Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYSR30001 ALL State of New York Hearing Exhibits List ("NYS Exhibits List")
12/15/2011 NYS000002 NYS-8 State of New York Statement of Position, NYS-8 ("NYS-8 SOP")
12/12/2011 NYSR00003 NYS-8 Pre-filed Testimony of Robert C. Degeneff ("Degeneff PFT")
12/14/2011 NYS000004 NYS-8 Curriculum Vitae of Robert C. Degeneff ("2011 Degeneff CV")
12/12/2011 NYSR00005 NYS-8 Report of Robert C. Degeneff (December 2011) (2011 Degeneff Report) 12/14/2011 NYS000006 NYS-8 L.F. Blume, Transformer Engineering (1938, 1951 General Electric Company), Excerpted: pp. ix, 1-2 (Blume) 12/12/2011 NYS000007 NYS-8 Flanagan, The Handbook of Transformer Design &
Application, 2nd Edition, McGraw-Hill (1993),
Excerpted: pp. 1.1-1.2 (Flanagan")
12/12/2011 NYS000008 NYS-8 Harlow, James H., Electric Power Transformer Engineering, CRC Press, (2004), Excerpted: pp. xi, 2-1 2 (2004 Harlow) 12/12/2011 1
NYSR30001 Revised: December 15, 2011
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000009 NYS-8 Harlow, James H., Electric Power Transformer Engineering, 2d Edition, CRC Press, (2007),
Excerpted: pp. v-vi, 2 2-2 (2007 Harlow) 12/12/2011 NYS000010 NYS-8 IEEE Standard Dictionary of Electrical and Electronic Terms, IEEE Std 100-1996, 6th Edition (1996),
Excerpted: p. 1131 (IEEE Dictionary) 12/12/2011 NYSR00011 NYS-8 IEEE Standard Terminology for Power and Distribution Transformers, IEEE Std C57.12.80TM-2010 (Sept. 30, 2010), Excerpted: pp. 39-41 ("IEEE Standard Terminology")
12/14/2011 NYS000012 NYS-8 NUREG/CR-5753, Aging of Safety Class Transformers in Safety Systems of Nuclear Power Plants (February 1996) (NUREG/CR-5753) 12/12/2011 NYS000013 NYS-8 UFSAR, Rev. 20, Indian Point Unit 3, Excerpted:
Chapter 8 - Electrical Systems (IPEC00035933-IPEC00035963) (submitted with license renewal application) (2007) ("IP3 UFSAR, Rev. 20")
12/12/2011 2
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000014 NYS-8 UFSAR, Rev. 20, Indian Point Unit 2, Excerpted:
Chapter 8 - Electrical Systems (OAGI0000215_1039-OAGI0000215_1067) and Electrical Distribution and Transmission System, DWG NO. A250907-21, figure 8.2-1 and 8.2-2 (OAGI0000215_1069)(submitted with license renewal application)(2007) ("IP2 UFSAR, Rev. 20")
12/12/2011 NYS000015 NYS-8 Indian Point No. 3 Nuclear Power Plant, Electrical Distribution & Transmission System, DWG NO. 9321-F-33853, REV 17 (electrical drawing) (ML090400895)
(Feb. 28, 2008) ("DWG 9321-F-33853")
12/12/2011 NYS000016 NYS-8 Nuclear Power Plant License Renewal; Revisions, 60 Fed. Reg. 22,461 (May 8, 1995)(SOC, 60 Fed. Reg.
22,461) 12/12/2011 3
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000017 NYS-8 IEEE Guide for the Evaluation and Reconditioning of Liquid Immersed Power Transformers [C57.140TM-2006]
(April 2007) Excerpted: pp. iv-v, 11-26 (2007 IEEE Report) 12/12/2011 NYS000018 NYS-8 Sandia National Laboratories, Aging Management Guideline for Commercial Nuclear Power Plants - Power and Distribution Transformers (Contractor Report, SAND93-7068, UC-523, Unlimited Release) (May 1994)
Excerpted: pp. 4-1 to 4-23 (1994 Sandia Report) 12/12/2011 NYS000019 NYS-8 NRC Information Notice 2009-10, Transformers Failures-Recent Operating Experience (Jul. 7, 2009)
(ML090540218) (NRC IN 2009-10) 12/12/2011 NYS000020 NYS-8 Electric Power Research Institute, Plant Support Engineering: Large Transformer End-of-Expected-Life Considerations and the Need for Planning, Final Report, 1013566 (December 2006) (EPRI PSE Report) 12/12/2011 4
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000021 NYS-8 OECD, Nuclear Energy Agency, Operating Experience Report: Recent Failures of Large Oil-Filled Transformers, NEA/CNRA/R(2001)6 (Mar. 14, 2011) (NEA Report) 12/12/2011 NYS000022 NYS-8 Pacific Gas and Electric Company (PG&E Letter DCL 089), Licensee Event Report 2-2008-001-00, Reactor Trip Due to Main Electrical Transformer Failure, Diablo Canyon Unit 2, Docket No. 50-323, OL-DPR-82 (Oct. 15, 2008) (ML082970221) ("Diablo Canyon 2 LER 2-2008-001-00")
12/12/2011 NYS000023 NYS-8 Exelon Nuclear (RA-09-008), Oyster Creek Nuclear Generating Station, Facility Operating License No.
DPR-16, NRC Docket No, 50-219, Licensee Event Report 2008-001-00, Automatic Reactor Shutdown Caused by Main Transformer Failure (Jan. 21, 2009)(ML090260082)
("Oyster Creek LER 2008-001-00")
12/12/2011 5
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000024 NYS-8 Exelon Nuclear (RA-09-026), Licensee Event Report 2009-001-00, Automatic Reactor Shutdown Caused by Main Transformer Failure, Oyster Creek Nuclear Generating Station, Facility Operating License No.
DPR-16, NRC Docket No. 50-219 (Mar. 31, 2009)
(ML090970735) ("Oyster Creek LER 2009-001-00")
12/12/2011 NYS000025 NYS-8 Exelon Nuclear, Licensee Event Report 09-001-00, Automatic Reactor Scram Due to Failure of Main Power Transformer Surge Arrestor, LaSalle County Station Unit 1, Facility Operating License No. 11, NRC Docket No. 50-373 (Jul. 20, 2009) (ML092020179) ("LaSalle 1 LER 09-001-00")
12/12/2011 6
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000026 NYS-8 Luminant Power (CP-201000074, Log # TXX-10010),
Licensee Event Report 445/10-001-00, Trip Due to Pressure Relay Actuation on Main Transformer 01, Comanche Peak Nuclear Power Plant Unit 1, Docket No.
50-445 (Mar. 3, 2010) (ML100740293) ("Comanche Peak 1 LER 445/10-001-00")
12/12/2011 NYS000027 NYS-8 DTE Energy (NRC-10-0043), Licensee Event Report 2010-001, Automatic Reactor Shutdown Due to Generator Current Transformer Wiring Failure, Fermi 2, NRC License No. NPF-43, NRC Docket No. 50-341 (May 19, 2010) (ML101400553) ("Fermi 2 LER 2010-001")
12/12/2011 7
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000028 NYS-8 PSEG Nuclear LLC (LR-N10-0320), Licensee Event Report 272/2010-002, Automatic Reactor Trip Due to Main Power Transformer Bushing Failure, Salem Nuclear Generating Station Unit 1, Facility Operating License No. DPR-70, NRC Docket No. 50-272 (Sept. 2, 2010)
(ML102780502) ("Salem 1 LER 272/2010-002")
12/12/2011 NYS000029 NYS-8 NRC Integrated Inspection Report 05000327/2010004, 05000328/2010004, Sequoyah Nuclear Plant (Oct. 29, 2010)(ML103020448) ("Sequoyah IR")
12/12/2011 NYS000030 NYS-8 Event Notification Report, Watts Bar Unit 1, Manual Reactor Trip Due to Loss of Cooling to the A Phase Main Bank Transformer, Event Number: 46418, Notification Date: 11/14/2010 ("Watts Bar 1 LER 46418")
12/12/2011 8
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000031 NYS-8 FPL (L-2010-272), Licensee Event Report 2010-003-00, Reactor Trip Due to Fault on 230kV Side of Generator Step-Up Transformer, Turkey Point Unit 3, NRC Docket No. 50-250 (Nov. 19, 2010)(ML103340517) ("Turkey Point 3 LER 2010-003-00")
12/12/2011 NYS000032 NYS-8 Entergy (NL-11-005), Licensee Event Report 2010-009-00, Automatic Reactor Trip Due to a Turbine Generator Trip Caused by a Fault of the 21 Main Transformer Phase B High Voltage Bushing, Indian Point Unit No.
2, NRC Docket No. 50-247, DPR-26 (Jan. 18, 2011)
(ML110280013) ("IP2 LER 2010-009-00")
12/12/2011 NYS000033 NYS-8 Wayne Parry, NJ's Oyster Creek Must Replace New Transformer, Associated Press (Dec. 10, 2010) ("Parry Article")
12/12/2011 9
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000034 NYS-8 Electric Power Research Institute, Life Cycle Management Planning Sourcebooks, Volume 4: Large Power Transformers, Final Report, 1007422 (March 2003) Excerpted: 4-1 to 4-6, 4-17 and 6-2 to 6-13 (Transformers Final Report) 12/12/2011 NYS000035 NYS-8 Preliminary Notification of Event or Unusual Occurrence (PNO-III-11-012A), Perry Nuclear Power Plant, Docket No. 50-440, License No. NPF-58, Perry Unplanned Shutdown Greater than 72 Hours (Update)
(Oct. 19, 2011) (ML11292A119) ("PNO-III-11-012A")
12/12/2011 NYS000036 NYS-8 Preliminary Notification of Event or Unusual Occurrence (PNO-III-11-015A), Monticello Nuclear Generating Plant, Unplanned Shutdown Greater Than 72 Hours Due to a Loss of the Auxiliary Power Transformer (Update) (Oct. 28, 2011) (ML11301A217)
("PNO-III-11-15A")
12/12/2011 10
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000037 NYS-8 Exelon Nuclear (RA11-013), Licensee Event Report 2011-001-00, Automatic Reactor Scram Due to Main Power Transformer C Phase Electrical Fault, LaSalle County Station Unit 1, Facility Operating License No.
NPF-11, NRC Docket No. 50-373 (Mar. 25, 2011)
(ML110890949) ("LaSalle 1 LER 2011-001-00")
12/12/2011 NYS000038 NYS-8 Email String; June 26, 2007 8:24 AM;
Subject:
Status of Regions Single Point Vulnerable Transformers; From: R.R. Davis; To: D.P. Wiles, M.A. Krupa, C.
Reasoner, and K.D. Nichols; CC: K.A. Jelks, M.A.
Wood, G.S. Matharu, R.T. Giguere, S. Saunders; June 26, 2007 3:12 PM;
Subject:
FW: Status of Regions Single Point Vulnerable Transformers; Attachments:
SPF Transformer writeup.doc, EN GSU Evaluation FINAL 6-25-2007.doc; From: R.R. Davis; To: R.A. Penny
("Jun. 26, 2007 Email String")
12/12/2011 11
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000039 NYS-8 Entergy Nuclear Northeast, Power Transformer Spare Purchase Recommendations, January 4, 2006, John Bonner ("Spare Purchase")
12/12/2011 NYS000040 NYS-8 EN Large Power Transformer Status (Feb. 15, 2007)
("Transformer Status")
12/12/2011 NYS000041 NYS-8 Email; July 18, 2005 6:26 PM;
Subject:
IPEC Transformer Review; From: J. Bonner; To: G. Bijoor, T.S. McCaffrey, V. Andreozzi; CC: R. Penny, J.
Bonner, D. Morris ("Jul. 18, 2005 Email")
12/12/2011 12
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000042 NYS-8 Email String; August 7, 2008 2:46 PM;
Subject:
Risks; From: C. Jackson; To: J.J. Curry; August 7, 2008 3:02 PM;
Subject:
FW: Risks; From: J.J. Curry; To: C.
Caputo; August 11, 2008 2:25 PM;
Subject:
RE: Risks; From: C. Caputo; To: J.J. Curry, C. Jackson; August 11, 2008 3:11 PM;
Subject:
RE: Risks; From: C.
Jackson; To: C. Caputo, J.J. Curry; August 11, 2008 3:23 PM;
Subject:
RE: Risks; From: C. Caputo; To: C.
Jackson, J.J. Curry ("August 2008 Email String")
12/12/2011 NYS000043 NYS-8 Letter, M.H. Philips, Jr. and W.A. Horin, Nuclear Utility Group on Equipment Qualification to J.C.
Hoyle, Acting Secretary, U.S. Nuclear Regulatory Commission (PDR Fiche 9412130158 941208) (Dec. 8, 1994) ("NUGEQ Letter")
12/12/2011 NYS000044 NYS-8 Declaration of Assistant Attorney General Lisa M.
Burianek ("PFT Burianek Decl. NYS-8")
12/12/2011 13
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000045 NYS-37 State of New York Statement of Position, NYS-37 ("NYS-37 SOP")
12/14/2011 NYS000046 NYS-37 Pre-filed Testimony of David A. Schlissel ("Schlissel PFT")
12/14/2011 NYS000047 NYS-37 Pre-filed Testimony of Peter J. Lanzalotta
("Lanzalotta PFT")
12/14/2011 NYS000048 NYS-37 Pre-filed Testimony of Peter A. Bradford ("Bradford PFT")
12/14/2011 NYS000049 NYS-37 Declaration of Assistant Attorney General Susan C.
von Reusner ("PFT von Reusener Decl. NYS-37")
12/14/2011 NYS000050 NYS-37 Curriculum Vitae of David A. Schlissel ("2011 Schlissel CV")
12/14/2011 NYS000051 NYS-37 Declaration of David A. Schlissel (Nov. 28, 2007)
(ML073400205) (2007 Schlissel Decl.)
12/14/2011 NYS000052 NYS-37 Report on the Availability of Replacement Capacity and Energy for Indian Point Units 2 & 3, (Nov. 28, 2007) (ML073400205) (2007 Synapse Report) 12/14/2011 14
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000053 NYS-37 Declaration of David A. Schlissel (Feb. 27, 2009)
(ML090690303) (2009 Schlissel Decl.)
12/14/2011 NYS000054 NYS-37 Declaration of David A. Schlissel (Jan. 31, 2011)
(ML110680290) (2011 Schlissel Decl.)
12/14/2011 NYS000055 NYS-37 National Research Council of the National Academies, Committee on Alternatives to Indian Point for Meeting Energy Needs, Alternatives to the Indian Point Energy Center for Meeting New York Electric Power Needs (June 2006) (2006 National Research Council) 12/14/2011 NYS000056 NYS-37 Indian Point Retirement Options, Replacement Generation, Decommissioning/Spent Fuel Issues, and Local Economic/Rate Impacts, prepared for the County of Westchester and the County of Westchester Public Utility Service Agency, by Levitan & Associates, Inc.
(Jun. 9, 2005)(2005 Levitan Report) 12/14/2011 NYS000057 NYS-37 NYISO, 2010 Summer Outlook (May 27, 2010) (2010 NYISO Summer Outlook) 12/14/2011 15
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000058 NYS-37 NYISO, 2010 Reliability Needs Assessment Final Report (September 2010) Excerpted: pp. ES-i, 4, 9, 12, 17, C-3, C-4(2010 NYISO RNA Report) 12/14/2011 NYS000059 NYS-37 NYISO, 2009 Annual Report: Energizing the Empire State Excerpted: p. 6 ("2009 NYISO Energizing Annual Report")
12/14/2011 NYS000060 NYS-37 Electric & Natural Gas Efficiency Potential in New York, presentation by Philip Mosenthal, Optimal Energy, Inc. at the New York State Public Service Commission Energy Efficiency Portfolio Standard Overview Forum (Jul. 19, 2007) (2007 Optimal Slide) 12/14/2011 NYS000061 NYS-37 NYS PSC, Order, Establishing Energy Efficiency Portfolio Standard and Appraising Programs, Case No.
07-M-0548 (Jun. 23, 2008) Excerpted: pp. 1-3 (June 2008 NYS PSC Order) 12/14/2011 16
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000062 NYS-37 New York State Energy Plan, Energy Efficiency Assessment (December 2009) Excerpted: Overview and pp. 1-3, 28-29 (2009 NYS Energy Efficiency Assessment) 12/14/2011 NYS000063 NYS-37 Optimal Energy, Inc., Achievable Electric Energy Efficiency Potential in New York State (2008)
Excerpted: pp. 5-6 (2008 Optimal Report) 12/14/2011 NYS000064 NYS-37 NYISO, Reliability Summary 2009-2018 Excerpted: pp.
5-6 ("2009-2018 NYISO Reliability Summary")
12/14/2011 NYS000065 NYS-37 Section 8.2.5. Utility Sponsored Conservation, Shearon Harris FSEIS, NUREG-1437, Supplement 33 (August 2008) Excerpted: pp. 8-63-68 (2008 Shearon Harris FSEIS) 12/14/2011 NYS000066 NYS-37 Section 8.3 Energy Conservation/Energy Efficiency, Three Mile Island FSEIS, NUREG-1437, Supplement 37 (June 2009) Excerpted: pp. 8-25-30 (2009 Three Mile Island FSEIS) 12/14/2011 17
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000067 NYS-37 Governor David A Paterson, Our Time to Lead: State of the State Address (2009) (2009 Paterson Address) 12/14/2011 NYS000068 NYS-37 New York State Energy Planning Board, 2009 NYS Energy Plan: Renewable Energy Assessment (December 2009)
("2009 NYS REA")
12/14/2011 NYS000069 NYS-37 NYISO, Integration of Wind into System Dispatch, A New York ISO White Paper (October 2008) Excerpted:
pp. 1-1, 5-1 ("2008 Integration of Wind")
12/14/2011 NYS000070 NYS-37 NYISO, Growing Wind: Final Report of the NYISO 2010 Wind Generation Study (September 2010) Excerpted: pp.
i-v (2010 NYISO Growing Wind Report) 12/14/2011 NYS000071 NYS-37 GE Financial Services, New Jerseys and New York Citys Electricity Systems Now Talking to Each Other, Thanks to GE's Smart Grid Technology & Smart Capital,
Press Release (Dec. 8, 2009) (2009 Smart Press Release) 12/14/2011 18
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000072 NYS-37 NYS PSC, Commission Approves Transmission Line to NYS: Power Line Would Improve Reliability, Increase Supply, Press Release (Sept. 8, 2010) (2010 NYS PSC Press Release) 12/14/2011 NYS000073 NYS-37 Cavallo Energy, Cavallo Cross Hudson Management LLC Accepting Open Season Applications for New Transmission Capacity from New Jersey to New York (May 26, 2010) ("2010 Cavallo Press Release")
12/14/2011 NYS000074 NYS-37 London Economics International, LLC, Projected Energy Market, Capacity Market and Emissions Impact Analysis of the Champlain-Hudson Power Express Transmission Project for New York (Jul. 16, 2010) Excerpted: pp.
1, 7-14 ("2010 LEI Study")
12/14/2011 NYS000075 NYS-37 NYS PSC, PSC Correspondence, Case No. 06-T-0650,(Issued Apr. 21, 2009) (April 2009 NYS PSC Correspondence) 12/14/2011 19
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000076 NYS-37 United States Department of Energy, Champlain Hudson Power Express EIS, Docket # PP-362, main home page, available at http:// chpexpresseis.org ("CHPET")
12/14/2011 NYS000077 NYS-37 NRG Astoria Gas Turbine Power LLC - Repowering Project, State Environmental Quality Review (SEQR),
Scoping Document for Draft Environmental Impact Statement (Oct. 8, 2008) Excerpted: p. 3 (2008 Astoria Scoping) 12/14/2011 NYS000078 NYS-37 Report and Recommendations Concerning the Little Gypsy Unit 3 Repowering Project, submitted by Entergy Louisiana to the Louisiana Public Service Commission (Apr. 1, 2009) ("2009 Little Gypsy Unit 3 Report")
12/14/2011 NYS000079 NYS-37 Remarks by Governor Eliot Spitzer, "15 by 15:" A Clean Energy Strategy for New York (Apr. 19, 2007)
(2007 Spitzers 15 x 15) 12/14/2011 20
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000080 NYS-37 Optimal Energy, Inc., Energy Efficiency and Renewable Energy Resource Development Potential in New York State, Final Report, Volume One: Summary Report (August 2003) (2003 Optimal Report) 12/14/2011 NYS000081 NYS-37 NYS PSC, Order, Approving "Fast Track" Utility-Administered Electric Energy Efficiency Programs with Modifications, Case Nos. 08-E-1003, 08-E-1007, 08-E-1014, and 08-E-1019 (Jan. 16, 2009) Excerpted: pp. 1-4 (January 2009 NYS PSC Order) 12/14/2011 NYS000082 NYS-37 New York's Solar Roadmap; A Plan for Energy Reliability, Security, Environmental Responsibility and Economic Development in New York State (May 2007)
Excerpted: Executive Summary (Solar Roadmap) 12/14/2011 21
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000083 NYS-37 NYSERDA, Combined Heat and Power, Market Potential for New York State, Final Report 02-12 (October 2002)
Excerpted: ES-1-ES-11 (2002 NYSERDA Final Report) 12/14/2011 NYS000084 NYS-37 The Feasibility of Re-Powering KeySpan's Long Island Electric Generating Plants to Meet Future Energy Needs, Long Island University, Center for Management Analysis (Aug. 6, 2002) Excerpted: pp. 7-8 (2002 LIU Study) 12/14/2011 NYS000085 NYS-37 Wind Integration Study - Final Report, prepared for Xcel Energy and the Minnesota Department of Commerce by EnerNex Corporation and Wind Logics, Inc. (Sept.
28, 2004) Excerpted: Project Summary (2004 EnerNex Study) 12/14/2011 NYS000086 NYS-37 NYSERDA, Wind Powering America: New York ("NY Wind Power")
12/14/2011 22
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000087 NYS-37 The Effects of Integrating Wind Power on Transmission System Planning, Reliability, and Operations, Report on Phase 1, Preliminary Overall Reliability Assessment, prepared for NYSDERA by GE Energy Consulting (2004) Excerpted: pp. ii-iii, vi-ix, 2.1-2.9 (2004 Phase 1 Report) 12/14/2011 NYS000088 NYS-37 The Effects of Integrating Wind Power on Transmission System Planning, Reliability, and Operations, Report on Phase 2, System Performance Evaluation, prepared for NYSDERA by GE Energy Consulting (March 2005)
Excerpted: pp. v-x, 1.1-2.16 (2005 Phase 2 Report) 12/14/2011 NYS000089 NYS-37 NYSERDA, New York State Renewable Portfolio Standard Performance Report for the Program Period ending March 2007 (August 2007) Excerpted: p. ES-2 (March 2007 NYS RPS Report) 12/14/2011 23
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000090 NYS-37 The Proposed Broadwater LNG Import Terminal Update of Synapse Analysis (Jan. 19, 2007) (2007 Broadwater Update) 12/14/2011 NYS000091 NYS-37 Astoria Repowering Project, Progress Report to Stakeholders and Interested Parties (July 2010)
(2010 Astoria Repowering Report) 12/14/2011 NYS000092 NYS-37 Remizowski, Leigh, $1.5B makeover for NRG Energy power plants means better air for residents, New York Daily News (Apr. 25, 2010) (2010 Remizowski) 12/14/2011 NYS000093 NYS-37 NYPA, NYPA to Cease Operations of Queens Power Plant on January 31st, Press Release (Jan. 29, 2010) (2010 NYPA Press Release) 12/14/2011 NYS000094 NYS-37 Empire Generating Co., LLC, Project Timeline as of May 19, 2010 (2010 Empire Project Timeline) 12/14/2011 NYS000095 NYS-37 Estimate Places Natural Gas Reserves 35 percent Higher, New York Times (Jun. 18, 2009) ("2009 NYT Article")
12/14/2011 24
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000096 NYS-37 NYISO, 2007 Load and Capacity Data Excerpted: pp. 1-9
("2007 NYS Data")
12/14/2011 NYS000097 NYS-37 Curriculum Vitae of Peter J. Lanzalotta (2011 Lanzalotta CV) 12/14/2011 NYS000098 NYS-37 Declaration of Peter J. Lanzalotta (Feb. 1, 2011)(ML110680290) (2011 Lanzalotta Decl.)
12/14/2011 NYS000099 NYS-37 NYISO's 2009 Comprehensive Review of Resource Adequacy: Covering the New York Control Area for the period 2010 to 2014 (Mar. 10, 2010) (2010 NYISO NYCA Resource Adequacy) 12/14/2011 NYS000100 NYS-37 NYISO, 2010 Load & Capacity Data - "Gold Book" (April 2010) Excerpted: pp. 5-8 (2010 NYISO Gold Book) 12/14/2011 NYS000101 NYS-37 Wilderness Society Et. Al U.S. Dept. of Energy (9th Cir. No. 08-71074) (Feb. 1, 2011) ("Wilderness Society")
12/14/2011 25
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000102 NYS-37 FERC Docket No. OA08-52-003, New York Independent System Operator, Inc., Order on Rehearing, 126 FERC ¶ 61,320 (Issued Mar. 31, 2009) Excerpted: pp. 1-2 (2009 Order on Rehearing) 12/14/2011 NYS000103 NYS-37 NYISO, Final Report, Comprehensive Reliability Plan:
Comprehensive System Planning Process (May 19, 2009)
Excerpted: p.1 (2009 NYISO Reliability Annual Report) 12/14/2011 NYS000104 NYS-37 Curriculum Vitae of Peter A. Bradford ("2011 Bradford CV")
12/14/2011 NYS000105 NYS-37 Declaration of Peter A. Bradford, dated November 28, 2007 (ML073400205) (2007 Bradford Decl.)
12/14/2011 NYS000106 NYS-37 Declaration of Peter A. Bradford, dated February 2, 2011 (ML110680290) (2011 Bradford Decl.)
12/14/2011 NYS000107 NYS-37 Power NY Act of 2011 (2011 NY Power Act) 12/14/2011 26
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000108 NYS-37 NYISO, Power Trends 2010: New Yorks Emerging Energy Crossroads (April 2010) (2010 NYISO Power Trends) 12/14/2011 NYS000109 NYS-37 New York State Energy Planning Board, 2009 NYS Energy Plan: Energy Demand and Price Forecasts (December 2009) Excerpted: p. 10 (2009 NYS Energy Forecasts) 12/14/2011 NYS000110 NYS-37 NYISO News Release, New York Sets Power Usage Record in July: Summer Heat Spurs Electricity Demand (Aug.
9, 2010) (2010 NYISO Press Release) 12/14/2011 NYS000111 NYS-37 NYS PSC, Order, Granting Certificate of Environmental Capability and Public Need, Case No. 08-T-0034 (September 15, 2010) Excerpted: pp. 44-47 (Sept. 15, 2010 NYS PSC Order) 12/14/2011 NYS000112 NYS-37 ACEEE, 2010 State Energy Efficiency Scorecard, Excerpted: p. 1-5 (2010 ACEEE Scorecard) 12/14/2011 27
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000113 NYS-37 NYSERDA, New York's Clean-Energy Economy, 2009-2010 Annual Report ("NYSERDA 2010 Clean Energy Report")
12/14/2011 NYS000114 NYS-37 Susan Tierney, The Analysis Group, The New York Independent System Operator: A Ten-Year Review (Apr.
12, 2010) Excerpted: p. 50 (2010 Tierney Review) 12/14/2011 NYS000115 NYS-37 United States Energy Information Administration, Department of Energy, Annual Energy Outlook 2010 with Projections to 2035 (April 2010)Excerpted: Executive Summary (2010 Energy Outlook) 12/14/2011 NYS000116 NYS-37 Gerald Warburg, A Study of NRC Procedures for Assessing Need for Power and Alternative Energy Sources in Fulfillment of the NEPA Requirements for Environmental Impact Statements (July 1979) (1979 Warburg Study) 12/14/2011 28
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000117 NYS-37 NYSERDA, New York State Renewable Portfolio Standard Performance Report Program Period December 31, 2010 (2010 NYS RPS Report) 12/14/2011 NYS000118 NYS-37 SMUD's history: 1990: Moving Into Leadership on Green Energy, Conservation (SMUD History) 12/14/2011 NYS000119 NYS-37 Energy Choices Revisited: An Examination of the Costs and Benefits of Maine's Energy Policy, a study for Mainewatch Institute by Economic Research Associates, the American Council for an Energy Efficient Economy and the Tellus Institute (1994) Excerpted: Executive Summary (1994 Mainewatch Study) 12/14/2011 NYS000120 NYS-37 Goldman, C., J. Eto, and G. Barbose, California customer load reductions during the electricity crisis: did they help to keep the lights on? (LBNL-49733) (May 2002) Excerpted: Abstract (2002 Eto Paper) 12/14/2011 29
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000121 NYS-37 Energy Efficiency: California's Highest Priority Resource, California Public Utilities Commission and California Energy Commission (June 2006) Excerpted:
- p. 4 (2006 CPUC and CEC Report) 12/14/2011 NYS000122 NYS-37 New York State Energy Planning Board, New York State Energy Plan, Natural Gas Assessment (December 2009)
Excerpted: p. 9 (2009 NYS NGA) 12/14/2011 NYS000123 NYS-37 NYISO, 2010 Comprehensive Reliability Plan (Jan. 11, 2011) Excerpted: pp. 1, 8-9(2010 NYISO Reliability Plan) 12/14/2011 NYS000124 NYS-37 NYS PSC, Order, Authorizing Workforce Development Initiatives, Case 07-M-0548, (Jun. 22, 2009)(June 2009 NYS PSC Order) 12/14/2011 NYS000125 NYS-37 56 Fed. Reg. 47,016, Environmental Review for Renewal of Operating Licenses - Part 51 (Sept. 17, 1991) (56 Fed. Reg. 47,016) 12/14/2011 30
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000126 NYS-37 NUREG-1440, Regulatory Analysis of Proposed Amendments to Regulations Concerning the Environmental Review for Renewal of Nuclear Power Plant Operating Licenses: Draft Report for Comment (August 1991) (1991 NUREG-1440 Draft for Comment) 12/14/2011 NYS000127 NYS-37 61 Fed. Reg. 28,467, Environmental Review for Renewal of Nuclear Power Plant Operating Licenses(Jun. 5, 1996) (61 Fed. Reg. 28,467) 12/14/2011 NYS000128 NYS-37 61 Fed. Reg. 66,537, Environmental Review for Renewal of Nuclear Power Plant Operating Licenses(Dec. 18, 1996) (61 Fed. Reg. 66,537) 12/14/2011 NYS000129 NYS-37 National Renewable Energy Laboratory, Land-Use Requirements of Modern Wind Power Plants in the United States, Paul Denholm, Maureen Hand, Maddalena Jackson, and Sean Ong (August 2009) Excerpted: p. 22 (2009 NREL Report) 12/14/2011 31
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000130 NYS-37 68 Fed. Reg. 55,905, Denial of Petition for Rulemaking(Sept. 29, 2003) (68 Fed. Reg. 55,905) 12/14/2011 NYS00131A-NYS00131I NYS-37 NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Main Report, Volumes 1 and 2 (May 1996) (GEIS) 12/14/2011 NYS00132A-NYS00132D NYS-37 NUREG-1437, Draft Supplemental Environmental Impact Statement for License Renewal of Nuclear Plants:
Regarding Indian Point Units 2 and 3, Supplement 38, Volumes 1 and 2 (December 2008) (DSEIS) 12/14/2011 NYS00133A-NYS00133D NYS-37 NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Indian Point Nuclear Generating Unit Nos. 2 and 3, Supplement 38, Volumes 1, 2 and 3 (December 2010)
(FSEIS) 12/14/2011 32
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000134 NYS-37 New York State Attorney General, Comments on the Draft Supplemental Environmental Impact Statement, Indian Point Units 2 and 3 (Mar. 19, 2009)(ML090771328)(2009 NYS AG Comments) 12/14/2011 NYS000135 NYS-6/7 State of New York Statement of Position, NYS-6/7
("NYS-6/7 SOP")
12/15/2011 NYS000136 NYS-6/7 Pre-filed Testimony of Earle Bascom ("Bascom PFT")
12/15/2011 NYS000137 NYS-6/7 Curriculum Vitae of Earle Bascom ("2011 Bascom CV")
12/15/2011 NYS000138 NYS-6/7 Report of Earle Bascom in Support of Contentions NYS-6/7 ("2011 Bascom Report")
12/15/2011 NYS000139 NYS-6/7 T. Miyashita, Deterioration of Water-Immersed Polyethylene-Coated Wire by Treeing, IEEE Transactions on Electrical Insulation (September 1971)("Miyashita")
12/15/2011 33
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000140 NYS-6/7 L. A. Dissado and J.C. Fothergill, Electrical Degradation and Breakdown in Polymers, IEE Materials and Devices Series 9 (1992) Excerpted: p. 18-19
("Dissado")
12/15/2011 NYS000141 NYS-6/7 S. Boggs, J. Densley, and J. Kuang, Mechanism for Impulse Conversion of Water Trees to Electrical Trees in XLPE, IEEE Trans. Power Del., Vol. 13, No. 2 (Apr. 1998) ("Boggs")
12/15/2011 NYS000142 NYS-6/7 C.T. Meyer and A. Chamel, Water and Ion Absorption by Polyethylene in Relation to Water Treeing, IEEE Transactions on Electrical Insulation, Vol. EI-15, No. 5 (October 1980) ("Meyer")
12/15/2011 34
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000143 NYS-6/7 R. Ross, Water Treeing Theories Current Status, Views and Aims, Proceedings of 1998 International Symposium on Electrical Insulating Materials, in conjunction with 1998 Asian International Conference on Dielectrics and Electrical Insulation and the 30th Symposium on Electrical Insulating Materials, Toyohashi, Japan (Sept. 27-30, 1998) ("Ross")
12/15/2011 NYS000144 NYS-6/7 N. Hampton, R. Hartlein, et. al., Long-Life XLPE Insulated Power Cable, Jicable (2007) ("Hampton")
12/15/2011 NYS000145 NYS-6/7 W. Shu, S.A. Boggs, Effect of Cable Restoration Fluid on Inhibiting Water Tree Initiation, IEEE Transactions on Power Delivery, Vol. 26, No. 1 (January 2011) ("Shu")
12/15/2011 NYS00146A-NYS00146C NYS-6/7 NUREG-1801, Rev. 1, Volumes 1 and 2, Generic Aging Lessons Learned (GALL) Report (September 2005) ("GALL Rev 1")
12/15/2011 35
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS00147A-NYS00147D NYS-6/7 NUREG-1801, Rev. 2, Generic Aging Lessons Leared (GALL) Report, Final Report (December 2010) ("GALL Rev 2")
12/15/2011 NYS000148 NYS-6/7 NUREG/CR-7000, BNL-NUREG-90318-2009, Essential Elements of an Electric Cable Condition Monitoring Program, Office of Nuclear Regulatory Research, U.S.
Nuclear Regulatory Commission (January 2010)
("NUREG/CR-7000")
12/15/2011 NYS000149 NYS-6/7 NRC Generic Letter 2007-01: Inaccessible or Underground Power Cable Failures That Disable Accident Mitigation Syatems or Cause Plant Transients (Feb. 7, 2007) ("Generic Letter 2007-01")
12/15/2011 NYS000150 NYS-6/7 NRC Request For Additional Information For The Review Of The Indian Point Nuclear Generating Unit Number 2 and 3 (Feb. 10, 2011) ("RAI")
12/15/2011 36
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000151 NYS-6/7 Entergy Response (NL-11-032) to Request for Additional Information (RAI), Aging Management Programs, Indian Point Nuclear Generating Unit Nos. 2
& 3, Docket Nos. 50-247 and 50-286, License Nos. DPR-26 and DPR-643 (Mar. 28, 2011) ("Entergy's March 28 Response")
12/15/2011 NYS000152 NYS-6/7 Entergy Response (NL-11-074) to Request for Additional Information (RAI), Aging Management Programs, Indian Point Nuclear Generating Unit Nos. 2
& 3, Docket Nos. 50-247 and 50-286, License Nos. DPR-26 and DPR-64 (Jul. 14, 2011) ("Entergy's July 14 Response")
12/15/2011 NYS000153 NYS-6/7 Entergy Response (NL-11-090) to Request for Additional Information for the Review Of The Indian Point Nuclear Generating Unit Number 2 and 3 (Jul.
27, 2011) ("Entergy's July 27 Response")
12/15/2011 37
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000154 NYS-6/7 Entergy Clarification (NL-11-096) for Request for Additional Information (RAI), Aging Management Programs, Indian Point Nuclear Generating Unit Nos. 2
& 3, DOcket Nos. 50-247 and 50-286, License Nos. DPR-26 and DPR-64 (Aug. 9, 2011) ("Entergy's August 9 Response")
12/15/2011 NYS000155 NYS-6/7 Inquiry Into The Auckland Power Supply Failure, Technical Report - Cable Failures, Integral Energy Australia (May 5, 1998) ("Auckland")
12/15/2011 NYS00156A-NYS00156E NYS-6/7 SAND96-0344, "Aging Management Guideline for Commercial Nuclear Power Plants - Electrical Cable and Terminations (September 1996) ("SAND96-0344")
12/15/2011 NYS000157 NYS-6/7 EPRI, Technical Report (1003664), Medium-Voltage Cables in Nuclear Plant Applications - State of Industry and Condition Monitoring, Final Report (October 2003) ("EPRI 1003664")
12/15/2011 38
Revised: December 15, 2011 Entergy Nuclear Operations, Inc. (Indian Point Units 2 and 3),
Docket Nos. 50-247-LR and 50-286-LR, ASLBP No. 07-858-03-LR-BD01 Evidentiary Hearing State of New York ("NYS") Hearing Exhibits NYS Exhibit Contentions Addressed by Exhibit Exhibit Name Exhibit Submission /
Revision Date NYS000158 NYS-6/7 EPRI, Plant Support Engineering: Aging Management Program Guidance for Medium-Voltage Cable Systems for Nuclear Power Plants, Final Report (1020805) (June 2010) ("EPRI 1020805")
12/15/2011 NYS000159 NYS-6/7 Entergy (NL-07-153) Amendment 1 to License Renewal Application, Excerpted: Attachment 3 - AMP Audit at 32-33 (Dec. 18, 2007) ("LRA Amendment 1")
12/15/2011 NYS000160 NYS-6/7 NUREG-1930, Safety Evaluation Report Related to the License Renewal of Indian Point Nuclear Generating Unit Nos. 2 and 3, Supplement No. 1, Docket Nos. 50-247 and 50-286 (Agust 2011) ("SSER")
12/15/2011 NYS000161 NYS-6/7 NUREG-1800, Final Report, Rev. 2, Standard Review Plan for Review of License Renewal Applications for Nuclear Plants (December 2010) ("SRP Rev 2")
12/15/2011 NYS000162 NYS-6/7 Declaration of Assistant Attorney General Lisa Feiner
("PFT Feiner Decl.")
12/15/2011 39