ML12342A113
| ML12342A113 | |
| Person / Time | |
|---|---|
| Site: | Limerick |
| Issue date: | 11/06/2012 |
| From: | Schlaseman C Exelon Generation Co, MPR Associates |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| RS-12-171 MPR-3796, Rev 1 | |
| Download: ML12342A113 (40) | |
Text
Sheet 1 of 2 Status:& N U Seismic Walkdown Checklist (SWC)
Equipment ID No. 1DDI03 /
Equip. Class" (14) Batte Charers and Invertcrs Equipment Description 125 VDC Batter Charger Location: Bldg. Control Floor El. 217 Room, Area Room 323 Structure Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results ofjudgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorane
- 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
fý-e-#rZ-35 2106 C'-63Z 96C- '149/
- 2. Is the anchorage free of bent, broken, missing or loose hardware?
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
- 4. Is the anchorage free of visible cracks in the concrete near the anchors?
YX NEI YP ND UE N/AD YKND UD N/AD-YA NO UD N/AD
- 5. Is the anchorage configuration consistent with plant documentation?
Yf NI] U-N/A]
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration venrficationomi) q*d0, Dc &
- 6.
e naovef horeu potentially adverse seismic conditions?
12 Enter the equipment class name from Appendix B: Classes of Equipment.
<C-3 >"
Limerick Generating Station Unit 1 MPR-3796, RevisiOn 1 r.nrriqnnndHPnr.p Nn
- RS-19-171 C-252
Sheet 2 of 2 Equipment ID No. IDD103 Equip. Class12 4U4 Batte Chargers and Inverters Equipment Description 125 VDC Batter Charger Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures?
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage?
- 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
.N-L UD N/AOl YND ur-I N/Ao Y0NEI UE N/AD Y1NO UO Other Adverse Conditions
- 11. Have you looked for and found no other seismic conditions that could Yd NO UE adversely affect the safety functions of the equipment?
/
Comments (Additional pages may be added as necessary)
Evaluated by:
Date:
Lo/2274A
< C-4 >
Limerick Generating Station Unit 1 MPR-3796, Revision 1 r.nrrPqnnndP*nrA. Nn' RR-12-171 C-253
Equipment ID: 1DD103 Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrm;nnndPnrA Nn' RR-17-171 C-254
Sheet 1 of 2 Status: (ON U Seismic Walkdown Checklist (SWC)
Equipment ID No. IFV2I I Equip. Class"2 (08) Fans & Air Handlers Equipment Description B Core Spray Pump Room Unit Cooler F Location: Bldg. Reactor Floor El. 177 Room, Area Room 117 Enclosure Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware?
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
- 4. Is the anchorage free of visible cracks in the concrete near the anchors?
- 5. Is the anchorage configuration consistent with plant documentation?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
, MS6Jw On #
~o/-
~())
Rev.
- 6. Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?
-/V'NE]
Y1Z NO U-N/AD YO ND UD N/AD YK NDI UD N/AD YXIN'ND UD N/AD NXIN<DE UDE 12 Enter the equipment class name from Appendix B: Classes of Equipment.
<C-3 >
Limerick Generating Station Unit 1 MPR-3796, Revision 1 r.nrrPgnnndPnrP Nn
- RR-19-171 C-255
Sheet 2 of 2 Equipment ID No. 1FV211 Equip. Class' 2 (08) Fans & Air Handlers Equipment Description B Core Spray Pump Room Unit Cooler F Interaction Effects
- 7. Are soft targets free frpm impact by nearby equipment or structures?
NO-A l
Yh NEI UL N/AD
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y$ NO UD N/AD and masonry block walls not likely to collapse onto the equipment?
FI~t 5 CMt
ýVbE5 frvl'J."
- 9. Do attached lines have adequate flexibility to avoid damage?
- 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
YP NE UD N/AD Yk NEI UO Other Adverse Conditions
- 11. Have you looked for and found no other seismic conditions that could YX ND UD adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
~i-a.j'~1 Evaluiated hv: h'u"
\\j el- ýjiý55Lý Date:
< C-4 >
Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrmnnnrdPnra* Nn " R-12-171 C-256
Equipment ID: 1FV211 p
Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrpf.nnndPnr.P Nn* RR-19-171 C-257
Equipment ID: 1FV211 Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrP.nnndrnrP Nn" RR-19-171 C-258
Equipment ID: 1FV211 Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrE.%nnnrldnrP. Nn
- R.-19-171 C-259
Equipment ID: 1FV211 Limerick Generating Station Unit 1 MPR-3796, Revision 1 r.nrrPnnndP~nr. Nn - RR-12-171 C-260
Sheet 1 of 2 Status:)
N U Seismic Walkdown Checklist.(SWC)
Equipment ID No. FT-5!-IN001 Equip. Class'2 (17) Temperature Sensors/Local Instruments (Not on Racks)
Equipment Description RHR HTX A & Pump A Discharge Flow Location: Bldg. Reactor Floor El. 217 Room, Area Room 304W Enclosure Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchoraae
- 1. Is the anchorage configuration verification required (i.e., is the item one Y)ý NEI of the 50% of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware?
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
Yb ND UD N/AD 14 ND UD N/AD
- 4. Is the anchorage free of visible cracks in the concrete nearthj anchors?
YX NO U"
- 5. Is the anchorage configuration consistent with plant documentation?
Y4 NE UD (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
N/AD N/AD a) Rev. 0)
- 6. Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?
-From~e rov
"~ori 4 z a~
m wlcasanry (C12456) Rev. 0 bwý' #S aw-6-~oR~ev' 0 CO17 aw 12 Enter the equipment class name from Appendix B: Classes of Equipment.
<C-3 >*
Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrmnnndPnr'., Nn
- RR-17-171 C-261
Sheet 2 of 2 Equipment ID No. FT-5 1-INOOI Equip. Class' 2 (17) Temperature Sensors/Local Instruments (Not on Racks)
Equipment Description RHR HTX A & Pump A Discharge Flow Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures?
Yk(ND UO-I N/All
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
odve,'ckwjo&~~ 4,roy o~ec~aa4y 10ad10
- 9. Do attached lines have adequate flexibility to avoid damage?
- 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
YP<ND UD] N/AOl YKND U[I N/AQ YNEI Ur Other Adverse Conditions
- 11. Have you looked for and found no other seismic conditions that could YX NE UD adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
F~no MI1E w,4b jooep r anat'-
10164V y1~
V~n ar) 0 Evaluated by:
1'4MIURF ID V &~R f
Date:
&53c)(
V Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrr,-nnndrnr* Nn
- RR-19-171 C-262
Equipment ID: FT-51-1NO01 Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrP..nnnrlPnr.p Nn - RS-12-171 C-263
Equipment ID: FT-51-1NO01 Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrPnnndrnrP. Nn - RR-12-171 C-264
Equipment ID: FT-51-1NO01 Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrsqnnnrI-nr.* Nn - RR-19-171 C-265
Sheet 1 of 2 Status:
N U Seismic Walkdown Checklist (SWC)
Equipment ID No. HV-01 1-042 Equip. Class12 (05) Fluid (Air/Hyd) Valves Equipment Description HPCI PP RM CLR RET to ESW Loop B Location: Bldg. v Floor El. 177 Room, Area Room 109 Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchoraze
- 1. Is the anchorage configuration verification required (i.e., is the item one YE N, of the 50% of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware?
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
YA ND UQ N/AD Y1, ND UD N/AD
- 4. Is the anchorage free of visible racks in the concrete near the anchors?
YXj NEI
,-moo=4r I a VdWr wloor,,
4_
volu ri
,VOrIye e w oA lb~ 1'vi~
.~
4 corlv 4
UD N/AD
- 5. Is the anchorage configuration consistent with plant documentation?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?
YO NEI UD N/Ag YA NEI UD 12 Enter the equipment class name from Appendix B: Classes of Equipment.
SC-3 >*
Limerick Generating Station Unit 1 MPR-3796, Revision 1 flnrrPnnndpnr'P INn
- R-19-171 C-266
Sheet 2 of 2 Equipment ID No. HV-0 11-042 Equip. Clags1 2 (05) Fluid (Air/Hyd) Valves Equipment Description HPCI PP RM CLR RET to ESW Loop B Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures?
YX NI] U[] N/Al]
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YX NEI UD N/AD and masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage?
Y' NEI UD N/Al
- 10. Based on the above seismic interaction evaluations, is equipment free YX NEI Ul of potentially adverse seismic interaction effects?
0* Clo',ýIcr Y
- 0i IOd-I44 IdIPs'
-6 fleor~irrJ C-rc uA9S Other Adverse Conditions
- 11. Have you looked for and found no other seismic conditions that could Y,
NEI u--
adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
N/A Evaluated by:
zLiY/?.
~
r Date:
/
v-o
/44/
Limerick Generating Station Unit 1 MPR-3796, Revision 1 rn.rrPnnnrIPnr-j Nn R.R-19-171 C-267
Equipment ID: HV-11-042 I
Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrm~nnnrl~nr*P Nn RR-19-171 C-268
Equipment ID: HV-11-042 Limerick Generating Station Unit 1 MPR-3796, Revision 1
,nrrPqnnndlP~nr.p Nn -RS-19-171 C-269
Equipment ID: HV-11-042 Limerick Generating Station Unit 1 MPR-3796, Revision 1 rTnrrPqnnnrl.nr.A Nn - RR-1 9-171 C-270
Sheet 1 of 2 Status: 0 N U Seismic Walkdown Checklist (SWC) os!
Equipment ID No. HLV-"-IF014A Equip. Class12 (06) Motor Operated Valves Equipment Description ]A RHR HTXJRHRSW Inlet Valve Location: Bldg. Reactor Floor El. 201 Room, Area Room 203 Enclosure Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchoraize
- 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware?
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
YOINX Y) NEI UE] N/AE]
Yt NEI U-N/AEJ
- 4. Is the anchorage free of visible cracks in the concrete near the anchors?
Y NEI UE' N/Afl
,Volur vslve onad nc*
else Ner.67 Pee 'ruff afll Aorfcý sl CCemk Are conCrOJV
- 5. Is the anchorage configuration consistent with plant documentation?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?
YE NO] UD N/AN(
YK NO UD 12 Enter the equipment class name from Appendix B: Classes of Equipment.
<C-3 >
Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrP nnndPnPNn*
RR-91-171 C-271
Sheet 2 of 2 o-5i Equipment ID No. HV-'K-IF014A Equip. Class 12 (06) Motor Operated Valves Equipment Description ]A RHR HTXRHRSW Inlet Valve Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures?
.No
£644 --605 Yk NEI UD N/AQ
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YX NEI UO N/AD and masonry block walls not likely to collapse onto the equipment?
.-No ovr eqpyer~iet or b6o4 *0OlS s1 ace
- 9. Do attached lines have adequate flexibility to avoid damage?
- 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
Y)RND] UD] N/AD VgNEI UO Other Adverse Conditions
- 11. Have you looked for and found no other seismic conditions that could Y'X NI UI adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
N/A QVAW qTA-Evaluated by:
'V Date:
Limerick Generating Station Unit 1 MPR-3796, Revision 1 CnrrPq.nnndPnr.P Nn
- RR-19-171 C-272
Equipment ID: HV-051-1FO14A Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrp.nnndipnrp Nn RS-17-171 C-273
Equipment ID: HV-051-1FO14A Limerick Generating Station Unit 1 MPR-3796, Revision 1 rlnrrfp.nnndlPnr.P Nn Rq-1 9-171 C-274
Sheet 1 of 2 Status:0 N U Seismic Walkdown Checklist (SWC)
Equipment ID No. HV-11-104A Equip. Class"2 (05) Fluid (Air/Hyd) Valves Equipment Description RHR PP RM CLR A Su I Valve Location: Bldg. Reactor Floor El. 177 Room, Area Room 102 Enclosure Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is the anchorage configuration verification required (i.e., is the item one YE] N of the 50% of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware?
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
YP NE] UE N/AE]
Y NEI UE N/AE]
- 4. Is the anchorage free of visible cracks in the concrete near the anchors?
Y* NE] UD N/AE]
An4wreA -h o
-4oi -') c0r)c4v4.
4Vrre i
ci,5 nW(-
- 5. Is the anchorage configuration consistent with plant documentation?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?
YE] NEI UO N/Adý YXNEI UD 1 12 Enter the equipment class name from Appendix B: Classes of Equipment.
-KC-3 >
Limerick Generating Station Unit 1 MPR-3796, Revision 1 fnrr-qnnnd.nr'.n-Nn *R-19-171 C-275
Sheet 2 of 2 Equipment ID No. HV-1 1-104A Equip. Class'2 (05) Fluid (Air/H d) Valves Equipment Description RHR PP RM CLR A Sunpply Valve Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures?
NENI. U[
N/AD
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, YX ND UO N/AO and masonry block walls not likely to collapse onto the equipment?
- No overmi Eywirf fWC or 61 wolls
- 9. Do attached lines have adequate flexibility to avoid damage?
YM NO UO N/A[
- 10. Based on the above seismic interaction evaluations, is equipment free Yq NO UO of potentially adverse seismic interaction effects?.
I
-61o'se soe;*rt 4,o neoA~y
-4IWW-EAelon Aioly,'> s No. PI -", - obsA, Rrv.
- Other Adverse Conditions
- 11. Have you looked for and found no other seismic conditions that could YX NO UO adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
N/A Evaluated by Date:
<C-4 >
Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrPnnndPnrP Nn
- RR-1 -171 C-276
Equipment ID: HV-11-104A Limerick Generating Station Unit 1 MPR-3796, Revision 1
.nrrqnnndpnrA. Nn
- RR-1-171 C-277
Equipment ID: HV-11-104A I
I Limerick Generating Station Unit 1 MPR-3796, Revision 1 r':nrrp~nnnripnr-Kin - P*R-19-171 C-278
Equipment ID: HV-11-104A Limerick Generating Station Unit 1 MPR-3796, Revision 1
'.nrrpnnndpnrp. Nn " RS-19-171 C-279
Sheet 1 of 2 Status:
N U Seismic Walkdown Checklist (SWC)
Equipment ID No. HV-11-132A Equip. Class 2 (06) Motor Operated Valves Equipment Description ESW EDG JW Cooling Isolation Valve Location: Bldg. Diese Floor El. 217 Room, Area Room 311A Generator Building Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware?
V"4'.
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
- 4. Is the anchorage free of visible cracks in the concrete near the anchors?
- 5. Is the anchorage configuration consistent with plant documentation?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?
Y$NEIJUEJ Y$%NO UO N11
-0;0-UO N/ -L YD NE UO N/AO_
YXNDJ UO' 2 Enter the equipment class name from Appendix B: Classes of Equipment.
<C-3 >
Limerick Generating Station Unit 1 MPR-3796, Revision 1 r.nrrP~qnnnd".nrP Nn" RR-19-171 C-280
Sheet 2 of 2 Equipment ID No. HV-11-132A Equip. Class"2 (06) Motor Operated Valves Equipment Description ESWEDG JW Cooling Isolation Valve Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures?
))( NE UD N/AO
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, Y, ND UO N/AD and maso block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage?
V.NQ UEJ N/AO 4%
0
- 10. Based on the above seýiLcite'ic r
on evCaluations,,s e4 p tffree Y"k NE UD of potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no other seismic conditions that could 11D UO adversely affect the safety functions of the equipment?
I Comments (Additional pages may be added as necessary) 4?x Evaluated by:
Date:
Eautdby:_
/6/
-e,4/SA-ý Date:
Q.
I
(/1
<C-4>
Limerick Generating Station Unit 1 C-281 MPR-3796, Revision 1 rnrrPgnnnHPanr.* Nn - RS-19-171
Equipment ID: HV-11-132A Limerick Generating Station Unit 1 MPR-3796, Revision 1 r.nrrp~nnnrl~nr-p Nn* RR-19-171 C-282
Shee 1 of 2 Status:0 N U Seismic Walkdown Checklist (SWC)
Equipment ID No. HV-49-1F029 Equip. Class12 (06) Motor Operated Valves Equipment Description RCIC Suypression Pool Isolation Valve Location: Bldg. Reactor Floor El. 177 Room, Area Room 108 Enclosure Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorane
- 1. Is the anchorage configuration verification required (i.e., is the item one of the 50% of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware?
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
- 4. Is the anchorage free of visible cracks in the concrete near the anchors?
- Mucuvr
, mauae
-6 valve) mat4 o.t ar&
n
- 5. Is the anchorage configuration consistent with plant documentation?
(Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?
YE] NP YNI NEI UD N/AD YV NE UIJ N/AD Y4 NO UD N/AD YO N[l UD" N/Az Y)
ND UEI 12 Enter the equipment class name from Appendix B: Classes of Equipment.
< C-3 >"
Limerick Generating Station Unit 1 MPR-3796, Revision 1
('nrrn.*nnndi'Pnr.p Nn - RR-19-171 C-283
Sheet 2 of 2 Equipment ID No. HVe49-I F029Vl Equip. Class 12 (06) Motor Operated Valves Equipment Description RCIC Supp~ression Pool Isolation Valve Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures?
, No sarT -rl 8.. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage?
- 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
YPQ NO UO N/AD YK NO UD N/AO YX NO UD N/AO YX NO UQ1 Other Adverse Conditions
- 11. Have you looked for and found no other seismic conditions that could Y)
NE UE adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
VAl/
Evaluated by:
,/(
k((d/4 Date:
7 Limerick Generating Station Unit 1 MPR-3796, Revision 1 r.nrrPQnnndtPnrn Nn
- RR-19-171 C-284
Equipment ID: HV-49-1F029 Limerick Generating Station Unit 1 MPR-3796, Revision 1 r*nrro.nnndP~nrt.
Nn ' RR-12-171 C-285
Sheet 1 of 2 Status:
N U Seismic Walkdown Checklist (SWC)
Equipment 1D No. HV-52-1F037 Equip. Class12 (06) Motor Operated Valves Equipment Description Core S&ray Isolation Valve (MOV outboard of Drvwell)
Location: Bldg. Reactor Floor El. 283 Room, Area Room 523 Enclosure Manufacturer, Model, Etc. (optional but recommended)
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchoraye
- 1. Is the anchorage configuration verification required (i.e., is the item one YE NA of the 50% of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware?
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation?
YX NEI U0 N/AE Yk N[
UQ N/AE
- 4. Is the anchorage free of visible cracks in the concrete near the anchors?
Y NEI UE N/A
°
,Ab~ormovrteci 40o votue ')d e-Doc-&be~ of- 0J ocer-I
- 5. Is the anchorage configuration consistent with plant documentation?
YE NE UE N/At (Note: This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of potentially adverse seismic conditions?
YX NEI UE 12 Enter the equipment class name from Appendix B: Classes of Equipment.
<C-3 >
Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrn.nnndrnP.A Nn" RR-19-171 C-286
Sheet 2 of 2 Equipment ID No. HV 1 F037 Equip. Classl2 (06) Motor Operated Valves Equipment Description Core Spray Isolation Valve (MOV outboard of Drvwell)
Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures?
J VO C3-0
-Otor 4 5 0 65 D~0eo'd vW/
e~otevii
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and masonry block walls not likely to collapse onto the equipment?
( Cole 4Q:/,s
(--A T ty 5DPPor'fJ
- 9. Do attached lines have adequate flexibility to avoid damage?
- 10. Based on the above seismic interaction evaluations, is equipment free of potentially adverse seismic interaction effects?
WNO UD Nhý4-qff qlý*
YX NEI UL N/AD YV NEI UEJ N/AQ YPNEI UEJ Other Adverse Conditions
- 11. Have you looked for and found no other seismic conditions that could YX NEI U[
adversely affect the safety functions of the equipment?
Comments (Additional pages may be added as necessary)
IV/A O-QQM~r~a%__
Evaluated byY:
Date:
/,
< C-4 >
Limerick Generating Station Unit 1 MPR-3796, Revision 1
.nrrp.qnnndpnrP. Nno R5-19-171 C-287
Equipment ID: HV-52-1F037 C-288 Limerick Generating Station Unit 1 MPR-3796, Revision 1 r.nrrPqnnntlPnr.A Nn* RR-19-171
Equipment ID: HV-52-1F037 Limerick Generating Station Unit 1 MPR-3796, Revision 1 r.nrrPnnndPnrA Nn
- RA-19-171 C-289
Equipment ID: HV-52-1F037 Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrqnnndonr~lP Nn " Rq-1 -171 C-290
Equipment ID: HV-52-1F037 Limerick Generating Station Unit 1 MPR-3796, Revision 1 rnrrP.nnnnlnr*P Nn" RR-19-171 C-291