MONTHYEARW3F1-2011-0067, License Amendment Request, Proposed Change to Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train2011-10-13013 October 2011 License Amendment Request, Proposed Change to Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: Request ML1131204702011-11-0808 November 2011 Email, Supplemental Information Request for Acceptance Review, License Amendment Request to Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: Acceptance Review W3F1-2011-0082, Supplement to License Amendment Request Proposed Change to Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train2011-11-25025 November 2011 Supplement to License Amendment Request Proposed Change to Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: Supplement ML12023A0802012-01-18018 January 2012 Calculations Requested for License Amendment Request, Proposed Change to Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: Request ML1202303452012-01-23023 January 2012 Acceptance Review Following Supplement Email, License Amendment Request to Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: Acceptance Review ML1205807382012-02-27027 February 2012 Request for Additional Information License Amendment Request for Proposed Change to Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: RAI ML1205807292012-02-27027 February 2012 Email, Request for Additonal Information License Amendment Request for Proposed Change to Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: Other W3F1-2012-0019, Response to Request for Additional Information, License Amendment Request to Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train2012-04-0303 April 2012 Response to Request for Additional Information, License Amendment Request to Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: Response to RAI W3F1-2012-0028, Of License Amendment Request to Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train2012-05-22022 May 2012 Of License Amendment Request to Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: Request ENOC-12-00017, Entergy Letter Dated May 22, 2012 Re EA-10-090, EA-10-248, EA-11-1062012-05-22022 May 2012 Entergy Letter Dated May 22, 2012 Re EA-10-090, EA-10-248, EA-11-106 Project stage: Other ML1217105922012-06-19019 June 2012 Email, Request for Additional Information, Round 2, License Amendment Request for Proposed Change to Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: RAI W3F1-2012-0053, Response to a Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train2012-07-17017 July 2012 Response to a Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: Response to RAI ML12250A4352012-10-31031 October 2012 Issuance of Amendment No. 237, Revise Technical Specification 3/4.7.4 Table 3.7-3, Ultimate Heat Sink Minimum Fan Requirements Per Train Project stage: Approval 2012-10-31
[Table View] |
Text
From:
Kalyanam, Kaly Sent:
Monday, February 27, 2012 11:29 AM To:
STEELMAN, WILLIAM J Cc:
Lent, Susan; Burkhardt, Janet
Subject:
TAC No. ME7342 - Request for Additional Information Attachments:
RAI from SBPB_ML120450859.docx
- Billy, By letter dated October 13, 2011, as supplemented by letters dated November 25, 2011, and January 18, 2012, Entergy Operations, Inc. (Entergy) made application to amend the Technical Specifications (TS) 3/4.7.4 Table 3.7-3, "Ultimate Heat Sink Minimum Fan Requirements Per Train." of the Waterford Steam Electric Station, Unit 3 (Waterford 3).
This TS change modifies the fan requirements to indicate the number of fans required to be operable per cell, rather than per train. In addition, a note will be modified to delete the allowance for an entire cell to be out-of-service because it incorrectly indicates that four fans can be out of service in a single cell. The note modification also removes the implication that covers are not needed to maintain an operable train. In concert with the above change, the wet and dry bulb temperature limits are lowered to account for the increased heat duty resulting from the Replacement Steam Generators.
The NRC Staff has reviewed the amendment request and determined that we require additional information to complete our review. A request for additional information is attached.
The staff requests you to provide a response to the RAI within 30 days from the date of this email. If this is not feasible, please let me know, in advance, when the response will be sent.
Thanks Kaly N, Kalyanam PM, Waterford 3 and ANO 1 & 2 NRR/DORL/LPL4