MONTHYEARBW110021, Response to NRC Verification Inspection Report; 05000456/2011009; 05000457/20110092011-03-0202 March 2011 Response to NRC Verification Inspection Report; 05000456/2011009; 05000457/2011009 Project stage: Request ML1117900402011-04-12012 April 2011 Westinghouse Electric Company Affidavit Supporting Withholding, Attachment 6 to Braidwood Station, Units 1 & 2, Byron Station, Unit 1 & 2, Request for License Amendment Regarding Measurement Uncertainty Recapture (MUR) Power Uprate Project stage: Request ML1117900432011-05-0909 May 2011 Affidavit from Cameron International Corporation Supporting Withholding of Attachments 8a Through 8d Project stage: Request ML1117900422011-06-21021 June 2011 MUR Technical Evaluation, (Non-Proprietary Version), Attachment 7 to Braidwood Station, Units 1 & 2, Byron Station, Unit 1 & 2, Request for License Amendment Regarding Measurement Uncertainty Recapture (MUR) Power Uprate Project stage: Request ML1117900382011-06-23023 June 2011 Steam Generator Tube Rupture Analysis Report, Attachment 5a to Braidwood Station, Units 1 & 2, Byron Station, Unit 1 & 2, Request for License Amendment Regarding Measurement Uncertainty Recapture (MUR) Power Uprate Project stage: Request RS-11-099, Request for License Amendment Regarding Measurement Uncertainty Recapture (MUR) Power Uprate2011-06-23023 June 2011 Request for License Amendment Regarding Measurement Uncertainty Recapture (MUR) Power Uprate Project stage: Request ML11224A0832011-08-0303 August 2011 NRR E-mail Capture - Draft - Supplemental Information Request Braidwood and Byron MUR LAR (ME6587-ME6590) Project stage: Draft Approval ML1121505632011-08-22022 August 2011 Supplemental Information Needed for Acceptance of Licensing Action Measurement Uncertainty Recapture Power Uprate Project stage: Acceptance Review ML11266A0022011-09-19019 September 2011 NRR E-mail Capture - Draft RAI Braidwood/Byron - Measurement Uncertainty Recapture LAR Project stage: Draft RAI ML1122315742011-09-19019 September 2011 Acceptance Review of License Amendment Request (LAR) Measurement Uncertainty Recapture (MUR) Power Uprate Project stage: Acceptance Review ML11262A1612011-10-12012 October 2011 Request for Addtional Information Measurement Uncertainty Power Uprate Request Project stage: Other RS-11-169, Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2011-11-0101 November 2011 Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Request ML1129305492011-11-0303 November 2011 Request for Withholding Information from Public Disclosure Affidavit CAW-11-03 Project stage: Withholding Request Acceptance ML1129203422011-11-0303 November 2011 Request for Withholding Information from Public Disclosure Affidavit CAW-11-3137 Project stage: Withholding Request Acceptance ML1130104032011-11-28028 November 2011 Request for Additional Information 2 Measurement Uncertainty Power Uprate Request Project stage: RAI ML1202609362012-02-14014 February 2012 Request for Additional Information Measurement Uncertainty Recapture Power Uprate Request Project stage: RAI ML1202701462012-02-14014 February 2012 Request for Additional Information Measurement Uncertainty Recapture Power Uprate Request Project stage: RAI ML1205302582012-02-24024 February 2012 Request for Additional Information Measurement Uncertainty Recapture Power Uprate Request Project stage: RAI ML12068A3822012-03-0808 March 2012 E-MAIL - MUR LAR 1 Response Date Project stage: Approval ML12068A2942012-03-0808 March 2012 Request for Additional Information Regarding Reactor Systems MUR Review (TACs ME6587, ME6588, ME6589, and ME6590) Project stage: RAI ML1205904602012-03-0909 March 2012 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML12089A4902012-03-29029 March 2012 E-MAIL - Draft Balance of Plant Request for Additional Information for MUR Review Project stage: Draft RAI ML12121A6942012-05-10010 May 2012 Request for Additional Information Related to License Application for Measurement Uncertainty Recapture Uprate Project stage: RAI RS-12-081, Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2012-05-16016 May 2012 Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Request ML12157A0632012-06-13013 June 2012 Request for Additional Information Related to Measurement Uncertainty Recapture Uprate Project stage: RAI ML12233A6012012-08-27027 August 2012 Request for Additional Information, Measurement Uncertainty Recapture Power Uprate Request Project stage: RAI RS-12-144, Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2012-09-13013 September 2012 Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Request ML12216A0002012-09-27027 September 2012 Request for Additional Information Related to Measurement Uncertainty Uprate Project stage: RAI ML12271A3082012-12-0606 December 2012 Request for Additional Information and Suspension of Review of License Amendment Request for Power Uprate Project stage: RAI RS-13-227, Response to NRC HELB Audit Request for Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2013-09-0505 September 2013 Response to NRC HELB Audit Request for Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Request RS-13-261, Supplemental Response to NRC HELB Audit Request for Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2013-10-24024 October 2013 Supplemental Response to NRC HELB Audit Request for Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Supplement RS-13-267, Supplemental Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2013-11-13013 November 2013 Supplemental Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Supplement 2012-02-14
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 27, 2012 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
BYRON STATION, UNIT NOS. 1 AND 2, AND BRAIDWOOD STATION, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE REQUEST (TAC NOS. ME6587, ME6588, ME6589, AND ME6590)
Dear Mr. Pacilio:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated June 23, 2011, Exelon Generation Company, LLC submitted a request associated with a measurement uncertainty recapture power uprate for the Braidwood Station, Units 1 and 2, and Byron Station, Unit Nos. ~ '3nd 2.
The NRC staff has reviewed your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter. During a discussion with your staff on August 15, 2012, it was agreed that you would provide a response within 30 days from the date of this letter.
The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC's goal of efficient and effective use of staff resources. If circumstances result in the need to revise the requested response date, please contact Mr. Joel Wiebe at (301) 415-6606.
ichael Mahoney, Pro ct Manager Plant Licensing Bran 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-456, STN 50-457, STN 50-454 and STN 50-455
Enclosure:
Request for Additional Information cc w/encl: Distribution via Listserv
REQUEST FOR ADDITIONAL INFORMATION (RAI)
BYRON STATION, UNIT NOS. 1 AND 2, AND BRAIDWOOD STATION, UNITS 1 AND 2 REGARDING MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE LICENSE AMENDMENT REQUEST DOCKET NOS. STN 50-454, STN 50-455, STN 50-456 AND STN 50-457 TAC NOS. ME6587, ME6588, ME6589, ME6590 In reviewing the Exelon Generation Company, LLC (EGC) submittal dated June 23, 2011, related to a measurement uncertainty recapture (MUR) power uprate, for the Braidwood Station (Braidwood), Units 1 and 2, and Byron Station (Byron), Unit Nos. 1 and 2, the U.S. Nuclear Regulatory Commission (NRC) staff has determined that the following information is needed in order to complete its review:
EGC's supplemental submittal dated May 16, 2012, states:
The SFP [spent fuel pool] liner and racks were evaluated in the existing analyses of record for a design temperature of 200 OF [degrees Fahrenheit],
which bounds the peak MUR SFP temperature of 166.6 OF.
Page 9.1-29 of the Byron and Braidwood updated final safety analysis report (UFSAR) states:
The liner plate and anchorage system have been designed for the forces resulting from long-term shrinkage of concrete, and a temperature rise to 158 OF from the 70 OF ambient temperature with nominal cooling.
The design temperature for the liner (158 OF) in the UFSAR, and the temperature noted in the response to RAI-13 in your May 16, 2012 submittal (200 OF), do not appear to be consistent.
Please clarify the statement in EGC's May 16, 2012, submittal.
Enclosure
Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
BYRON STATION, UNIT NOS. 1 AND 2, AND BRAIDWOOD STATION, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE REQUEST (TAC NOS. ME6587, ME6588, ME6589, AND ME6590)
Dear Mr. Pacilio:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated June 23, 2011, Exelon Generation Company, LLC submitted a request associated with a measurement uncertainty recapture power uprate for the Braidwood Station, Units 1 and 2, and Byron Station, Unit Nos. 1 and 2.
The NRC staff has reviewed your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter. During a discussion with your staff on August 15, 2012, it was agreed that you would provide a response within 30 days from the date of this letter.
The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC's goal of efficient and effective use of staff resources. If circumstances result in the need to revise the requested response date, please contact Mr. Joel Wiebe at (301) 415-6606.
Sincerely, IRAI Michael Mahoney, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. SrN 50-456, STN 50-457, STN 50-454 and STN 50-455
Enclosure:
Request for Additional Information cc w/encl: Distribution via Listserv DISTRIBUTION PUBLIC LPL3-2 R/F RidsNrrDorlLpl3-2 Resource RidsNrrPMByron Resource RidsNrrPMBraidwood Resource RidsNrrLASRohrer Resource RidsOgcRp Resource RidsRgn3MailCenler Resource RidsNrrDorlDpr Resource RidsAcrsAcnw_MailCTR Resource ADAMS Accession No. ML12233A601 OFFICE LPL3-2/PM NAME MMahoney DATE 8127/12 LPL3-2ILA SRohrer 8/27/12 LPL3-2/PM MMahoney 8/27/12 OFFICIAL RECORD COpy