EOC Assessment Letter 2011
ML12065A228
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 03/05/2012
From: Frank Ehrhardt
NRC/RGN-II/DRP/RPB2
To: Madison D
Southern Nuclear Operating Co
References
IR-11-007
Download: ML12065A228 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 5, 2012 Mr. Dennis R. Madison Vice President Southern Nuclear Operating Company, Inc.

Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513

SUBJECT:

ANNUAL ASSESSMENT LETTER - EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 (REPORT 05000321/2011007 AND 05000366/2011007)

Dear Mr. Madison:

On February 14, 2012, the NRC staff completed its end-of-cycle performance review of the Edwin I. Hatch Nuclear Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2011, through December 31, 2011. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.

The NRC determined that overall, Hatch Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Hatch Units 1 and 2 for the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., Green) safety significance, and all performance indicators (PIs) indicated that your performance was within the nominal, expected range (i.e., Green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2013. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. The NRC will also conduct temporary instructions 2515/177, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems (NRC Generic Letter 2008-01) and 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks and operator licensing examinations.

SNC 2

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 997-4611 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Frank Ehrhardt, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-321, 50-366 License Nos.: DPR-57, NPF-5

Enclosure:

Hatch Inspection/Activity Plan (01/01/2012 - 06/30/2013) cc w/encl: (See page 3)

__ ML12065A228 __ ___

G SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP RII:DRP SIGNATURE

/RA/

/RA/

/RA/

NAME TLighty MMiller FEhrhardt DATE 2/28/2012 3/5/2012 3/5/2012 E-MAIL COPY?

YES NO YES NO YES NO YES NO

SNC 3

cc w/encl:

S. Kuczynski Chairman, President and CEO Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution J. L. Pemberton SVP & General Counsel-Ops & SNC Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution D. G. Bost Chief Nuclear Officer Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Paula Marino Vice President Engineering Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution M. J. Ajluni Nuclear Licensing Director Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution B. D. McKinney, Jr.

Regulatory Response Manager Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution D. W. Daughhetee Licensing Engineer Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution T. D. Honeycutt Regulatory Response Supervisor Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Bradley J. Adams Vice President Fleet Operations Support Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution N. J. Stringfellow Licensing Manager Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution L. P. Hill Licensing Supervisor Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution L. L. Crumpton Administrative Assistant, Sr.

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Steven B. Tipps Hatch Principal Engineer - Licensing Edwin I. Hatch Nuclear Plant Electronic Mail Distribution W. E. Duvall Site Support Manager Edwin I. Hatch Nuclear Plant Electronic Mail Distribution (cc w/encl contd - See page 4)

SNC 4

(cc w/encl contd)

Senior Resident Inspector U.S. Nuclear Regulatory Commission Edwin I. Hatch Nuclear Plant U.S. NRC 11030 Hatch Parkway N Baxley, GA 30334 Mr. Ken Rosanski Resident Manager Edwin I. Hatch Nuclear Plant Oglethorpe Power Corporation Electronic Mail Distribution Mark Williams Commissioner Georgia Department of Natural Resources Electronic Mail Distribution Lee Foley Manager of Contracts Generation Oglethorpe Power Corporation Electronic Mail Distribution Arthur H. Domby, Esq.

Troutman Sanders Electronic Mail Distribution James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Al Frazier Emergency Response and Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Judson H. Turner Director Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution James A. Capp Program Coordination Branch Chief Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Mr. Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia Electronic Mail Distribution Reece McAlister Executive Secretary Georgia Public Service Commission Electronic Mail Distribution Chairman Appling County Commissioners County Courthouse 69 Tippins Street, Suite 201 Baxley, GA 31513 Amy Whaley Resident Manager Electronic Mail Distribution

SNC 5

Letter to Dennis R. Madison from Frank Ehrhardt dated March 5, 2012

SUBJECT:

ANNUAL ASSESSMENT LETTER - EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 (NRC INSPECTION REPORT 05000321/2011007 AND 05000366/2011007)

Distribution w/encl:

C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMHatch Resource ROP Reports Institute of Nuclear Power Operations (INPO)