Notification of Inspection and Request for Information
ML121510378
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 05/24/2012
From: Vias S
NRC/RGN-II/DRS/EB3
To: Annacone M
Progress Energy Carolinas
References
Download: ML121510378 (8)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 May 24, 2012 Mr. Michael J. Annacone Vice President Brunswick Steam Electric Plant P.O. Box 10429 Southport, NC 28461-0429

SUBJECT:

BRUNSWICK NUCLEAR PLANT - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Annacone:

The Nuclear Regulatory Commission (NRC) will perform the Triennial Baseline Heat Sink Inspection (HS) at the Brunswick Nuclear Plant from July 16 - 20, 2012. Experience has shown that this inspection is resource intensive for both the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups. The first group (Section A of the Enclosure) identifies information to be provided prior to the inspection to ensure that the inspectors are adequately prepared. The second group (Section B of the Enclosure) identifies the information the inspectors will need upon arrival at the site. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection.

We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Mr. Lee Grzeck of your organization. Our inspection dates are subject to change based on your updated schedule. If there are any questions about this inspection or the material requested, please contact the lead inspector Matt Endress at 404-997-4524 (matthew.endress@nrc.gov).

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its Enclosure will be available electronically for public inspection in the NRC Public Document

CP&L 2

Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Steven J. Vias, Branch Chief Engineering Branch 3 Division of Reactor Safety Docket No.

50-325, 50-324 License No. DPR-71, DPR-62

Enclosure:

Pre-Inspection Document Request cc w/encl: (See page 3)

_ml121510378 ____________ X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII/DRS: EB-3 RII/DRS: EB-3 RII/DRS: EB-3 SIGNATURE RA RA RA NAME M. Endress C. Fletcher S. Vias DATE 5/ 17 /2012 5/ 17 /2012 5/ 17 /2012 E-MAIL COPY YES NO YES NO YES NO

CP&L 3

cc w/encl:

Edward L. Wills, Jr.

Director Site Operations Brunswick Steam Electric Plant Electronic Mail Distribution Robert J. Duncan II Vice President Nuclear Operations Progress Energy Electronic Mail Distribution Joseph M. Frisco, Jr.

Plant General Manager Brunswick Steam Electric Plant Progress Energy Electronic Mail Distribution Annette H. Pope Manager, Support Services Brunswick Steam Electric Plant Progress Energy Carolinas, Inc.

Electronic Mail Distribution Lee Grzeck Supervisor - Licensing/Regulatory Programs (Acting)

Brunswick Steam Electric Plant Progress Energy Carolinas, Inc.

Electronic Mail Distribution Randy C. Ivey Manager, Nuclear Oversight Brunswick Steam Electric Plant Progress Energy Carolinas, Inc.

Electronic Mail Distribution Paul E. Dubrouillet Manager, Training Brunswick Steam Electric Plant Electronic Mail Distribution Kelvin Henderson General Manager Nuclear Fleet Operations Progress Energy Electronic Mail Distribution Joseph W. Donahue Vice President Nuclear Oversight Progress Energy Electronic Mail Distribution David T. Conley Senior Counsel Legal Department Progress Energy Electronic Mail Distribution Senior Resident Inspector U.S. Nuclear Regulatory Commission Brunswick Steam Electric Plant U.S. NRC 8470 River Road, SE Southport, NC 28461 John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Peggy Force Assistant Attorney General State of North Carolina P.O. Box 629 Raleigh, NC 27602 Chairman North Carolina Utilities Commission Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff - NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Anthony Marzano Director Brunswick County Emergency Services Electronic Mail Distribution (cc w/encl contd - see page 4)

CP&L 4

(cc w/encl contd)

Public Service Commission State of South Carolina P.O. Box 11649 Columbia, SC 29211 W. Lee Cox, III Section Chief Radiation Protection Section N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Warren Lee Emergency Management Director New Hanover County Department of Emergency Management 230 Government Center Drive Suite 115 Wilmington, NC 28403

Enclosure HEAT SINK PERFORMANCE DOCUMENT REQUEST Inspection Dates:

July 16 - July 20, 2012 Inspection Procedures:

IP 71111.07 Heat Sink Performance Inspectors:

M. Endress, Reactor Inspector (Lead Inspector)

A.

Information Requested for the In-Office Preparation Week The following information should be sent to the Region II office in hard copy or electronic format (preferred), in care of Matt Endress by June 29, 2012 to facilitate the selection of specific items that will be reviewed during the on-site inspection week. The inspector will select specific items from the information requested below and then request from your staff additional documents needed during the on-site inspection week (Section B of this Enclosure). We ask that the specific items selected from the lists be available and ready for review on the first day of inspection. *Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the inspector(s), and provide subject documentation during the first day of the on-site inspection. If you have any questions regarding this information request, please call the inspector as soon as possible.

A.1 Heat Exchangers and Service Water Equipment a) List of heat exchangers (HXs) or equipment cooled by service water (SW) directly or indirectly

  • For HXs directly cooled by SW provide the schedule, procedures, and results of testing, inspection, maintenance, and monitoring of biotic fouling and macrofouling programs.

b) HX performance inspections methods and results for HXs that are inspected/cleaned c) Response to Generic Letter 89-13 d) Design Basis documents associated with the SW system e) Design Basis documents associated with the Ultimate Heat Sink (UHS) f) SW system flow diagrams g) Recent Health Reports associated with the SW System and systems that are cooled by SW h) List of SW system related corrective action documents (with a brief description) which have received a Root Cause Analysis or an elevated severity level in the last two year

2 Enclosure i) Recent (industry-wide) Operating Experience Events (2009-2012) documents that have been evaluated for applicability to the site in the area of the UHS or safety-related HXs j) List of applicable Codes and Industry Guidelines k) List of redundant or infrequently used HXs l) Chemistry Program procedures and documentation relevant to the SW system m) Provide whether the UHS is above ground encapsulated by embankments, weirs or excavated side slopes, underwater weir or excavation, or forced draft cooling tower or spray pond n) Provide a list of buried or inaccessible piping and the piping test program, inspection or monitoring program o) List of safety-related and non-safety related valve interface B.

Information to be provided on-site to the inspector at the entrance meeting (July 16, 2012):

B.1 Heat Exchangers and Service Water Equipment The inspector will select two to four heat exchangers and/or heat sink samples as required by the inspection procedure during in-office preparation. The following items will be requested when the selections are made.

a) Updated list of System Engineers b) List of any thru-wall leaks including completed or planned corrective actions, and structural evaluations c) Provide a copy of the corrective actions and supporting documentation d) For the HXs that have Visual and/or Eddy Current Testing performed provide a copy of the examination records, examiner qualification records, and associated corrective action documents.

e) Heat transfer calculations f) Evaluations for the potential of Water Hammer g) Documentation for controls and operational limits for excessive flow induced vibrations

3 Enclosure h) Periodic Flow test results at/or near maximum design flow i) For an UHS that is encapsulated by embankments, weirs of excavated side slopes provide (1) third party dam inspection results, and (2) documentation showing that there is sufficient reservoir capacity j) For an UHS that is an underwater weir or excavation provide documentation showing:

a. Periodic monitoring and trending of sediment build-up
b. Sufficient reservoir capacity
c. Considerations for adjacent non-seismic and/or non-safety related structures possible degradation, or blocking of safety-related flow paths due to severe weather, or seismic events
d. Performance monitoring of Heat Transfer capabilities
e. Performance monitoring of UHS structural integrity k) SW flow balance test results Inspector Contact Information:

Matt Endress Reactor Inspector 404-997-4524 Matthew.Endress@nrc.gov Mailing Address:

US NRC Region 2 Attn: Matt Endress Marquis One Tower 245 Peachtree Center Avenue, NE Suite 1200 Atlanta, GA 30303