Letter Sequence Acceptance Review |
|---|
|
|
MONTHYEARML1130102002011-10-24024 October 2011 LAR-11-006 - Revision to Technical Specification 3.3.5. Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation Project stage: Request DCL-11-072, Attachment 2 - Potential Transformer Characteristic Ratio and Phase Angle Curve2011-10-24024 October 2011 Attachment 2 - Potential Transformer Characteristic Ratio and Phase Angle Curve Project stage: Request ML1202406872012-01-24024 January 2012 Acceptance Review Email, License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power DG Start Instrumentation and Fsaru Project stage: Acceptance Review ML1206101612012-03-0101 March 2012 Email, Request for Additional Information, License Amendment Request 11-06, Revision to Technical Specification 3.3.5, Loss of Power Diesel Generator Start Instrumentation Project stage: RAI ML1206902582012-03-0909 March 2012 Email, Request for Additional Information, Round 2, Amendment Request, Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation, and Fsaru Project stage: RAI DCL-12-031, Response to NRC Request for Additional Information Regarding PG&E Letter DCL-11-072, License Amendment Request 11-06, Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation Dated October2012-03-30030 March 2012 Response to NRC Request for Additional Information Regarding PG&E Letter DCL-11-072, License Amendment Request 11-06, Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation Dated October 1 Project stage: Response to RAI DCL-12-038, Response to NRC Request for Additional Information Regarding PG&E Letter DCL-11-072. License Amendment Request 11-06, Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start2012-04-12012 April 2012 Response to NRC Request for Additional Information Regarding PG&E Letter DCL-11-072. License Amendment Request 11-06, Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Project stage: Response to RAI DCL-12-047, Proposed Implementation Schedule for License Amendment Request 11-06, Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation2012-04-30030 April 2012 Proposed Implementation Schedule for License Amendment Request 11-06, Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation Project stage: Request ML1213205642012-05-11011 May 2012 Email, Request for Additional Information, Round 3, Amendment Request, Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation, and Final Safety Analysis Report Update Project stage: RAI DCL-12-062, Response to NRC Request for Additional Information Regarding PG&E Letter DCL-11-0722012-06-18018 June 2012 Response to NRC Request for Additional Information Regarding PG&E Letter DCL-11-072 Project stage: Response to RAI ML1217903462012-06-27027 June 2012 Email, Request for Additional Information, Round 4, Amendment Request, Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation, and Final Safety Analysis Report Update Project stage: RAI ML12275A1452012-10-0303 October 2012 FRN, Withdrawal of License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation, and Final Safety Analysis Report Update Project stage: Withdrawal ML12275A1442012-10-0303 October 2012 Withdrawal of License Amendment Request Project stage: Withdrawal 2012-03-09
[Table View] |
Text
From:
Lynch, Steven Sent:
Tuesday, January 24, 2012 3:16 PM To:
Soenen, Philippe R; Baldwin, Thomas Cc:
Wang, Alan; Lent, Susan; Burkhardt, Janet
Subject:
Acceptance of Diablo Canyon Request to Revise TS 3.3.5, "Loss of Power" DG Start Instrumentation and FSARU (ME7520-1)
Tom and Philippe, By letter dated October 24, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML113010200), Pacific Gas and Electric Company, (PG&E, the licensee) submitted a license amendment request to the U.S. Nuclear Regulatory Commission (NRC) requesting to revise Technical Specification (TS) 3.3.5 Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation, revise Final Safety Analysis Report Update (FSARU)
Appendix 6.2D and Sections 6.3, 15.3, and 15.4, revise the loss-of-coolant accident (LOCA) control room operator and offsite dose analysis of record described in the FSARU, and provide a new process for revising input values to this analysis.
The purpose of this letter is to provide the results of the NRC staff's acceptance review of this license amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it provides technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed license amendment request in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
If you have any questions, please contact me at (301) 415-1524 or Alan Wang at (301) 415-1445.
Steven Lynch Project Manager (Diablo Canyon Power Plant)
Nuclear Regulatory Commission Division of Operating Reactor Licensing Steven.Lynch@nrc.gov