 2014 Initial Exam 2014-301 Draft Administrative JPMs ML14234A0132014-08-21021 August 2014 Initial Exam 2014-301 Final Administrative Documents ML14234A0192014-08-21021 August 2014 Initial Exam 2014-301 Final Administrative JPMs ML14234A0182014-08-21021 August 2014 Initial Exam 2014-301 Final Simulator and in Plant JPMs ML14234A0152014-08-21021 August 2014 Initial Exam 2014-301 Final Simulator Scenarios ML14188C2322014-07-0707 July 2014 301 SRO Answer Key ML14188C2772014-07-0707 July 2014 301 SRO Written Exam References ML14188C2462014-07-0707 July 2014 301 SRO As-Given Written Exam ML14188B9952014-07-0707 July 2014 301 RO Answer Key 2022-08-29
[Table view] |
Text
May 26, 2022
Mr. Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 29060
SUBJECT:
NORTH ANNA POWER STATION - NRC INITIAL LICENSE EXAM APPROVAL 05000338/2022301 AND 05000339/2022301
Dear Mr. Stoddard:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing written examination at North Anna Power Station (Units 1 and 2).
The U.S. Nuclear Regulatory Commission (NRC) has approved the subject examinations, and you may administer the written examination in accordance with Revision 12 to NUREG-1021, Operator Licensing Examination Standards for Power Reactors, during the week of June 13, 2022. The NRC staff will administer the operating tests during the week of June 6, 2022. The list of the applicants approved to take the examination has been provided to your office. The examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (404) 997 -4703.
Please contact your Chief Examiner, Mr. Michael Kennard, at (404) 997 -4627, if you have any questions or identify any errors or changes in license level (reactor operator or senior reactor operator) or type of examination (partial or complete written examination or operating test, or both) specified for each applicant approved to take the examination.
Sincerely,
/RA/
Thomas A. Stephen, Chief Operations Branch 1 Division of Reactor Safety
Docket No.: 50- 338, 50-339 License No.: NPF-4, NPF-7
ML22147A016 SUNSI REVIEW COMPLETE FORM 665 ATTACHED
OFFICE RII:DRS RII:DRS RII:DRS NAME DEGELSTAD MKENNARD TSTEPHEN DATE 5/ 24 /2022 5/ 26 /2022 5/ 26 /2022