Mid-Cycle Performance Review and Inspection Plan 2012 - Limerick Generating Station
ML12248A025
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 09/04/2012
From: Darrell Roberts
Division Reactor Projects I
To: Pacilio M
Exelon Nuclear, Exelon Generation Co
KROHN, P
References
IR-12-006
Download: ML12248A025 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 September 4, 2012 Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd.

Warrenville, lL 60555

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

LIMERICK GENERATING STATION (REPORT 05000352/2012006 and 05000353/2012006)

Dear Mr. Pacilio:

On August 15, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of the Limerick Generating station Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011 through June 30, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This assessment reflects the integration of the Security Cornerstone into the Inspection Manual Chapter (IMC) 0305, Operating Reactor Assessment Program.

The NRC determined the performance at Limerick Unit 1 during the most recent quarter was within the Licensee Response Column of the NRC=s Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). There-fore, the NRC plans to conduct ROP baseline inspections at Unit 1.

The NRC determined the performance at Limerick Unit 2 during the most recent quarter was within the Regulatory Response Column of the NRC=s ROP Action Matrix because of a self-revealing finding of low to moderate safety significance (White) involving a failure by Exelon to ensure sufficient technical guidance was contained in operating procedures to: (1) ensure that a feedwater (FW) motor-operated valve (MOV) could close against expected system differential pressures; and (2) prevent operators from attempting to close FW MOVs out of sequence resulting in differential pressures for which they are not designed. As a result, two FW valves failed to fully shut resulting in a primary containment isolation valve and the reactor core isolation cooling system being inoperable for greater than their Technical Specification allowed outage time. This finding was assigned to the third quarter of 2011 (ML113410132).

On August 2, 2012, the NRC issued a supplemental inspection report and assessment follow-up letter (ML12215A272) documenting an inspection performed in accordance with Inspection Procedure (IP) 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area, to review the performance of Limerick Unit 2 in addressing the White finding discussed above. The NRC concluded your actions met the objectives of IP 95001. Therefore, in accordance with the guidance in IMC 0305, the White finding will only be considered in

M. Pacilio 2 assessing plant performance for a total of four quarters. As a result, the NRC determined the performance at Limerick Unit 2 to be in the Licensee Response Column of the ROP Action Matrix beginning with the third calendar quarter of 2012.

The enclosed inspection plan lists the inspections scheduled through December 31, 2013.

Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the baseline inspections, consistent with the Agencys actions related to Fukushima, the NRC will perform TI-187, Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns and TI-188, Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns. We also plan to conduct independent spent fuel storage installation inspections (lSFSl) using Inspection Procedure 60855.1, Operation of an ISFSI at Operating Plants, and an infrequently performed inspection using IP 92723, Follow-Up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period, to follow up on three traditional enforcement violations in the area of impeding the regulatory process that occurred between the 3rd quarter 2011 and the 2nd quarter 2012 (ML112550468, ML12128A373, and ML12215A272). The NRC will schedule and conduct IP 92723 when your staff has notified us of your readiness for this inspection. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Paul Krohn at 610-337-5120 with any questions you have regarding this letter.

Sincerely,

/RA/

Darrell J. Roberts Division of Reactor Projects Docket Nos. 50-532, 50-353 License Nos. NPF-39, NPF-85

Enclosure:

Limerick Generating Station Inspection/Activity Plan cc w/encl: Distribution via ListServ

ML12248A025 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME SMcCarver/SM PKrohn/PGK DRoberts/DJR DATE 08/ 27 /12 08/27 /12 08/30 /12 M. Pacilio 3 Distribution w/encl:

W. Dean, RA D. Lew, DRA D. Roberts, DRP J. Clifford, DRP C. Miller, DRP P. Wilson, DRS P. Krohn, DRP A. Rosebrook, DRP S. Ibarrola, DRP E. Miller, DRP E. DiPaolo, DRP, SRI J. Hawkins, DRP, RI N. Esch, DRP, AA S. Kennedy, RI, OEDO DRS Branch Chiefs (6)

N. McNamara, RI, SLO D. Tifft, RI. SLO D. Screnci, RI, PAO N. Sheehan, RI, PAO RidsNrrPMLimerick Resource RidsNrrDorlLpl1-2 Resource ROPreports Resource RidsNrrDirslpab Resource ROPassessment Resource

Page 1 of 3 Limerick 08/22/2012 13:29:41 Inspection / Activity Plan Report 22 07/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 10/08EXM - LIMERICK INITIAL OL EXAM 4 1 09/10/2012 09/14/2012 U01858 FY13-LIMERICK INITIAL OPERATOR LICENSING EXAM 1 10/08/2012 10/19/2012 U01858 FY13-LIMERICK INITIAL OPERATOR LICENSING EXAM HP - RADIATION SAFETY INSPECTIONS 1 1, 2 07/09/2012 07/13/2012 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 07/09/2012 07/13/2012 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 07/09/2012 07/13/2012 IP 71151-PR01 RETS/ODCM Radiological Effluent TI-188 - SEISMIC WALKDOWNS 1 1, 2 07/30/2012 08/03/2012 IP 2515/188 Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns TI 182 - DEGRADATION UNDERGROUNG PIPING - PHASE 1 1 1, 2 08/06/2012 08/10/2012 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping TI-187 - TI-187 FLOODING WALKDOWNS 1 1, 2 08/03/2012 08/20/2012 IP 2515/187 Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns 7111121 - CDBI 7 1, 2 08/27/2012 08/31/2012 IP 7111121 Component Design Bases Inspection 1, 2 09/10/2012 09/14/2012 IP 7111121 Component Design Bases Inspection 1, 2 09/24/2012 09/28/2012 IP 7111121 Component Design Bases Inspection 7111111B - LIMERICK ON-SITE RQL INSP W/ P/F RESULTS 3 1, 2 11/05/2012 11/09/2012 IP 7111111B Licensed Operator Requalification Program 71152B - PI&R 5 1, 2 10/22/2012 10/26/2012 IP 71152B Problem Identification and Resolution 1, 2 11/05/2012 11/09/2012 IP 71152B Problem Identification and Resolution HP - RADIATION SAFETY INSPECTIONS 1 1, 2 11/05/2012 11/09/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 11/05/2012 11/09/2012 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 11/05/2012 11/09/2012 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 11/05/2012 11/09/2012 IP 71151-PR01 RETS/ODCM Radiological Effluent EP PROGR - EP PROGRAM INSPECTION 1 1, 2 12/03/2012 12/07/2012 IP 7111402 Alert and Notification System Testing 1, 2 12/03/2012 12/07/2012 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 12/03/2012 12/07/2012 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 12/03/2012 12/07/2012 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 92723 - FOLLOWUP FOR 3 SLIV TE VIOS IN 12 MONTHS 1 1, 2 01/01/2013 03/31/2013 IP 92723 Follow Up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in the S This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 3 Limerick 08/22/2012 13:29:41 Inspection / Activity Plan Report 22 07/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 7/15 EXM - LIMERICK LSRO INITIAL EXAM 2 1 06/24/2013 06/28/2013 U01869 FY13-LIMERICK LSRO INITIAL OPERATOR LICENSING EXAM 1 07/15/2013 07/19/2013 U01869 FY13-LIMERICK LSRO INITIAL OPERATOR LICENSING EXAM HP - RADIATION SAFETY INSPECTIONS 1 1, 2 03/04/2013 03/08/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 03/04/2013 03/08/2013 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 03/04/2013 03/08/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/04/2013 03/08/2013 IP 71124.04 Occupational Dose Assessment 1, 2 03/04/2013 03/08/2013 IP 71124.05 Radiation Monitoring Instrumentation 60855 - ISFSI LOADING INSPECTION 2 1, 2 03/13/2013 06/30/2013 IP 60855 Operation Of An ISFSI 1, 2 03/13/2013 06/30/2013 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 7111108G - U2 INSERVICE INSPECTION 1 2 04/01/2013 04/05/2013 IP 7111108G Inservice Inspection Activities - BWR HP - RADIATION SAFETY INSPECTIONS 1 1, 2 04/01/2013 04/05/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 04/01/2013 04/05/2013 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 04/01/2013 04/05/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 04/01/2013 04/05/2013 IP 71124.04 Occupational Dose Assessment 1, 2 04/01/2013 04/05/2013 IP 71124.05 Radiation Monitoring Instrumentation TRI FI - TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 05/06/2013 05/10/2013 IP 7111105T Fire Protection [Triennial]

1, 2 05/20/2013 05/24/2013 IP 7111105T Fire Protection [Triennial]

HP - RADIATION SAFETY INSPECTIONS 1 1, 2 07/08/2013 07/12/2013 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 07/08/2013 07/12/2013 IP 71124.07 Radiological Environmental Monitoring Program HP - RADIATION SAFETY INSPECTIONS 1 1, 2 11/04/2013 11/08/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 11/04/2013 11/08/2013 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 11/04/2013 11/08/2013 IP 71151-PR01 RETS/ODCM Radiological Effluent TI 182 - DEGRAD IATION UNDERGROUND PIPING-PHASE 2 1 1, 2 11/12/2013 11/15/2013 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping EP EX - EP EXERCISE EVALUATION 5 1, 2 11/18/2013 11/22/2013 IP 7111401 Exercise Evaluation This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 3 of 3 Limerick 08/22/2012 13:29:41 Inspection / Activity Plan Report 22 07/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP EX - EP EXERCISE EVALUATION 5 1, 2 11/18/2013 11/22/2013 IP 7111404 Emergency Action Level and Emergency Plan Changes This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.