MONTHYEARSBK-L-11245, License Amendment Request 11-04, Changes to the Technical Specifications for New and Spent Fuel Storage2012-01-30030 January 2012 License Amendment Request 11-04, Changes to the Technical Specifications for New and Spent Fuel Storage Project stage: Request ML1207302702012-03-30030 March 2012 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Acceptance Review ML12131A3782012-05-10010 May 2012 Annual Assessment Meeting Signing Sheets April 2012 Project stage: Request SBK-L-12099, Supplement to LAR 11-04, Changes to the Technical Specifications for New and Spent Fuel Storage2012-05-10010 May 2012 Supplement to LAR 11-04, Changes to the Technical Specifications for New and Spent Fuel Storage Project stage: Supplement ML1204105872012-06-19019 June 2012 Acceptance Letter Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Acceptance Review ML1213500632012-06-20020 June 2012 Request for Withholding Information from Public Disclosure Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Withholding Request Acceptance ML1204106342012-06-20020 June 2012 Request for Withholding Information from Public Disclosure Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Withholding Request Acceptance ML12192A2322012-07-24024 July 2012 Request for Additional Information Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: RAI SBK-L-12199, Response to Request for Additional Information Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage2012-09-20020 September 2012 Response to Request for Additional Information Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Response to RAI ML12264A6292012-09-20020 September 2012 Notice of Appearance for Anita Ghosh Project stage: Request ML12270A4312012-10-0202 October 2012 Request for Withholding Infomation from Public Disclosure Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Other ML12270A4232012-12-0505 December 2012 Non-Proprietary - Request for Additional Information Regarding License Amendment Request 11-04. Changes to Technical Specifications for New and Spent Fuel Storage Project stage: RAI SBK-L-13061, Response to December 2012 Request for Additional Information Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage2013-03-27027 March 2013 Response to December 2012 Request for Additional Information Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Request ML13095A1222013-04-26026 April 2013 Request for Withholding Information from Public Disclosure Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Withholding Request Acceptance ML13095A0262013-04-26026 April 2013 Request for Withholding Information from Public Disclosure Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Withholding Request Acceptance ML13095A1012013-05-0202 May 2013 Request for Withholding Information from Public Disclosure Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Withholding Request Acceptance ML13094A4092013-05-0202 May 2013 Request for Withholding Information from Public Disclosure Regarding License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: Withholding Request Acceptance L-2013-334, Ctr., and Point Beach, Units 1 & 2, 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2013-12-20020 December 2013 Ctr., and Point Beach, Units 1 & 2, 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums Project stage: Request SBK-L-13224, Request for Review and Approval of License Amendment Request (LAR) 11-04, Changes to Technical Specifications for New and Spent Fuel Storage, in Two Parts2013-12-20020 December 2013 Request for Review and Approval of License Amendment Request (LAR) 11-04, Changes to Technical Specifications for New and Spent Fuel Storage, in Two Parts Project stage: Request ML13268A4682014-01-0808 January 2014 Request for Additional Information for License Amendment Request 11-04, Changes to Technical Specifications for New and Spent Fuel Storage Project stage: RAI SBK-L-14018, Response to Request for Additional Information for License Amendment Request 11-04, Changes to Technical Specifications for Spent Fuel Storage2014-01-29029 January 2014 Response to Request for Additional Information for License Amendment Request 11-04, Changes to Technical Specifications for Spent Fuel Storage Project stage: Response to RAI ML14184A7952014-09-0303 September 2014 Issuance of Amendment Regarding License Amendment Request Regarding Fuel Storage Changes Project stage: Approval SBK-L-15036, Response to Request for Additional Information for License Amendment Request 11-04, Changes to Technical Specifications for New Fuel Vault2015-02-25025 February 2015 Response to Request for Additional Information for License Amendment Request 11-04, Changes to Technical Specifications for New Fuel Vault Project stage: Response to RAI 2012-09-20
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 24, 2012 Mr. Kevin Walsh Site Vice President clo Michael O'Keefe Seabrook Station NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874
SUBJECT:
SEABROOK STATION, UNIT NO.1 - REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST 11-04, CHANGES TO TECHNICAL SPECIFICATIONS FOR NEW AND SPENT FUEL STORAGE (TAC NO. ME8688)
Dear Mr. Walsh:
By letter dated January 30,2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12038A036), as supplemented by letter dated May 10, 2012 (ADAMS Accession No. ML12136A126), NextEra Energy Seabrook, LLC (NextEra) submitted license amendment request (LAR) 11-04 for Seabrook Station, Unit 1. The proposed change revises the Technical Specifications (TSs) for new and spent fuel storage, as a result of the new criticality analyses for the new fuel vault (NFV) and the spent fuel pool (SFP),
The proposed amendment would revise the TSs to: (1) reflect elimination of the need to credit Boraflex neutron absorbing material for reactivity control in the SFP; (2) credit soluble boron, burnup, cooling time, peripheral leakage, and rod cluster control assemblies within the storage racks to maintain SFP reactivity within the effective neutron multiplication factor (keff) limits of Title 10 of the Code of Federal Regulations (10 CFR), Section 50.68(b)(4); and (3) revise the requirements for fuel storage within the NFV.
The U.S. Nuclear Regulatory Commission (NRC) staff has determined that additional information is required to complete its review. The NRC staff's request for additional information (RAI) is contained in the enclosed RAI. A draft of these questions was previously sent to Mr. Gary Kilby of your staff with an opportunity to have a teleconference to ensure that the licensee understood the questions and their regulatory basis, as well as to verify that the information was not previously docketed. A conference call was held on July 11, 2012, and Mr. Kilby agreed that NextEra would respond to the RAI within 60 days of the date of this letter. Please note that if you do not respond to the RAJ within 60 days, the NRC staff may reject your request for relief under the provisions of Title 10 of the Code of Federal Regulations, Section 2.108, "Denial of application for failure to supply information."
K. Walsh
- 2 If you have any questions, please contact me at (301) 415-3100.
G. Lamb, Senior Project Manager Pat Licensing Branch 1-2 i sion of Operating Reactor Licensing ice of Nuclear Reactor Regulation Docket No. 50-443 cc: Distribution via Listserv
REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST 11-04, CHANGES TO TECHNICALSPECIFICATIONS FOR NEW AND SPENT FUEL STORAGE NEXTERA ENERGY SEABROOK. LLC SEABROOK STATION, UNIT 1 DOCKET NUMBER 50-443 1.0 SCOPE By letter dated January 30, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12038A036), as supplemented by letter dated May 10, 2012 (ADAMS Accession No. ML12136A126), NextEra Energy Seabrook, LLC (NextEra) submitted a license amendment request (LAR) 11-04 for Seabrook Station, Unit 1. The proposed change revises the Technical Specifications (TSs) for new and spent fuel storage as the result of a new criticality analyses for the new fuel vault (NFV) and the spent fuel pool (SFP).
The proposed amendment would revise TSs to: (1) reflect elimination of the need to credit Boraflex neutron absorbing material for reactivity control in the SFP; (2) credit soluble boron, burnup, cooling time, peripheral leakage, and rod cluster control assemblies within the storage racks to maintain SFP reactivity within the effective neutron multiplication factor (keff) limits of Title 10 of the Code of Federal Regulations (10 CFR), Section 50.68(b)(4); and (3) revise the requirements for fuel storage within the NFV.
The U.S. Nuclear Regulatory Commission (NRC) staff has determined that additional information is required to complete its review. The NRC staft's request for additional information (RAI) is contained below.
2.0 RAI In the letter dated May 10, 2012, NextEra states that the acceptance criteria is 45 mil for the uniform void. Please clarify how the 45 mil limit was determined and why the uniform void is the conservative parameter to model the blisters. Also, please clarify how the uniform void volume is calculated including what measured blister dimensions are used in the calculations.
Enclosure
K. Walsh
- 2 If you have any questions, please contact me at (301) 415-3100.
Sincerely, Ira!
John G. Lamb, Senior Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPLI-2 R/F RidsNrrLAABaxter Resource RidsNRRDor1Lp11-2 Resource RidsOgcRP Resource RidsNrrPMSeabrook Resource RidsNrrDorlDpr Resource RidsRgn1 MailCenter Resource RidsNrrDorlResource RidsAcrsAcnw_MailCTR Resource ADAMS Accession No: ML12192A232 fl
~-""--""
- / OFFICE LPL 1-2/PM " LPL 1-2/LA i LPL1-2/BC i LPL 1-2/PM
~AME
! JLamb
' AB.,te,
! MKhanna JLamb
~ATE i 07/23/12 I 07/16/12: 07/24/12 07124112 OFFICIAL RECORD COp~y:=====~====d