Riverkeeper (Riv) Pre-Filed Hearing Exhibit RIVR00001, Riverkeeper Hearing Exhibits Lists (Riv Exhibit List)
ML12171A557
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 06/19/2012
From:
Riverkeeper
To:
Atomic Safety and Licensing Board Panel
SECY RAS
Shared Package
ML12171A553 List:
References
RAS 22625, 50-247-LR, 50-286-LR, ASLBP 07-858-03-LR-BD01
Download: ML12171A557 (13)


Text

1 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIVR00001 All Riverkeeper Hearing Exhibit List ("RIV Exhibit List")

Dec. 22, 2011 RIV000002 RK-TC-2 Riverkeeper Initial Statement of Position Regarding Contention RK-TC Flow Accelerated Corrosion ("RK-TC-2 SOP")

Dec. 22, 2011 RIV000003 RK-TC-2 Pre-Filed Testimony of Joram Hopenfeld in Support of RK-TC-2 ("Hopenfeld Testimony RK-TC-2")

Dec. 22, 2011 RIV000004 RK-TC-2 Curriculum Vitae of Joram Hopenfeld ("Hopenfeld CV")

Dec. 22, 2011 RIV000005 RK-TC-2 Report of Joram Hopenfeld in Support of RK-TC-2 ("Hopenfeld RK-TC-2 Report")

Dec. 22, 2011 RIV000006 RK-TC-2 NRC Information Notice No 86-106, Feed Water Line Break, December 16, 1986 ("NRC IN 86-106")

Dec. 22, 2011 RIV000007 RK-TC-2 NRC Bulletin 87-01, Thinning Pipe Walls in Nuclear Plants, July 9, 1987

("NRC Bulletin 87-01")

Dec. 22, 2011 RIV000008 RK-TC-2 NRC Information Notice 1991-019, Steam Generator Feed Water Distribution Piping Damage," March 12, 1991 ("NRC IN 1991-019")

Dec. 22, 2011 RIV000009 RK-TC-2 Monitoring Report 5-93-0042, Steam Generator Feedring Nozzle Through Wall Erosion, June 15, 1993 ("NRC MR 5-93-0042")

Dec. 22, 2011 RIV000010 RK-TC-2 NRC Information Notice 1997-084, Rupture of Extraction Steam Piping,"

December 11, 1997 ("NRC IN 1997-084")

Dec. 22, 2011 RIV000011 RK-TC-2 NRC Information Notice 2006-008, Secondary Piping Rupture at Mihama Power Station in Japan," March 16, 2006 ("NRC IN 2006-008")

Dec. 22, 2011 RIVR00001 Revised: June 19, 2012

2 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000012 RK-TC-2 EPRI, Recommendations for an Effective Flow-Accelerated Corrosion Program, NSAC-202L-R3 ("EPRI NSAC-202L-R3")

Dec. 22, 2011 RIV000013 RK-TC-2 Safety Evaluation by the Office of Nuclear Reactor Regulations Related to Amendment No. 229 to Facility Operating License No. DPR-28 Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc.

(Vermont Power Station, Docket No. 50-571), at § 2.8.7.1, p. 190, ADAMS Accession No. ML060050028 ("VY Safety Eval")

Dec. 22, 2011 RIV000014 RK-TC-2 Aging Management Program Evaluation Report - Non-Class 1 Mechanical, IP-RPT-06-LRD07, Revision 5, March 18, 2009 ("AMP Eval Report Rev 5")

Dec. 22, 2011 RIV000015 RK-TC-2 EN-DC-315, Revision 3, Flow Accelerated Corrosion Program (March 1, 2010) ("Entergy FAC Program")

Dec. 22, 2011 RIV00016A RK-TC-2 Graphs excerpted from CHECWORKS Reports ("CHECWORKS Wear Graphs Part 1")

Dec. 22, 2011 RIV00016B RK-TC-2 Graphs excerpted from CHECWORKS Reports ("CHECWORKS Wear Graphs Part 2")

Dec. 22, 2011 RIV000017 RK-TC-2 V.K. Chexal, W.H. Layman, & J.S. Horowitz, Tackling the Single-Phase Erosion Corrosion Issue, To Be Presented at the American Power Conference April 18-20, 1988, Chicago Illinois (EPRI) ("Chexal APC")

Dec. 22, 2011

3 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000018 RK-TC-2 CHECWORKSTM Steam/Feedwater Application, Guidelines for Plant Modeling and Evaluation of Component Inspection Data, 1009599, Final Report, September 2004, IPECPROP00000271, at p.6-7 (IPECPROP00000334) ("CHECWORKS Proprietary Report 1009599")

Dec. 22, 2011 RIV000019 RK-TC-2 Rudolf H. Hausler, Flow Assisted Corrosion (FAC) and Flow Induced Localized Corrosion: Comparison and Discussion, at 1, 8 (RHH Rebuttal, June 2, 2008, Vermont Yankee License Renewal Proceeding, 06-849-03-LR

("Hausler VY Testimony")

Dec. 22, 2011 RIV000020 RK-TC-2 CSI, Technologies, Inc., Indian Point Unit 3 CHECWORKS SFA Model, Calculation No. 0705.100-01, Revision 2, August 2, 2011, at p.26 (excerpt re:

LCF) ("IP3 CHECWORKS SFA Model Aug 2011")

Dec. 22, 2011 RIV000021 RK-TC-2 CSI, Technologies, Inc., Indian Point Unit 3 CHECWORKS SFA Model, Calculation No. 0705.100-01, Revision 2, August 2, 2011, Appendix K -

Components with Negative Time to Tcrit, IPEC00238096 ("CHECWORKS SFA Model Aug 2011 App K")

Dec. 22, 2011 RIV000022 RK-TC-2 Statement by Dr. F. Peter Ford, transcript of January 26, 2005 meeting of the ACRS Subcommittee on Thermal Hydraulics (January 26, 2005), at 198, ADAMS Accession No. ML050400613 ("2005 ACRS Transcript")

Dec. 22, 2011

4 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000023 RK-TC-2 NUREG/CR-6936, PNNL 16186,Probabilities of Failure and Uncertainty Estimate Information for Passive Components - a Literature Review (May 2007) ("NUREG/CR-6936")

Dec. 22, 2011 RIV000024 RK-TC-2 Entergy Engineering Report, Operating Experience Review Report, IP-RPT LRD05, Rev. 3 (2008), IPEC00186046 ("Entergy Op Ex Rev Report")

Dec. 22, 2011 RIV000025 RK-TC-2 Daily DER Report, DER-01-01522, April 25, 2001, IPEC00020501 ("DER Report")

Dec. 22, 2011 RIV000026 RK-TC-2 Entergy Operations, Inc, Condition Report List, IPEC00185743 ("Condition Report List 1")

Dec. 22, 2011 RIV000027 RK-TC-2 Entergy Operations, Inc., Condition Report List, IPEC00092551 ("Condition Report List 2")

Dec. 22, 2011 RIV000028 RK-TC-2 Entergy Condition Report CR-IP2-2001-10525, IPEC00092616 ("Entergy CR-IP2-2001-10525")

Dec. 22, 2011 RIV000029 RK-TC-2 Entergy Condition Report CR-IP3-2006-02270, IPEC00025699 ("Entergy CR-IP3-2006-02270")

Dec. 22, 2011 RIV000030 RK-TC-2 Transcript of Meeting of Advisory Committee on Reactor Safeguards (Sept.

10, 2009), ADAMS Accession No. ML092670114, at 90-96 ("ACRS Mtg Transcript Sept 2009")

Dec. 22, 2011

5 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000031 RK-TC-2 Lynn R. Sykes, John G. Armbruster, Won-Young Kim, & Leonardo Seeber, Observations and Tectonic Setting of Historic and Instrumentally Located Earthquakes in the Greater New York City-Philadelphia Area, Bulletin of the Seismological Society of America, Vol. 98, No. 4, pp. 1696-1719, August 2008 ("Sykes Study")

Dec. 22, 2011 RIV000032 RK-TC-2 Generic Issue 199 (GI-199), Implications of Updated Probabilistic Seismic Hazard Estimates in Central and Eastern United States on Existing Plants Safety/Risk Assessment, August 2010, at Appendix D ("Seismic Sore-Damage Frequencies) ("NRC GI-199")

Dec. 22, 2011 RIV000033 RK-TC-2 Bill Dedman, What are the odds? US nuke plants ranked by quake risk, March 17, 2011 ("Dedman Article")

Dec. 22, 2011 RIV000034 RK-TC-1B Dr.Hopenfeld Pre-filed Testimony Dec. 22, 2011 RIV000035 RK-TC-1B; RK-TC-5 Dr. Hopenfeld Report Dec. 22, 2011 RIV000036 RK-TC-1B; RK-TC-5 Westinghouse "EnvFat User's Manual Version 1" IPECPROP00056785 Dec. 22, 2011 RIV000037 RK-TC-1B; RK-TC-5 Official Transcript, ACRS Subcommittee, 12/6/2006 Dec. 22, 2011 RIV000038 RK-TC-1B; RK-TC-5 NRC IN 2011-04 Dec. 22, 2011 RIV000039 RK-TC-1B; RK-TC-5 Entergy Nuclear Vt. Yankee, Affidavit of Kenneth C. Chang, 5/12/08 Dec. 22, 2011 RIV000040 RK-TC-1B; RK-TC-5 Taylor, EPRI R & D Status Report, Jan/Feb 1983 Dec. 22, 2011 RIV000041 RK-TC-1B; RK-TC-5 Entergy, Table of Environmental Correction Actions for Metal Fatigue, 11/6/07 Dec. 22, 2011

6 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000042 RK-TC-1B; RK-TC-5 DC Cook Charging Nozzle LR Fatigue Evaluations, IPECPROP00061294 Dec. 22, 2011 RIV000043 RK-TC-1B; RK-TC-5 Diablo Canyon Unit 1 Insurge/Outsurge Eval, IPECPROP00061179 Dec. 22, 2011 RIV000044 RK-TC-1B; RK-TC-5 NRC Bulletin 88-08 Dec. 22, 2011 RIV000045 RK-TC-1B; RK-TC-5 NRC Bulletin 88-08 Supp. 1 Dec. 22, 2011 RIV000046 RK-TC-1B; RK-TC-5 NRC Bulletin 88-08 Supp. 2 Dec. 22, 2011 RIV000047 RK-TC-1B; RK-TC-5 NRC IN 97-46 Dec. 22, 2011 RIV000048 RK-TC-1B; RK-TC-5 Final Report of the NESC-Thermal Fatigue Project, EUR22763 Dec. 22, 2011 RIV000049 RK-TC-1B; RK-TC-5 Entergy Indian Point U3, FAC, 3RF13 Outage, 2005 Dec. 22, 2011 RIV000050 RK-TC-1B; RK-TC-5 Westinghouse, WCAP-14950, IPECPROP00059247 Dec. 22, 2011 RIV000051 RK-TC-1B; RK-TC-5 Kwang Chu Kim, Journal of Mechanical Science/Technology, 2008 Dec. 22, 2011 RIV000052A-D RK-TC-1B; RK-TC-5 Combustion Engineering, Inc., CENC-1110 Dec. 22, 2011 RIV000053 RK-TC-1B; RK-TC-5 Combustion Engineering, Inc., CENC-1122 Dec. 22, 2011 RIV000054 RK-TC-1B; RK-TC-5 letter from P. Bessette to D. Brancato, 10/18/11 Dec. 22, 2011 RIV000055 RK-TC-1B; RK-TC-5 Westinghouse CN-PAFM-09-64, IPECPROP00058077 Dec. 22, 2011 RIV000056 RK-TC-1B; RK-TC-5 Systems Standard Design Criteria, IPECPROP00059698 Dec. 22, 2011 RIV000057 RK-TC-1B; RK-TC-5 RAI Indian Point U2 and U3 LRA, 2/10/11 Dec. 22, 2011 RIV000058 RK-TC-1B; RK-TC-5 Response to RAI, Indian Point U2 and U3, 3/28/11 Dec. 22, 2011

7 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000059 RK-EC-3/CW-EC-1 Riverkeeper and Clearwater Initial Statement of Position Regarding Consolidated Contention RK-EC-3/CW-EC-1 (Spent Fuel Pool Leaks) ("RK-EC-3-CW-EC-1 SOP")

Dec. 22, 2011 RIV000060 RK-EC-3/CW-EC-1 Testimony of Arnold Gundersen on Consolidated Contention RK-EC-3/CW-EC Spent Fuel Pool Leaks ("Gundersen Testimony")

Dec. 22, 2011 RIV000061 RK-EC-3/CW-EC-1 Testimony of Gillian Stewart on Consolidated Contention RK-EC-3/CW-EC-1

- Spent Fuel Pool Leaks ("Stewart Testimony")

Dec. 22, 2011 RIV000062 RK-EC-3/CW-EC-1 Curriculum Vitae of Arnold Gundersen ("Gundersen CV")

Dec. 22, 2011 RIV000063 RK-EC-3/CW-EC-1 Curriculum Vitae of Gillian Stewart ("Stewart CV")

Dec. 22, 2011 RIV000064 RK-EC-3/CW-EC-1 NUREG-1437, Revision 1, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (July 2009) Draft Report for Comment

("GEIS Update")

Dec. 22, 2011 RIV000065 RK-EC-3/CW-EC-1 U.S. EPA, Radionuclides in Drinking Water: A Small Entity Compliance Guide (February 2002)

Dec. 22, 2011 RIV000066 RK-EC-3/CW-EC-1 GZA, GeoEnvironmental, Inc., Hydrogeologic Site Investigation Report, Indian Point Energy Center, January 7, 2008, IPEC00195418 Dec. 22, 2011

8 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000067 RK-EC-3/CW-EC-1 Indian Point Nuclear Generating Units 1 & 2 - NRC Inspection Report Nos.

05000003/2007010 and 05000247/2007010, EA-08-088, May 13, 2008 Dec. 22, 2011 RIV000068 RK-EC-3/CW-EC-1 Entergy, Groundwater Investigation Executive Summary, Indian Point Energy Center, Buchanan, NY (January 2008)

Dec. 22, 2011 RIV000069 RK-EC-3/CW-EC-1 Indian Point Nuclear Generating Unit 2 - NRC Special Inspection Report No.

05000247/2005011, March 16, 2006 Dec. 22, 2011 RIV000070 RK-EC-3/CW-EC-1 Indian Point Energy Center Status Report (Sept. 6, 2007)

Dec. 22, 2011 RIV000071 RK-EC-3/CW-EC-1 In the Matter of Entergy Nuclear Indian Point 2, LLC, and Entergy Nuclear Indian Point 3, LLC, and Entergy Nuclear Operations Incs Joint Application for CWA § 401 Water Quality Certification, Prefiled Testimony of Matthew J.

Barvenik, Issue for Adjudication No. 3 - Radiological Materials (July 22, 2011)

Dec. 22, 2011 RIV000072 RK-EC-3/CW-EC-1 E-mail from Michael Rutkoske to Steven Verrochi (Entergy), Re: SFP Exams -

What's Next? (Nov. 19, 2005), IPEC00065830 Dec. 22, 2011 RIV000073 RK-EC-3/CW-EC-1 Entergy, U2 SFP Leak Monitoring Wells and Underground Piping (3/31/06),

IPEC00063518 Dec. 22, 2011 RIV000074 RK-EC-3/CW-EC-1 Entergy, Problem Development Sheet - Groundwater, IPEC00207416 Dec. 22, 2011

9 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000075 RK-EC-3/CW-EC-1 E-mail from Ronald Sachatello to Donald Mayer (Entergy), Joseph Adler (TLG), Gary Hinrichs (Entergy), Re: IS THE POOL LEAK OFF COLLECTION BOX EFFECTIVE?, IPEC00063351 Dec. 22, 2011 RIV000076 RK-EC-3/CW-EC-1 GZA, GeoEnvironmental, Inc. Final IPEC Quarterly Long-Term Groundwater Monitoring Report, Quarter Two 2010 (Report No. 10) (February 15, 2011),

IPEC00227561 Dec. 22, 2011 RIV000077 RK-EC-3/CW-EC-1 Entergy Chart of Leak Locations, I PEC00059360 Dec. 22, 2011 RIV000078 RK-EC-3/CW-EC-1 IPEC Site Management Manual, IP-SMM, CY-110, Rev. 1, 8.6 RGWMP Quarterly Integrated Review Checklist (Quarter 1, 2009), IPEC00225217 Dec. 22, 2011 RIV000079 RK-EC-3/CW-EC-1 Annie Correal, Indian Pt. Broken Pipe Spurs Safety Worries, THE NEW YORK TIMES (March 1, 2009)

Dec. 22, 2011 RIV000080 RK-EC-3/CW-EC-1 IPEC Site Management Manual, IP-SMM, CY-110, Rev. 3, 8.6 RGWMP Quarterly Integrated Review Checklist (Quarter 1, 2010), IPEC00225219 Dec. 22, 2011 RIV000081 RK-EC-3/CW-EC-1 IPEC Site Management Manual, IP-SMM, CY-110, Rev. 1, 8.6 RGWMP Quarterly Integrated Review Checklist (Quarter 2, 2010), IPEC00225223 Dec. 22, 2011 RIV000082 RK-EC-3/CW-EC-1 Entergy, Nuclear Management Manual, EN-MA-125, Rev. 4, Attachment 9.1, Initial Investigation, Troubleshooting Plan for H-3 Investigation, Storm Drain System A, March/April 2009, IPEC00194517 Dec. 22, 2011

10 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000083 RK-EC-3/CW-EC-1 IPEC Site Management Manual, IP-SMM, CY-110, Rev. 3, 8.6 RGWMP Quarterly Integrated Review Checklist (Quarter 4, 2010), IPEC00233519 Dec. 22, 2011 RIV000084 RK-EC-3/CW-EC-1 IPEC Site Management Manual, IP-SMM, CY-110, Rev. 4, 10.7 RGWMP Quarterly Integrated Review Checklist (Quarter 1, 2011), IPEC00233515 Dec. 22, 2011 RIV000085 RK-EC-3/CW-EC-1 Indian Point Nuclear Generating Unit 3 - NRC Integrated Inspection Report 05000286/2011004 (November 7, 2011)

Dec. 22, 2011 RIV000086 RK-EC-3/CW-EC-1 Entergy correspondence, e-mails regarding approach to groundwater contamination, IPEC00067228, IPEC00065510, IPEC00130549, IPEC00062936 Dec. 22, 2011 RIV000087 RK-EC-3/CW-EC-1 Potential Sources of Tritium at IPEC & Inspection Method, IPEC00065506 Dec. 22, 2011 RIV000088 RK-EC-3/CW-EC-1 Supplemental Report of the Public Oversight Panel Regarding the Comprehensive Reliability Assessment of the Vermont Yankee Nuclear Power Plant, July 20, 2010 Dec. 22, 2011 RIV000089 RK-EC-3/CW-EC-1 GAO Report to Congressional Requesters, Nuclear Regulatory Commission, Oversight of Underground Piping Systems Commensurate with Risk, but Proactive Measures Could Help Address Future Leaks, GAO-11-563 (June 2011)

Dec. 22, 2011 RIV000090 RK-EC-3/CW-EC-1 Entergy Groundwater Well Data, Quarter 2, 2011, IPEC00225100 Dec. 22, 2011

11 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000091 RK-EC-3/CW-EC-1 Liquid Radioactive Release Lessons Learned Task Force Final Report, U.S.

NRC (September 1, 2006)

Dec. 22, 2011 RIV000092 RK-EC-3/CW-EC-1 Coastal Fish & Wildlife Habitat Rating Form, Haverstraw Bay Dec. 22, 2011 RIV000093 RK-EC-3/CW-EC-1 National Research Council, Health Risks from Exposure to Low Levels of Ionizing Radiation: BEIR VII - Phase 2 (2006)

Dec. 22, 2011 RIV000094 RK-EC-3/CW-EC-1 Entergy E-mail from David Winslow (GZA) to Donald Mayer (Entergy), G.

Hinrichs (Entergy), Re: Remedial Report (May 19, 2006), IPEC00064221 Dec. 22, 2011 RIV000095 RK-EC-3/CW-EC-1 Groundwater Investigation 06 Quarter 4 Activities and Results, IPEC00063899 Dec. 22, 2011 RIV000096 RK-EC-3/CW-EC-1 Entergy E-mail from Kathleen McMullin (Entergy) to various, Re: IPEC Status Report for Dec. 21 Dec. 22, 2011 RIV000097 RK-EC-3/CW-EC-1 Entergy Document, Unit 1 Status for ENC Presentation notes, Groundwater Status, IPEC00062939 Dec. 22, 2011 RIV000098 RK-EC-3/CW-EC-1 Letter from Kathryn Sutton (Counsel for Entergy) to Deborah Brancato (Riverkeeper), Re: Entergy Nuclear Operations, Inc. (Indian Point Nuclear Generating Units 2 and 3), Docket Nos. 50-247-LR and 50-286-LR (June 24, 2011)

Dec. 22, 2011

12 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000099 RK-EC-3/CW-EC-1 In the Matter of Entergy Nuclear Indian Point 2, LLC, and Entergy Nuclear Indian Point 3, LLC, and Entergy Nuclear Operations Incs Joint Application for CWA § 401 Water Quality Certification, Combined Prefiled Rebuttal Testimony of Thomas C. Esselman, Ph.D., Matthew J. Barvenik, and Owen Hoffman, Ph.D., Radiological - Issue for Adjudication No. 3 (October 4, 2011)

Dec. 22, 2011 RIV000100 RK-EC-3/CW-EC-1 E-mail From Dara Gray (Entergy) to J. Noggle (NRC) (Jan. 24, 2007), Re:

Historical Sr Data (Exhibit RIV000100)

Dec. 22, 2011 RIV000101 RK-EC-3/CW-EC-1 Haverstraw Water Supply Project DEIS, Draft EIS Chapter 2 Dec. 22, 2011 RIV000102 RK-TC-5 Pre-Filed Testimony of Joram Hopenfeld in Support of RK-TC-5 June 19, 2012 RIV000103 RK-TC-5; RK-TC-1B Hopenfeld, Small Sodium-to-Gas Leak Behavior in Relation to LMFBR Leak Detection System Design (International Conference on Liquid Metal Technology, May 3-6, 1976)

June 19, 2012 RIV000104 RK-TC-5; RK-TC-1B Memorandum from S. Collins (NRR) to W. Travers (EDO), Re: Steam Generator Action Plan Revision to Address Differing Professional Opinion on Steam Generator Tube Integrity (WITS ITEM 200100026), May 11, 2011 June 19, 2012

13 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),

Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing Riverkeeper ("RIV") Hearing Exhibits RIV Exhibit #

Contentions Addressed by Exhibit Exhibit Name Exhibit Submission Date RIV000105 RK-TC-5; RK-TC-1B NUREG-1740, Voltage-Based Alternative Repair Criteria, A Report to the Advisory Committee on Reactor Safeguards by the Ad Hoc Subcommittee on a Differing Professional Opinion (March/Feb. 2001)

June 19, 2012 RIV000106 RK-TC-5; RK-TC-1B Associated Press, Nuke inspectors focus on 'unusual' wear on tubes, Fox News.com, February 3, 2012 June 19, 2012