MONTHYEARBSEP 12-0050, Request for License Amendments - Diesel Generator (DG) Completion Time (CT) Extension for Technical Specification (TS) 3.8.1, AC Sources - Operating2012-06-19019 June 2012 Request for License Amendments - Diesel Generator (DG) Completion Time (CT) Extension for Technical Specification (TS) 3.8.1, AC Sources - Operating Project stage: Request ML12193A4402012-07-10010 July 2012 NRR E-mail Capture - Brunswick 1 & 2: Diesel Generators Completion Time Extension for TS 3.8.1 (ME8893 and ME8894) Project stage: Other ML12300A3082012-10-26026 October 2012 NRR E-mail Capture - Rais for Brunswick LAR, EDG CT Extension (TACs ME8893, ME8894) Project stage: RAI ML12310A3052012-11-21021 November 2012 Request for Additional Information Regarding the Risk Evaluation for the Emergency Diesel Generator Completion Time Extension for Technical Specifications 3.8.1 AC Sources-Operating. Project stage: RAI BSEP 12-0140, Additional Information Supporting License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition)2012-12-17017 December 2012 Additional Information Supporting License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) Project stage: Request ML13022A5722013-01-21021 January 2013 Response to NRC Request for Additional Information Re Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating Project stage: Response to RAI BSEP 13-0010, Attachment 1: Requested Drawings2013-01-21021 January 2013 Attachment 1: Requested Drawings Project stage: Other BSEP 13-0054, Supplement to Request for License Amendments - Diesel Generator (DG) Completion Time (CT) Extension for Technical Specification (TS) 3.8.1, AC Sources - Operating2013-05-14014 May 2013 Supplement to Request for License Amendments - Diesel Generator (DG) Completion Time (CT) Extension for Technical Specification (TS) 3.8.1, AC Sources - Operating Project stage: Supplement ML13175A3472013-07-10010 July 2013 Request for Additional Information Regarding Request for Diesel Generator Completion Time Extension Project stage: RAI BSEP 13-0099, Response to NRC Request for Additional Information Regarding Diesel Generator (DG) Completion Time (CT) Extension for Technical Specification(Ts) 3.8.1, AC Sources - Operating.2013-08-29029 August 2013 Response to NRC Request for Additional Information Regarding Diesel Generator (DG) Completion Time (CT) Extension for Technical Specification(Ts) 3.8.1, AC Sources - Operating. Project stage: Response to RAI BSEP 14-0010, Supplement to Request for License Amendments - Diesel Generator (DG) Completion Time (CT) Extension for Technical Specification (TS) 3.8.1, AC Sources - Operating2014-01-22022 January 2014 Supplement to Request for License Amendments - Diesel Generator (DG) Completion Time (CT) Extension for Technical Specification (TS) 3.8.1, AC Sources - Operating Project stage: Supplement ML13329A3622014-02-24024 February 2014 License Amendments Regarding Changes to Technical Specifications for Extension of Completion Time for Inoperable Emergency Diesel Generator Project stage: Acceptance Review 2013-01-21
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24179A1292024-06-24024 June 2024 Acceptance Review for LAR to Revise TS to Adopt TSTF-234-A, Revision 1 ML24066A0132024-03-0505 March 2024 Bru 2024-002 Radiation Safety Baseline Inspection Information Request ML23248A2612023-09-0505 September 2023 NRR E-mail Capture - Brunswick Steam Electric Plant, Units 1 and 2 - Acceptance of License Amendment Request to Revise the 10 CFR 50.69 Categorization Process ML23202A0652023-07-19019 July 2023 NRR E-mail Capture - Request for Additional Information - Brunswick Steam Electric Plant, Units 1 and 2, Torus Liner Inspection Alternative Request (L-2022-LLR-0089) ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23073A2282023-03-13013 March 2023 Duke Fleet- Adoption of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements - Acceptance Review ML23032A2472023-01-26026 January 2023 Document Request Letter for Brunswick Upcoming RP Inspection 2023002 ML23018A1892023-01-17017 January 2023 Document Request for RP Inspection at Brunswick Inspection Report 2023-01 ML23006A0642023-01-0606 January 2023 NRR E-mail Capture - Acceptance Review Results for Brunswick, Unit Nos. 1 and 2 - Proposed Alternative Request RA-22-0308 ML23006A1892023-01-0606 January 2023 NRR E-mail Capture - Corrected - Acceptance Review Results for Brunswick, Unit Nos. 1 and 2 - Proposed Alternative Request RA-22-0308 NRC-2100-2022, EN 55999 Valcor Coil Shell Assemblies Final Notification (004)2022-09-12012 September 2022 EN 55999 Valcor Coil Shell Assemblies Final Notification (004) NRC 2110-2022, EN 55999 - Valcor Engineering Corporation (009)2022-07-18018 July 2022 EN 55999 - Valcor Engineering Corporation (009) ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22038A1572022-02-0707 February 2022 NRR E-mail Capture - Duke Energy Fleet - Acceptance of License Amendment Request Regarding Adoption of TSTF-541, Revision 2 ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML21357A0472021-12-23023 December 2021 NRR E-mail Capture - Brunswick Steam Electric Plant, Units 1 and 2 - Acceptance of License Amendment Request Regarding Adoption of TSTF-580 ML21361A0122021-12-23023 December 2021 NRR E-mail Capture - Accepted for Review - Duke Energy Fleet License Amendment Request to Relocate Emergency Operations Facility ML21354A8612021-12-15015 December 2021 NRR E-mail Capture - Request for Additional Information - Duke Fleet Request RA-19-0352 - Alternative for RPV Closure Stud Exams (L-2020-LLR-0156) ML21277A0952021-10-0101 October 2021 NRR E-mail Capture - Request for Additional Information - Brunswick Exemption Request from 10CFR 55.47 License Operator Exam Two-year Waiver Limit ML21200A1582021-07-16016 July 2021 NRR E-mail Capture - Accepted for Review - Brunswick License Amendment Request to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery ML21168A0042021-06-17017 June 2021 Notification of Inspection and Request for Information ML21137A1622021-04-26026 April 2021 NRR E-mail Capture - Accepted for Review - Brunswick License Amendment Request to Adopt TSTF-505 Risk-Informed Completion Time (L-2021-LLA-0060) ML21082A0162021-03-22022 March 2021 Accepted for Review - Brunswick License Amendment Request to Change Tech Spec Limit for Standby Liquid Control System Boron Solution Storage Tank Volume L-2021-LLA-0022 ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 ML21049A2632021-02-0404 February 2021 NRR E-mail Capture - Request for Additional Information - Duke Energy Fleet License Amendment Request to Revise Emergency Plan ML21019A3772021-01-13013 January 2021 002 Radiation Safety Baseline Inspection Information Request ML21007A3722021-01-0707 January 2021 NRR E-mail Capture - Acceptance Review - Duke Fleet - RA-19-0352 - Proposed Alternative for Reactor Vessel Close Stud Examinations (L-2020-LLR-0156) ML20323A4072020-11-18018 November 2020 NRR E-mail Capture - Request for Additional Information - Brunswick License Exemption Request from 10CFR73 Annual Force on Force Exercise Requirements (EPIC L-2020-LLE-0180) ML20309A5212020-10-29029 October 2020 Request for Additional Information - Brunswick License Amendment Request to Modify Its Approved 10 CFR 50.69, Risk-Informed Categorization and Treatment of SSC Categorization Process ML20294A0642020-10-20020 October 2020 NRR E-mail Capture - Accepted for Review - Duke Energy Fleet License Amendment Request to Adopt TSTF-582 RPV Water Inventory Control Enhancements(L-2020-LLA-0218) ML20297A3102020-10-13013 October 2020 NRR E-mail Capture - Acceptance Review - Duke Fleet - RA-20-0191 - Request to Use a Provision of a Later Edition of the ASME B&PV Code, Section XI - IWA-5120, IWA-5213, IWA-5241, IWA-5242, and IWA-5250 (L-2020-LLR-0126) ML20297A3082020-10-0707 October 2020 NRR E-mail Capture - Acceptance Review - Duke Fleet - RA-20-0263 - Request to Use a Provision of a Later Edition of the ASME B&PV Code, Section XI for Repair/Replacement (L-2020-LLR-0124) ML20297A3092020-10-0606 October 2020 NRR E-mail Capture - Acceptance Review - Duke Fleet - RA-20-0262 - Request to Use a Provision of a Later Edition of the ASME B&PV Code, Section XI - IWA-4540(b) (L-2020-LLR-0125) ML20275A2972020-10-0101 October 2020 NRR E-mail Capture - Request for Additional Information - Brunswick Request for Alternate Examination of Reactor Vessel Nozzles ML21033A8562020-08-0505 August 2020 NRR E-mail Capture - Accepted for Review - Brunswick Relief Request for RPV Nozzle-to-Vessel Weld and Inner Radii Examination Requirements EPID-L-2020-LLR-0091 ML20121A1262020-04-29029 April 2020 Radiation Safety Baseline Inspection Information Request ML20111A1212020-04-20020 April 2020 NRR E-mail Capture - Accepted for Review - Brunswick Request for Alternative to Examination Category B-N-1 (VT-3) Visual Examination of Accessible Areas of the Reactor Vessel Interior - EPID: L-2020-LLR-0048 ML20017A1602020-01-17017 January 2020 E-mail Notification of Inspection and Request for Additional Information ML19283D0852019-10-0909 October 2019 Request for Additional Information - Brunswick Atrium 11 LAR ML19252A4572019-09-0808 September 2019 (FEMA Email 09-08-19) Tentative Notification of Brunswick Preliminary Capability Assessment Results ML19252A4092019-09-0606 September 2019 (E-mail to FEMA 09-06-19) FEMA Notification for Planned Restart of Brunswick Units 1 and 2 ML19219A2132019-08-0707 August 2019 NRR E-mail Capture - Duke Energy Fleet - Acceptance of Requested Licensing Action Amendment Requests to Relocate the TSs Staff Qualification Requirements to the Duke Energy Corporation QAPD ML19179A1312019-06-27027 June 2019 NRR E-mail Capture - Brunswick RAIs - LAR to Revise TS 5.5.12, Primary Containment Leakage Rate Testing Program for Permanent Extension of Maximum Appendix J Test Intervals (L 2019-LLA-0031) ML19177A0122019-06-25025 June 2019 NRR E-mail Capture - Draft Brunswick RAIs - LAR to Revise TS 5.5.12, Primary Containment Leakage Rate Testing Program for Permanent Extension of Maximum Appendix J Test Intervals (L 2019-LLA-0031) ML19162A3912019-06-11011 June 2019 NRR E-mail Capture - Duke Energy Fleet - Acceptance of Requested Licensing Action Relief Request (19-GO-001) Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination in Lieu of Radiography ML19162A3902019-06-11011 June 2019 NRR E-mail Capture - Brunswick Steam Electric Plant, Units 1 and 2 - Acceptance of Requested Licensing Action Fourth 10-Year Inservice Inspection Interval ISI-12 ML19092A1152019-04-0101 April 2019 NRR E-mail Capture - Brunswick Steam Electric Plant, Unit Nos. 1 and 2 - Acceptance of Requested Licensing Action Amendment Request to Modify Surveillance Requirements for Safety Relief Valves (L-2019-LLA-0043) ML19092A1142019-04-0101 April 2019 NRR E-mail Capture - Brunswick Plant, Unit 1 and 2 - Acceptance of Requested Licensing Action Amendment Request to Modify TS 5.5.12 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (L-2019-LLA-0031) ML19067A2712019-03-0707 March 2019 NRR E-mail Capture - Brunswick 3rd Round RAI - LAR to Allow Implementation of the Provisions 10 CFR 50.69 2024-09-04
[Table view] |
Text
NRR-PMDAPEm Resource From: Saba, Farideh Sent: Tuesday, July 10, 2012 4:58 PM To: Murray, William R. (Bill)
Cc: Lingam, Siva
Subject:
Brunswick 1 & 2: Diesel Generators completion Time Extension for TS 3.8.1 (ME8893 and ME8894)
Importance: High By letter dated June 19, 2012, Carolina Power & Light (the licensee) submitted a license amendment request for Brunswick Steam Electric Plant Unit Nos. 1 and 2 . The proposed amendment would extend the completion Time of TS 3.8.1 required action D.4 for an inoperable diesel generator. The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
Please let me know, if you have any questions, Farideh E. Saba, P.E.
Senior Project Manager NRC/ADRO/NRR/DORL 301-415-1447 Mail Stop O-8G9A Farideh.Saba@NRC.GOV 1
Hearing Identifier: NRR_PMDA Email Number: 406 Mail Envelope Properties (Farideh.Saba@nrc.gov20120710165700)
Subject:
Brunswick 1 & 2: Diesel Generators completion Time Extension for TS 3.8.1 (ME8893 and ME8894)
Sent Date: 7/10/2012 4:57:43 PM Received Date: 7/10/2012 4:57:00 PM From: Saba, Farideh Created By: Farideh.Saba@nrc.gov Recipients:
"Lingam, Siva" <Siva.Lingam@nrc.gov>
Tracking Status: None "Murray, William R. (Bill)" <william.murray@pgnmail.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 2424 7/10/2012 4:57:00 PM Options Priority: High Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:
Recipients Received: ZZZ