MONTHYEARHNP-11-065, Supplement Information in Regard to Measurement Uncertainty Recapture Power Uprate License Amendment Request2011-06-23023 June 2011 Supplement Information in Regard to Measurement Uncertainty Recapture Power Uprate License Amendment Request Project stage: Supplement ML12082A2102012-03-0505 March 2012 License Amendment Request for Measurement Uncertainty Recapture Power Uprate Project stage: Request ML12117A1752012-04-27027 April 2012 Request for Additional Information Regarding License Amendment Related to Measure Uncertainty Recapture Power Uprate Project stage: RAI ML12138A2672012-05-22022 May 2012 Request for Additional Information Regarding License Amendment Related to Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML12160A0852012-05-29029 May 2012 Response to Request for Additional Information Regarding License Amendment Related to Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML12158A4812012-06-0606 June 2012 Request for Additional Information Regarding License Amendment Related to Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML12168A0022012-06-15015 June 2012 NRR E-mail Capture - Request for Additional Information for License Amendment Request Dated March 5, 2012 Project stage: RAI ML12187A1742012-06-21021 June 2012 Response to Request for Additional Information Regarding License Amendment Related to Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML1218006502012-07-0303 July 2012 Mcguire Nuclear Station, Units 1 and 2 - Fire Protection Fire Protection Safety Evaluation Input Regarding License Amendment Request Measurement Uncertainty Recapture Power Uprate Project stage: Approval ML12199A0232012-07-0606 July 2012 Response to Request for Additional Information Regarding License Amendment Related to Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML12209A1752012-07-16016 July 2012 Response to Request for Additional Information Regarding License Amendment Related to Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML12215A3302012-08-0101 August 2012 NRR E-mail Capture - Request for Additional Information for License Amendment Request Dated March 5, 2012 Project stage: RAI ML12219A2712012-08-0606 August 2012 NRR E-mail Capture - Request for Additional Information for License Amendment Request Dated March 5, 2012 (TAC Nos. ME8213 and ME8214), RAI Questions 43 and 44 Project stage: RAI ML12250A6222012-08-15015 August 2012 Response to Request for Additional Information Regarding License Amendment Request Related to Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML12254A0182012-08-23023 August 2012 NRR E-mail Capture - Request for Additional Information for License Amendment Request Dated March 5, 2012 (TAC Nos. ME8213 and ME8214), RAI Questions 45 and 46 Project stage: RAI ML12251A0282012-09-13013 September 2012 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML12251A0242012-09-13013 September 2012 Request for Withholding Information from Public Disclosure (TAC Nos. ME8213 and ME8214 Project stage: Withholding Request Acceptance ML12284A1302012-09-27027 September 2012 Response to Request for Additional Information Regarding License Amendment Request Related to Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML12310A3842012-11-0101 November 2012 Response to Request for Additional Information Regarding License Amendment Request Related to Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML13024A4062013-01-0202 January 2013 Revision to a Response to a Request for Additional Information Regarding License Amendment Request Related to Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML13079A3302013-03-0707 March 2013 Restatement of License Condition Proposed in August 15, 2012 Response to Request for Additional Information Related to License Amendment Request for Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML13073A0412013-05-16016 May 2013 Issuance of Amendments Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Approval ML13151A2002013-06-0404 June 2013 Correction Letter to Issuance of Amendment Nos. 269 and 249, Measurement Uncertainty Recapture Power Uprate Project stage: Approval 2012-07-03
[Table View] |
Text
1 NRR-PMDAPEm Resource From:
Thompson, Jon Sent:
Thursday, August 23, 2012 10:48 AM To:
Ashe, Ken Cc:
Sheng, Simon
Subject:
Request for Additional Information for License Amendment Request dated March 5, 2012 (TAC Nos. ME8213 and ME8214), RAI Questions 45 and 46
SUBJECT:
MCGUIRE NUCLEAR STATION, UNITS 1 AND 2, REQUEST FOR ADDITIONAL INFORMATION, QUESTIONS 45 AND 46 REGARDING LICENSE AMENDMENT RELATED TO MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE (TAC NOS. ME8213 AND ME8214)
By letter dated March 5, 2012, Duke Energy Carolinas, LLC (the licensee), submitted a proposed license amendment to change the McGuire Nuclear Station, Units 1 and 2 (McGuire 1 and 2), Technical Specifications (TSs). The proposed change revises the TSs to implement a measurement uncertainty recapture power uprate for McGuire 1 and 2.
The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the licensees submittal and determined that additional information is needed in order to complete our review. The enclosed document describes this request for additional information (RAI). Please note that the numbering of the questions in this RAI does not begin at the number one. Six prior RAIs regarding this proposed license amendment were issued to you by letters dated April 27, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12117A175), May 22, 2012 (ADAMS Accession No. ML12138A267), June 6, 2012, (ADAMS Accession No. ML12158A481), June 15, 2012 (ADAMS Accession No. ML12168A002), August 1, 2012 (ADAMS Accession No. ML12215A330), and August 6, 2012 (ADAMS Accession No. ML12219A271) with RAI questions numbered 1-4, 5-19, 20-31, 32-40, 41-42, and 43-44, respectively.
A telephone conference will be set up to discuss these RAI questions, if needed. If you have any questions, please call me at 301-415-1119.
Sincerely, Jon Thompson, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-369 and 50-370
Enclosure:
RAI REQUEST FOR ADDITIONAL INFORMATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION REGARDING LICENSE AMENDMENT REQUEST RELATED TO THE IMPLEMENTATION OF A MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE
2 MCGUIRE NUCLEAR STATION, UNITS 1 AND 2 By letter dated March 5, 2012 (Agencywide Documents Access and Management System (ADAMS),
Accession No. ML12082A210), as supplemented, Duke Energy Carolinas, LLC (Duke Energy, the licensee),
submitted a license amendment request (LAR) to change the McGuire Nuclear Station, Units 1 and 2 (McGuire 1 and 2), Technical Specifications (TSs). The proposed change revises the TSs to implement a measurement uncertainty recapture (MUR) power uprate for McGuire 1 and 2.
The NRC staff has reviewed the licensees response and determined that following additional information are needed to complete the safety evaluation:
- 45. Please provide the current operating EFPYs for McGuire 1 and 2 to assist in determining the margin available in the current Pressure-Temperature limits for 34 EFPY.
- 46. Please confirm that the ISI records for McGuire 1 and 2 show no Reactor Vessel (RV) surface flaws. If any RV surface flaws were detected, please characterize them.
Hearing Identifier:
NRR_PMDA Email Number:
458 Mail Envelope Properties (Jon.Thompson@nrc.gov20120823104800)
Subject:
Request for Additional Information for License Amendment Request dated March 5, 2012 (TAC Nos. ME8213 and ME8214), RAI Questions 45 and 46 Sent Date:
8/23/2012 10:48:07 AM Received Date:
8/23/2012 10:48:00 AM From:
Thompson, Jon Created By:
Jon.Thompson@nrc.gov Recipients:
"Sheng, Simon" <Simon.Sheng@nrc.gov>
Tracking Status: None "Ashe, Ken" <Ken.Ashe@duke-energy.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 3236 8/23/2012 10:48:00 AM Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received: