Issuance of License Amendment Request to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection
ML13018A086
Person / Time
Site: Surry  Dominion icon.png
Issue date: 01/28/2013
From: Cotton K
Plant Licensing Branch II
To: Heacock D
Virginia Electric & Power Co (VEPCO)
Cotton K
References
TAC ME9199, TAC ME9200
Download: ML13018A086 (32)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 28, 2013 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

SURRY POWER STATION, UNIT NO.1 AND 2 ISSUANCE OF AMENDMENTS TO ADOPT TECHNICAL SPECIFICATION TASK FORCE (TSTF) 510, REVISION 2, REVISION TO STEAM GENERATOR PROGRAM INSPECTION FREQUENCIES AND TUBE SAMPLE SELECTION (TAC NO. ME9199 AND ME9200)

Dear Mr. Heacock:

The U.S. Nuclear Regulatory Commission has issued the enclosed Amendment No. 278 to Renewed Facility Operating License No. DPR-32 and Amendment No. 278 to Renewed Facility Operating License No. DPR-37 for the Surry Power Station, Unit Nos. 1 and 2, respectively. The amendments change the Technical Specifications (TSs) in response to your application dated July 31,2012, as supplemented by letter dated November 6,2012.

These amendments revise Limiting Condition for Operation (LCO) 3.1.H, "Steam Generator (SG)

Tube Integrity," TS 6.4.Q, "Steam Generator (SG) Program," and TS 6.6.A.3, "Steam Generator Tube Inspection Report," and include TS Bases changes that summarize and clarify the purpose of the TS in accordance with TS Task Force Traveler (TSTF) 510, "Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection."

A copy of the Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's biweekly Federal Register notice.

Sincerely, t<CWvL ~

Karen Cotton, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-280 and 50-281

Enclosures:

1. Amendment No. 278 to DPR-32
2. Amendment No. 278 to DPR-37
3. Safety Evaluation cc w/encls: Distribution via Listserv

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 VIRGINIA ELECTRIC AND POWER COMPANY DOCKET NO. 50-280 SURRY POWER STATION, UNIT NO.1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 278 Renewed License No. DPR-32

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment by Virginia Electric and Power Company (the licensee) dated July 31,2012, as supplemented by letter dated November 6, 2012, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

-2

2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 3.B of Renewed Facility Operating License No. DPR-32 is hereby amended to read as follows:

(B) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 278 , are hereby incorporated in the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications.

3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days.

FOR THE NUCLEAR REGULATORY COMMISSION Robert J. Pascarelli, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Attachment:

Changes to License No. DPR-32 and the Technical Specifications Date of Issuance: -January 28, 2013

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 VIRGINIA ELECTRIC AND POWER COMPANY DOCKET NO. 50-281 SURRY POWER STATION, UNIT NO.2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 278 Renewed License No. DPR-37

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment by Virginia Electric and Power Company (the licensee) dated July 31,2012, as supplemented by letter dated November 6,2012, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

-2

2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 3.B of Renewed Facility Operating License No. DPR-37 is hereby amended to read as follows:

(B) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 278 , are hereby incorporated in the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications.

3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days.

FOR THE NUCLEAR REGULATORY COMMISSION Robert J. Pascarelli, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Attachment:

Changes License No. DPR-37 and the Technical Specifications Date of Issuance: January 28, 2013

ATTACHMENT TO LICENSE AMENDMENT NO. 278 RENEWED FACILITY OPERATING LICENSE NO. DPR-32 DOCKET NO. 50-280 AND TO LICENSE AMENDMENT NO. 278 RENEWED FACILITY OPERATING LICENSE NO. DPR-37 DOCKET NO. 50-281 Replace the following pages of the Licenses and the Appendix A Technical Specifications (TSs) with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

Remove Pages Insert Pages License License License No. DPR-32, page 3 License No. DPR-32, page 3 License No. DPR-37, page 3 License No. DPR-37, page 3 TSs TSs 3.1-26 3.1-26 3.1-28 3.1-28 3.1-30 3.1-30 4.19-1 4.19-1 4.19-2 4.19-2 4.19-2a 6.4-11 6.4-11 6.4-12 6.4-12 6.4-13 6.4-13 6.4-13a 6.6-3 6.6-3 6.6-3a

-3

3. This renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations: 10 CFR Part 20, Section 30.34 of 10 CFR Part 30, Section 40.41 of 10 CFR Part 40, Sections 50.54 and 50.59 of 10 CFR Part 50, and Section 70.32 of 10 CFR Part 70; and is subject to all applicable provisions of the Act and the rules, regulations, and orders of the Commission now or hereafter in effect: and is subject to the additional conditions specified below:

A. Maximum Power Level The licensee is authorized to operate the facility at steady state reactor core power levels not in excess of 2587 megawatts (thermal).

B. Technical Specifications The Technical Specifications contained in Appendix A. as revised through Amendment No.

are hereby incorporated in the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications.

C. Reports The licensee shall make certain reports in accordance with the requirements of the Technical Specifications.

D. Records The licensee shall keep facility operating records in accordance with the requirements of the Technical Specifications.

E. Deleted by Amendment 65 F. Deleted by Amendment 71 G. Deleted by Amendment 227 H. Deleted by Amendment 227 I. Fire Protection The licensee shall implement and maintain in effect the provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report and as approved in the SER dated September 19, 1979, (and Supplements dated May 29,1980, October 9, 1980, December 18,1980, February 13,1981, December4. 1981, April 27. 1982, November 18, 1982, January 17, 1984, February 25,1988. and SURRY UNIT 1 Renewed License No. DPR-32 Amendment No. : 278

-3 E. Pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.

3. This renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations: 10 CFR Part 20, Section 30.34 of 10 CFR Part 30, Section 40.41 of 10 CFR Part 40, Sections 50.54 and 50.59 of 10 CFR Part 50, and Section 70.32 of 10 CFR Part 70; and is subject to all applicable prOVisions of the Act and the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified below:

A. Maximum Power Level The licensee is authorized to operate the facility at steady state reactor core power levels not in excess of 2587 megawatts (thermal).

B. Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 278, are hereby incorporated in this renewed license. The licensee shall operate the facility in accordance with the Technical Specifications.

C. Reports The licensee shall make certain reports in accordance with the requirements of the Technical Specifications.

D. Records The licensee shall keep facility operating records in accordance with the requirements ofthe Technical Specifications.

E. Deleted by Amendment 54 F. Deleted by Amendment 59 and Amendment 65 G. Deleted by Amendment 227 H. Deleted by Amendment 227 SURRY - UNIT 2 Renewed License No. DPR-37 Amendment No.2 78

TS 3.1-26 H. Steam Generator (SG) Tube Integrity Applicability The following specifications are applicable whenever Tavg (average RCS temperature) exceeds 200°F (200 degrees Fahrenheit).

Specifications .

1. SG tube integrity shall be maintained, and all SG tubes satisfying the tube plugging

. criteria shall be plugged in accordance with the Steam Generator Program.

2. If the requirements of 3.l.H.l are not met for one or more SG tubes, then perform the following: I '
a. Within 7 days, verify tube integrity of the affected tube(s) is maintained until the next refueling outage or SG tube inspection; and I
b. Plug the affected tube(s) in accordance with the Steam Generator Program prior to Tavg exceeding 200°F following the next refueling outage or SG tube inspection.
3. If the required actions of Specification 3.1.H.2 are not completed within the specified completion time, or SG tube integrity is not maintained, the unit shall be brought to HOT SHUTDOWN within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

Note:

1. A separate TS action entry is allowed for each SG tube.

BASES BACKGROUND - Steam generator (SG) tubes are small diameter, thin walled tubes that carry primary coolant through the primary to secondary heat exchangers. The SG tubes have a number of important safety functions. Steam generator tubes are an integral part of the reactor coolant pressure boundary (RCPB) and, as such, are relied on to maintain the primary system's pressure and inventory. The SG tubes isolate the radioactive fission products in the primary coolant from the secondary system. In addition, as part of the RCPB, the SG tubes are unique in that they act as the heat transfer surface between the primary and secondary systems to remove heat from the primary system. This Specification addresses only the RCPB integrity function of the SG. The SG heat removal function is addressed by LCO 3.1.A.2.

SG tube integrity means that the tubes are capable of performing their intended RCPB safety function consistent with the licensing basis, including applicable regulatory requirements.

Amendment Nos. 278, 278

TS 3.1-28 Steam generator tube integrity satisfies Criterion 2 of 10 CFR 50.36(c)(2)(ii).

LIMITING CONDITIONS FOR OPERATION - The LCO requires that SG tube integrity be maintained. The LCO also requires that all SG tubes that satisfy the plugging criteria be plugged in accordance with the Steam Generator Program.

During an SG inspection, any inspected tube that satisfies the Steam Generator Program plugging criteria is removed from service by plugging. If a tube was determined to satisfy the plugging criteria but was not plugged, the tube may still have tube integrity.

In the context of this Specification, a SG tube is defined as the entire length of the tube, including the tube wall between the tube-to-tubesheet weld at the tube inlet and the tube-to-tubesheet weld at the tube outlet. The tube-to-tubesheet weld is not considered part of the tube.

A SG tube has tube integrity when it satisfies the SG performance criteria. The SG performance criteria are defined in Specification 6.4.Q, "Steam Generator Program," and describe acceptable SG tube performance. The Steam Generator Program also provides the evaluation process for determining conformance with theSG performance criteria.

There are three SG performance criteria: structural integrity, accident induced leakage, and operational LEAKAGE. Failure to meet anyone of these criteria is considered fai1ure to meet the LCO.

The structural integrity performance criterion provides a margin of safety against tube burst or collapse under normal and accident conditions, and ensures structural integrity of the SG tubes under all.anticipated transients included in the design specification. Tube burst is defined as, "The gross structural failure of the tube wall. The condition typically corresponds to an unstable opening displacement (e.g., opening area increased in response to constant pressure) accompanied by ductile (plastic) tearing of the tube material at the ends of the degradation." Thbe collapse is defined as, "For the load displacement curve for a given structure, collapse occurs at the top of the load versus displacement curve where the slope of the curve becomes zero." The structural integrity performance criterion provides guidance on assessing loads that significantly affect burst or collapse. In that context, the term "significantly" is defined as "An accident loading condition other than differential pressure is considered significant when the addition of such loads in the assessment of the structural integrity performance criterion could cause a lower structural limit or limiting burst/collapse condition to be established." For tube integrity evaluations, except for circumferential degradation, axial thermal loads are classified as secondary loads. For circumferential degradation, the classification of axial thermal loads as primary or secondary loads will be evaluated on a case-by-case basis. The division between primary and secondary classifications will be based on detailed analysis and/or testing.

Amendment Nos. 278, 278

TS 3.1-30 3.I.H.2.a and b Specification 3.I.H.2 applies if it is discovered that one or more SO tubes examined in an in service inspection satisfy the tube plugging criteria but were not plugged in accordance with the Steam Oenerator Program as required by SR 4.19. An evaluation of SG tube integrity of the affected tube(s) must be made. Steam generator tube integrity is based on meeting the SG performance criteria described in the Steam Generator Program. The SG plugging criteria define limits on SG tube degradation that allow for flaw growth between inspections while still providing assurance that the SO performance criteria will continue to be met. In order to determine if a SO tube that should have been plugged has tube integrity, an evaluation must be completed that demonstrates that the SO performance criteria will continue to be met until the next refueling outage or SO tube inspection. The tube integrity determination is based on the estimated condition of the tube at the time the situation is discovered and the estimated growth of the degradation prior to the next SO tube inspection. If it is determined that tube integrity is not being maintained, Specification 3.l.H.3 applies.

A completion time of 7 days is sufficient .to complete the evaluation while minimizing the risk of unit operation with a SO tube that may not have tube integrity.

If the evaluation determines that the affected tube(s) have tube integrity, required action 3.I.H.2.b allows unit operation to continue until the next refueling outage or SO inspection provided the inspection interval continues to be supported by an operational assessment that reflects the affected tubes. However. the affected tube(s) must be plugged prior to Tavg exceeding 2000 P following the next refueling outage or SO inspection. This completion time is acceptable since operation until the next inspection is supported by the operational assessment.

3.l.H.3 If the required actions and associated completion times of Specification 3.1.H.2 are not met or if SO tube integrity is not being maintained, the reactor must be brought to HOT SHUTDOWN within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

The allowed completion times are reasonable, based on operating experience, to reach the desired unit conditions from full power conditions in an orderly manner and without challenging plant systems.

Amendment Nos. 278, 278

TS 4.19-1 4.19 STEAM GENERATOR (SG) TUBE INTEGRITY Applicability Applies to the verification of SG tube integrity in accordance with the Steam Generator Program.

Objective To provide assurance of SG tube integrity.

Specifications A. Verify SG tube integrity in accordance with the Steam Generator Program.

B. Verify that each inspected SG tube that satisfies the tube plugging criteria is plugged in accordance with the Steam Generator Program prior to T avg exceeding 200 0 P following a SG tube inspection.

BASES SURVEILLANCE REQUIREMENTS (SR)

SR4.19.A During shutdown periods the SGs are inspected as required by this SR and the Steam Generator Program. NEI 97-06, Steam Generator Program Guidelines (Ref. 1), and its referenced EPRI Guidelines, establish the content of the Steam Generator Program. Use of the Steam Generator Program ensures that the inspection is appropriate and consistent with accepted industry practices.

During SG inspections a condition monitoring assessment of the SG tubes is performed. The condition monitoring assessment determines the "as found" condition of the SG tubes. The purpose of the condition monitoring assessment is to ensure that the SG performance criteria have been met for the previous operating period.

The Steam Generator Program determines the scope of the inspection and the methods used to determine whether the tubes contain flaws satisfying the tube plugging criteria. Inspection scope (i.e., which tubes or areas of tubing within the SG are to be inspected) is a function of existing and potential degradation locations. The Steam Generator Program also specifies the inspection methods to be used to find potential degradation. Inspection methods are a function of degradation morphology, non-destructive examination (NDE) technique capabilities, and inspection locations.

Amendment Nos. 278, 278

TS 4.19-2 The Steam Generator Program defines the frequency of SR4.19.A. The frequency is determined by the operational assessment and other limits in the SG examination guidelines (Ref. 7). The Steam Generator Program uses information on existing degradations and growth rates to determine an inspection frequency that provides reasonable assurance that the tubing will meet the SG performance criteria at the next scheduled inspection. In addition, Specification 6.4.Q contains prescriptive requirements concerning inspection intervals to provide added assurance that the SG performance criteria will be met between scheduled inspections. If crack indications are found in any SG tube, the maximum inspection interval for all affected and potentially affected SGs is restricted by Specification 6.4.Q until subsequent inspections s.upport extending the inspection interval.

SR4.19.B During an SG inspection, any inspected tube that satisfies the Steam Generator Program plugging criteria is removed from service by plugging. The tube plugging criteria delineated in Specification 6.4.Q are intended to ensure that tubes accepted for continued service satisfy the SG performance criteria with allowance for error in the flaw size measurement and for future flaw growth. In addition, the tube plugging criteria, in conjunction with other elements of the Steam Generator Program, ensure that the SG performance criteria will continue to be met until the next inspection of the subject tube(s). Reference 1 and Reference 7 provide guidance for performing operational assessments to verify that the tubes remaining in service will continue to meet the SG performance criteria.

The frequency of prior to Tavg exceeding 2000 P following a SG inspection ensures that the Surveillance has been completed and all tubes meeting the plugging criteria are plugged prior to subjecting the SG tubes to significant primary to secondary pressure differentiaL Amendment Nos. 278, 278

TS 4.19-2a REFERENCES

1. NEI 97-06, "Steam Generator Program Guidelines."
2. 10 CFR 50 Appendix A, GDC 19.
3. 10 CFR 50.67.
4. Regulatory Guide 1.183, "Alternative Radiological Source Tenns for Evaluating Design Basis Accidents at Nuclear Power Reactors," July 2000.
5. ASME Boiler and Pressure Vessel Code, Section ill, Subsection NB.
6. Draft Regulatory Guide 1.121, "Basis for Plugging Degraded Steam Generator Tubes," August 1976.
7. EPRI, "Pressurized Water Reactor Steam Generator Examination Guidelines."

Amendment Nos. 278, 278

TS 6.4-11 Q. Stearn Generator (SG) Program A Stearn Generator Program shall be established and implemented to ensure that SG tube integrity is maintained. In addition, the Stearn Generator Program shall include the following:

1. Provisions for condition monitoring assessments. Condition monitoring assessment means an evaluation of the "as found" condition of the tubing with respect to the performance criteria for structural integrity and accident induced leakage. The "as found" condition refers to the condition of the tubing during an SG inspection outage, as determined from the inservice inspection results or by other means, prior to the plugging of tubes. Condition monitoring assessments shall be conducted during each outage during which the SG tubes are inspected or plugged to confirm that the performance criteria are being met.
2. Performance criteria for SG tube integrity. SG tube integrity shall be maintained by meeting the performance criteria for tube structural integrity, accident induced leakage, and operational LEAKAGE.
a. Structural integrity performance criterion: All in-service stearn generator tubes shall retain structural integrity over the full range of normal operating conditions (including startup, operation in the power range, hot standby, and cool down), all anticipated transients included in the design specification, and design basis accidents. This includes retaining a safety factor of 3.0 against burst under normal steady state full power operation primary to secondary pressure differential and a safety factor of 1.4 against bun~t applied to the design basis accident primary to secondary pressure differentials. Apart from the above requirements, additional loading conditions associated with the design basis accidents, or combination of accidents in accordance with the design and licensing basis, shall also be evaluated to determine if the associated loads contribute significantly to burst or collapse. In the assessment of tube integrity, those loads that do significantly affect burst or collapse shall be determined and assessed in combination with the loads due to pressure with a safety factor of 1.2 on the combined primary loads and 1.0 on axial secondary loads.
b. Accident induced leakage performance criterion: The primary to secondary accident induced leakage rate for any design basis accident, other than a SG tube rupture, shall not exceed the leakage rate assumed in the accident analysis in terms of total leakage rate for all SGs and leakage rate for an individual SG.

Leakage is not to exceed I gpm for aU SG.

Amendment Nos. 278, 278

.TS 6.4-12

c. The operational LEAKAGE perfonnance criterion is specified in TS 3.1.C and 4.13, "RCS Operational LEAKAGE."
3. Provisions for SG tube plugging criteria. Tubes found by inservice inspection to contain flaws with a depth equal to or exceeding 40% of the nominal tube wall thickness shall be plugged.

The following alternate tube plugging criteria shall be applied as an alternative to the 40% depth-based criteria:

a. Tubes with service-induced flaws located greater than 17.89 inches below the top of the tubesheet do not require plugging. Tubes with service-induced flaws located in the portion ofthe tube from the top of the tubesheet to 17.89 inches below the top of the tubesheet shall be plugged upon detection.
4. Provisions for SG tube inspections. Periodic SG tube inspections shall be performed. The number and portions of the tubes inspected and methods of inspection shall be perfonned with the objective of detecting flaws of any type (e.g., volumetric flaws, axial and circumferential cracks) that may be present along the length of the tube, from the tube-to-tubesheet weld at the tube inlet to the tube-to-tubesheet weld at the tube outlet, and that may satisfy the applicable tube plugging criteria. Portions of the tube greater than 17.89 inches below the top of the tube sheet are excluded from this requirement. The tube-to-tubesheet weld is not part of the tube. In addition to meeting the requirements of 4.a, 4.b, and 4.c below, the inspection scope, inspection methods, and inspection intervals shall be such as to ensure that SO tube integrity is maintained until the next SO inspection.

A degradation assessment shall be perfonned to detennine the type and location of flaws to which the tubes may be susceptible and, based on this assessment, to detennine which inspection methods need to be employed and at what locations.

a. Inspect 100% of the tubes in each SG during the first refueling outage following SO installation.

Amendment Nos. 278, 278

TS 6.4-13

b. After the first refueling outage following SO installation, inspect each SO at least every 48 effective full power months or at least every other refueling outage (whichever results in more frequent inspections). In addition, the minimum number of tubes inspected at each scheduled inspection shall be the number of tubes in all SOs divided by the number of SO inspection outages scheduled in each inspection period as defined in b.l. b.2, and b.3 below. If a degradation assessment indicates the potential for a type of degradation to occur at a location not previously inspected with a technique capable of detecting this type of degradation at this location and that may satisfy the applicable tube plugging criteria. the minimum number of locations inspected with such a capable inspection technique during the remainder of the inspection period may be prorated. The fraction of locations to be inspected for this potential type of degradation at this location at the end of the inspection period shall be no less than the ratio of the number of times the SO is scheduled to be inspected in the inspection period after the determination that a new form of degradation could potentially be occurring at this location divided by the total number of times the SO is scheduled to be inspected in the inspection period. Each inspection period defined below may be extended up to 3 effective full power months to include a SO inspection outage in an inspection period and the subsequent inspection outage in an inspection period and the subsequent period begins at the conclusion of the included SO inspection outage.

J. After the first refueling outage following SO installation, inspect 100% of the tubes during the next 120 effective full power months. This constitutes the first inspection period;

2. During the next 96 effective full power months. inspect 100% of the tubes.

This constitutes the second inspection period; and

3. During the remaining life of the SOs, inspect 100% of the tubes every 72 effective full power months. This constitutes the third and subsequent inspection periods.

Amendment Nos.278 , 278

TS 6.4-13a

c. If crack indications are found in the portions of the SG tube not excluded above, then the next inspection for each affected and potentially affected SG for the degradation mechanism that caused the crack indication shall not exceed 24 effective full power months or one refueling outage (whichever results in more frequent inspections). If definitive information, such as from examination of a pulled tube, diagnostic non-destructive testing, or engineering evaluation indicates that a crack-like indication is not associated with a crack(s), then the indication need not be treated as a crack.
5. Provisions for monitoring operational primary to secondary LEAKAGE.

Amendment Nos. 278, 278

TS 6.6-3

b. The results of specific activity analysis in which the primary coolant exceeded the limits of Specification 3.1.D.4. In addition, the information itemized in Specification 3.1.D.4 shah be included in this report.
3. Steam Generator Tube Inspection Report A report shall be submitted within 180 days after Tavg exceeds 2000 P following completion of an inspection performed in accordance with the Specification 6.4.Q, Steam Generator (SG) Program. The report shall include:
a. The scope of inspections performed on each SG,
b. Degradation mechanisms found,
c. Nondestructive examination techniques utilized for each degradation mechanism,
d. Location, orientation (if linear), and measured sizes (if available) of service induced indications,
e. Number of tubes plugged during the inspection outage for each degradation mechanism,
f. The number and percentage of tubes plugged to date, and the effective plugging percentage in each steam generator.
g. The results of condition monitoring, inc1uding the results of tube pulls and I

in-situ testing,

h. The primary to secondary LEAKAGE rate observed in each SG (if it is not practical to assign the LEAKAGE to an individual SG, the entire primary to secondary LEAKAGE should be conservatively assumed to be from one SG) during the cycle preceding the inspection which is the subject of the report, Amendment Nos. 278, 278

TS 6.6-3a

i. The calculated accident induced LEAKAGE rate from the portion of the tubes below 17.89 inches from the top ofthe tubesheet for the most limiting accident in the most limiting SG. In addition, if the calculated accident induced LEAKAGE rate from the most limiting accident is less than 1.80 times the maximum operational primary to secondary LEAKAGE rate, the report should*

describe how it was determined. and

. j. The results of the monitoring for tube axial displacement (slippage). If slippage is discovered, the implications of the discovery and corrective action shall be provided.

Amendment Nos. 278, 278

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 278 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-32 AND AMENDMENT NO. 278 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-37 VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION, UNIT NOS. 1 AND 2 DOCKET NOS. 50-280 AND 50-281

1.0 INTRODUCTION

By letter dated July 31,2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12222A340), as supplemented by letter dated November 6, 2012 (ADAMS Accession No. ML12319A006), Virginia Electric and Power Company (the licensee) submitted a request for changes to the Surry Power Station, Unit Nos. 1 and 2 (Surry 1/2),

Technical Specifications (TSs). The requested changes would revise Limiting Condition for Operation (LCO) 3.1.H, "Steam Generator (SG) Tube Integrity," TS 6.4.Q, "Steam Generator (SG)

Program," and TS 6.6.A.3, "Steam Generator Tube Inspection Report," and include TS Bases changes that summarize and clarify the purpose of the TS in accordance with TS Task Force Traveler {TSTF)-510, "Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection."

The supplement dated November 6, 2012, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the staff's original proposed no significant hazards consideration determination.

The licensee stated that the license amendment request (LAR) is consistent with the Notice of Availability of TSTF-51 0, Revision 2, announced in the Federal Register on October 27, 2011 (72 FR 66763) as part of the consolidated line item improvement process.

The current STS requirements in the above specifications were established in May 2005 with the NRC staff's approval of TSTF-449, Revision 4, "Steam Generator Tube Integrity" {U.S. Nuclear Regulatory Commission (NRC) Federal Register Notice of Availability (70 FR 24126>>. The TSTF-449 changes to the STS incorporated a new, largely performance-based approach for ensuring the integrity of the SG tubes is maintained. The performance-based requirements were supplemented by prescriptive requirements relating to tube inspections and tube repair limits to ensure that conditions adverse to quality are detected and corrected on a timely basis. As of

-2 September 2007, the TSTF-449, Revision 4, changes were adopted in the plant TS for all pressurized water reactors (PWRs).

The proposed changes in TSTF-51 0, Revision 2, reflects the licensees' early implementation experience with respect to the TSTF-449, Revision 4. TSTF-510 characterizes the changes as editorial corrections, changes, and clarifications intended to improve internal consistency, consistency with implementing industry documents, and usability without changing the intent of the requirements. The proposed changes are an improvement to the existing SG inspection requirements and continue to provide assurance that the plant licensing basis will be maintained between SG inspections.

2.0 REGULATORY EVALUATION

The SG tubes in PWRs have a number of important safety functions. These tubes are an integral part of the reactor coolant pressure boundary (RCPB) and, as such, are relied upon to maintain primary system pressure and inventory. As part of the RCPB, the SG tubes are unique in that they are also relied upon as a heat transfer surface between the primary and secondary systems such that residual heat can be removed from the primary system and are relied upon to isolate the radioactive fission products in the primary coolant from the secondary system. In addition, the SG tubes are relied upon to maintain their integrity to be consistent with the containment objectives of preventing uncontrolled fission product release under conditions resulting from core damage during severe accidents.

The regulation at Title 10 of the Code of Federal Regulations (10 CFR) establishes the requirements with respect to the integrity of the SG tubing. Specifically, the General Design Criteria (GOC) in Appendix A to 10 CFR Part 50 state that the RCPB shall have "an extremely low probability of abnormalleakage ... and of gross rupture" (GOC 14), "shall be designed with sufficient margin" (GOC 15 and 31), shall be of "the highest quality standards practical" (GOC 30),

and shall be designed to permit "periodic inspection and testing ... to assess ... structural and leaktight integrity" (GOC 32).

The General Design Criteria (GOC) included in Appendix A to 10 CFR Part 50 did not become effective until February 20, 1971. The Construction Permits for SPS Units 1 and 2 were issued prior to February 20, 1971; consequently, these units were not subject to GOC requirements.

Section 1.4, "Compliance with Criteria" of the Updated Final Safety Analysis Report (UFSAR) discusses the design of the station relative to the design criteria published in 1971. However, the following information demonstrates compliance with GOC 14,15,30,31, and 32 of 10 CFR 50, Appendix A:

  • UFSAR Section 1.4.1, "Quality Standards" states that the systems and components of reactor facilities that are essential to the prevention of accidents that could affect the public health and safety or to the mitigation of their consequences are designed, fabricated, and erected in accordance with quality standards that reflect the importance of the safety function to be performed.
  • UFSAR Section 1.4.9, "Reactor Coolant Pressure Boundary" states that the RCPB is designed, fabricated, and constructed so as to have an exceedingly low probability of gross rupture or significant uncontrolled leakage throughout its design lifetime.

-3

  • UFSAR Section 1.4.33, "Reactor Coolant Pressure Boundary Capability" states that the RPCB is capable of accommodating without rupture the static and dynamic loads imposed on any boundary component as a result of an inadvertent and sudden release of energy to the coolant.
  • UFSAR Section 1.4.34, "Reactor Coolant Pressure Boundary Rapid Propagation Failure Prevention" states that the RCPB is designed and operated to reduce to an acceptable level the probability of a rapidly propagating failure.
  • UFSAR Section 1.4.36, "Reactor Coolant Pressure Boundary Surveillance" states that the RCPB components have provisions for the inspection, testing, and surveillance of critical areas by appropriate means to assess the structural and leaktight integrity of the boundary components during their service lifetime.

To this end, 10 CFR 50.55a specifies that components which are part of the RCPB must meet the requirements for Class 1 components in Section III of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code). Section 50.55a further requires, in part, that throughout the service life of a PWR facility, ASME Code Class 1 components meet the requirements, except design and access provisions and pre-service examination requirements, in Section XI, "Rules for Inservice Inspection [(lSI)] of Nuclear Power Plant Components," of the ASME Code, to the extent practical. This requirement includes the inspection and repair criteria of Section XI of the ASME Code.

The regulation at 10 CFR 50.36, "Technical Specifications," establishes the requirements related to the content of the TS. Pursuant to 10 CFR 50.36, TSs are required to include items in the following five categories related to station operation: (1) safety limits, limiting safety system settings, and limiting control settings; (2) LCOs; (3) SRs; (4) design features; and (5) administrative controls. LCOs and accompanying action statements and SRs in the STS relevant to SG tube integrity are in TS 3.4.13, "RCS [reactor coolant system] Operational Leakage," and Specification [3.4.17], "Steam Generator (SG) Tube Integrity." The SRs in the "Steam Generator (SG) Tube Integrity" specification reference the SG Program which is defined in the STS administrative controls.

The regulation at 10 CFR 50.36(c)(5) defines administrative controls as "the provisions relating to organization and management, procedures, recordkeeping, review and audit, and reporting necessary to assure the operation of the facility in a safe manner." Programs established by the licensee to operate the facility in a safe manner, including the SG Program, are listed in the administrative controls section of the TS. The SG Program is defined in TS 6.4.0, while the reporting requirements relating to implementation of the SG Program are in TS 6.6.A.3.

TS 6.4.0 requires that an SG Program be established and implemented to ensure that SG tube integrity is maintained. SG tube integrity is maintained by meeting the performance criteria specified in TS 6.4.0.2 for structural and leakage integrity, consistent with the plant design and licensing basis. TS 6.4.0.1 requires that a condition monitoring assessment be performed during each outage in which the SG tubes are inspected, to confirm that the performance criteria are being met. TS 6.4.0.4 includes provisions regarding the scope, frequency, and methods of SG tube inspections. These provisions require that the inspections be performed with the objective of detecting flaws of any type that (1) may be present along the length of a tube, from the tube-to-tubesheet weld at the tube inlet to the tube-to-tubesheet weld at the tube outlet {portions

-4 of the tube greater than 17.89 inches below the top of the tubesheet are excluded from this requirement), and (2) may satisfy the applicable tube repair criteria. The applicable tube repair criteria, specified in TS 6.4.Q.3., are that tubes found during lSI to contain flaws with a depth equal to or exceeding 40 percent of the nominal wall thickness shall be plugged, unless the tubes are permitted to remain in-service through application of the alternate repair criteria provided in TS 6.4.Q.3.a.

3.0 TECHNICAL EVALUATION

Each proposed change to the TS is described individually below, followed by the NRC staff's assessment of the change.

3.1 Technical Specification 6AQ, "Steam Generator (SG) Program" Proposed Change: The last sentence of the introductory paragraph currently states: "In addition, the Steam Generator Program shall include the following provisions." The change would delete the word "provisions" such that the sentence would state: "In addition, the Steam Generator Program shall include the following." The basis for this change is that subsequent paragraphs in TS 6.4.Q start with "Provisions for ... " and the word "provisions" in the introductory paragraph is duplicative.

Assessment: The NRC staff has reviewed TS 6.4.Q and agrees that the word, "provisions," in the introductory paragraph is duplicative. The NRC staff agrees that the change is administrative in nature, and therefore is acceptable.

3.2 Paragraph 6AQ.2, "Structural integrity performance criterion" The first sentence currently states: "All in-service steam generator tubes shall retain structural integrity over the full range of normal operating conditions (including startup, operation in the power range, hot standby, and cool down, and all anticipated transients included in the design specification) and design basis accidents".

Proposed Change: Revise the sentence as follows:

All in-service steam generator tubes shall retain structural integrity over the full range of normal operating conditions (including startup, operation in the power range, hot standby, and cool down),

all anticipated transients included in the design specification, and design-basis accidents.

The basis for the change is that this sentence inappropriately includes anticipated transients in the description of normal operating conditions.

Assessment: The NRC staff agrees the current wording is incorrect and that anticipated transients should be differentiated from normal operating conditions. Therefore, the NRC staff finds the change acceptable.

-5 3.3. Paragraph 6.4.Q.3, "Provisions for SG tube repair criteria," Paragraph 6.4.Q.4, "Provisions for SG tube inspections," LCO 3.1.H, "Steam Generator (SG) Tube Integrity," SR 4.19, "Steam Generator (SG) Tube Integrity" Proposed Change: Change all references to "tube repair criteria" to "tube plugging criteria." This change is intended to be consistent with the treatment of SG tube repair throughout TS 6.4.Q.

Assessment: The NRC staff finds that the proposed change provides a more accurate label of the criteria and, therefore, adds clarity to the specification. This is because one of two actions must be taken when the criteria are exceeded. One action is to remove the tube from service by plugging the tube at both tube ends. The alternative action is to repair the tube, but only if such a repair is permitted by paragraph 6.4.Q.3. Therefore, the NRC staff finds the change acceptable.

3.4 Paragraph 6.4.Q.4, "Provisions for SG tube inspections" Proposed Change: Change the term "assessment of degradation" to "degradation assessment" to be consistent with the terminology used in industry program documents.

Assessment: The NRC staff agrees that the terminology should be consistent and finds the change acceptable.

3.5 Paragraph 6.4.Q.4.a Proposed change: The paragraph currently states: "Inspect 100% of the tubes in each SG during the first refueling outage following SG replacement." The change would replace "SG replacement" with "SG installation." The basis for the change is that it will allow the SG Program to apply to both existing plants and new plants.

Assessment: The NRC staff agrees the SG Program can apply to both existing and new plants.

Therefore, the NRC staff finds the change acceptable.

3.6 Paragraph 6.4.Q.4.b for plants with SGs with alloy 600 thermally treated (TT) tubes The paragraph currently states:

Inspect 100% of the tubes at sequential periods of 120, 90, and, thereafter, 60 effective full power months. The first sequential period shall be considered to begin after the first inservice inspection of the SGs. In addition, inspect 50% of the tubes by the refueling outage nearest the midpoint of the period and the remaining 50% by the refueling outage nearest the end of the period. No SG shall operate for more than 48 effective full power months or two refueling outages (whichever is less) without being inspected.

-6 Proposed Change: Revise paragraph 6A.QA.b as follows:

After the first refueling outage following SG installation, inspect each SG at least every 48 effective full power months or at least every other refueling outage (whichever results in more frequent inspections). In addition, the minimum number of tubes inspected at each scheduled inspection shall be the number of tubes in all SGs divided by the number of SG inspection outages scheduled in each inspection period as defined in b.1, b.2, and b.3 below. If a degradation assessment indicates the potential for a type of degradation to occur at a location not previously inspected with a technique capable of detecting this type of degradation at this location and that may satisfy the applicable tube plugging criteria, the minimum number of locations inspected with such a capable inspection technique during the remainder of the inspection period may be prorated. The fraction of locations to be inspected for this potential type of degradation at this location at the end of the inspection period shall be no less than the ratio of the number of times the SG is scheduled to be inspected in the inspection period after the determination that a new form of degradation could potentially be occurring at this location divided by the total number of times the SG is scheduled to be inspected in the inspection period. Each inspection period defined below may be extended up to 3 effective full power months to include a SG inspection outage in an inspection period and the subsequent inspection period begins at the conclusion of the included SG inspection outage.

1) After the first refueling outage following SG installation, inspect 100% of the tubes during the next 120 effective full power months. This constitutes the first inspection period;
2) During the next 96 effective full power months, inspect 100% of the tubes.

This constitutes the second inspection period; and

3) During the remaining life of the SGs, inspect 100% of the tubes every 72 effective full power months. This constitutes the third and subsequent inspection periods.

Assessment: Paragraph 6.4.QA.b in its current form and with the proposed changes is similar for each of the tube alloy types, but with differences that reflect the improved resistance of alloy 600 TT to stress corrosion cracking relative to alloy 600 MA and the improved resistance of alloy 690 TT relative to both alloy 600 MA and alloy 600 TT. These differences include progressively larger maximum inspection interval requirements and sequential inspection periods (during which 100%

of the tubes must be inspected) for alloy 600 MA, 600 TT, and alloy 690 TT tubes, respectively. In addition, because of the longer maximum inspection intervals allowed for alloy 600 TT and 690 TT tubes, paragraph 6A.QA.b includes a restriction on the distribution of sampling over each sequential inspection period for alloy 600 TT and 690 TT tubes that is not included for alloy 600 MA tubes.

For SGs with alloy 600 TT tubing, the licensee proposes to move the first two sentences of paragraph 6.4.QA.b to the end of the paragraph and make editorial changes to improve clarity.

The NRC staff finds these changes to be of a clarifying nature, not changing the current intent of these two sentences. However, the LAR also includes two changes to when inspections are performed as follows:

  • The second inspection period would be revised from 90 to 96 EFPM.

-7

  • The third and subsequent inspection periods would be revised from 60 to 72 EFPM.

The licensee characterizes these changes as marginal increases for consistency with typical fuel cycle lengths that better accommodate the scheduling of inspections. The NRC staff notes that plants with alloy 600 IT SG tubes typically inspect at 18- or 36-month intervals (one or two fuel cycles, respectively) depending on whether stress corrosion crack activity was observed during the most recent inspection. With these intervals, the last scheduled inspection during the first inspection period would occur at 108 months after the first refueling outage following SG installation. This is 12 months before the end of the first 120 EFPM inspection period. However, with the proposed changes to the length of the second and subsequent inspection periods, the NRC staff finds that the last scheduled inspections in the second and subsequent inspection periods will coincide exactly with the end of these periods.

The proposed changes would generally increase the number of inspections in each of the second and subsequent inspection periods by up to one additional inspection. This could reduce the required average minimum sample size during these periods. However, inspection sample sizes will continue to be subject to paragraph 6.4.0.4 which states that in addition to meeting the requirements of paragraphs 6.4.0.4.a, 4.b, and 4.c, the inspection scope, inspection methods, and inspection intervals shall be such as to ensure SG tube integrity is maintained until the next scheduled inspection. Therefore, the NRC staff concludes that with the proposed changes to the length of the second and subsequent inspection periods, compliance with the SG program requirements in TS 6A.0 will continue to ensure both adequate inspection scopes and tube integrity.

For each inspection period, paragraph 6A.OA.b currently requires that at least 50 percent of the tubes be inspected by the refueling outage nearest to the mid-point of the inspection period and the remaining 50 percent by the refueling outage nearest the end of the inspection period. The NRC staff notes that if there are not an equal number of inspections in the first half and second half of the inspection period, the average minimum sampling requirement may be markedly different for inspections in the first half of the inspection period compared to those in the second half, even when there are uniform intervals between each inspection. For example, a plant in the first (120 EFPM) inspection period with a scheduled 36-month interval (two fuel cycles) between each inspection would currently be required to inspect 50 percent of the tubes by the refueling outage nearest the midpoint of the inspection which would be the third refueling outage in the period, six months before the mid-point. However, since no inspection is scheduled for that outage, then the full 50 percent sample must be performed during the inspection scheduled for the second refueling outage in the period. Two inspections would be scheduled to occur in the second half of the inspection period, at 72 and 108 months into the inspection period. Thus, the current sampling requirement could be satisfied by performing a 25 percent sample during each of these inspections or other combinations of sampling (e.g., 10 percent during one and 40 percent in the other) totaling 50 percent. The NRC staff finds there is no basis to require the minimum initial sample size to vary so much from inspection to inspection. The licensee proposes to revise this requirement such that the minimum sample size for a given inspection in a given inspection period is 100 percent divided by the number of scheduled inspections during that inspection period. For the above example, the proposed change would result in a uniform initial minimum sample size of 33.3 percent for each of the three scheduled inspections during the inspection period. The NRC staff concludes this proposed revision to be an improvement to the existing requirement since it provides a more consistent minimum initial sampling requirement.

-8 The proposed changes to parqgraph 6.4.0.4.b include two new sentences addressing the prorating of required tube sample sizes if a degradation assessment indicates the potential for a type of degradation to occur at a location not previously inspected with a technique capable of detecting this type of degradation at this location and that may satisfy the applicable tube plugging criteria. For example, new information from another similar plant becomes available indicating the potential for circumferential cracking at a specific location on the tube. Previous degradation assessments had not identified the potential for this type of degradation at this location. Thus, previous inspections of this location had not been performed with a technique capable of detecting circumferential cracks. However, now that the potential for circumferential cracking has been identified at this location, paragraph 6.4.0.4 requires a method of inspection to be performed with the objective of detecting circumferential cracks which may be present at this location and that may satisfy the applicable tube plugging criteria. Suppose this inspection is performed for the first time during the third of four SG inspections scheduled for one of the inspection periods. Paragraph 6.4.0.4.b currently does not specifically specify whether this location needs to be 100 percent inspected by the end of the inspection period, or whether a prorated approach may be taken. The NRC staff addressed this question in Issue 1 of NRC Regulatory Information Summary (RIS) 2009-04, "Steam Generator Tube Inspection Requirements," dated April 3, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML083470557), as follows:

Issue 1: A licensee may identify a new potential degradation mechanism after the first inspection in a sequential period. If this occurs, what are the expectations concerning the scope of examinations for this new potential degradation mechanism for the remainder of the period (e.g., do 100 percent of the tubes have to be inspected by the end of the period or can the sample be prorated for the remaining part of the period)?

[NRC Staff Position:] The TS contain requirements that are a mixture of prescriptive and performance-based elements. Paragraph "d" of these requirements indicates that the inspection scope, inspection methods, and inspection intervals shall be sufficient to ensure that SG tube integrity is maintained until the next SG inspection. Paragraph "d" is a performance-based element because it describes the goal of the inspections but does not specify how to achieve the goal. However, paragraph "d.2" is a prescriptive element because it specifies that the licensee must inspect 100 percent of the tubes at specified periods.

If an assessment of degradation performed after the first inspection in a sequential period results in a licensee concluding that a new degradation mechanism (not anticipated during the prior inspections in that period) may potentially occur, the scope of inspections in the remaining portion of the period should be sufficient to ensure SG tube integrity for the period between inspections.

In addition, to satisfy the prescriptive requirements of paragraph "d.2" that the licensee must inspect 100 percent of the tubes within a specified period, a prorated sample for the remaining portion of the period is appropriate for this potentially new degradation mechanism. This prorated sample should be such that if the licensee had implemented it at the beginning of the period, the TS requirement for the 100 percent inspection in the entire period (for this degradation mechanism) would

-9 have been met. A prorated sample is appropriate because (1) the licensee would have performed the prior inspections in this sequential period consistently with the requirements, and (2) the scope of inspections must be sufficient to ensure that the licensee maintains SG tube integrity for the period between inspections.

The NRC staff finds that proposed Sentences 4 and 5 clarify the existing requirement consistent with the NRC staffs position from RIS 2009-04 quoted above and are, therefore, acceptable.

The proposed fifth sentence in paragraph 6.4.Q.4.b states, "Each inspection period defined below may be extended up to 3 effective full power months to include a SG inspection outage in an inspection period and the subsequent inspection period begins at the conclusion of the included SG inspection outage." Allowing extension of the inspection periods by up to an additional 3 EFPM potentially impacts the average tube inspection sample size to be implemented during a given inspection in that period. For example, if three SG inspections are scheduled to occur within the nominal 60 EFPM period, the minimum sample size for each of the three inspections could average as little as 33.3 percent of the tube population. If a fourth inspection can be included within the period by extending the period by 3 EFPM, then the minimum sample size for each of the four inspections could average as little as 25 percent of the tube population. Since the subsequent period begins at the end of the included SG inspection outage, the proposed change does not impact the required frequency of SG inspection.

Required tube inspection sample sizes are also subject to the performance-based requirement in paragraph 6.4.Q.4, which states, in part, that in addition to meeting the requirements of paragraph 6.4.Q.4.a, 4.b, and 4.c, "the inspection scope, inspection methods, and inspection intervals shall be such as to ensure that SG tube integrity is maintained until the next SG inspection." This requirement remains unchanged under the proposal. The NRC staff concludes the proposed fifth sentence, by allowing the potential for smaller sample sizes, involves only a relatively minor relaxation to the existing sampling requirements in paragraph 6.4.Q.4.b. However, the performance-based requirements in 6.4.Q.4 ensure that adequate inspection sampling will be performed to ensure tube integrity is maintained. Thus, the NRC staff concludes that the proposed change is acceptable.

Finally, the first sentence of the proposed revision to paragraph 6.4.Q.4.b replaces the last sentence of the current paragraph 6.4.Q.4.b. This sentence establishes the minimum allowable SG inspection frequency as at least every 48 EFPM or at least every other refueling outage (whichever results in more frequent inspections). This minimum inspection frequency is unchanged from the current sentence. The NRC staff finds that the wording changes in the sentence are of an editorial and clarifying nature and are not material, such that the current intent of the requirement is unchanged. Thus, the NRC staff concludes the first sentence of proposed paragraph 6.4.Q.4.b is acceptable.

3.7 Paragraph 6.4.Q.4.c (for plants with SG tubing fabricated from alloy 600 TT)

The first sentence of paragraph 6.4.Q.4.c currently states:

If crack indications are found in the portions of the SG tube not excluded above, then the next inspection for each SG for the degradation mechanism that caused the crack indication shall not exceed 24 effective full power months or one refueling outage (whichever is less).

- 10 Proposed Change: Revise this sentence as follows:

If crack indications are found in the portions of the SG tube not excluded above, then the next inspection for each affected and potentially affected SG for the degradation mechanism that caused the crack indication shall not exceed 24 effective full power months or one refueling outage (whichever results in more frequent inspections).

The proposed change is replacing the words "for each SG" with the words "for each affected and potentially affected SG. The licensee states that the existing wording can be misinterpreted. The licensee further states that the intention is that those SGs that are affected and those SGs that are potentially affected must be inspected for the degradation mechanism that caused the crack indication. However, some licensees have questioned whether the current reference to "each SG" requires only the SGs that are affected to be inspected for the degradation mechanism. The proposed revision is intended to clarify the intent of the requirement.

Assessment: Paragraph 6A.OA.b permits SG inspection intervals to extend over multiple fuel cycles for SGs with alloy 600 TT tubing, assuming that such intervals can be implemented while ensuring tube integrity is maintained in accordance with paragraph 6A.OA. However, stress corrosion cracks may not become detectable by inspection until the crack depth approaches the tube repair limit. In addition, stress corrosion cracks may exhibit high growth rates. For these reasons, once cracks have been found in any SG tube, paragraph 6.4.0.4.c restricts the allowable interval to the next scheduled inspection to 24 EFPM or one refueling outage (whichever is less). The intent of this requirement is that it applies to the affected SG and to any other SG which may be potentially affected by the degradation mechanism that caused the known crack(s). For example, a root cause analysis in response to the initial finding of one or more cracks might reveal that the crack(s) are associated with a manufacturing anomaly which causes locally high residual stress which in turn caused the early initiation of cracks at the affected locations. If it can be established that the extent of condition of the manufacturing anomaly applies only to one SG and not the others, then the NRC staff agrees that only the affected SG needs to be inspected within 24 EFPM or one refueling cycle in accordance with paragraph 6.4.0A.b. The next scheduled inspections of the other SGs will continue to be subject to all other provisions of paragraph 6.4.0A. The NRC staff finds the proposed change to paragraph 6.4.0.4.c acceptable, because it clarifies the intent the paragraph.

3.8 TS 6.6.A.3, "Steam Generator Inspection Report" This specification lists items a. through k. to be included in a report which shall be submitted within 180 days after Tavg exceeds 200°F following completion of an inspection performed in accordance with the TS 6.4.0, "Steam Generator (SG) Program."

Proposed Change: Item b. currently reads: "Active degradation mechanisms found ... " to be revised to read: "Degradation mechanisms found ..."

Item e. currently reads: "Number of tubes plugged during the inspection outage for each active degradation mechanism ... " to be revised to read: "Number of tubes plugged during the inspection outage for each degradation mechanism ... "

- 11 Item f. currently reads, "Total number and percentage of tubes plugged to date ... " to be revised to read: "The number and percentage of tubes plugged to date, and the effective plugging percentage in each steam generator. .."

Item h. currently reads: 'The effective plugging percentage for all plugging in each SG," which will be deleted.

Assessment: This proposal would delete the word "Active" in items b. and e above. Thus, all degradation mechanisms found, whether deemed to be active or not, would now be reportable.

The NRC staff finds the proposed change acceptable. The proposal to combine items f. and h. is an editorial change that does not materially change the reporting requirements. The NRC staff finds this change acceptable.

4.0 STATE CONSULTATION

In accordance with the Commission's regulations, the Virginia State official was notified of the proposed issuance of the amendments. The State official had no comments.

5.0 ENVIRONMENTAL CONSIDERATION

The amendments change requirements with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendments involve no significant increase in the amounts and no significant change in the types of any effluents that may be released offsite and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration, and there has been no public comment on such finding (77 FR 63351). Accordingly, the amendments meet the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.

6.0 CONCLUSION

The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) there is reasonable assurance that such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public.

Principal Contributor: K. Bucholtz Date: January 28, 2013

Mr. David A. Heacock January 28, 2013 President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

SURRY POWER STATION, UNIT NO.1 AND 2 ISSUANCE OF AMENDMENTS TO ADOPT TECHNICAL SPECIFICATION TASK FORCE (TSTF) 510, REVISION 2, REVISION TO STEAM GENERATOR PROGRAM INSPECTION FREQUENCIES AND TUBE SAMPLE SELECTION (TAC NO. ME9199 AND ME9200)

Dear Mr. Heacock:

The U.S. Nuclear Regulatory Commission has issued the enclosed Amendment No. 278 to Renewed Facility Operating License No. DPR-32 and Amendment No. 278 to Renewed Facility Operating License No. DPR-37 for the Surry Power Station, Unit Nos. 1 and 2, respectively. The amendments change the Technical Specifications (TSs) in response to your application dated July 31,2012, as supplemented by letter dated November 6,2012.

These amendments revise Limiting Condition for Operation (LCO) 3.1.H, "Steam Generator (SG)

Tube Integrity," TS 6.4.Q, "Steam Generator (SG) Program," and TS 6.6.A.3, "Steam Generator Tube Inspection Report," and include TS Bases changes that summarize and clarify the purpose of the TS in accordance with TS Task Force Traveler (TSTF) 510, "Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection."

A copy of the Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's biweekly Federal Register notice.

Sincerely, IRA!

Karen Cotton, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-280 and 50-281

Enclosures:

1. Amendment No. 278 to DPR-32
2. Amendment No. 278 to DPR-37
3. Safety Evaluation cc w/encls: Distribution via Listserv DISTRIBUTION:

Public RidsNrrLASFigueroa Resource RidsNrrDirsltsb Resource LPL2-1 RlF RidsOgcRp Resource RidsRgn2MailCenter Resource RidsNrrDorlLpl2-1 Resource RidsAcrsAcnw_MailCTR Resource RidsNrrDorlDpr Resource RidsNrrPMSurry Resource RidsNrrDeEsgb Resource KBucholtz, NRR ADAMS Accession No. ML13018A086 NRR/LPL2-1/LA OGC NLO DIRS/ITSB/BC NRR/LPL2-1/BC SFi ueroa BHarris RElliott RPascarelli 1/23/13 1/24/13 11/20/12 1/28/13 OFFICIAL RECORD COpy