Summary of Meeting with Duke Energy Carolinas, LLC to Discuss Ongoing Major Projects at Oconee Nuclear Station, Units 1, 2, and 3
ML12023A239
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 02/16/2012
From: Stang J
Plant Licensing Branch II
To:
Duke Energy Carolinas
Stang J
Shared Package
ML12024A002 List:
References
Download: ML12023A239 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555..()001 February 16, 2012 LICENSEE: Duke Energy Carolinas, LLC FACILITY: Oconee Nuclear Station, Units 1, 2, and 3

SUBJECT:

SUMMARY

OF JANUARY 18,2012, MEETING WITH DUKE ENERGY CAROLINAS, LLC, TO DISCUSS ONGOING MAJOR PROJECTS AT OCONEE NUCLEAR STATION, UNITS 1,2, AND 3 (ONS 1/2/3)

On January 18, 2012, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Duke Energy Carolinas, LLC (the licensee) at the Oconee Nuclear Station, World of Energy, 7812 Rochester Highway, Seneca, South Carolina.

The purpose of the meeting was to provide for the NRC the status of the ongoing major projects at the Oconee Nuclear Station, Units 1, 2, and 3 (ONS 1/2/3). A list of attendees is enclosed.

The licensee presented information (See the licensee's handouts at Agencywide Documents Access and Management System (ADAMS) Accession No. ML12017A092).

The licensee presented a summary of the status of the following major projects which are ongoing at ONS 1/2/3:

  • Digital Reactor Protective System (RSP) and Engineered Safeguards (ES) system
  • National Fire Protection Association (NFPA) Standard 805 Transition
  • Natural Phenomena Barrier System (NPBS)

The licensee is currently replacing the existing RPS and ES systems in all three Oconee units with new state of the art digital systems. These systems are used to automatically safely shutdown the reactors and maintain the reactors in a safe and stable condition. During the meeting the licensee indicated that the new RSP and ES systems had been installed, and are operational in Unit 1 (performed during the spring 2011 refueling outage). The licensee is preparing to install the systems in Unit 3 during the spring 2012 refueling outage, followed by installation at Unit 2 during the spring 2013 refueling outage.

ONS 1/2/3 was one of two pilot plants that are in the process of transitioning to NFPA 805 for compliance with the NRC fire protection regulations, Title 10 of the Code of Federal Regulations, Part 50, Section 50.48. The NRC staff completed its review of the license amendment request requesting approval of the transition, and issued the license amendments approving the transition on December 29,2010 (ADAMS Accession No. ML103630612). The licensee indicated during the meeting that they are currently completing all modifications required by the license amendments, and will be in full compliance with NFPA 805 by December 2012.

-2 The licensee has upgraded the Oconee site by installing an NPBS. The NPBS provides additional protection to structures, systems, and components that are necessary to safely shutdown the reactors following high winds or a tornado. During the meeting, the licensee stated that the installation of the entire system had been completed in August 2011, and was now fully operational. This upgrade gives the Oconee site additional protection against high winds and tornados.

The licensee will be installing new MSIVs for all three Oconee units. The MSIVs will provide additional margin to ensure high energy line breaks (HELBs) can be mitigated. During the meeting, the licensee indicated that the initial scope of the MSIVs installation has been completed, the MSIV have been ordered from a vendor, and a detailed scope for the MSIVs installation is being developed. The licensee's current schedule for installing the MSIVs is as follows:

  • Unit 1 - 2014
  • Unit 2 - 2015
  • Unit 3 - 2016 The licensee is in the process of installing a new PSW system. The PSW system is a diverse system to other plant systems for the mitigation of fires, high energy line breaks (HELBs), and tornados. The PSW system consists of new electrical power supplies for existing plant safety systems, as well as new pumps to remove decay heat from the reactor coolant system once the reactor is shutdown, if the normal plants systems are not available. The installation of the PSW system will reduce the overall plant risk in the event of a fire, HELB, or a tornado at the Oconee site. During the meeting the licensee indicated that they are on schedule for the completion of the PSW system in July of 2012.

Members of the public were in attendance at the meeting. Public Meeting Feedback forms were made available to the public. As of the date of this meeting summary, no comments have been received. If comments are received at a later date, they will be forwarded to the NRC Office of Nuclear Reactor Regulation, Senior Communications Analyst, who will forward them to the NRC Office of the Executive Director for Operations.

The public portion of the meeting concluded with one question from a member of the public.

The NRC addressed the question. The NRC and the licensee continued with the non-public portion of the meeting. This portion of the meeting was closed to the public because sensitive security related information was discussed.

- 3 If you have any questions, please call me at 301-415-1345.

Sincerely,

~g. Senior P ~ ct Manager Plant Licensing BrancH 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287

Enclosure:

List of Attendees cc w/encl: Distribution via Listserv

LIST OF ATTENDEES JANUARY 18, 2012, MEETING WITH DUKE ENERGY CAROLINAS, LLC TO DISCUSS ONGOING MAJOR PROJECTS AT OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 DUKE ENERGY MEMBERS OF THE PUBLIC Eric Leeds Dhaa Jamil Rick Lecler Victor McCree Bill Pitesa Ben Turetzky William Ruland Preston Gillespie Michael Spradlin Allen Howe Dave Baxter Dick Mangrum Michael Cheok Dan McRainry Anna Mitchell Nancy Salgado Scott Batson Emily Pace Jonathan Bartley Bob Guy Ross Deaver John Stang Scott Lynch Bob Swank Andrew Sabisch Chris Noland John Hester Kevin Ellis Terry Patterson Judy Peables Melana Singletary Richard Freudenberger Tom Peables Thomas Ray Anna Simon Dean Hubbard Kent Alter Sherri Western Ann Duckett David Haile Enclosure

-3 If you have any questions, please call me at 301-415-1345.

Sincerely, IRA!

John Stang, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287

Enclosure:

List of Attendees cc w/encl: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrPMOconee Resource NSalgado, NRR LPL2-1 RlF RidsOgcRp Resource MCheok, NRR RidsNrrDorl Resource RidsRgn2MailCenter Resource VMcCree, RII RidsNrrDss Resource RidsNrrOd Resource JBartley, RII RidsAcrsAcnw_MailCTR Resource CSteger, NRR KEllis, RII RidsNrrDorlLpl2-1 Resource MSingletary, NRR ASabisch, RII RidsNrrLASFigueroa Resource MKotzalas, EDO Region II ADAMS Accession No. PKG ML12024A002 Meeting Notice ML12006A050 Summa ML12023A239 Handouts ML12017A092 OFFICE DORULPL2-1/PM LPL2-1/LA DORULPL2-1/BC DORULPL2-1/PM NAME JStang NSalgado (JThompson for) JStang DATE 02/16/12 02/16/12 02/16/12 OFFICIAL RECORD COpy