MONTHYEARML11286A0192011-10-10010 October 2011 Response to Request for Additional Information Restart Readiness Determination Plan Project stage: Response to RAI ML11293A1162011-10-20020 October 2011 G20110757/EDATS: OEDO-2011-0701 - Paul Gunter, Kevin Kamps and Thomas Saporito Et Al. Re 2.206 - Request for Emergency Enforcement Action to Suspend the Restart and Operation of the North Anna Nuclear Generating Station Project stage: Request ML11307A3772011-11-0101 November 2011 G20110757/EDATS: OEDO-2011-0701 - Incoming - Eleanor Amidon E-Mail Safety First at North Anna Nuclear Reactors Project stage: Request ML11308A0272011-11-0202 November 2011 G20110757/EDATS: OEDO-2011-0701 - Paul Gunter, Kevin Kamps, Thomas Saporito, Ltr. Et Al. Re Supplement to October 20, 2011 Emergency Enforcement Petition (10 CFR 2.206) to Suspend the Restart and Operation of the North Anna Nuclear Power St Project stage: Request ML11308A0322011-11-0303 November 2011 G20110757/EDATS: OEDO-2011-0701 - Incoming - Lovell King E-mail Request to Co-Sign on the Request for Emergency Enforcement Action to Suspend and Restart and Operation of the North Anna Nuclear Generating Station, Mineral Virginia Per 10 CF Project stage: Request ML11311A1952011-11-0606 November 2011 G20110757/EDATS: OEDO-2011-0701 - Incoming - Erika Kretzmer E-mail Petition to Suspend North Anna Station Project stage: Request ML11314A0692011-11-0707 November 2011 Independent Spent Fuel Storage Installation, Revised Long-Term Actions Commitment List Project stage: Request ML11314A1182011-11-0909 November 2011 G20110757/EDATS: OEDO-2011-0701 - Incoming - David Levy Email Co-Signer Request for Emergency Enforcement Action of North Anna Nuclear Generating Station Project stage: Request ML11326A1802011-11-20020 November 2011 G20110757/EDATS: OEDO-2011-0701 - Incoming - Hillary Boyd Email North Anna Nuclear Plant - Petition Project stage: Request ML11326A0172011-11-28028 November 2011 Notice of Meeting with the Petitioners, Beyond Nuclear Et Al., Requesting Action Under 10 CFR 2.206 Regarding Suspension of the Operating Licenses for Naps Due to Concerns About Damage to the NAPS Reactors from the August 23, 2011, Earthqua Project stage: Request ML11349A2482011-12-11011 December 2011 G20110757/EDATS: OEDO-2011-0701 - Incoming - Richard Ball E-mail, Co-Petitioner Project stage: Request ML12033A0252011-12-12012 December 2011 G20110757/EDATS: OEDO-2011-0701 - Corrected Transcript - Forthcoming Meeting with the Petitioners, Beyond Nuclear Et Al., Requesting Action Under Title 10 of Code of Federal Regulations (10 CFR) 2.2 Project stage: Request ML12060A1972011-12-15015 December 2011 NRR E-mail Capture - Follow Up on Eep PRB Meeting Project stage: Request ML12018A2282012-01-19019 January 2012 G20110757/EDATS: OEDO-2011-0701 - Forthcoming Meeting with the Petitioners, Beyond Nuclear Et Al., Requesting Action Under 10 CFR 2.206 Regarding Suspension of the Operating Licenses for North Anna Power Station (NAPS) Due to Concerns About Project stage: Request ML12060A3522012-03-0101 March 2012 G20110757/EDATS: OEDO-2011-0701 - 12/12/11 - Meeting Summary of Meeting with Paul Gunter Et Al. Regarding Their 10 CFR 2.206 Petition to Suspend the Operating Licenses (Ols) for North Anna 1 and 2 Project stage: Meeting ML12060A3682012-03-0101 March 2012 G20110668/EDATS: OEDO-2011-0622 - 02/02/12 - Meeting Summary for Meeting with Paul Gunter Et Al. Regarding Their 10 CFR 2.206 Petition to Suspend the Operating Licenses for North Anna Power Station, Unit Nos. 1 and 2 Project stage: Meeting ML12060A0912012-03-16016 March 2012 G20110757/EDATS: OEDO-2011-0701 - Federal Register Notice - Receipt of Request for Action Under 10 CFR 2.206 for North Anna Power Station, Unit Nos. 1 and 2 Project stage: Other ML12060A0902012-03-16016 March 2012 G20110757/EDATS: OEDO-2011-0701 - Acknowledgement Letter to Paul Gunter Re.: Request for Emergency Enforcement Action to Suspend and Restart and Operation of the North Anna Nuclear Generating Station, Units 1 and 2 Project stage: Other NRC-2012-0075, G20110757/EDATS: OEDO-2011-0701 - Federal Register Notice - Receipt of Request for Action Under 10 CFR 2.206 for North Anna Power Station, Unit Nos. 1 and 22012-03-16016 March 2012 G20110757/EDATS: OEDO-2011-0701 - Federal Register Notice - Receipt of Request for Action Under 10 CFR 2.206 for North Anna Power Station, Unit Nos. 1 and 2 Project stage: Other ML12165A2132012-07-10010 July 2012 G20110757/EDATS: OEDO-2011-0701 - Proposed Director'S Decision Under 10 CFR 2.206 Project stage: Acceptance Review 2011-11-07
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000338/20240032024-10-28028 October 2024 – Integrated Inspection Report 05000338-2024003 and 05000339-2024003 ML24283A0392024-10-0909 October 2024 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.D ML24281A1372024-10-0707 October 2024 ISFSI - Submittal of Cask Registration for Spent Fuel Storage 05000338/LER-2024-001-01, Automatic Reactor Trip Due to Prni High Negative Rate2024-09-24024 September 2024 Automatic Reactor Trip Due to Prni High Negative Rate IR 05000338/20244202024-09-23023 September 2024 Security Baseline Inspection Report 05000338/2024420 and 05000339/2024420, Cover Letter ML24243A0872024-09-20020 September 2024 Response to EPA Comments Regarding the Final Site Specific Supplement to the Generic Eist for License Renewal North Anna Power Station, Units 1 and 2 IR 05000338/20244022024-09-17017 September 2024 Security Baseline Inspection Report 05000338/2024402 and 05000339/2024402 ML24215A2622024-08-28028 August 2024 Transmittal Letter for Subsequent Renewed License IR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) 05000339/LER-2024-001-01, Loss of Generator Field for 2J Eog During 2-PT-82.282024-08-20020 August 2024 Loss of Generator Field for 2J Eog During 2-PT-82.28 ML24234A0742024-08-15015 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-23-63, NEI 03-08 Needed Guidance: PWR Thermal Shield Flexure Inspection Requirements ML24221A1932024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Upper Mattaponi Tribe ML24206A0052024-08-0808 August 2024 SLR Final EIS Letter to Achp ML24221A1882024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Monacan Indian Nation ML24221A1842024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Nation, Oklahoma ML24221A1922024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Tuscarora Nation of New York ML24221A1912024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Rappahannock Tribe, Inc ML24221A1942024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-United Keetoowah Band of Cherokee Indians in Oklahoma ML24221A1852024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Delaware Tribe of Indians ML24221A1832024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Chickahominy Indian Tribe-Eastern Division ML24206A0062024-08-0808 August 2024 Notice of Availability of the Final Environmental Impact Statement for the North Anna Nuclear Power Station Unit Numbers 1 and 2 Subsequent License Renewal (Docket Numbers: 50-338 and 50-339) ML24163A3002024-08-0808 August 2024 Request for Relief Request N1-I5-NDE-007 Inservice Inspection Alternative ML24208A0142024-08-0808 August 2024 Tribal Section 106 Letters-North Anna-Absentee-Shawnee Tribe of Indians of Oklahoma ML24221A1872024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Shawnee Tribe of Oklahoma ML24221A1862024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Eastern Band of Cherokee Indians ML24221A1902024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Pamunkey Indian Tribe ML24221A1812024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Catawba Indian Nation ML24221A1822024-08-0808 August 2024 Tribal Section 106 Letters - North Anna - Chickahominy Indian Tribe ML24221A1892024-08-0808 August 2024 Tribal Section 106 Letters-North Anna - Nansemond Indian Nation ML24241A0692024-08-0606 August 2024 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000338/20240022024-08-0202 August 2024 Integrated Inspection Report 05000338/2024002 and 05000339/2024002 ML24206A0432024-07-26026 July 2024 Feis - Letter to the Applicant 05000338/LER-2024-001, Automatic Reactor Trip Due to Prni High Negative Rate2024-07-25025 July 2024 Automatic Reactor Trip Due to Prni High Negative Rate ML24206A0902024-07-24024 July 2024 Owners Activity Report ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code 05000339/LER-2024-001, Loss of Generator Field for 2J EDG During 2-PT-82.282024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 ML24165A1462024-06-0505 June 2024 Loss of Generator Field for 2J EDG During 2-PT-82.28 IR 05000338/20240102024-05-24024 May 2024 NRC Fire Protection Team Inspection (FPTI) Report 05000338/2024010 and 05000339/2024010 IR 05000338/20240012024-05-10010 May 2024 Integrated Inspection Report 05000338/2024001 and 05000339/2024001 IR 05000338/20244032024-04-30030 April 2024 – Security Baseline Inspection Report 05000338-2024403 and 05000339-2024403 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24110A1462024-04-18018 April 2024 Independent Spent Fuel Storage Installation (Sfsi) - Annual Radiological Environmental Operating Report ML24110A1502024-04-18018 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24110A1392024-04-18018 April 2024 Annual Environmental Operating Report ML24087A0572024-04-16016 April 2024 Correction to Issuance of Amendment Nos. 296 and 279 ML24088A2692024-03-27027 March 2024 Core Operating Limits Report Cycle 31 Pattern Sos Revision 0 ML24086A4292024-03-25025 March 2024 Response to Request for Additional Information Associated with Alternative Request N1-I5-NDE-007 Request to Deter Additional Required Reactor Coolant Pump Casing Inspection 2024-09-24
[Table view] |
Text
VIRGINIA ELECTRIC AND POWER COMPANY I RICHMOND, VIRGINIA 23261 November 7, 2011 10 CFR 100, Appendix A U.S. Nuclear Regulatory Commission Serial No.: 11-520D Attention: Document Control Desk NL&OS/GDM R1 Washington, DC 20555 Docket Nos.: 50-338/339 72-16/72-56 License Nos.: NPF-4/7 SNM-2507 VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 AND 2 INDEPENDENT SPENT FUEL STORAGE INSTALLATION REVISED LONG-TERM ACTIONS COMMITMENT LIST By letter dated November 3, 2011 (Serial No. 11-520C), Virginia Electric and Power Company (Dominion) submitted a compilation of long-term programmatic actions that Dominion committed to perform to address the August 23, 2011 earthquake. The compilation includes the scheduled completion dates for the actions, as well as the associated letters that contain the commitments as applicable. During subsequent conference calls between Dominion and the NRC staff, in which the long-term action commitments were discussed, it became evident that several of the commitments contained in the list require revision to more clearly reflect the scope of the actions to be taken. Consequently, Dominion has revised the Long-Term Actions Commitment List that was contained in the November 3, 2011 letter to provide clarifying detail for certain actions included in the list. The Long-Term Actions Commitment List provided in the attachment updates and supersedes the long-term commitments previously provided in earlier Dominion correspondence associated with the August 23, 2011 earthquake.
If you have any questions or require additional information, please contact Mr. Gary D..Miller at (804) 273-2771.
Sincerely, E. S. Grecheck Vice President - Nuclear Development ViCKI L. HULL,
Attachment:
. Notary Public Commonwealth of Virginia Long-Term Actions Commitment List yC s1405420 1 My Commission Expires Mavy131.:2014],
COMMONWEALTH OF VIRGINIA COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by E. S. Grecheck who is Vice President - Nuclear Development, of Virginia Electric and Power Company. He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of that Company, and that the statements in the document are true to the best of his knowledge and belief.
Acknowledged before me this I-IZ day of4*. kj2 , 2011.
My Commission Expires: . /.
7ý 0(_Dý Notary Public o ýýýo
Serial Number 11-520D Docket Nos. 50-338/339/72-16/72-56 Page 2 of 2 cc: Regional Administrator U.S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Senior Resident Inspector North Anna Power Station M. Khanna Branch Chief - Mechanical and Civil Engineering Branch U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 09 E-3 11555 Rockville Pike Rockville, MD 20852-2738 R. E. Martin NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 P. G. Boyle NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 J. B. Davis NRC Senior Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop EBB-E3-D2M 11555 Rockville Pike Rockville, MD 20852-2738 J. E. Reasor, Jr.
Old Dominion Electric Cooperative Innsbrook Corporate Center 4201 Dominion Blvd.
Glen Allen, Virginia 23060
Serial No. 11-520D Docket Nos. 50-338/339/72-16/72-56 Attachment Long-Term Actions Commitment List Virginia Electric and Power Company (Dominion)
North Anna Power Station Units 1 and 2
Serial No. 11-520D Docket Nos. 50-338/339/72-16/72-56 Attachment Page 1 of 2 Long-Term Actions Commitment List North Anna Power Station Units I and 2 Item Commitment Scheduled No. Completion Date Dominion will perform long-term evaluations of plant structures, systems and components in accordance anomalies identified during with RG 1.167/EPRI the evaluations will beNP-6695, entered Section 6.3. Any into the corrective April 30, 2013 action system and evaluated for extent of condition.
Dominion will develop a plan to characterize the seismic source and any 2 special ground motion effects due to the relative locations of the fault and the March 31, 2012 site and will update the NRC accordingly.
Dominion will revise the North Anna Updated Final Safety Analysis Report to document:
- a. The recorded August 23, 2011 seismic event. April 30, 2012
- b. A summary of the evaluation and results of the seismic analysis of April 30, 2013 the recorded event completed per RG 1.167/EPRI NP-6695.
3 c. Design controls on seismic margin management (i.e., the Seismic Margin Management Plan). April 30, 2012
- d. Incorporation of Regulatory Guide (RG) 1.166, "Pre-Earthquake Planning and Immediate Nuclear Power Plant Operator Post-Earthquake Actions," and RG 1.167, "Restart of a Nuclear Power December 31, 2012 Plant Shut Down by a Seismic Event," into the North Anna licensing basis.
Dominion will implement a design change to replace the existing seismic equipment and Main Control Room indication with upgraded and enhanced seismic monitoring instrumentation equipment, which includes installation of a December 31, 2012 permanent, free field seismic monitor. Permanent, seismically qualified (subject to receipt 4 backup power to a new Seismic Monitoring Panel will also be installed of seismic including a backup battery power supply. The seismic instrumentation will be monitoring installed and maintained in accordance with RG 1.12, Rev 2, NuclearPower equipment and Plant Instrumentation for Earthquakes. The project will also install seismic outage schedules) recording instrumentation at the station Independent Spent Fuel Storage Installation (ISFSI) pad.
Dominion will perform a re-evaluation of the plant equipment identified in the 5 IPEEE review with HCLPF capacity <0.3g, which will include an assessment March 31, 2013 of potential improvements.
Dominion will develop a plan with the NSSS vendor consisting of additional 6 evaluations or inspections, as warranted, to assure long term reliability of the February 29, 2012 reactor internals.
Dominion will perform a comparison of the calculated load from the August 7 23, 2011 earthquake and the existing leak-before-break (LBB) analysis and March 31, 2013 submit the results.
In accordance with the MRP-227 Dominion will perform inspections at North Anna Power Station in accordance inspection plan, with the latest MRP-227 revision approved by the NRC. which will be provided by March 31, 2013
Serial No. 11-520D Docket Nos. 50-338/339/72-16/72-56 Attachment Page 2 of 2 Long-Term Actions Commitment List North Anna Power Station Units 1 and 2 Item Commitment Scheduled No. Completion Date Dominion will re-evaluate the Time-Limiting Aging Analyses (TLAAs) that include seismic inputs to either: 1) quantitatively demonstrate that the TLAAs March 31, 2013 are still bounding, or 2) re-analyze the TLAAs, based on the August 23, 2011 earthquake.
Dominion will implement a long term Seismic Margin Management Plan to address the impact of the August 23, 2011 earthquake. Specifically, to ensure adequate seismic margins are maintained for plant SSCs, Dominion will revise the design change process for North Anna Power Station to require
,explicit evaluation of plant modifications for the effects of the August 23, 2011 earthquake using In-Structure Response Spectra (ISRS) for the event for the Containment, Auxiliary Building, and other buildings containing safety related December 31, 2011 SSCs developed based on actual time-histories recorded during the/event. In support of future plant design changes, the evaluation of plant SSCs will 10 require design verification and code compliance with the stresses, loads, accelerations, and displacements generated from the analysis with the design basis ISRS and the analysis with the ISRS for the August 23, 2011 earthquake, whichever are higher.
Dominion will provide 30-days prior written notification to the NRC if it determines the Seismic Margin Management Plan is no longer required based on the implementation of comparable actions as part of the resolution N/A of the NRC's recommendations emanating from the Fukushima Daiichi Task Force and/or Generic Issue (GI)-199.