Category:Letter
MONTHYEARML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23263A0192023-09-20020 September 2023 Operator Licensing Examination Approval ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 L-23-208, Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA00256152023-09-14014 September 2023 Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA0025615 L-23-167, Twenty-Third Refueling Outage Inservice Inspection Summary Report2023-09-13013 September 2023 Twenty-Third Refueling Outage Inservice Inspection Summary Report L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23219A0592023-08-0707 August 2023 Steam Generator Inspection Reports - Spring 2023 Spring Refueling Outrage L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-179, Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-07-18018 July 2023 Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA0025615 ML23188A0982023-07-17017 July 2023 Correction to the Safety Evaluation Issued Related to Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23188A0672023-07-10010 July 2023 Project Manager Assignment L-23-165, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-06-26026 June 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-139, Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report2023-06-13013 June 2023 Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 ML23143A0272023-05-23023 May 2023 Licensed Operator Positive Fitness-For-Duty Test L-23-055, Submittal of the Updated Final Safety Analysis Report, Revision 342023-05-23023 May 2023 Submittal of the Updated Final Safety Analysis Report, Revision 34 ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23135A7872023-05-19019 May 2023 Summary of Conference Calls Regarding the Spring 2023 Steam Generator Tube Inspections L-23-137, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-05-18018 May 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 L-23-125, Cycle 24 Core Operating Limits Report2023-05-17017 May 2023 Cycle 24 Core Operating Limits Report ML23124A3882023-05-16016 May 2023 Summary of Regulatory Audit in Support of License Amendment Request to Revise Technical Specification 5.6.3, Core Operating Limits Reports (COLR) and TS 4.2.1 Fuel Assemblies ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) L-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-129, Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations2023-05-0505 May 2023 Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23118A3812023-04-28028 April 2023 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations L-23-115, Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological2023-04-27027 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological L-23-126, Discharge Monitoring Report (Npdes), Permit No. PA00256152023-04-22022 April 2023 Discharge Monitoring Report (Npdes), Permit No. PA0025615 CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML23107A2502023-04-18018 April 2023 Requalification Program Inspection 2024-01-25
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary ML23237B4412023-09-29029 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Federal Register Notice, Direct and Indirect License Transfer Issuance Order ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23019A0032023-03-16016 March 2023 Issuance of Amendment Nos. 320 and 210 Adoption of Technical Specifications Task Force (Tstf) Traveler Tstf-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23062A5212023-03-0606 March 2023 Issuance of Amendment No. 319 Revise Technical Specification (TS) 3.5.2, ECCS Operating, Limiting Condition for Operation (LCO) 3.5.2, ML22277A8142022-10-0707 October 2022 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 315 and 205 Regarding Changes to the Emergency Preparedness Plan ML22210A0102022-09-16016 September 2022 Energy Harbor Fleet- Issuance of Amendments Regarding Adoption of TSTF 554, Revise Reactor Coolant Leakage Requirements ML22222A0862022-09-0101 September 2022 Issuance of Amendment Nos. 317 and 208 Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start and Bus Separation Instrumentation ML22140A2092022-06-28028 June 2022 Issuance of Amendment No. 207 Correct TS 3.1.7 Change Made by TSTF-547 ML22095A2352022-05-10010 May 2022 Issuance of Amendment Nos. 316 and 206 Revise Technical Specification 5.6.3, Core Operating Limits Report (COLR) ML21286A7822022-05-0606 May 2022 Issuance of Amendment Nos. 315 and 205 Regarding Changes to the Emergency Plan ML22077A1342022-05-0202 May 2022 Issuance of Amendment Nos. 314 and 204 Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML21320A3592021-11-23023 November 2021 Correction to License Page 4 ML21197A0092021-11-0101 November 2021 Issuance of Amendment Nos. 313 and 203 Reactor Coolant System, Pressure and Temperature Limits Report ML21214A2752021-10-15015 October 2021 Issuance of Amendment Nos. 312 and 202 Atmospheric Dump Valves ML21153A1762021-06-30030 June 2021 Issuance of Amendment No. 201 Revision of Technical Specifications Related to Steam Generator Tube Inspection, and Repair Methods ML21075A1132021-04-16016 April 2021 Issuance of Amendment Nos. 311, 200, and 302 to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, Into the Technical Specifications ML21070A0002021-03-22022 March 2021 Issuance of Amendment 310, Revise Technical Specification 5.5.5.1, Unit 1 SG Program, to Defer Spring 2021 Refueling Outage Steam Generator Inspections to Fall 2022 Refueling Outage ML20346A0222021-03-10010 March 2021 Issuance of Amendment Nos. 309 and 199 to Change Technical Specifications to Implement New Surveillance Methods for the Heat Flux Hot Channel Factor ML20335A0522021-02-18018 February 2021 Issuance of Amendment Nos. 308 and 198 to Modify Certified Fuel Handler Related Technical Specifications for Permanently Defueled Condition ML21034A3892021-02-18018 February 2021 Correction to Amendment Nos. 307 and 197 to Add Containment Sump Technical Specifications to Address Generic Safety Issue 191 Issues ML21014A3042021-02-0505 February 2021 Correction to Amendment Nos. 306 and 196 to Remove License Conditions B and C Related to the Irradiated Fuel Management Plans ML20345A2362021-01-28028 January 2021 Issuance of Amendment Nos. 307 and 197 to Add Containment Sump Technical Specifications to Address GSI-191 Issues ML21014A1142021-01-12012 January 2021 Correction Letter Notification from Licensee ML20335A0232020-12-28028 December 2020 Issuance of Amendment Nos. 306 and 196 to Remove License Conditions B and C Related to the Irradiated Fuel Management Plans ML20285A2662020-10-21021 October 2020 Correction to Safety Evaluation for Amendment Nos. 305 and 195 Issued September 23, 2020, Modify Primary and Secondary Coolant Activity Technical Specifications ML20213A7312020-09-23023 September 2020 Issuance of Amendment Nos. 305 and 195 to Modify Primary and Secondary Coolant Activity Technical Specifications ML20080H7112020-03-23023 March 2020 Correction Letter for Conforming License Amendments Nos. 304 and 194, Order Approving Transfer of Licenses and Conforming License Amendments ML20030A4402020-02-27027 February 2020 Issuance of Amendment Nos. 304, 194, 299, and 187; Order Approving Transfers of Facility Operating Licenses and Independent Spent Fuel Storage Installation General Licenses and Conforming Amendments ML19326A7592019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Non-Proprietary, Letter & Encl 2-5, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML18348B2062019-02-25025 February 2019 Issuance of Amendment No. 193 Revise Steam Generator Technical Specifications ML18179A4672018-07-30030 July 2018 FENOC-Beaver Valley Power Station, Unit No. 1 and 2; Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 - Issuance of Amendments Request to Adopt TSTF-529, Clarify Use and Application Rules ML18099A2322018-04-18018 April 2018 Correction of an Error in the Renewed Facility Operating License No. DPR-66 Associated with License Amendment No. 301 CAC No. MF3301; EPID L-2013-LLF-0001) ML18022B1162018-03-0101 March 2018 Issuance of Amendment Nos. 302 and 191 Regarding the Use of Optimized Zirlo Fuel Rod Cladding (CAC Nos. MF9580 and MF9581; EPID L-2017-LLA-0201) ML17291A0812018-01-22022 January 2018 Issuance of Amendments Transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (CAC Nos. MF3301 and MF3302; EPID L-2013-LLF-0001) ML18016A1032018-01-19019 January 2018 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 300 and 189 (CAC Nos. MF8448 and MF8449; EPID L-2016-LLA-0011 and EPID L-2017-LRO-0069) ML17216A5702017-10-12012 October 2017 Issuance of Amendments Emergency Action Level Scheme Changed Based on NEI 99-01, Revision 6 (CAC Nos. MF8448 and MF8449; EPID L-2016-LLA-0011) ML17221A2802017-08-16016 August 2017 Issuance of Amendments to Adopt Technical Specifications Task Force (TSTF) Traveler 547, Revision 1 ML17157B2842017-06-0707 June 2017 Correction to Conforming Amendment No. 187 Order to Transfer License ML17115A1232017-05-30030 May 2017 Issuance of Amendment Application for Order to Transfer License and Conforming Amendment ML17081A5092017-05-11011 May 2017 ISFSI, Davis-Besse ISFSI, Perry Nuclear Power Plant, Perry Nuclear Power Plant ISFSI - Issuance of Amendments Re. Application to Revise Technical Specifications to Adopt TSTF-545 Revision 3 ML17081A4332017-04-14014 April 2017 Nonproprietary, Order Approving Transfer of License and Conforming Amendment ML16040A0842016-06-0707 June 2016 FENOC, Beaver Valley Power Station, Unit Nos. 1 and 2; and Davis-Besse Nuclear Power Station, Unit No. 1 - Issuance of Amendments Revision to Technical Specification 5.3.1, Unit Staff Qualifications ML15294A4392015-12-16016 December 2015 Issuance of Amendments License Amendment Request to Revise Steam Generator Technical Specifications (CAC Nos. MF6054 and 6055) ML15302A4332015-12-0101 December 2015 Issuance of Amendments Request to Change Cyber Security Implementation Plan Milestone 8 Completion Date ML15208A2852015-07-28028 July 2015 Correction to Amendment Nos. 294 and 182 Regarding Modification of Emergency Preparedness Plan Regarding the Emergency Planning Zone Boundary ML15086A2512015-05-20020 May 2015 Issuance of Amendment Revise Technical Specification 4.3.2, Spent Fuel Storage Minimum Inadvertent Drainage Elevation ML15078A0582015-04-0808 April 2015 Issuance of Amendment License Amendment Request to Extend Containment Leakage Rate Test Frequency (TACs MF3985 and MF3986) 2023-09-29
[Table view] Category:Safety Evaluation
MONTHYEARML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 ML23188A0982023-07-17017 July 2023 Correction to the Safety Evaluation Issued Related to Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23019A0032023-03-16016 March 2023 Issuance of Amendment Nos. 320 and 210 Adoption of Technical Specifications Task Force (Tstf) Traveler Tstf-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23062A5212023-03-0606 March 2023 Issuance of Amendment No. 319 Revise Technical Specification (TS) 3.5.2, ECCS Operating, Limiting Condition for Operation (LCO) 3.5.2, ML22277A8142022-10-0707 October 2022 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 315 and 205 Regarding Changes to the Emergency Preparedness Plan ML22210A0102022-09-16016 September 2022 Energy Harbor Fleet- Issuance of Amendments Regarding Adoption of TSTF 554, Revise Reactor Coolant Leakage Requirements ML22222A0862022-09-0101 September 2022 Issuance of Amendment Nos. 317 and 208 Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start and Bus Separation Instrumentation ML22235A7672022-09-0101 September 2022 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 315 and 205 Regarding Changes to the Emergency Preparedness Plan ML22202A4642022-06-29029 June 2022 Emergency Plan Safety Evaluation ML22140A2092022-06-28028 June 2022 Issuance of Amendment No. 207 Correct TS 3.1.7 Change Made by TSTF-547 ML22095A2352022-05-10010 May 2022 Issuance of Amendment Nos. 316 and 206 Revise Technical Specification 5.6.3, Core Operating Limits Report (COLR) ML21286A7822022-05-0606 May 2022 Issuance of Amendment Nos. 315 and 205 Regarding Changes to the Emergency Plan ML22077A1342022-05-0202 May 2022 Issuance of Amendment Nos. 314 and 204 Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22082A2532022-03-29029 March 2022 Correction Letter - Issuance of Authorization of Proposed Alternative to Use ASME OM Code Case OMN-27 ML22012A2972022-01-21021 January 2022 Proposed Alternative to Use ASME OM Code Case OMN-27 ML21197A0092021-11-0101 November 2021 Issuance of Amendment Nos. 313 and 203 Reactor Coolant System, Pressure and Temperature Limits Report ML21214A2752021-10-15015 October 2021 Issuance of Amendment Nos. 312 and 202 Atmospheric Dump Valves ML21153A1762021-06-30030 June 2021 Issuance of Amendment No. 201 Revision of Technical Specifications Related to Steam Generator Tube Inspection, and Repair Methods ML21075A1132021-04-16016 April 2021 Issuance of Amendment Nos. 311, 200, and 302 to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, Into the Technical Specifications ML21070A0002021-03-22022 March 2021 Issuance of Amendment 310, Revise Technical Specification 5.5.5.1, Unit 1 SG Program, to Defer Spring 2021 Refueling Outage Steam Generator Inspections to Fall 2022 Refueling Outage ML20346A0222021-03-10010 March 2021 Issuance of Amendment Nos. 309 and 199 to Change Technical Specifications to Implement New Surveillance Methods for the Heat Flux Hot Channel Factor ML20335A0522021-02-18018 February 2021 Issuance of Amendment Nos. 308 and 198 to Modify Certified Fuel Handler Related Technical Specifications for Permanently Defueled Condition ML20345A2362021-01-28028 January 2021 Issuance of Amendment Nos. 307 and 197 to Add Containment Sump Technical Specifications to Address GSI-191 Issues ML20335A0232020-12-28028 December 2020 Issuance of Amendment Nos. 306 and 196 to Remove License Conditions B and C Related to the Irradiated Fuel Management Plans ML20285A2662020-10-21021 October 2020 Correction to Safety Evaluation for Amendment Nos. 305 and 195 Issued September 23, 2020, Modify Primary and Secondary Coolant Activity Technical Specifications ML20279A4402020-10-0808 October 2020 Energy Harbor Fleet-Beaver Valley Power Station; Davis-Besse Nuclear Power Station, and Perry Nuclear Power Plant - Request to Use a Provision of a Later Edition of the ASME Engineers Boiler and Pressure Vessel Code, Section XI ML20213A7312020-09-23023 September 2020 Issuance of Amendment Nos. 305 and 195 to Modify Primary and Secondary Coolant Activity Technical Specifications ML20223A0142020-08-20020 August 2020 Issuance of Relief Request SSR-1, Revision 0, from the Requirements of the ASME Code (EPID L-2020-LLR-0050 (COVID-19)) ML20206K8652020-08-0707 August 2020 Relief Requests 2-TYP-4-RV-06 and 2-TYP-4-RV-07 from the Requirements of the ASME Code (EPID L-2020-LLR-0053 and EPID L-2020-LLR-0054 (COVID-19)) ML20153A0142020-07-16016 July 2020 Relief from the Requirements of the American Society of Mechanical Engineers Code Regarding Request VRR4 (EPID L-2020-LLR-0052 (COVID-19)) ML20145A0002020-06-0303 June 2020 Relief from the Requirements of the ASME Code for Requests VRR6 and VRR5 (EPID L-2020-LLR-0049 and EPID L-2020-LLR-0051 (COVID-19)) ML20080J7892020-04-28028 April 2020 Relief Requests 2 TYP-3-B3.110-1, 2-TYP-3-C2.21-1, 2-TYP-3-C1.30-1, and 2-TYP-3-RA-1 Regarding Weld Examination Coverage for the Third Inservice Inspection Interval ML20079F8162020-03-26026 March 2020 Relief Requests 1-TYP-4-C2.21-1 and 1-TYP-4-RA-1 Regarding Weld Examination Coverage for the Fourth Inservice Inspection Interval ML19336A0282019-12-18018 December 2019 Safety Evaluation Irradiated Fuel Management Plans ML19305B1312019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Enclosure 6, Non-Proprietary Safety Evaluation, Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML19275E2942019-10-16016 October 2019 Issuance of Relief Request Proposed Alternative to Reactor Vessel Nozzle Weld Examination Frequency Requirements in Lieu of Specific ASME Code Requirements ML19028A0302019-04-11011 April 2019 FENOC - Beaver Valley Power Station, Unit 1 & 2; Davis-Besse Nuclear Power Station Unit 1; and Perry Nuclear Power Plant Unit 1 - Approval of Certified Fuel Handler Training and Retraining Program ML18348B2062019-02-25025 February 2019 Issuance of Amendment No. 193 Revise Steam Generator Technical Specifications ML18249A1692018-09-0707 September 2018 Seismic Hazard Mitigation Strategies Assessment (CAC Nos. MF7800 and MF7801; EPID L-2016-JLD-0006) ML18227A7332018-08-27027 August 2018 Request for Relief from the Requirements of the ASME Code ML18205A2922018-08-10010 August 2018 Correction of Errors in Safety Evaluation Associated with Relief Request 2-TYP-4-RV-02 ML18179A4672018-07-30030 July 2018 FENOC-Beaver Valley Power Station, Unit No. 1 and 2; Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 - Issuance of Amendments Request to Adopt TSTF-529, Clarify Use and Application Rules ML18178A1122018-07-0202 July 2018 Relief Request No. 2-TYP-4-RV-02 Regarding the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-729-4 Examination Requirements ML18065A4032018-04-0505 April 2018 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 301 and 190 ML18073A1062018-03-28028 March 2018 Safety Evaluation of Proposed Alternatives 1-TYP-4-BA-01 and TYP-4-BN-01 Regarding the Fourth 10- Year Interval of the Inservice Inspection Program ML18075A0962018-03-27027 March 2018 Safety Evaluation of Proposed Alternative to Use ASME Code Cases N-695-1 and N-696-1 in Lieu of Certain Requirements of the ASME Code 2023-09-28
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 April 6, 2012 Mr. Paul A Harden Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB 1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NO.2 - CORRECTION LETTER TO THE REVISED STEAM GENERATOR INSPECTION SCOPE USING F*
INSPECTION METHODOLOGY AMENDMENT (TAC NO. ME3498)
Dear Mr. Harden:
By letter dated February 24, 2011, the Nuclear Regulatory Commission (NRC) issued Amendment No. 172 to Renewed Facility Operating License (FOL) No. NPF-73 for the Beaver Valley Power Station Unit, No.2 to modify the Technical Specifications to revise the scope of the steam generator (SG) tube inspections for the portion of the tube in the tubesheet on the cold-leg side of the SG by using the F* methodology.
For clarification purposes, the NRC staff would like to make some corrections to the amendment. Enclosed are the corrected pages. If you have any questions, please contact me at (301) 415-1016.
Sincerely,
~~~--~~~-~----- __c _ _ _ .
!:.diyah S. Morgan, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412
Enclosure:
As stated cc w/encl: Distribution via Listserv
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 FIRSTENERGY NUCLEAR OPERATING COMPANY FIRSTENERGY NUCLEAR GENERATION CORP.
OHIO EDISON COMPANY THE TOLEDO EDISON COMPANY DOCKET NO. 50-412 BEAVER VALLEY POWER STATION, UNIT 2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 172 License No. NPF-73
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by FirstEnergy Nuclear Operating Company, et al. (the licensee), dated February 26,2010, as supplemented by letters dated November 30, 2010, and January 26, 2011, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-73 is hereby amended to read as follows:
Corrected by letter dated, Friday, April 6, 2012
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 172 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-73 FIRSTENERGY NUCLEAR OPERAriNG COMPANY FIRSTENERGY NUCLEAR GENERATION CORP.
OHIO EDISON COMPANY THE TOLEDO EDISON COMPANY BEAVER VALLEY POWER STATION, UNIT NO.2 DOCKET NO. 50-412
1.0 INTRODUCTION
By application dated February 26, 2010 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML100630422), as supplemented by letters dated November 30,2010 (ADAMS Accession No. ML103370240) and January 26,2011 (ADAMS Accession No. ML110320242), FirstEnergy Nuclear Operating Company (FENOC, the licensee), requested changes to the Technical Specifications (TSs) for Beaver Valley Power Station, Unit No.2 (BVPS-2). The supplements dated November 10, 2010, and January 26, 2011, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the Nuclear Regulatory Commission (NRC) staff's original proposed no significant hazards consideration determination as published in the Federal Register on January 11, 2011 (76 FR 1648).
The changes would revise the scope of the steam generator (SG) tube inspections for the portion of the tube in the tubesheet on the cold-leg side of the SG by using the F* methodology.
Previously, the NRC staff approved the use of the F* methodology for use on the hot-leg side of the SGs by letter dated September 27,2006 (ADAMS Accession No. ML062580419). The existing TS 5.5.5.2.c.1 states that, "tubes found by inservice inspection (lSI) to contain a flaw in a non-sleeved region with a depth equal to or exceeding 40% of the nominal tube wall thickness shall be plugged or repaired except if permitted to remain inservice through application of the alternate repair criteria discussed in Specification 5.5.5.2.cA or 5.5.5.2.c.5." TS 5.5.5.2.c.5 currently specifies that the 40 percent depth criterion for tube repair does not need to be applied in the hot-leg tubesheet region below the "F* distance" in the tubesheet. The license amendment request (LAR) adds the COld-leg tubesheet region to hot-leg region already Corrected by letter dated, Friday, April 6, 2012
- 2 specified in TS 5.5.5.2.c.5, and also prohibits application of the F* methodology in the tubesheet region where laser or tungsten inert gas welded sleeves have been installed. According to the F* methodology in TS 5.5.5.2.c.5, flaws below the F* distance may remain in service regardless of size. Implementing the F* methodology also eliminates the need to inspect the portion of the tube within the hot-leg and cOld-leg tubesheet regions below this specified distance, since the inspection provision in TS 5.5.5.2.d requires that tubes be inspected with the objective of detecting flaws that may satisfy the applicable tube repair criteria. With no repair criteria to satisfy, the portion of the tube below the specified distance is not subject to the inspection provision. The proposed amendment adds reporting of the cold-leg tubesheet region inspection results (associated with the F* methodology) to the reporting requirement of the hot-leg tubesheet region inspection results, currently required in TS Section 5.6.6.2.4.
2.0 REGULATORY EVAULATION 2.1 Description of System Steam generator tubes function as an integral part of the reactor coolant pressure boundary and, in addition, serve to isolate radiological fission products in the primary coolant from the secondary coolant and the environment. Because of the importance of SG tube integrity, the NRC requires the performance of periodic ISis of SG tubes. These inspections detect, in part, flaws in the tubes resulting from interaction with the SG operating environment. ISis may also provide a means of characterizing the nature and cause of any tube flaws so that corrective measures can be taken. Tubes with flaws that exceed the tube repair criteria specified in a plant's TS are removed from service by plugging or are repaired by sleeving. The TSs provide the acceptance criteria related to the results of SG tube inspections.
The requirements for the inspection of SG tubes are intended to ensure that this portion of the reactor coolant system maintains its integrity. Tube integrity means that the tubes are capable of performing these functions in accordance with the plant design and licensing basis. Tube integrity includes both structural and leakage integrity. Structural integrity refers to maintaining adequate margins against gross failure, rupture, and collapse of the SG tubes. Leakage integrity refers to limiting primary-to- secondary leakage during normal operation, plant transients, and postulated accidents. These limits ensure the radiological dose consequences associated with any leakage are within acceptable limits and they limit the frequency of SG tube ruptures.
2.2 Regulatory Requirements and Guidance In reviewing requests of this type, the NRC staff verifies that a methodology exists that maintains the structural and leakage integrity of the tubes consistent with the plant design and licensing basis. This includes verifying that the applicable General Design Criteria (GDC), e.g.,
GDCs 14 and 32, contained in Appendix A of Part 50 to Title 10 of the Code of Federal Regulations (10 CFR) and the performance criteria in the plant TSs are satisfied. The NRC staff's evaluation is based, in part, on ensuring that the structural margins inherent in Regulatory Guide (RG) 1.121, "Bases for Plugging Degraded PWR [pressurized-water reactor] SG Tubes,"
Corrected by letter dated, Friday, April 6, 2012
-3 are maintained. The NRC staff's evaluation also includes verifying that a conservative methodology exists for determining the amount of primary-to-secondary leakage that may occur during design-basis accidents (DBAs). The amount of leakage is limited to ensure that offsite and control room dose criteria are met. The radiological dose criteria are specified, in part, in 10 CFR Part 100, in 10 CFR 50.67, and in GDC 19 of Appendix A to 10 CFR Part 50.
The NRC approved a similar redefinition of a tube inspection for the original SGs at the Kewaunee Power Station in 1996 (NUDOCS 9609230197), for the Joseph M. Farley Plant, Unit 2 (Farley Unit 2) in 1996 (NUDOCS 9610220228), for the Comanche Peak Steam Electric Station, Unit 1 in 1999 (NUDOCS 9909030072), for the Watts Bar Nuclear Plant, Unit 1 in 2000 (ADAMS Accession No. ML003748725) and others. In each case, plant-specific repair criteria were determined.
3.0 TECHNICAL EVALUATION
3.1 Background BVPS-2 is a 3-loop, Westinghouse-designed plant with Model 51 M SGs. Each SG contains 3376 mill-annealed Alloy 600 tubes with an outside diameter of 0.875-inch and a wall thickness of 0.050-inch. The tubes in each SG are supported by horizontal support plates with drilled holes. All tube support material is carbon steel. The tubes were expanded with a mechanical rolling process (hardroll) at both ends for the full length of the tubesheet (21 inches). A weld joins the tube end to the cladding on the primary face of the tubesheet, providing a leak-tight boundary and resistance to tube pullout. The hardroll process produces an interference fit between the tube and tubesheet which can also provide resistance to tube pullout. The transition from the expanded portion of the tube to the unexpanded portion of the tube is referred to as the roll transition. Prior to operation, the internal surfaces of the tubes within the tubesheet on the hot-leg and cold-leg sides of the tubesheet were shotpeened, which applies a compressive stress that generally increases resistance to stress-corrosion cracking. The existing TSs for BVPS -2 permit the installation of three types of sleeves in order to repair flaws.
The sleeves have both upper and lower joints that form the interface with the parent tube.
The tube-to-tubesheet joint consists of the tube, which is roll-expanded against the bore of the tubesheet, the tube-to-tubesheet weld located at the tube end, and the tubesheet. Typically, plants designed the tube-to-tubesheet joint as a welded jOint rather than a friction or expansion joint. That is, the weld itself was designed as a pressure boundary element, and it was designed to transmit the entire end cap pressure load during normal and DBA conditions from the tube to the tubesheet with no credit taken for the friction developed between the roll-expanded tube and the tubesheet. In addition, the weld makes the joint leak tight.
The existing inspection and repair requirements in the plant TSs do not take into account the reinforcing effect of the tubesheet on the external surface of the expanded tube. Nonetheless, the presence of the tubesheet constrains the tube and complements tube integrity in that region, by preventing tube deformation beyond the expanded outside diameter of the tube. The resistance to both tube rupture and tube collapse is significantly enhanced by the tubesheet reinforcement. In addition, the proximity of the tubesheet to the expanded tube significantly reduces the leakage from any through-wall defect.
Corrected by letter dated, Friday, April 6, 2012
-4 Based on these considerations, power reactor licensees have proposed, and the NRC has approved, alternate repair criteria for SG tube defects located in the lower portion of the tubesheet, when these defects are a specific distance below the expansion transition or the top of the tubesheet (TIS), whichever is lower. The F* methodology defines a distance, referred to as the F* distance, such that any type or combination of flaws below this distance (including flaws in the tube-to-tubesheet weld) is considered acceptable. That is, even if inspections below the F* distance identify flaws, the regulatory requirements pertaining to tube structural and leakage integrity would be met provided there were no significant flaws within the F*
distance. The F* distance is measured from the TIS or the bottom of the roll transition (BRT),
whichever is lower.
Determination of the F* distance includes a nondestructive examination (NDE) uncertainty value of 0.25 inch, which was established in the F* evaluation for Farley Unit 2 and subsequently approved as part of the staff's safety evaluation for that repair criteria. It also includes an adjustment for the location of the BRT in relation to the TIS. The value of F* calculated for structural and leakage integrity, without adjustments for NDE uncertainty and BRT location, is called the F* length. That is, the F* distance is the sum of the F* length, the NDE uncertainty, and the BRT adjustment.
The F* evaluation presented in WCAP-16385, "F* Tube Plugging Criterion For Tubes With Degradation In The Tubesheet Roll Expansion Region Of The Beaver Valley Unit 2 Steam Generators," Revision 1 (ADAMS Accession No. ML051040084), was performed for the expected operating conditions at BVPS-2 (including an 8-percent extended power uprate (EPU) which was subsequently approved by the NRC on July 19, 2006) and for DBAs. The F* value determined for the limiting faulted condition (SG feedwater line break (FLB)) bounds the current normal operating conditions and EPU conditions, with up to 22 percent tube plugging.
The F* analysis considered the forces acting to pull the tube out of the tubesheet (i.e., from the internal pressure in the tube) and the forces acting to keep the tube in place. These latter forces are a result of friction and the forces arising from (1) the residual preload from the installation (rolling) process, (2) the differential thermal expansion between the tube and the tubesheet, and (3) internal pressure in the tube within the tubesheet. In addition, the effects of tubesheet bow, due to pressure and thermal differentials across the tubesheet, were considered since this bow causes dilation of the tubesheet holes from the secondary face to approximately the midpoint of the tubesheet and reduces the ability of the tube to resist pullout. The amount of tubesheet bow varies as a function of radial position, with locations near the periphery experiencing less bow. The effects of tubesheet hole dilation were analyzed using the worst case hole (location) in the tubesheet.
3.2 FENOC Proposal The licensee's basis for revising the criteria for tube repair within the cold-leg tubesheet region is documented in its LAR, in WCAP-16385, Revision 1, and in the November 10, 2010, and January 26,2011, supplemental letters. These documents also referred to WCAP-11306, "Tubesheet Region Plugging Criterion for the Alabama Power Company Farley Nuclear Station Unit 2 Steam Generators," Revision 2, April 1987, which describe the analysis and testing performed to justify a similar modification in the tube repair criteria for the Farley Nuclear Station, Unit 2.
Corrected by letter dated, Friday, April 6, 2012
- S-For tubes with no portion of a lower sleeve joint in the hot-leg or cold-leg tubesheet region, TS S.S.S.2.c.S.a specifies that the tube must be repaired or plugged if any flaw is detected within 3 inches below the TIS or 2.22 inches below the BRT, whichever elevation is lower. For tubes which have any portion of a sleeve joint in the hot-leg tubesheet region, TS S.S.S.2.c.S.b specifies that the tube must be plugged if any flaw is detected within 3 inches below the lower end of the lower sleeve joint. Any flaw located below the elevations specified in proposed TSs S.S.S.2.c.S.a and S.S.S.2.c.S.b would be allowed to remain in service regardless of size.
The following sections summarize the NRC staff's evaluation of the proposed BVPS-2 F*
proposal in terms of maintaining SG structural and leakage integrity.
3.3 Tube Structural Integrity The amendment would permit tubes with flaws to remain in service; therefore, the licensee must demonstrate that the tubes kept in service using the F* methodology will maintain adequate structural integrity for the period of time between inspections. Tube rupture and pullout of a tube from the tubesheet are the two potential credible modes of structural failure considered for tubes returned to service under the F* methodology.
In order for a tube to rupture, a flaw would need to grow above the tubesheet's secondary face.
If the entire flaw remains within the tubesheet, the reinforcement provided by the tubesheet will prevent tube rupture. The F* methodology proposed by the licensee for BVPS-2 requires an inspection of the top portion of the tube within the hot-leg or cold-leg tubesheet and the plugging of any flaws in this region. Therefore, any known flaws remaining in service following the inspections will be located a minimum of 3 inches below the TIS or the lower joint of a sleeve.
Industry operating experience shows flaw growth rates within the tubesheet are well below those necessary to propagate a flaw from 3 inches below the TIS to outside the tubesheet in one operating cycle (typically 18 months). Therefore, it is unlikely that any of these flaws will grow in an axial direction and extend outside the tubesheet during one operating cycle.
Similarly, it is unlikely that a flaw would propagate upward to a sleeve jOint from 3 inches below the joint during one operating cycle. Thus, tube burst is precluded for these flaws due to the reinforcement provided by the surrounding tubesheet.
In the event that undetected flaws are present in the F* distance, or that new flaws initiate in the F* distance during the operating cycle following an inspection, it is possible that these flaws could grow in the axial direction and extend outside the tubesheet. As a result, the NRC staff considered the conditions that would be necessary to structurally fail a tube with this type of flaw. Steam generator tube rupture is primarily a function of flaw geometry, the differential pressure across the tube wall, and the flaw location. Axial through-wall flaws may result in a tube failing to maintain adequate margins for burst under all operating conditions. However, this would require the flaws to exceed a certain length, typically on the order of one-half inch or longer, and have no external restraint (Le., occur in the free span). Partially through-wall flaws would require additional length (beyond the one-half inch postulated above) in order to become susceptible to spontaneous rupture based on empirical models for tube burst. Thus, these flaws would have to extend a significant distance above the tubesheet to degrade the margins of structural integrity for the affected tube (Le., tubes with undetected flaws slightly below the TIS).
In addition, constraining a flaw at one end by the tubesheet would further elevate the burst pressure of this tube (compared to an identical flaw with no constraint). Flaw growth rates Corrected by letter dated, Friday, April 6, 2012
ML120940576 *Concurred via email OFFICE LPLI-1/PM LPLI-1/LA LPL1-1/BC NAME NMorgan SLittie GWilson (JKim for)
DATE 4/5/2012 4/5/2012* 012