ML113050588

From kanterella
Jump to navigation Jump to search
Response to Public Comments on Docket Id NRC-2011-0013-NRC Regulatory Issue Summary 2011-12, Revision 1, Adequacy of Station Electric Distribution System Voltages
ML113050588
Person / Time
Issue date: 12/29/2011
From:
Office of Nuclear Reactor Regulation, Office of New Reactors
To:
Mensah, T M, NRR/DPR, 415-3610
Shared Package
ML113050591 List:
References
NRC-2011-0013 RIS-11-012, Rev 1
Download: ML113050588 (56)


See also: RIS 2011-12

Text

1

RESPONSE TO PUBLIC COMMENTS ON DOCKET ID NRC-2011-0013

PROPOSED GENERIC COMMUNICATIONS: DRAFT NRC REGULATORY ISSUE

SUMMARY 2011-XX: ADEQUACY OF STATION ELECTRIC DISTRIBUTION

SYSTEM VOLTAGE*

On January 18, 2011, a Notice of Opportunity for Public Comment was published in the Federal

Register to clarify the NRC staffs technical position on existing regulatory requirements and

guidance for Degraded Voltage Relay (second level undervoltage protection) protection setting

bases and Transmission Network/Offsite/Onsite station electric power system design bases. On

February 23, 2011, a Notice was published in the Federal Register extending the comment

period to March 19, 2011, based on the request from NEI (ADAMS Accession No.

ML110330025). Comments were received from 14 organizations/individuals. The staff also

conducted a workshop on June 28-29, 2011, to discuss the NRCs existing regulatory

requirements and guidance for nuclear power plant electric power system degraded voltage

protection and addressed workshop participants questions

1. (1-7) Dominion

Resources, Inc

(ADAMS Accession No.

ML110540357)

2. (8-31) Exelon

Generation Company, LLC

(ADAMS Accession No.

ML110540358)

3. (32-39) Southern

Nuclear Operating

Company

(ADAMS Accession No.

ML110540360)

4. (40-45, 59-85 & 86-96)

NEI

1776 I Street NW

Washington, DC, 20006

(ADAMS Accession Nos.

ML110660379,

ML110810619)

5. (49-51) Jerry Nicely

Self

(ADAMS Accession No.

ML110800530)

6. (52-58) Larry Nicholson

Nextera

(ADAMS Accession No.

ML110800536)

7. (97-108) PPL

Susquehanna, LLC

(ADAMS Accession No.

ML110830675)

8. (109-124) APS, Palo

Verde Nuclear Generating

Station

(ADAMS Accession No.

ML110820342)

9. (125-131) Nextera

Energy

(ADAMS Accession No.

ML110820119)

10. (132) TVA

(ADAMS Accession No.

ML110840041)

11. (133-137)Progress

Energy

(ADAMS Accession No.

ML110840040)

12. (138-139) STARS

(ADAMS Accession No.

ML110870916)

13. (140) Greg Reimers/

Diablo Canyon

Email (ADAMS Accession

No. ML112010028)

14. (141) Brian Wilson

(ADAMS Accession No.

ML110960076)

The NRC staffs review and disposition of the comments are provided in the following Table.

  • This response supersedes the information provided earlier in ADAMS at Accession Nos.

ML111600659 and ML112371830. These documents were incorrectly released as final

documents when in fact they were drafts. Changes between the draft and final public comment

resolution documents can be viewed in ADAMS at Accession No. ML11357A142xxxxxxxxx.

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

1.

SUMMARY OF

ISSUES - 1. DVR

Setting Design

Calculations

Dominion

Resources

Services, Inc

Section DVR Setting Design

In this manner, the DVR ensures adequate

operational (starting and running) voltage to all

safety related equipment, independent of voltage

controlling equipment external to the plant safety

related electrical distribution system.

The approach could imply that the load(s) should

start from the lowest DVR dropout setting. A

specific example for illustration is as follows:

If voltage is at the lowest possible value above

Disagree

NRC Staff has the following clarification with

this position.

2

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

dropout, starting a load will cause DVR dropout,

but, since the new steady state voltage will be

lower than the initial value, then DVR reset cannot

occur.

Many utilities use the ABB 27N with harmonic filter

which has a minimum 0.5% reset. Thus, with a

setting of 93.6% +/- 0.9%, dropout could be as low

as 92.7%. However, for motors causing more than

0.5% voltage dip at initial start, even if the voltage

at the beginning of the event was 93.2% and a load

was started, then DVR will dropout and never reset

causing a separation. A clarification that allows

evaluation of motor starting as well-as other

conditions is:

If the DVR could possibly not cause separation

then the required safety functions must be

performed successfully. Thus, depending on the

design of the plant, a voltage value for beginning

the event with all required starts could be

determined by an iterative process.

If the offsite power has adequate capacity

and capability, any voltage just above the

DVR setpoint should not separate the offsite

power source from the safety bus when

starting large motors. The grid voltage is

expected to recover.

The key point is that the voltage setting(s)

selected should ensure that adequate

voltage is available at the component

terminal(s) to operate the most limiting

component (s) at a plant during the most

limiting design basis event. The offsite/onsite

interface calculation should show that, with

the grid at the lower limit of the normal

operating range, voltage at the safety bus is

always well above the degraded voltage

setpoint for all design basis event loading

conditions (normal, abnormal and accident

conditions including anticipated operational

occurrence).

The safety related equipment should be

protected from two types of low voltage

issues:

1.

Loss of voltage event which

implies a sudden sharp voltage

drop in grid system. Typically a

nominal delay is allowed for relay

actuation to separate onsite

busses from the grid if voltage

does not recover to normal

operating band.

2.

Degraded voltage event that

postulates sustained low voltage

conditions for several seconds and

subsequent recovery to normal

operating band. If the offsite power

system does not recover to

nominal operating conditions, it is

preferable to separate from the

source.

The ABB relay with harmonic filter should be

able to reset if the grid perturbation is limited

to a short duration.

2.

SUMMARY OF

ISSUES -- 2 .

Offsite/Onsite

Design Interface

Calculations(page

7)

Dominion

Resources

Services, Inc

This section contains elements that are too

prescriptive. Many analyses will show that the unit

loads/sequences assessed for determination of

DVR setpoint adequacy for equipment protection

are the same as those for evaluating offsite power.

Since evaluating offsite power always involves

higher voltages, it is clear the equipment will

function and providing terminal voltages for this

equipment is bounded by DVR adequacy analysis.

A clarification that helps frame adequate analysis

is:

If the DVR could initiate separation then offsite

power is not operable. Using the example above

when evaluating offsite power would require that

the safety bus recover above 93.6%+0.9%+0.5%

or 95% before the earliest time delay for the DVR

expires. Since a reset also resets the time delay,

multiple DVR drop outs could occur without

separation during load sequencing. Also, since

92.7% was evaluated for equipment protection,

Disagree

NRC Staff has the following clarification for

this position.

To meet GDC 17 requirements, the licensee

must demonstrate capability to safely shut

down the plant for all design basis events

with the grid voltage at the lowest allowable

value as afforded by the transmission system

operator.

The voltage studies done for evaluating

offsite power/onsite power interface should

use minimum expected voltage at the

plant/grid interface node, demonstrating

adequate voltage for starting and running of

plant components during normal, abnormal

and accident conditions. The expected plant

loading at 100% power operation may be

higher than accident loading. Hence the

3

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

evaluating 95% (used for offsite power evaluation)

would require the two sequences be substantially

different (2.3%) for the DVR adequacy evaluation

(at 92.7%) to not be bounding for equipment

evaluation. Thus, providing calculation detail to

motor terminals for offsite power evaluation is

unnecessary in many designs.

voltage drop in the plant auxiliary system will

be higher for normal operating conditions.

The DVR setpoint should be below the

normal operating voltage of the plant to avoid

multiple spurious actuations. A separate

analysis may be needed for DVR setpoint.

The comment implies that DVR setpoint

overlaps with system voltage during normal

operation.

Calculation details to motor terminals are

helpful in gaining margin between DVR

setpoint and normal grid operating voltages.

To avoid spurious DVR actuation during

normal plant operation and during load

sequencing, the DVR setpoint should be

lower than normal operating band for offsite

power. This can be achieved by :

1) Specifying equipment for safety related

applications to function at voltage levels

well below the nominal bus voltage.

2) Reducing the onsite system

impedance/voltage drop. This can be

achieved by reducing the cable impedance

for the limiting safety loads and tripping

non-essential loads after unit trip.

3.

SUMMARY OF

ISSUES -- 2 .

Offsite/Onsite

Design Interface

Calculations(page

7)

Dominion

Resources

Services, Inc

Part a states:

This transmission owner/operator supplied voltage

range should address all transmission

network and plant system operating configurations

and should also include voltage drop due to

the bounding worst case transmission system

contingency (transmission system contingencies

include trip of the nuclear power unit).

Certainly the trip of the nuclear power unit must

always be considered. However, the definition of

the worst case transmission system contingency

requires clarifying statements. Certainly some

analyses are done using "strong grid" for fault

analyses or "weak grid" for voltage analyses.

These modeled sources have a number of

contingencies built into them. Voltage drop from the

loss of the unit can vary considerably with system

conditions. Arguments can be made that the worst

case contingency (if different than the nuclear

power unit) should only be considered once it has

occurred. However, a key question should be

applied: Is the contingency of interest monitored? If

the status is not monitored, then how would the

nuclear unit know when to apply the contingency?

Thus, if the status of a key transmission line to the

nuclear unit switchyard is known, either by

instrumentation at the plant or timely notification

by the grid operator, then the contingencies need

only be considered when applicable. When

evaluating voltage drop, most situations which

cause meaningful changes are nearby and can be

monitored.

Disagree

The plant electrical distribution system

should be designed based on the grid

voltage range including the bounding worst

case grid contingency (strong or weak grid

depending on which one is bounding). In this

way, the plants design ensures adequate

voltage to plant equipment as long as grid is

operating as expected.

Contingencies that are beyond design basis

(line outages during peak grid loading

conditions) that occur during plant operation

should be evaluated uniquely to assess the

capability of offsite power to provide

shutdown capability post trip as required by

GDC 17.

GDC 17 requires that offsite power has

sufficient capacity and capability to assure

that (1) specified acceptable fuel design

limits and design conditions of the reactor

coolant pressure boundary are not exceeded

as a result of anticipated operational

occurrences, and (2) the core is cooled and

containment integrity and other vital

functions are maintained in the event of

4

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

postulated accidents.

4.

SUMMARY OF

ISSUES -- 2 .

Offsite/Onsite

Design Interface

Calculations(page

8)

Dominion

Resources

Services, Inc

Part c states:

For multi-unit stations, a separate analysis should

be performed for each unit assuming (1) an

accident in the unit being analyzed and

simultaneous shutdown of all other units at the

station,' or (2) an anticipated transient (anticipated

operational occurrence) in the unit being analyzed

(e.g., unit trip) and simultaneous shutdown of all

other units at that station, whichever presents the

largest load situation.

This requires clarification as an accident or

anticipated transient both require unit trip. The

word used for other units at the station is

"shutdown" which is more orderly and takes more

time. Simultaneous unit trip results in bigger

voltage drops from VAR support (not loading). This

is because VARs are local. System X/R is typically

-50 so it is 50 times more difficult to move a VAR a

hundred miles than a watt. Thus, most analyses

show the worst voltage drop for the loss of the

nuclear unit is when all of the nearby units (any

type of generation) are already off. Changing that

to tripping all units at the same time increases the

voltage drop because grid compensatory actions

are not included. Even a small (minute) time

difference between losses of units can be

meaningful in the voltage result. However, if the

intent of the wording was simultaneous trip, then

this is a special case of item 3 above, which is

likely a monitored contingency.

Disagree

This statement is consistent with GDC 17,

GL 79-36, and IEEE Standard 308-1971,

Class IE Electrical Systems, Section 8,

Multi-Unit Station Considerations.

Multi-unit sites have been licensed in

accordance with above documents and

should therefore evaluate the plants

according to their licensing basis.

5.

SUMMARY OF

Dominion

Part j states:

5

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

ISSUES -- 2 .

Offsite/Onsite

Design Interface

Calculations(page

8)

Resources

Services, Inc

To provide assurance that actions taken to assure

adequate voltage levels for safety related loads

do not result in excessive voltages, assuming the

maximum expected value of voltage at the

connection to the offsite circuit, a determination

should be made of the maximum voltage

expected at the terminals of all safety related

equipment and their starting circuits (if applicable).

If this voltage exceeds the maximum voltage rating

of any safety related equipment, immediate

remedial action should be taken.

The word "immediate" describing remedial action

should be removed from this section. Immediate

remedial action could imply control room

intervention. The control room has alarm

procedures to address high voltage should it occur.

Timeliness of remedial actions depends on how

high actual voltage is since minor incursions have

only long term implications for most equipment.

Analyses of high grid voltage with light plant load

are standard and provide insights as to what grid

voltage upper limit should be or what compensating

activities might be required for light load operations

(refueling). In those cases where unit trip can result

in a step increase in grid voltage (most common on

higher voltage connections like 765kv), anticipated

excursions above desired voltages should be

addressed by compensating measures (changing

excitation for nearby units, switching in reactor

banks, etc.).

Disagree

The wording is consistent with GL 79-36.

The Offsite/Onsite design should address all

grid operating conditions to prevent

overvoltages from occurring.

The point here is that if a design problem is

identified such as overvoltage conditions,

immediate actions should be taken

(compensatory and/or permanent design

changes) to address the design problem

rather than taking actions after it occurs.

6.

SUMMARY OF

ISSUES (top of

page 6)

Dominion

Resources

Services, Inc

States: This interface calculation establishes

operating voltage bands for all plant electrical

buses, which ensures that all plant components

and systems (Class 1E and Non Safety Related)

have proper voltage for starting and running in all

operational configurations (expected operational

and accident conditions).

This statement needs clarification in that not all

non-safety load voltages need to be evaluated.

Typically, large motors (like reactor coolant pumps)

need to be evaluated for starting impact on the

safety bus. However, once a motor is found to be

small enough to not impact safety bus operation,

further evaluation is unnecessary. The statement in

the RIS can easily be interpreted as requiring

evaluation of all non-safety loads down to the

lowest levels of distribution.

Agree

The reference to non-safety related is being

removed. However, non-safety related loads

should be modeled to the extent that their

operation can affect safety bus/equipment

voltage.

7.

SUMMARY OF

ISSUES - 1. DVR

Setting Design

Calculations (page

6)

Dominion

Resources

Services, Inc

States:

Licensee voltage calculations should provide the

basis for their DVR settings, ensuring safety related

equipment is supplied with adequate operating

voltage (typically a minimum of 0.9per

unit voltage at the terminals of the safety related

equipment per equipment manufacturers

requirements), based on bounding conditions for

the most limiting safety related load (in terms of

voltage) in the plant.

Clarification that voltages other than 90% voltage

are common based on detailed plant analysis

should be added. As an example, motors below

90% voltage continue to have plenty of margin in

Agree.

90% was mentioned as an example used for

illustration. The voltage values are plant-

6

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

torque but may encroach on long time thermal

limits. However, unless a motor is fully into its

service factor (typically 1.15), as well as below 90%

voltage, operation will be acceptable.

specific. Evaluations like mentioned in this

comment could be acceptable as long as

there is adequate engineering justification.

Ensuring that voltages are within nominal

limits greatly simplifies the analysis required.

8.

General

Background -

Pages 2 and 3

Exelon

Generation

Company,

LLC

General Comments:

The RIS uses terms such as "LVR (loss-of-voltage

relay) voltage setting," "DVR (degraded

voltage relay) settings" and "DVR dropout setting"

without clarifying the intent or highlighting the

differences.

IEEE 741-2006, Annex A (Reference 1), has a

discussion on the tolerances to be considered and

recommends following ANSI/ISA 67.04.01

(Reference 2) treating the voltage relays and

associated time delays as instruments.

For the DVR, one example might be

represented as follows:

Analytical limit: Minimum voltage that assures

actuation of the relay

Allowable value, Lower: Higher than analytical limit

to allow for drift and test equipment tolerance;

abbreviated AVDO. Tech Spec value.

Dropout setpoint: Lower voltage band of nominal

setpoint. Abbreviated SPc DO (Setpoint calculated

Drop Out)

Pickup setpoint: Upper voltage band of nominal

setpoint. Abbreviated SPc PU (Setpoint calculated

Pick Up)

Allowable value, Upper: Higher than SPc PU to

allow for drift and test equipment tolerance;

abbreviated AVPU. Tech Spec value.

Maximum Dropout: Highest voltage that relay could

actuate. Only importance is for establishing reset

voltage.

Maximum Pickup: The voltage required to assure

DVR resets.

The RIS states that two sets of calculations are

required. It appears that at least three (3)

distinctly different calculations are required (four if

the site has different DVR time delays for accident

and normal conditions). These would be at different

bus voltage values. The "degraded voltage relaying

design calculations" would be a load flow

performed at the DVR analytical limit; the "plant

voltage analysis" would be load flows and motor

starting performed at the minimum transmission

contingency voltage with an acceptance criterion of

greater than relay maximum pickup (the voltage

where DVR reset is assured) at the bus where the

degraded voltage relays are connected (generally

the medium voltage bus where the Emergency

Diesel Generator is connected); finally, the

evaluation of protective device actuation would be

performed at the analytical limit of the loss of

voltage relay setting comparing the motor running

current to the thermal damage curve and protective

Disagree.

The terminology used in the RIS is

consistent with the guidance documents.

The setpoint accuracies and methodologies

are beyond the scope of this RIS.

The point of the RIS was to highlight that the

DVR setting and design interface

calculations have different requirements.

The staff agrees that there are other

calculations required to demonstrate the

electrical system design basis.

7

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

device characteristic curve.

Page 2, criteria b) - Some approved DVR designs

sense and trip at an emergency bus level, and take

advantage of inherent redundancy of the

emergency buses. It should be an owner's option

with respect to coincident logic. Change the "shall"

to "may."

Page 2/3 - The listed 6 criteria are good for setting

the DVR. Early correspondence of the issue

also included a second function for the DVR in that

the design should minimize the effects of

spuriously disconnecting the offsite sources.

Although criteria b) and c)(2) are intended to add

robustness to the design, a few sentences should

be added to the discussion to accentuate the

point.

RIS is consistent with the NRC letter dated

June 2, 1977.

The coincident logic is to ensure that

spurious or inadvertent separation of a

reliable offsite power source. The

redundancy of the safety buses alone does

not address the above concern

Current wording seems adequate to address

the point that spurious trips of offsite power

should be precluded by the design.

9.

SUMMARY OF

ISSUES - 1.

Degraded Voltage

Relaying Design

Calculations (page

6)

Exelon

Generation

Company,

LLC

Under "Degraded Voltage Relaying Design

Calculations," the RIS states in part "During normal

plant operation, the Class 1 E safety related buses

should automatically separate from the power

supply within a short interval (typically less than 60

seconds) if sustained degraded voltage

conditions are detected." Branch Technical Position

PSB-1 clause B.1.b.2 included provisions

for operator manual actions to restore bus voltage

on the Class 1 E distribution system. The

sixty second time delay would not allow operator

actions. This appears to be a new NRC

position.

Disagree.

This is not a new requirement.

RIS will be revised to remove the reference

to auto separate in 60 seconds. The 60

seconds time delay was identified as an

example to illustrate that the time delay

chosen for the sustained degraded condition

(DVR settings) should be short to ensure that

permanently connected Class 1E loads are

not damaged.

However, it should be noted that when

voltage alarms occur (alarm setpoint is set

higher than the DVR setpoint), the grid

voltage at that point may be well below the

normal operating values and is approaching

the DVR setpoint and operator actions may

be taken to improve the voltage conditions to

prevent separation from offsite power.

The time delay chosen should ensure that

until the relay automatic action is initiated, all

Class 1E equipment are protected. The

licensee must provide the bases and

justification in support of the actual delay

chosen.

10.

SUMMARY OF

ISSUES - 1.

Degraded Voltage

Relaying Design

Calculations Page

6

Exelon

Generation

Company,

LLC

The next to last sentence under item 1 states: 'The

staff considers degraded voltage

conditions coincident with a postulated design

basis accident to be a credible event. The event

is credible in that it has occurred previously

(although nonaccident). It is acknowledged that

safety loads combined with loss of generator

reactive power support will cause a decrease in

bus voltage. However, if the plant is operated

within the bounds of the operating procedures

(which are reflected in the voltage regulation

calculations as described under the subsequent

section), then the Class 1 E equipment should not

experience a degraded voltage condition.

The sentence can be removed without diminishing

the need for the DVR, or without changing

the intent of this section.

Disagree.

The point being made in the RIS is that

setting of the DVR should include

consideration of a coincident accident, in that

the time delay chosen for the DVR should

support the accident analysis assumptions

consistent with the NRC1977 letter.

Operating a plant within allowable voltage

range should minimize the potential for

degraded voltage conditions on 1E busses.

However, grid perturbations cannot be

predicted. Hence the need for automatic

protection.

11.

SUMMARY OF

ISSUES - 1.

Degraded Voltage

Relaying Design

Calculations -

Exelon

Generation

Company,

LLC

DVR Setting Design Calculations - Add a sentence

"The model should utilize loads on the plant

distribution system consistent with the specific

transient or accident being analyzed."

Agree.

The suggested sentence will be added to the

RIS.

8

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

Page 6,

12

SUMMARY OF

ISSUES - 1.

Degraded Voltage

Relaying Design

Calculations -

Page 6,

Exelon

Generation

Company,

LLC

In addition, Branch Technical Position (BTP) PSB-1

clause B. 1 .b.2 (Reference 4) included provisions

for operator manual actions to restore bus voltage

on the Class 1 E distribution system. The RIS

specifically excludes manual load shedding under

the Offsite/Onsite Design Interface Calculations

whereas the BTP allows for manual actions to

avoid separation from offsite power. Please clarify

if manual actions taken to restore voltages now

require prior NRC approval.

Disagree

All actions required to protect the Class 1E

equipment from degraded voltage must be

automatic in accordance with 10 CFR

50.55a(h)(2).

Manual actions are allowed as stated in

PSB-1, B.1.b.2 for improving the voltage in

response to the alarm in control room that

alerted the operator to the degraded

condition. However, to demonstrate the

adequacy of onsite/offsite interface design

and offsite power capacity and capability, as

specified in GL 79-36, manual load shedding

should not be assumed.

13

SUMMARY OF

ISSUES - 1.

Degraded Voltage

Relaying Design

Calculations -

Page 6,

Exelon

Generation

Company,

LLC

Under "DVR Setting Design Calculations," the RIS

states in part "...would allow calculation of

voltages at terminals or contacts of all safety

related equipment with the voltage at the DVR

monitored bus at the DVR dropout setting." It is not

clear what "contacts" are in this context. It

is assumed that the concern is motor control center

contactors and/or motor starting control circuits.

Agree

RIS will be revised to just state terminals

and not Contacts.

14

SUMMARY OF

ISSUES - 1.

Degraded Voltage

Relaying Design

Calculations -

Page 6,

Exelon

Generation

Company,

LLC

Under discussion of DVR setting calculations, the

RIS states that setting cannot cause any

degradation of the safety related components,

including actuation of their protective devices.

The BTP only stated damage to normally operating

safety related equipment. The RIS language

seems broader then BTP and appears to open up

the position that the DVR studies have to consider

starting of loads under non-accident conditions.

Disagree

The DVR ensures that voltage requirements

of the Class 1E loads are always preserved

for operating the equipment under accident

and non accident conditions including all

abnormal operational occurrences.

15

SUMMARY OF

ISSUES - 1.

Degraded Voltage

Relaying Design

Calculations -

Page 6,

Exelon

Generation

Company,

LLC

The DVR time delay seems to be considering

operation down to LVR setting for evaluations.

However, there is no discussion on LVR setting

considerations in any original requirements or the

RIS. Under Guidelines for Voltage Drop

Calculations, the summary states that the plant

voltage analysis, while supplied from the

transmission network, should be based on the

operating voltage range of the transmission

network connection. Grid operating voltage ranges

do not allow operation down to levels that would

cause sustained operation at LVR levels.

Therefore, consideration for operation at the LVR

setpoint would be inconsistent with this guidance.

The condition that occurred at Arkansas Nuclear

One (ANO) in 1978 would appear to be related to

inadequate operating procedures and a lack of a

rigorous analysis of the AC power distribution

system. It would not be credible for present day

operation. In addition, the operator would be

alerted by an alarm on degraded voltage conditions

(less than the analytical limit) as required by

Branch Technical Position PSB- B.l.b.1.

Disagree.

The point is that the DVR setting is based on

the voltage requirements of the equipment,

which should equate to voltages on the grid

well below normal. It is understood that grid

operating procedures should prevent

sustained voltages at such low levels but

regardless of what happens on the grid the

DVRs will preserve the voltage limits for the

equipment.

Plant operation at LVR setpoint is not

expected and is not within the scope of the

RIS.

16

(17 not

used)

SUMMARY OF

ISSUES - 1.

DVR Setting

Design

Calculations -

Page 6

Exelon

Generation

Company,

LLC

In Section "DVR Setting Design Calculation"

reference is made to 0.9 per unit voltage for

adequate operating voltage. This would only apply

for the most part to rotating equipment

(motors). Motor Control Center (MCC) contactors,

battery chargers, Motor Operated Valves

(MOVs) all have less than a 90% operating voltage

requirement. This distinction should be

made and/or clarified.

Agree.

0.9 per unit voltage was mentioned as an

example and was not meant to cover

everything. RIS will be revised to delete

references to specific numbers and

emphasize voltage requirements and voltage

requirements are plant-specific.

18

SUMMARY OF

ISSUES - 1.

Exelon

Generation

The Degraded Voltage Relaying Design

Calculations section should include a statement to

Agree.

9

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

DVR Setting

Design

Calculations -

Page 6

Company,

LLC

emphasize that only steady state loading and

steady state acceptable voltages at the class IE

equipment are to be considered in determining the

DVR drop out settings including the allowable

tolerances. The paragraph does mention 0.9 per

unit voltages at the terminals which is steady state

but a positive statement about steady state loading

and steady state acceptable voltages would be

helpful. Also, there are alternatives to the 90%

terminal voltage criterion. The concern is heating,

causing a temperature rise, which decreases useful

life of the insulation. Inspectors may read too much

into the 90% criterion; a motor loaded to less than

nameplate will draw less than service factor current

at a lower terminal voltage. Therefore, a lower

voltage would prove adequate as long as adequate

torque is available.

0.9 per unit voltage was mentioned as an

example and was not meant to cover

everything. RIS will be revised to delete

references to specific numbers and

emphasize voltage requirements and voltage

requirements are plant-specific.

The suggested analysis may be acceptable if

properly developed and supported in the

design. The 90% voltage criteria may not be

adequate for certain components such as

SOVs, motor control center contactors, etc.

19

SUMMARY OF

ISSUES - 1.

DVR Setting

Design

Calculations -

Page 6

Exelon

Generation

Company,

LLC

MOVs are not steady state loads. MOVs have

traditionally been considered transient loads and,

therefore, not included in the steady state voltage

analysis. GL 89-10 (Reference 3) programs

perform these calculations. A statement in this

section that MOVs loads are not to be considered

in this calculation will be helpful if NRC agrees with

this interpretation

Disagree.

MOVs should be addressed specifically and

the DVR settings must support adequate

voltages for all Class 1E equipment including

MOVs.

20

SUMMARY OF

ISSUES - 1.

DVR Setting

Design

Calculations -

Page 6

Exelon

Generation

Company,

LLC

The starting voltage requirement is unclear. Some

sites have evaluated the capability of starting each

required safety related motor individually at the

degraded voltage analytical limit. Other sites use a

"block start analysis" where multiple motors are

started simultaneously on the offsite source. There

have been violations associated with both

approaches. The RIS should describe an

acceptable methodology for determination of motor

starting voltage adequacy.

Disagree.

The intent of the RIS is not to prescribe DVR

relay setpoint methodology for every plant.

The RIS provides the conditions for which

plant specific analyses should be performed.

The specific design of the plant dictates the

type of analyses required to demonstrate

adequacy of DVR setting. If the plant design

requires load sequencing on the offsite

source, then individual motor start is the

appropriate methodology. If the plant design

requires block starting accident loads, then

the DVR setpoint should be based on

multiple motor starts.

21

SUMMARY OF

ISSUES - 1.

DVR Setting

Design

Calculations -

Page 6

Exelon

Generation

Company,

LLC

The RIS implies this portion of the calculations

require that the licensee demonstrate that all

class IE motors can be started with the voltages

just above the analytical limit of the DVR

setpoint. However, with voltage just above the DVR

drop out value, any load addition (starting or

running) will result in separating from the offsite

source if no credit for external voltage controlling

equipment is taken. Therefore, the purpose of this

requirement is not clear. The intent of the starting

voltage evaluation should be clarified.

Some stations have evaluated the performance of

protective devices during degraded grid conditions

by mechanisms other than calculations (e.g.,

technical evaluations or computations). It is

suggested that the NRC add a statement for

acceptability of the same.

Disagree

NRC staff disagrees with the interpretation.

The staff agrees that a grid voltage freeze

corresponding to the DVR setpoint and a

subsequent motor start will eventually

separate the plant from offsite source as the

voltage will not recover to reset the DVR.

The 1977 NRC letter states that voltage and

time setpoints shall be determined from an

analysis of the voltage requirements of the

safety related loads. Safety related (Class

1E) equipment, particularly large motors,

have starting and running voltage

requirements.

When grid voltages are degraded (such as

resulting in Class 1E bus voltages down

close to where DVRs are set based on Class

1E equipment requirements), and the grid

does not automatically recover, separation

from the grid is appropriate. The DVR is

expected to reset after a perturbation of

sustained duration when automatic actions

such as clearing the grid fault that resulted

in degraded voltage conditions.

The NRC staff will accept standard industry

practices to evaluate performance

10

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

capabilities of DVR. Analyses supported by

calculation should clearly and succinctly

define plant design basis and compliance

with regulation.

22

SUMMARY OF

ISSUES - 1.

DVR Setting

Design

Calculations -

Page 6

Exelon

Generation

Company,

LLC

Under Offsite/Onsite Design Interface Calculations,

Guidelines for voltage drop calculations item

2, i), the acceptance criteria for demonstrating

voltage adequacy would appear to be DVR

Maximum Pickup (the voltage required to assure

relay reset) and not component level voltage

values.

Agree.

RIS Section 2 (i) will be modified to state: For

each case evaluated, the calculated voltages

on each safety bus should demonstrate

adequate voltage at the safety bus and down

to the component level. It is based on Class

1E component terminal voltage

requirements.

23

SUMMARY OF

ISSUES - 2.

Offsite/Onsite

Design Interface

Calculations

Exelon

Generation

Company,

LLC

Item 2 (Offsite/Onsite Design Interface

calculations) appears to be additional requirements

for those sites licensed to the Standard Review

Plan (NUREG 0800) Chapter 8 Appendix A Branch

Technical Position PSB-1, "Adequacy of Station

Electric Distribution System Voltages."

Disagree

RIS highlights the guidelines provided in GL

79-36 and NUREG 0800, Chapter 8

Appendix A Branch

Technical Position PSB-1, "Adequacy of

Station Electric Distribution System

Voltages.". There are no new requirements

24

SUMMARY OF

ISSUES - 2.

Offsite/Onsite

Design Interface

Calculations

Exelon

Generation

Company,

LLC

Page 7- The phrase "...all operating configurations

of transmission network and plant

systems..." appears in a few sentences. The station

interface agreement with the transmission

provider integrates the considerations among the

transmission network, the operability of the

off site sources, and the voltage regulation (drop)

calculations. The calculations identify certain

controlling parameters for the transmission

network. These controlling parameters are then

incorporated into the Bases for the operability of

the offsite source(s). If the plant configuration

or transmission network parameters are not

bounded by the calculations, then the operability of

the offsite sources needs to be examined. In most

cases, the plant operator has no control over

the "configuration" of the transmission network, but

does have agreements with the transmission

system operator that normal operating voltages

and post unit trip contingency voltages are

controlled within established bounds. Add a few

sentences detailing that the intent of the

phrase "all operating conditions of the transmission

network" means that the controlling

parameters from the transmission network that are

used in the calculations are consistent with

those utilized in the Bases for operability of the

offsite sources.

Disagree.

This is addressed in RIS Section 2 a.

As discussed in GL2006-02 Grid Reliability

and Impact on Plant Risk and the Operability

of Offsite Power, licensees are required to

provide the transmission system operator

(TSO), the operating voltage parameters

required by the plant during all modes of

operation. The analyses discussed in this

comment should be the bases for the

information provided to the TSO.

The DVR protects the safety related

equipment when a perturbation in the grid

system results in degraded voltage

conditions and the normal operating

parameters cannot be restored immediately

to protect safety related equipment. The

DVR setpoint evaluation should be a

separate analysis.

25

SUMMARY OF

ISSUES - 2.

Offsite/Onsite

Design Interface

Calculations

Exelon

Generation

Company,

LLC

Page 7, item a) - Change the last sentence to read

"... include voltage drop due to all

transmission system contingencies that are a direct

result of the transient or accident being

analyzed (typically this will include tripping of the

nuclear power unit)."

Disagree.

A transient grid perturbation may be a result

in a plant trip. The DVR setpoint should be

based on bounding voltage resulting from a

transient grid condition. The actual reason

for the perturbation is not a consideration. A

plant trip may result in limiting conditions for

DVR setpoint calculation.

26

SUMMARY OF

ISSUES - 2.

Offsite/Onsite

Design Interface

Exelon

Generation

Company,

LLC

Page 7, item a) - Either add to a) or add another

section immediately after a). The transmission

system controlling parameters are assumed to

remain unchanged throughout the initial stages of

Agree.

RIS will be revised to state a): The unit trip

11

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

Calculations

the event with the exception of those effects

resulting from the event (contingency due to the

loss of the unit). For purposes of the calculation,

the Unit trip contingency can be coincident with the

accident, or at a later time consistent with the

assumptions in the plant accident sequence

analyses."

grid contingency voltage drop value should

be used in the accident cases in accordance

with the plant accident analyses since a unit

trip occurs with an accident.

27

SUMMARY OF

ISSUES - 2.

Offsite/Onsite

Design Interface

Calculations

Exelon

Generation

Company,

LLC

Page 7, item b) - Delete the tabulation of sources

of power to the emergency buses and replace with

a simple statement of "all credited sources of offsite

power to the emergency buses."

Disagree.

The recommendation does not change the

intent of the tabulation. To maintain

consistency with GL 79-36, it is preferable to

maintain the tabulation.

28

SUMMARY OF

ISSUES - 2.

Offsite/Onsite

Design Interface

Calculations

Exelon

Generation

Company,

LLC

Page 8, item c) - Change to read: "...(1) an

accident in the unit being analyzed and shutdown

of all other units at the station consistent with the

licensing basis of the station; ... in the unit

being analyzed (e.g., unit trip) and shutdown of all

other units at that station consistent with the

licensing basis of the station, whichever represents

the largest load situation." Typically, the

licensing basis for multi-units site allow for an

orderly shutdown of the unit not being analyzed,

and do not require a "simultaneous" shutdown.

Disagree.

The RIS is consistent with GL 79-36.

The licensing basis of multi-unit sites has to

be uniquely considered.

29

SUMMARY OF

ISSUES - 2.

Offsite/Onsite

Design Interface

Calculations

Exelon

Generation

Company,

LLC

It is recommended that the NRC provide a positive

statement for allowing the credit for voltage

controlling equipment external to the class IE

equipment for this calculation. Licensees perform

LOCA load sequencing under this section of the

calculations and take credit for LTCs (or other

voltage regulating devices) to demonstrate the

adequacy of the offsite sources. In addition,

please clarify if MOVs are to be modeled during

this scenario, even though it appears from the

RIS that MOVs and other equipment like contactors

are to be evaluated with voltages obtained from the

Degraded Voltage Relaying Design Calculations

with voltage just above the lowest set point of DGV

relays.

Disagree.

Use of LTCs is acceptable for regulating

voltage during normal plant operation. LTCs

do not afford protection during a transient

degraded voltage condition that can affect

operation of redundant equipment.

The following changes will be incorporated in

the RIS: Add the following in section 2

(general) and d.

All actions the electric power system is

designed to automatically initiate or control

should be assumed to occur as designed

(e.g., automatic bulk or sequential loading or

automatic transfers of bulk loads from one

transformer to another, automatic starts of

components, operation of automatic voltage

controlling equipment, etc.,)

Yes. All equipment including MOVs,

contactors, solenoids, etc., should be

evaluated for adequate voltage based on the

DVR set point.

30

SUMMARY OF

ISSUES - 2.

Offsite/Onsite

Design Interface

Calculations

Exelon

Generation

Company,

LLC

Under Item a), for units with LTCs, please clarify if

the analysis is to be performed with the grid

at minimum expected voltage, maximum expected

voltage, or at both.

Disagree

See Question 29.

Analyses for normal operation should

evaluate effect of LTC operation at the

extreme settings for impact on operating

equipment. DVR setpoint should be based

on minimum voltage required for operation of

accident mitigation loads. For units with

LTCs, it is unlikely that voltage correction

can be achieved within the short time it takes

for contactors to drop out or fuses to blow

during a sustained degraded voltage or

overvoltage condition.

31

General

Exelon

Generation

In general the clarifications contained in the draft

RIS appear to be more restrictive and

Disagree.

12

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

Company,

LLC

prescriptive than the cited historical regulatory

documentation, and do not support plant unique

design and current licensing bases that have been

developed and accepted in previous licensing

activities. Unique design and licensing bases that

have previously been accepted and

approved that may not be strictly aligned with the

clarifications in the draft RIS may include use

of an inverse time under voltage relay set between

the DVR and LVR relays (such as .875 to

0.70 PU for a maximum of 60 seconds). Some

sites may not provide coincident logic to

preclude spurious trips; rather, the logic may

include alternate design features to conform to the

intent of the requirements of BTP PSB-1.

Unique designs that may have been

previously accepted should have

appropriate justification with NRC approval of

the licensing documents. Typically, detailed

calculations have not been reviewed as part

of Technical Specification changes. The staff

has relied on licensee correspondence

stating adequacy of DVR setpoint to approve

license amendment requests. Onsite

inspections are used to verify analytical

methods used to meet regulations.

Alternate methods used to demonstrate

conformance may be acceptable provided

they meet the intent of BTP PSB-1 to protect

safety related equipment

32

General

Southern

Nuclear

Operating

Company

Include a definition of key terms (ex. Normal grid

operation, sustained degraded voltage)

Agree

Additional clarifications will be provided in

the RIS wherever appropriate.

33

General

Southern

Nuclear

Operating

Company

The RIS does not address completely the specific

requirements in the PSB-1 (ADAMS Accession No.

ML052350520), Arkansas Nuclear One (ADAMS

Accession No.ML0311801180), and Millstone

(ADAMS Accession No. ML093521388)

documents. In some cases specific positions in

the above documents were omitted from the RIS.

Proposed resolution: include missing positions

especially those related to determining minimum

expected offsite system voltages and testing.

Disagree

The RIS covered the key topics intended to

address inspection findings.

The reference documents should be

reviewed for more details.

The expected offsite system voltages can

vary between 0-110 percent. The objective of

the LVR and DVR is to afford protection and

separation from the grid when plant specific

needs cannot be satisfied.

34

General

Southern

Nuclear

Operating

Company

The RIS lacks adequate guidance to perform the

requested calculation(s) without additional

interpretations by the licensee and auditors as to

the intent of the provided guidance.

Proposed resolution: Provide a guideline with

examples on how to perform the calculation(s)

including expected assumptions, other

considerations, and criteria to be used for

acceptance.

Disagree

The RIS is consistent with GL 79-36. The

licensee is responsible for performing

calculations, in accordance with industry

engineering practices, with properly

supported inputs and assumptions that

demonstrate compliance in accordance with

10 CFR Part 50, Appendix B, Criterion III.

The RIS addresses certain problem areas

identified mainly through NRC inspections

and to re-emphasize the existing NRC

requirements and staff positionsguidance.

35

General

Southern

Nuclear

Operating

Company

The RIS provides some examples of plants that

have NRC reviewed and approved analyses and

goes on to point out that "backfit rule" was applied

because the staff believed the sites were not in

compliance with regulations even though they had

approved the analysis. How is a licensee who has

an NRC approved or acceptable analysis supposed

to know that their analysis is no longer acceptable?

The RIS needs more clarification with regard to

individual plant licensing bases if it is to be useful

to licensees.

Some plants have installed degraded grid alarm

systems and, at the staff request, included them in

Unit Operating Technical Specifications. Required

Disagree

The licensee must be in compliance with all

regulations pertaining to onsite and offsite

power systems. Unless, licensees are

exempted from meeting certain regulatory

requirements, changes to the design and

licensing bases are required to meet the

regulations in accordance with 10 CFR

50.109. The RIS identified some of the

recent inspection findings.

Operator actions could be used only to

13

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

operator actions related to degraded grid

conditions are specified in the bases and

procedures. The RIS does not discuss this

approach.

There are a number of plants that have URIs

related to this issue. Issuance of this RIS could be

used by inspectors to close the URIs to violations

without regard to plant specific licensing bases,

resulting in regulation by inspection.

supplement the automatic DVR scheme by

providing alarm in the control room when grid

voltage is below nominal operating range.

Operator actions cannot be substituted for

protecting the safety related equipment from

degraded voltage. 10 CFR 50.55a(h)(2)

requires all protective actions to be

automatic.

The intent of the RIS is to highlight the basis

for DVR requirements and preclude future

findings in plant designs. The RIS does not

provide new guidelines for issuing violations.

36

.

Summary of

Issues", pg. 6,

Item 1. "Degraded

Voltage Relaying

Design

Calculations",

Line 5.

Southern

Nuclear

Operating

Company

The RIS states "The Class 1 E buses should

separate from the offsite power system within a few

seconds if an accident occurs coincident with

sustained degraded voltage conditions."

GDC 17 describes the requirements for onsite and

offsite power systems. One of its requirements is

that they each provide sufficient capacity and

capability to mitigate postulated events. The events

are described in Chapter 15 "Accident Analysis".

These analyses assume Loss of Offsite Power

simultaneous with the event. They do not require

assuming degraded grid voltage condition prior to

an event occurring. In addition because of FERC

and NERC requirements for voltage control, the

likelihood of a chapter 15 accident occurring

concurrent with a serious degraded grid voltage

condition is not believed to be credible.

Proposed resolution: Remove or clarify this

statement since proper offsite system design and

operation renders such simultaneous postulated

events as incredible.

Disagree.

The RIS correctly states that if an accident

signal is received during sustained

degraded grid conditions, it may be prudent

to separate from the grid as :

1.

The duration of degraded

conditions on the grid is unknown

2.

It precludes other complications

such as double sequencing.

Chapter 15 Accident Analyses assumes

Loss of Offsite Power as a limiting case for

safe shutdown in view of the limited power

and resources available from the onsite

power sources. The preferred power source

for all operating modes and accident related

safe shutdown is the offsite source. The

DVR provides assurance that the plant

shutdown capability is not compromised

when the offsite source is degraded and a

fast transfer can occur to the onsite sources

if the offsite source does not recover within

the allotted time. This preserves the Chapter

15 accident analyses.

NERC and FERC requirements for voltage

control are beneficial to nuclear plant

operators as they provide assurance that

grid parameters will be maintained within

acceptable limits for normal nuclear plant

operations. However, the transmission

system is always vulnerable to perturbations

such as line outages, overload conditions,

generation shortages etc. which are beyond

the control of the grid operator. The

magnitude and duration of these

perturbations cannot be predicted. The

safety of the nuclear plant must not be

compromised during these conditions. The

function of the DVR is to protect redundant

safety related equipment during these grid

perturbations.

The staff considers degraded voltage

condition and coincident LOCA can occur.

Until the DVR relay takes automatic action,

the offsite power is considered to have

adequate capacity and capability. Therefore,

the accident analysis assumption for a LOCA

with offsite power available applies.

37

Summary of

Issues", pg. 6,

Item 1. "Degraded

Southern

Nuclear

Operating

The RIS states "During normal plant operation, the

Class 1 E safety related buses should

automatically separate from the power supply

Disagree.

14

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

Voltage Relaying

Design

Calculations",

Line 7

Company

within a short interval (typically less than 60

seconds) if sustained degraded voltage conditions

are detected.

During normal plant operation (i.e. non LOCA), the

degraded grid relay settings may be overly

conservative. Therefore automatic separation from

the preferred power supply may not be desired.

Proposed resolution: Transmission Operators

should be allowed time to correct the degraded

voltage condition while Plant Operators monitor the

safety bus voltages for adequate voltage.

See staffs response to Comment No. 9

Voltages down at the DVR level should be

well below the normal grid voltage levels.

Transmission operators will be taking actions

when voltages fall below the normal low level

(or post contingency low) well above the

DVR value (assuming the plant design is

proper given the grid operating voltage

range).

The plant electrical distribution system

design should be based on the grid voltage

range including the bounding worst case grid

contingency (strong or weak grid depending

on which one is bounding). In this way, the

plants design ensures adequate voltage to

plant equipment as long as grid is operating

as expected.

GDC 17 requires that offsite power has

sufficient capacity and capability to assure

that (1) specified acceptable fuel design

limits and design conditions of the reactor

coolant pressure boundary are not exceeded

as a result of anticipated operational

occurrences, and (2) the core is cooled and

containment integrity and other vital

functions are maintained in the event of

postulated accidents.

38

Summary of

Issues, Last

paragraph of

"DVR criteria for

time delay

selections.

Setting Design

Calculations", pg.

7

Southern

Nuclear

Operating

Company

The discussion on time delays does not provide

adequate criteria for time delay selections.

Proposed Resolution: Clarify.

The RIS states In this manner, the DVR ensures

adequate operational (starting and running) voltage

to all safety related equipment, independent of

voltage controlling equipment external to the plant

safety related electrical distribution system. For the

purposes of this calculation, no t credit should be

taken for voltage controlling equipment external to

the Class 1E distribution system such as automatic

load tap changers and capacitor banks.

Proposed Resolution: This statement needs to be

clarified to allow reasonable assumptions for the

status of equipment external to the Class 1E

distribution system. For example it is unclear how

to perform motor starting calculations without

taking credit for some Non 1E voltage controlling

equipment. Additionally, normal Transmission grid

switching to prepare for the next contingency to

maintain minimum expected transmission system

voltages should be allowed.

Disagree

The acceptable level of time delay is based

on plant specific accident analyses and

electrical systems designs.

Different time delays may be selected for

different plant designs. BTP PSB-1 suggests

two relays with different settings to

accommodate motor starts and sustained

degraded conditions. Typically, chapter 15

accident analyses assume 10 second time

delay for onsite power sources to energize

safety busses. DVR time delay of 10seconds

or less may be acceptable to demonstrate

that the assumptions in the accident

analyses remain valid.

External voltage regulating equipment (tap

changers) does not afford timely protection

for safety related equipment during sudden

grid perturbations and therefore cannot be

credited for DVR settings including transient

voltages during motor starts.

See staffs response to Comment Nos. 76

and 118.

39

Summary of

Issues, Guidelines

for voltage drop

calculations, item

(f) pg. 8

Southern

Nuclear

Operating

Company

After paragraph (f) the RIS leaves out the guidance

in GL 79-36 concerning minimum expected values

(item 6 of enclosure 2) was omitted from the RIS

guidance.

Proposed resolution: Add item 6 of enclosure 2 in

GL 79-36 to the RIS.

Disagree

Item 6 was addressed in item(a) in the RIS

40

General

NEI 3/2/11

NEI contends that RIS represents new positions

15

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

Letter

Disagree

The RIS provides clarifications to avoid the

misconception of the existing requirements

and NRC staff positionsguidance.

No new requirements are identified in the

RIS.

41

NEI 3/2/11

Letter

77 Letter and PSB-1 Not consistent. Degraded

voltage event and accident coincident vs.

subsequent. Also, starting and running voltage vs.

just running (term sustained in PSB-1)

Disagree

PSB just states how the scheme should

react to a subsequent degraded voltage.

The 77 letter indicates that the time delay

should support the accident analysis which

means coincident events.

42

NEI 3/2/11

Letter

77 Letter and 79 GL are generic communications

not requirements

Both communications provide guidance on

how to meet regulatory criteria. To that

extent, they are related to compliance with

regulations, but are not themselves

regulatory requirements.

43

NEI 3/2/11

Letter

Multi-unit sites, accident and simultaneous

shutdown vs. orderly shutdown and cooldown per

GDC 5

Disagree

This RIS is consistent with GDC 17, GL 79-

36, and IEEE Standard 308-1971, Class IE

Electrical Systems, Section 8, Multi-Unit

Station Considerations.

44

NEI 3/2/11

Letter

During normal plant operation, a degraded voltage

for 60 seconds resulting in separation doesnt give

the operator enough time (implied by PSB-1) to

take actions

Disagree

See NRC response to .Comment No. 9.

45

(46- 48

not

used)

Also

see

Nos.

86-96

for this

NEI

Letter

NEI 3/2/11

Letter

Offsite/Onsite design interface calculations doesnt

allow for manual actions

Disagree

This means that manual actions for the

purposes of analyses of the offsite power

system voltages should not be assumed.

See GL 79-36 for more details.

PSB-1 allows manual actions after first alarm

at higher voltage.

49

Page 6, DVR

Setting Design

Calculations

Jerry Nicely

Section DVR Setting Design Calculations states:

At the DVR dropout setting ...... the DVR ensures

adequate operational (starting and running) voltage

to all safety related equipment, independent of

voltage controlling equipment external to the plant

safety related electrical distribution system.

BTP PSB-1 states, "sustained", implying a steady

state voltage condition and not a transient voltage

condition that exists during a motor starting event.

The original 1977 NRC Letter, the later PSB-1, or

GL 79-36 does not require plants to demonstrate

the ability to start motors at the DVR settings.

Requiring the ability to start motors at the DVR

dropout setting does not accomplish anything or

make sense, since starting a motor at this voltage

will ensure a resultant voltage below the DVR

dropout; result in not being able to be reset the

relay, and as a result causing a spurious

disconnection from offsite power and transferring to

Disagree

See Responses to Questions 1 & 2.

Sustained in the context that the loss of

voltage relay was designed for momentary

dip in voltage or complete loss of voltage.

Steady state operation is expected at normal

operating band.

The 1977 NRC letter states that voltage and

time setpoints shall be determined from an

analysis of the voltage requirements of the

safety related loads. Safety related

equipment, particularly large motors, have

starting and running voltage requirements.

This second level of protection should

address these voltage requirements.

Sustained degraded voltage, as discussed in

the 1977 NRC letter, refers to grid voltage

below the expected low value given normal

grid operation and grid post contingency

16

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

the emergency diesel generator. Having a

requirement to be able to start motors at the DVR

dropout setting will result in the raising the DVR

settings to a higher value and is more likely to

result in spurious separation from the grid which is

in direct conflict with PSB-1.

(Single, N-1). Thus, when grid voltages are

degraded beyond the minimum voltage

assured by the grid operator(such as

resulting in SR bus voltages down close to

where DVRs are set based on SR equipment

requirements), separation from the grid is

appropriate. Proper design of the plant

electrical distribution system and setting of

the DVRs, based on the grid voltage range

(described above) should provide proper

margin such that spurious separation from

the grid should not occur.

The key point is that the voltage setting(s)

selected should ensure that adequate

voltage is available at the component

terminal(s) to operate the most limiting

component (s) at a plant during the most

limiting design basis event. The offsite/onsite

interface calculation should show that, with

the grid at the lower limit of the normal

operating range, voltage at the safety bus is

always well above the degraded voltage

setpoint for all design basis event loading

conditions (normal, abnormal and accident

conditions including anticipated operational

occurrence).

50

Page 5, Peach

Bottom

Jerry Nicely

In the RIS section of recent inspection findings for

Peach Bottom, it was stated that since the load tap

changers are not safety-related and are subject to

operational limitations and credible failures, they

cannot be relied on.

Agree

The finding is correct.

The safety related equipment should be

protected by Class1E relays and not

dependent on non safety LTCs functioning.

The DVR action is independent of LTC

action. Therefore, no credit should be taken

for determining the setpoint of DVR relay.

The response time of tap changers is

relatively slow. Redundant safety related

equipment may be exposed to degraded

voltage conditions that can last for minutes

depending on tap changer response time.

51

Page 8, c)

Jerry Nicely

In the Offsite/Onsite Design Interface Calc section

(C) it states: an accident in the unit being analyzed

and simultaneous shutdown of all other units at the

station.

RG 1.81 states: The Regulatory staff has

determined that, because of the low probability of a

major reactor accident, a suitable design basis for

multi-unit nuclear power plants is the assumption

that an accident occurs in only one of the units at a

time, with all remaining units proceeding to an

orderly shutdown and a maintained cooldown

condition; 10CFR50 App A Criterion 5 states: ... in

the event of an accident in one unit, an orderly

shutdown and cooldown of the remaining units;

NUREG 0800 Section 8.2 states: ..... in the event

of an accident in one unit, with a simultaneous

orderly shutdown and cooldown of the remaining

units. Based on the above Regulatory positions,

the RIS should consider rewording the

"simultaneous shutdown" to "orderly shutdown".

Disagree

For electrical system, the statement in the

RIS is consistent with GDC 17, GL 79-36,

and IEEE Standard 308-1971, Class IE

Electrical Systems, Section 8, Multi-Unit

Station Considerations.

52

Page 6, DVR

Setting Design

Calculations

Larry

Nicholson,

Nexterra

This paragraph could be interpreted to require the

LOCA sequence to be modeled at the DVR dropout

setting. LOCA sequencing modeled at the DVR

Disagree

17

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

dropout setting would result in separation of the

buses from the Preferred Power Source (off-site

power) as the voltage would not recover above the

DVR reset value.

Proposed Resolution: Clarify the intent to show

safety related equipment will function at the

selected DVR dropout setting voltage and that it is

not expected to start the LOCA sequence from this

voltage level.

Clarify that LOCA sequencing is evaluated using

minimum switchyard voltage as the starting point.

See response to questions 1&2

The sustained degraded voltage conditions

are not expected to last the total sequencing

process. The analyses should demonstrate

that the largest load (limiting case) for

accident mitigation can be successfully

started under degraded grid conditions and

the loads that are normally operating will not

be adversely impacted. It is expected that

the grid will either recover to nominal voltage

and reset the DVR for the rest of the

sequencing process or the DVR will separate

the plant from source that cannot support

safe shutdown.

53

Page 6, DVR

Setting Design

Calculations

Larry

Nicholson,

Nexterra

Having a sustained degraded voltage just above

the LVR voltage setling (70%) is not practical

without grid collapse and does not exist in Branch

Technical Position #1 (PSB-1).

Proposed Resolution: Clarify degraded voltages to

be analyzed to a credible level.

Agree

Although undervoltage protection (first level)

is not within the scope of the RIS, the

licensees analysis should ensure that the

LVR and DVR settings protect the Class 1E

components from voltage ranges between

the DVR and LVR settings due to sustained

degraded conditions.

54

Page 6, DVR

Setting Design

Calculations

Larry

Nicholson,

Nexterra

The statement that the DVR ensures adequate

operational (starting and running) is the first time in

NRC correspondence that starting equipment at

the DVR setpoint is expected. The example letter

sent to Peach Bottom in June 1977 did not require

starting of equipment at the DVR setpoint. This

requirement should be removed from the RIS since

it is not possible to start equipment at the DVR

setpoint and not subsequently separate from offsite

power. If the equipment starts at the DVR setpoint,

the voltage will dip during the transient and must

then recover above the reset point to avoid

separation from offsite power. Since the reset point

will always be above the DVR dropout point it will

be impossible to reset the relay.

Proposed Resolution: Remove starting equipment

at the DVR setpoint as a requirement.

Disagree

The NRC 1977 letter states that voltage and

time setpoints shall be determined from an

analysis of the voltage requirements of the

safety related loads. Safety related (Class

1E) equipment, particularly large motors,

have starting and running voltage

requirements. This second level of

undervoltage protection should address

these voltage requirements

55

Page 7, DVR

Setting Design

Calculations

Larry

Nicholson,

Nexterra

It is agreed that no credit is to be taken for voltage

controlling equipment external to the Class 1 E

distribution system for the establishing the

degraded voltage relay (DVR) settings; however, it

should be clarified that for credit may be taken for

minimum switchyard voltage/voltage drop

calculations (or the Offsite/Onsite Design Interface

Calculations).

Proposed Resolution: Clarify that credit must be

taken for automatic load tap changers and/or

capacitor for minimum switchyard voltage/voltage

drop calculations (or the Offsite/Onsite Design

Interface Calculations).

Agree

Grid Interface calculations can take credit for

voltage correction equipment. The DVR

setpoint should be set independent of

voltage correction equipment that cannot

operate in a timely manner to protect 1E

equipment. RIS will be clarified regarding

crediting voltage controlling equipment

external to the 1E system for Offsite/Onsite

Design Interface.

56

Page 8, c)

Larry

Nicholson,

Nexterra

NRC Generic Letter 79-36, Enclosure 2, Item 2

states that For multi-unit stations a separate

analysis should be performed for each unit

assuming (1) an accident in the unit being analyzed

and simultaneous shutdown of all other units at the

station; or (2) an anticipated transient in the unit

being analyzed (e.g., unit trip) and simultaneous

18

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

shutdown of all other units at that station,

whichever presents the largest load situation."

Comment:

NRC Draft RIS re-states NRC GL 79-36 verbatim,

with an attempt to clarify "anticipated transient" by

adding in parenthesis "(anticipated operational

occurrence)" immediately afterwards. It is not clear

what the added parenthetical statement is meant to

convey, other than unit trip (which already exists in

GL 79-36).

Proposed Resolution: It is recommended that this

either be removed, or stated "anticipated transient

per station licensing basis".

Disagree

Anticipated Operational Transient is a more

general term for operational events per the

design except for design basis accidents

This is consistent with the term used in GDC

17.

57.

Page 8, c)

Larry

Nicholson,

Nexterra

NRC should clarify "simultaneous shutdown" with

consideration to:

Most multi-unit station's Licensing Basis consider

an "orderly or controlled safe shutdown" of the

other unit(s) not being analyzed.

NERC Std TPL-004-0; particularly Category D

events per Table 1, where a "loss of all generating

units at a station" may result in "portions or all of

the interconnected systems may or may not

achieve a new, stable operating point'.

IEEE Std 308-1974, Clause 8, subclause 8.1.1

"Capacity describes this as a "concurrent safe

shutdown on the remaining units".

Proposed Resolution: The wording for the

proposed RIS, sub clause 2.c should be revised to

indicate orderly or controlled safe shutdown of the

remaining units, as per the stations licensing

basis instead of simultaneous shutdown.

Alternatively, the wording shutdown consistent

with the station licensing basis could be used

instead of simultaneous shutdown.

Disagree

This statement is consistent with GDC 17,

GL 79-36, and IEEE Standard 308-1971,

Class IE Electrical Systems, Section 8,

Multi-Unit Station Considerations.

58

Page 8, e) and f)

Larry

Nicholson,

Nexterra

These guidelines seem contradictory that you

cannot credit procedurally controlled operator

actions to reduce load but you have to assume the

actions will be carried out when load is added.

Proposed Resolution: Delete e) Manual load

shedding should not be assumed or add

allowance to credit procedurally controlled operator

actions to decrease load.

Disagree

Adding loads manually per procedure is

conservative in terms of maximum loading,

but not for load reductions. Plant design

should not depend on manual load shedding.

This is not conservative. That was the point

of item e).

But

not59

General

NEI 3/18/11

Letter / 1

The RIS should identify that plant compliance with

the regulation (GDC 17) is by each plant operating

within its Licensing Basis.

Agree

Second level undervoltage protection

(degraded voltage protection) applies to all

operating plants whether the plant is GDC or

pre-GDC plant.

60

General

NEI 3/18/11

Letter / 2

Definitions vary for the same words used with

respect to this topic.

The RIS should include definitions for key terms,

e.g. normal grid operation, sustained degraded

voltage, etc.

Agree

Clarifications will be provided in the RIS

wherever appropriate.

19

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

61

General

NEI 3/18/11

Letter / 3

There are various documents that address the

Adequacy of Station Electric Distribution System

Voltages. These documents have differences in the

methodology, terminology, and level of detail. Such

differences challenge the users of these guidance

documents when they conflict.

Attachment 2 to the NEI supplemental comment

letter provides a table that shows the differences

between GL 79-36, (BTP) PSB-1, IEEE 741, and

the draft RIS.

The RIS should identify the guidance document

differences, establish the NRC position on each

conflicting topic, and provide the basis for each

change in previously accepted guidance.

Disagree

The RIS provides adequate clarifications to

the existing guidance.

The staff positions described in the NRC

1977 letter is are guidance for all licensees

as to how to meet GDC 17 or applicable

plants principle design criteria. This letter

focuses on the need for a second level

undervoltage protection scheme to protect

the Class 1E electrical components from the

consequences of sustained degraded

voltage conditions.

GL 79-36 emphasizes the electrical design

attributes to be considered for the interface

of onsite and offsite distribution systems to

ensure adequate voltages to the Class 1E

buses and safety related components for

normal, abnormal, and accident conditions to

comply with GDC 17 or applicable plants

principle design criteria requirements.

BTP PSB-1 incorporates both the above

staff positions and guidance to meet GDC 17

requirements.

IEEE 741 is only referenced in the SRP. The

NRC has not endorsed this industry

guidance.

62

Page 1, 3rd

paragraph

NEI 3/18/11

Letter / 4

"The U.S. Nuclear Regulatory Commission (NRC)

is issuing this Regulatory Issue Summary (RIS) to

clarify the NRC staff's technical position on existing

regulatory requirements and voltage studies

necessary for Degraded Voltage Relay (second

level undervoltage protection) setting bases and

Transmission Network/Offsite/Onsite station

electric power system design bases."

No regulatory requirements are referenced except

for a generic reference to GDC 17.

Reword the paragraph to read:

'The U.S. Nuclear Regulatory Commission (NRC)

is issuing this Regulatory Issue Summary (RIS) to

clarify the NRC staff's technical position on

Degraded Voltage Relay (second level

undervoltage protection) setting bases and

Transmission Network/Offsite/Onsite station

electric power system design bases appropriate for

meeting the regulatory requirements specified in

GDC 17.'

Agree

The RIS will be revised to incorporate this

comment.

63

Page 2,

Paragraph a)

NEI 3/18/11

Letter / 5

"The selection of voltage and time delay setpoints

shall be determined from an analysis of the

operating voltage requirements of safety related

loads at all onsite system distribution levels"

Requirements for DVR settings have never used

the term "operating voltage". They instead used

"sustained voltage" which by definition would be

steady state voltage, running voltage, or voltage

held at a constant value

(BTP) PSB-1 and BTP 8-6 are silent on

operating/running voltage in the DVR settings

section; however, running is implied by using the

Disagree in part.

Voltage requirements - all voltage

requirements of SR equipment

The term operating voltage is being

removed from the RIS as recommended.

20

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

term "sustained" in the Time Delay settings section.

To be consistent with (BTP) PSB-1, NRC letter,

and BTP 8.6 remove the word "operating".

The term sustained voltage used in the 1977

letter and the BTPs is referring to the voltage

condition on the grid, not steady state

voltage

64

Page 3, Arkansas

Nuclear One

NEI 3/18/11

Letter / 6

"...assuming all onsite sources of AC power are not

available, the offsite power system and the onsite

distribution system is of sufficient capacity and

capability to automatically start as well as operate

all required safety related loads."

This sentence implies that the NRC use of the term

"operate" does not mean the same thing as 'start',

i.e., operate/start/running are not synonymous. NEI

supports this interpretation; however, it conflicts

with the words "proper voltage for starting and

running in all operational configurations" in the 1st

paragraph of page 6.

Agree

The term operating voltage is being removed

from RIS.

65

Page 6, 1st

Paragraph

NEI 3/18/11

Letter / 7

"...components are provided adequate voltage

based on the design of the Class 1E distribution

system in the plant and its most limiting operating

configuration."

There is a need to better define "most limiting

operating configuration", since experience shows

that a component is most limiting.

Reword the RIS to:

'...components are provided adequate voltage

based on the design of the Class 1E distribution

system in the plant.'

Agree.

RIS will be revised to state the following:

"... all safety related components are

provided adequate voltage based on the

design of the plant power distribution system

(and the offsite circuits), including the design

of the Class 1E distribution system in the

plant and its most limiting operating

configuration(s)."

Operating configurations affect limits as well

as components.

66

Page 6, 1st

paragraph

NEI 3/18/11

Letter / 8

"The Offsite/Onsite Design Interface Calculations

specify the voltage operating parameters of the

plant electrical distribution system based on the

transmission system (Offsite) operating

parameters."

This paragraph could be interpreted to require the

LOCA sequence to be modeled at the DVR dropout

setting. LOCA sequencing modeled at the DVR

dropout setting would result in separation of the

buses from the referred Power Source (off-site

power) as the voltage would not recover above the

DVR reset value.

The RIS should state that the intent is to show

safety related equipment will function at the

selected DVR dropout setting voltage and that it is

not expected to start the LOCA sequence from this

voltage level. The RIS should state that LOCA

sequencing is typically evaluated using minimum

switchyard voltage as starting point.

Disagree

This sentence is not referring to calculations

for setting the relays but referring to

Offsite/Onsite Design Interface Calculations.

67

Page 6, 1st

paragraph

NEI 3/18/11

Letter / 9

"This interface calculation establishes operating

voltage bands for all plant electrical buses, which

ensures that all plant components and systems

(Class IE and Non Safety Related) have proper

voltage for starting and running in all operational

configurations (expected operational and accident

conditions)."

This statement needs clarification in that not all

21

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

non-safety load voltages need to be evaluated.

The statement that the DVR ensures adequate

operational (starting and running) is the first time in

NRC correspondence that starting equipment at

the DVR setpoint is expected.

Having a sustained degraded voltage just above

the LVR voltage setting (70%) is not practical

without grid collapse and does not exist in Branch

Technical Position #1 ((BTP) PSB-1).

Typically, large motors (like reactor coolant pumps)

need to be evaluated for starting impact on the

safety bus. Once a motor is found to be small

enough to not impact safety bus operation, further

evaluation is unnecessary. The statement in the

RIS can easily be interpreted as requiring

evaluation of all non-safety loads down to the

lowest levels of distribution.

Technical compliance with determining the

degraded voltage relay setpoint would not be

achievable because the RIS requires the DVR

dropout setpoint to be based on the starting voltage

required for motors. Basing the DVR setpoint

(dropout setting) on starting voltage requirements

(rather than steady-state operating voltage)

appears to be a new NRC requirement/position. It

is technically flawed in that it would not actually

provide the required protection for the Class1lE

loads. It also appears to disagree with the intended

purpose of the existing regulations (1977 NRC

Letters on degraded voltage protection and (BTP)

PSB-1).

The letter sent to Peach Bottom in June 1977 did

not require starting of equipment at the DVR

setpoint. This new requirement should be removed

from the RIS, since it is not possible to start

equipment at the DVR setpoint and not

subsequently separate from offsite power. If the

equipment starts at the DVR setpoint, the voltage

will dip during the transient and must then recover

above the reset point to avoid separation from

offsite power. Since the reset point will always be

above the DVR dropout point, it will be impossible

to reset the relay.

Disagree

See response to questions 1&2 for

clarification.

The 1977 NRC letter refers to SR equipment

voltage requirements.

NSR items are being removed from this

sentence in the RIS. However, non safety

related loads should be modeled to the

extent that their operation can affect safety

bus/equipment voltage.

DVR setpoints are based on low voltages

that can occur due to sustained grid

perturbations and can potentially degrade

capability of onsite safety related equipment.

The NRC 1977 letter states that voltage and

time setpoints shall be determined from an

analysis of the voltage requirements of the

safety related loads. Safety related

equipment, particularly large motors, have

starting and running voltage requirements.

This second level of protection should

address these voltage requirements.

Sustained degraded voltage, as discussed in

the 1977 letter, refers to grid voltage below

the expected low value given normal grid

operation and grid post contingency (Single,

N-1). Thus, when grid voltages are degraded

(such as resulting in SR bus voltages down

close to where DVRs are set based on SR

equipment requirements), separation from

the grid is appropriate. The design of the

plant electrical distribution system and

setting of the DVRs, based on the grid

voltage range (described above) should

provide proper margin such that spurious

separation from the grid should not occur

due to sequencing or block loading of loads

during a design basis events.

Motor starts have been discussed in several

questions above. An accident signal

concurrent with degraded grid conditions will

require motor starts. All NRC

communications discuss the requirement for

safe shutdown of the plant following

postulated events.

68

Page 6, 2nd

paragraph

NEI 3/18/11

Letter / 10

"The staff considers degraded voltage conditions

coincident with a postulated design basis accident

to be a credible event. DVRs should be set to

protect the safety related equipment from sustained

degraded voltage conditions."

GDC 17 should be identified as the regulatory

requirement. This RIS is creating conditions in

excess of GDC 17.

The RIS concludes that the staff considers

degraded voltage conditions coincident with a

postulated design basis accident to be a credible

Disagree

The 1977 NRC letter staff positions guidance

(implementation second level undervoltage

protection scheme) apply applies to all

22

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

event; however, this is not consistent with GDC 17.

The RIS should identify that plant compliance with

the regulation (GDC 17) is by each plant operating

within its Licensing Basis that was developed from

available NRC and industry guidance.

Most licensees are committed to a version of IEEE

308, Standard Criteria for Class 1E Power Systems

for Nuclear Power Generating Stations. This

Standard defines the malfunctions, accidents,

environmental events, and operating modes (i.e.,

design basis events) that could physically damage

Class 1E power systems or lead to degradation of

system performance and for which provisions shall

be incorporated.

A degraded voltage condition coincident with a

postulated design basis accident is not among the

identified design basis events; however, the

Standard does include a requirement for the

protection from common mode failure.

operating plants and provides guidance on

how to meet regulatory criteria..

The 1977 NRC letter indicates that the DVR

scheme time delays should support accident

analysis assumptions which ties degraded

event with an accident.

69

Page 6, 2nd

paragraph

NEI 3/18/11

Letter / 11

"The Class 1E buses should separate from the

offsite power system within a few seconds if an

accident occurs coincident with a sustained

degraded voltage conditions."

GDC 17 describes the requirements for onsite and

offsite power systems. One of its requirements is

that they each provide sufficient capacity and

capability to mitigate postulated events. The events

are described in Chapter 15 "Accident Analysis".

These analyses assume Loss of offsite Power

simultaneous with the event. They do not require

assuming degraded grid voltage condition prior to

an event occurring. In addition, because of FERC

and NERC requirements for voltage control, the

likelihood of a chapter 15 accident occurring

concurrent with a serious degraded grid voltage

condition is so low that it is believed to be not

credible.

Remove or clarify this statement, since proper

offsite system design and operation renders such

simultaneous postulated events as incredible.

This position assumes (BTP) PSB-1 (BTP 8-6) is

part of the license and design basis for all

licensees. An equivalent position was not identified

in the NRC letters issued following the Millstone

event. Specifically, this requirement is more

stringent than the position stated on Page 2, Item

d) and may constitute a backfit to some licensees.

Care must be exercised with regards to the scope

of this position. It does not apply to Section 2,

"Offsite/Onsite Design Interface Calculations" of the

RIS. This is confirmed in the draft RIS on Page 8,

Paragraph d) which states all electric system action

occur "as designed". It would be beneficial to clarify

the scope limitations associated with this or any

revised position.

Disagree

The NRC 1977 letter indicates that the DVR

scheme time delays should support accident

analysis assumptions which ties degraded

event with an accident.

See NRC response to Comment No. 36

Section 2 is not about DVR schemes and

separation during a degraded voltage

condition. It is about operation of the plant

during normal, abnormal and accident

conditions and assuming the normal

operation of the grid (including the bounding

N-1 contingency and the trip of the unit for

the accident cases).

70

Page 6, 2nd

paragraph

NEI 3/18/11

Letter / 12

... Position (BTP) PSB-1 (revised later to become

BTP-6), is to protect Class 1E safety related buses

23

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

and components from sustained degraded voltage

conditions on the offsite power system coincident

with an accident as well as during non-accident

conditions."

A definition of the word protect is needed. It is not

clear what is being protected: the components

(MOV, motor, etc.) or the class 1E function or

something else.

The word "coincident" should read "subsequent to"

or "followed by", per (BTP) PSB-1 and BTP 8-6.

Disagree

Protect means guard or defend safety

related components against the

consequence of sustained degraded voltage

conditions.

Coincident is appropriate based on the 1977

NRC letter verbiage. The BTPs just provide a

design which would also deal with an event

when a SIAS signal would occur subsequent

to the degraded voltage condition as well

(not conflicting)

71

Page 6, 2nd

paragraph

NEI 3/18/11

Letter / 13

"The Class 1E buses should separate from the

offsite power system within a few seconds if an

accident occurs coincident with a sustained

degraded voltage condition."

Per (BTP) PSB-1, the text should read:

'The Class 1E buses should separate from the

offsite power system immediately if an accident

occurs subsequent to a sustained degraded

voltage condition.'

Agree.

RIS will be revised to incorporate the

comment.

72

Page 6, 2nd

paragraph

NEI 3/18/11

Letter / 14

... Class 1E safety related buses should

automatically separate from the power supply

within a short interval (typically less than 60

seconds)..."

There is no basis for "typically less than 60

seconds". In the original context of the time delay

section, it was sufficient time for an operator to

intervene" which is much greater than 60 seconds.

Remove the parenthesis section of the sentence.

With this guidance during normal plant operation,

the degraded grid relay settings may be overly

conservative; automatic separation from the

preferred power supply may occur under conditions

where this action is inappropriate.

The RIS should allow Transmission Operators time

to correct the degraded voltage condition while

Plant Operators monitor the safety bus voltages for

adequate voltage.

Agree

RIS will be revised to delete the parenthesis

section of the sentence as suggested.

Disagree

10 CFR 50.55a(h(2)) requires all protective

actions to be automatic. Operator

intervention is probably not possible when

voltage gets down to the DVR setpoint (grid

voltage is well below normal).

Operator action takes minutes. Operation at

degraded voltage conditions can degrade

equipment performance capabilities within

seconds.

73

Page 6, 3rd

paragraph

NEI 3/18/11

Letter / 15

DVR Setting Design Calculations

This section would be a good place to describe this

type of analysis as having a "bottom-up" approach.

Such calculations would prevent confusion of

crediting anything above the DVR voltage sensors'

values.

In the context of DVR Setting Design Calculations,

using a steady state or sustained voltage analysis

Disagree

The approach is already described in this

paragraph.

24

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

is the only way that can result in a voltage 'setting'

requirement.

The term sustained voltage used in the NRC

1977 letter and the BTPs is referring to the

voltage condition on the grid, not steady

state voltage

74

Page 6, 3rd

paragraph

NEI 3/18/11

Letter / 16

"... DVR ensures adequate operational (starting

and running) voltage..."

The "operational voltage" cannot define both

starting and running voltages.

The only place "operational voltage" is referenced

in the associated documents is in the tap setting

section of (BTP) PSB-1 and BTP 8-6 when a plant

is connected to the offsite power supply. The only

qualifying term used in the protection of the

equipment is 'sustained' which is synonymous with

steady state or running.

Reword the RIS to:

'... DVR ensures adequate sustained voltage...'

Agree

RIS will be revised to state DVR ensures

adequate voltage (start and run

conditions)

Disagree

The term sustained voltage used in the NRC

1977 letter and the BTPs is referring to the

voltage condition on the grid, not steady

state voltage

75

Page 6, 3rd

paragraph

NEI 3/18/11

Letter / 17

"Licensee voltage calculations should provide the

basis for their DVR settings, ensuring safety related

equipment is supplied with adequate operating

voltage (typically a minimum of 0.9 per unit voltage

at the terminals of the safety related equipment per

equipment manufacturers requirements), based on

bounding conditions for the most limiting safety

related load (in terms of voltage) in the plant."

Equipment manufacturers do not provide the same

voltage requirement to perform both running and

starting a motor. The 0.9 per unit in this context

refers to the typical running voltage requirement of

a motor; whereas, 0.85 per unit is typical for a

starting voltage requirement.

The RIS should identify that voltages other than

90% voltage are common based on detailed plant

analysis.

For example, motors below 90% voltage continue

to have plenty of margin in torque but may

encroach on long time thermal limits. Unless a

motor is fully into its service factor (typicallyl.15)

and below 90% voltage, operation will be

acceptable.

Agreed

This sentence is being reworded

Starting requirements for motors have been

observed over a range of 0.75 to 0.85. It

depends on the particular plant and how the

motors were procured. Either way, the

voltage requirements must be preserved

(starting and running). However, there could

be other components that are more sensitive

to voltage for operation.

0.9 per unit voltage was mentioned as an

example and was not meant to cover

everything. RIS will be revised to delete

references to specific numbers and

emphasize voltage requirements and voltage

requirements are plant-specific.

The design basis of the plant should

determine the adequacy of voltage. The RIS

clarifies the regulation.

25

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

76

Page 6, 3rd

paragraph

NEI 3/18/11

Letter / 18

"In this manner, the DVR ensures adequate

operational (starting and running) voltage to all

safety related equipment, independent of voltage

controlling equipment external to the plant safety

related electrical distribution system."

The draft RIS suggests the DVR dropout setpoint

to be based on the starting voltage required for

motors.

Basing the DVR dropout setpoint on starting

voltage requirements rather than steady-state

operating voltage appears to be a new NRC

requirement/position. It also appears to disagree

with the intended purpose of the existing

requirements and guidance (1977 NRC Letters on

degraded voltage protection and (BTP) PSB-1).

As suggested, the approach incorrectly implies that

the load(s) should start from the lowest DVR

dropout setting. A specific example for illustration is

as follows: If the initial voltage value is at the lowest

possible value above dropout actuation, starting a

load will cause the DVR dropout. Since the new

steady state voltage will be lower than the initial

value because of the added loads, the DVR reset

will never occur.

Many utilities use the ABB 27N with harmonic filter

which has a minimum 0.5% reset. Thus, with a

setting of 93.6% +/- 0.9%, the dropout value could

be as low as 92.7%. For motors causing more than

0.5% voltage dip at initial start, even if the voltage

at the beginning of the event was 93.2% and a load

was started, the DVR will dropout and never reset.

This will lead to a grid separation.

Reword the RIS to remove "(starting and running)"

Disagree

The NRC 1977 letter states that voltage and

time setpoints shall be determined from an

analysis of the voltage requirements of the

safety related loads. Safety related (Class

1E) equipment, particularly large motors,

have starting and running voltage

requirements. This second level of

undervoltage protection should address

these voltage requirements. Sustained

degraded voltage, as discussed in the NRC

1977 letter as well, refers to grid voltage

below the expected low value given normal

grid operation. Thus, when grid voltages are

degraded (such as resulting in Class 1E bus

voltages down close to where DVRs are set

based on Class 1E equipment

requirements), and the grid does not

automatically recover, separation from the

grid is appropriate. Proper design of the plant

electrical distribution system and setting of

the DVRs, based on the grid voltage range

(described above) should provide proper

margin such that spurious separation from

the grid should not occur due to sequencing

or block loading of loads during a design

basis event.

Also, see response to questions 1 & 2.

77

Page 6, 3rd

paragraph

NEI 3/18/11

Letter / 19

"For the purposes of this calculation, no credit

should be taken for voltage controlling equipment

external to the Class 1E distribution system such

as automatic load tap changers and capacitor

banks."

The intent of the position appears to ensure that

the DVR setpoint(s) protect against the potential

loss of ESF equipment, regardless of the

component mode of operation. It does not imply

that the Class 1E bus must remain connected to

offsite power after starting a large motor with an

initial bus voltage corresponding to the DVR

setpoint and no voltage regulation capability.

Actually, the calculation should be performed with

the DVR monitored bus voltage at the TS limit, not

the DVR setpoint. All that is required is that under

motor starting conditions, separation from offsite

power occurs before starting loads trip on overload.

The intent could be conveyed in more detail.

The RIS should allow reasonable assumptions for

the status of equipment external to the Class 1E

distribution system. For example it is unclear how

to perform motor starting calculations without

taking credit for some Non 1E voltage controlling

equipment. Additionally, normal transmission grid

switching should be allowed to prepare for the next

Disagree

This sentence is being re-worded

The point being made is that calculations for

the DVR voltage settings should have cases

at voltages just above the DVR voltage

settings (well below what would be based on

normal grid operations and voltage

controlling equipment if applicable) to

demonstrate that the settings enforce the SR

equipment voltage requirements.

This is covered in Offsite/Onsite Design

Section calculations (not DVR calculations

section)

The offsite source is the preferred source of

power for plant shutdown. The DVR should

not separate the plant from the grid for motor

starts. In the event that grid conditions

degrade beyond an acceptable point and an

accident signal is actuated, BTP PSB-1

recommends separation from the grid.

26

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

grid event, so that minimum expected transmission

system voltages are maintained.

Credit for voltage controlling equipment in

the Offsite/Onsite Design Section

calculations is appropriate if corrective action

can be taken in a timely manner to preclude

safety related equipment malfunctions.

78

Page 7, 1st

paragraph

NEI 3/18/11

Letter / 20

"Voltage-time settings for DVR's should be selected

so as to avoid spurious separation of the safety

buses from the offsite power system during unit

startup, normal operation and shutdown."

This position is new and contrary to the NRC

historical position stated on Page 2, Item (c)(3).

Either the DVR protection scheme favors ESF-

equipment-protection or connectivity-to-offsite-

power. Otherwise, this position would result in a

mutually exclusive requirement. The prevention of

spurious separation is addressed by coincident

logic channels (Page 2, Item (b)), not the setpoint.

If no credit is to be taken for voltage controlling

equipment external to the Class 1E distribution

system for the establishing the degraded voltage

relay (DVR) settings, then the RIS should state that

credit may be taken for minimum switchyard

voltage/voltage drop calculations (Offsite/Onsite

Design Interface Calculations).

Disagree

This sentence is being re-worded

DVR setting always enforce SR equipment

voltage requirements. Offsite/Onsite Design

should ensure that there is proper margin

between where voltage is in the plant during

normal grid operation as compared to

voltages in the plant when the DVRs actuate.

Credit for voltage controlling equipment in

the Offsite/Onsite Design Section

calculations is appropriate. However, it is not

appropriate to use it for DVR calculations

since DVR setpoint is derived from the

minimum voltage required at the component

terminal at all voltage levels. (Also see

response to question #77)

79

Page 7, 1st

paragraph

NEI 3/18/11

Letter / 21

"These DVRs should disconnect the Class 1E

buses from any power source other than the

emergency diesel generators (onsite sources) if the

degraded voltage condition exists for a time interval

that could prevent the Class 1E safety related

loads from achieving their safety function."

This position ensures ESF functionality, should an

undervoltage condition persist.

(BTP) PSB-1 was written before the application of

voltage regulating devices within the nuclear power

plant offsite power circuit boundary. The RIS

should clarify that if the calculations necessary to

support RIS positions in Section 1, "Degraded

Voltage Relaying Design Calculations" and Section

2, "Offsite/Onsite Design Interface Calculations"

demonstrate completion of ESF functions within

accident analysis assumptions, then immediate

separation per (BTP) PSB-1, Section B(1)(b)(i), is

no longer the preferred NRC position.

(BTP) PSB-1 (BTP 8-6) states:

"The subsequent occurrence of a safety injection

actuation signal (SIAS) [after an undervoltage

condition longer than a motor starting transient]

should immediately separate the Class 1E

distribution system from the offsite power system."

The RIS should state that this (BTP) PSB-1

position is not included in the draft RIS because it

provides no added protection in terms of

establishing the DVR setpoint(s) or in establishing

operability of the offsite power interface. To the

contrary, this (BTP) PSB-1 increases the

probability of separation from offsite power.

Disagree

The BTP PSB-1 offers an option to set a

higher voltage alarm level to support

corrective action to restore voltage to normal

operating band.

Since offsite power is the preferred source of

power to mitigate design basis event, it is

important that the Offsite/Onsite Design

Interface calculations ensure the capacity

and capability of the offsite power is

adequate to sequence or block load during

design basis events without actuating DVRs

with sufficient margin available at the safety

buses. Separation of the safety buses from

the grid is only appropriate when the DVR

relays actuate indicating that SR equipment

voltage requirements are not being met (not

able to protect or provide adequate voltage

to the terminals of the SR limiting

components at the plant).

Analyses to determine such setpoints always

should have included modeling the plant

power distribution system such that proper

voltages throughout the plant system can be

calculated in all operating and accident

27

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

conditions.

80

Page 7,

paragraph 2 a)

NEI 3/18/11

Letter / 22

"Guidelines for voltage drop calculations

a)

The plant voltage analysis, while

supplied from the transmission

network, should be based on the

operating voltage range of the

transmission network connection."

It is recommended that the first sentence of

Paragraph 2(a) be deleted. It is covered by

Paragraph 2(b), as the switchyard is the "power

source" for the offsite power circuits.

Paragraph 2(a) addresses both plant and

transmission operator analyses. The purpose is to

identify that the switchyard voltage results from the

transmission operator analysis should be used as

an input to the power plant analysis. From the

nuclear power plant point of view, the

determination as to whether each offsite power

circuit is individually capable of performing its

design function is based on a postulated post-trip

switchyard voltage for the present grid

configuration and operating level (i.e. RIS

Paragraph 2(b)).

As written, it is conceivable that a reader of this

paragraph could conclude that the transmission

"contingency analysis" is a factor in the nuclear

plant analysis regarding "when" the contingency is

postulated to occur relative to the postulated plant

event. The alteration of the present basis to include

concurrent grid/plant events is a change in position

and would be subject to backfit consideration.

Disagree

Enclosure 2 of GL 79-36 provides guidelines

for voltage drop calculations.

Accident cases consider the unit trip grid

contingency since a trip is assumed to occur

coincident with an accident. However, if the

unit trip is not the most limiting grid

contingency (not the largest grid voltage

drop), the cases which assess normal and

abnormal operation (non-accident) need to

assume the bounding grid contingency

(normal grid operating range)

81

Page 8,

paragraph 2 c)

NEI 3/18/11

Letter / 23

"For multi-unit stations, a separate analysis should

be performed for each unit assuming (1) an

accident in the unit being analyzed and

simultaneous shutdown of all other units at the

station; or (2) an anticipated transient (anticipated

operational occurrence) in the unit being analyzed

(e.g., unit trip) and simultaneous shutdown of all

other units at that station, whichever presents the

largest load situation.

The RIS wording should be revised to indicate

"orderly or controlled safe shutdown of the

remaining units, as per the station's licensing basis"

instead of "simultaneous shutdown". Alternatively,

the wording 'shutdown consistent with the station

licensing basis" could be used instead of

"simultaneous shutdown'.

Most multi-unit stations Licensing Basis consider

an "orderly or controlled safe shutdown" of the

other unit(s) not being analyzed.

NERC Std TPL-004-0; particularly Category D

events per Table 1, where a "loss of all generating

units at a station" may result in "portions or all of

the interconnected systems may or may not

achieve a new, stable operating point".

IEEE Std 308-1974, Clause 8, sub-clause 8.1.1

"Capacity" describes this as a "concurrent safe

shutdown on the remaining units".

Disagree

Wording is the same as provided in GL 79-

36

This statement is consistent with GDC 17,

GL 79-36, and IEEE Standard 308-1971,

Class IE Electrical Systems, Section 8,

Multi-Unit Station Considerations.

28

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

This RIS re-states part of GL 79-36, with an

attempt to clarify "anticipated transient" by adding

in parenthesis "(anticipated operational

occurrence)". It is not clear what the added

parenthetical statement is meant to convey, other

than unit trip (which already exists in GL 79-36).

The RIS should remove this parenthetical addition

or state '...an anticipated transient per station

licensing basis...'

82

Page 8,

paragraph 2 d)

NEI 3/18/11

Letter / 24

"All actions the electric power system is designed

to automatically initiate should be assumed to

occur as designed..."

This statement is consistent with GDC 17 in that

the presumption is the onsite AC sources are lost.

The postulation of concurrent malfunctions in both

the onsite and offsite sources is not required.

The RIS should retain this sentence, since it may

not have been consistently applied during recent

CDBI's.

Agree.

No change to this sentence.

83

Page 8,

paragraph 2 e) &

f)

NEI 3/18/11

Letter / 25

"e) Manual load shedding should not be assumed.

f) For each event analyzed, the maximum load

necessitated by the event and the mode of

operation of the unit at the time of the event should

be assumed in addition to all loads caused by

expected automatic actions and manual actions

permitted by administrative procedures."

These guidelines seem contradictory in that e)

states that there may be no credit for procedurally

controlled operator actions to reduce load but f)

states that the manual action loads must be

considered in the maximum load.

The RIS should delete "e) Manual load shedding

should not be assumed" or add allowance to credit

procedurally controlled operator actions to

decrease load.

Disagree

This guidance is consistent GL 79-36.

Adding loads manually per procedure is

conservative in terms of maximum loading,

but not for load reductions. Plant design for

maximum load should not depend on manual

load shedding (not conservative). That was

the point of item e).

84

Page 8,

paragraph 2 f)

NEI 3/18/11

Letter / 26

Omission

After paragraph 2 f), the RIS leaves out the

guidance in GL 79-36 concerning minimum

expected values (item 6 of enclosure 2).

Add item 6 of enclosure 2 in GL 79-36 to the RIS:

"6. The voltage at the terminals of each safety load

should be calculated based on the above listed

consideration and assumptions and based on the

assumption that the grid voltage is at the "minimum

expected value". The "minimum expected value"

should be selected based on the least of the

following:

a.

The minimum steady-state voltage

experience at the connection to the

offsite circuit.

b.

The minimum voltage expected at the

connection to the offsite circuit due to

contingency plans which may result in

reduced voltage from this grid.

c.

The minimum predicted voltage from grid

stability analysis. (e.g., load flow

Disagree

It was not omitted. This is covered in item a)

29

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

studies)."

85

Page 8,

paragraph 2 j)

NEI 3/18/11

Letter / 27

"To provide assurance that actions taken to assure

adequate voltage levels for safety related loads do

not result in excessive voltages, assuming the

maximum expected value of voltage at the

connection to the offsite circuit, a determination

should be made of the maximum voltage expected

at the terminals of all safety related actual

equipment and their starting circuits (if applicable).

If this voltage exceeds the maximum voltage rating

of any safety related equipment, immediate

remedial action should be taken."

The RIS should remove the word "immediate"

describing remedial action. Immediate remedial

action could imply control room intervention. The

control room has alarm procedures to address high

voltage should it occur. Timeliness of remedial

actions depends on how high actual voltage

reaches and is addressed by procedures.

Analyses of high grid voltage with light plant load

are standard and provide insights as to what the

grid voltage upper limit should be or what

compensating activities might be required for light

load operations (refueling).

The RIS should provide examples of typical

responses to high grid voltages. For example: in

those cases where unit trip can result in a step

increase in grid voltage (most common on higher

voltage connections like 765kv), anticipated

excursions above desired voltages should be

addressed by compensating measures (changing

excitation for nearby units, switching in reactor

banks, etc.).

Disagree

The Offsite/Onsite design should address all

grid operating conditions to prevent

overvoltages from occurring.

The point here is that if a design problem is

identified such as overvoltage conditions,

immediate actions should be taken

(compensatory and/or permanent design

changes) to address the design problem

rather than taking actions after it occurs.

It is not the intent of the RIS to highlight

reasons for voltage perturbations.

86

General

NEI 3/2/11

Letter

Page 2, Paragraph 1

While NEI supports efforts to obtain greater clarity

with respect to the staff's technical position in this

important area, the draft RIS greatly oversimplifies

the regulatory and licensing aspects of the

degraded grid voltage protection issue. As a result

of this oversimplification, the draft RIS

inappropriately combines several generic

communications and guidance documents that

affected the licensing bases of individual plants in

different ways, and fails to adequately address the

significant backfitting concerns that arise when

attempting to eliminate licensing basis variability

via a RIS (or any other guidance document).

Disagree

NRC Staffs position is that the RIS is

intended to clarify the requirements and

associated existing staff positions guidance

which would apply to all plants.

Any inspection findings that questions the

plant-specific licensing bases will be

reviewed by the NRR staff in accordance

NRCs TIA process.

87

General

NEI 3/2/11

Letter

Page 2, Paragraph 2

Unless it is revised, the draft RIS will unnecessarily

increase the potential for loss of the preferred off-

site power source and, consequently, increase

reliance on emergency diesel generators. NEI

believes that the use of emergency diesel

generators more frequently than necessary is

inconsistent with GDC 17 and results in an

unnecessary loss of defense-in-depth.

Disagree

Proper design of the plant electrical

distribution system, given the operating

range of the grid and the proper selection of

DVR settings (based on the voltage

requirements of the 1E equipment), should

provide more than adequate operating

margin, preventing unnecessary separation

from offsite power.

88

General

NEI 3/2/11

Letter

Page 2, Paragraph 3, Comment I

The Draft RIS Fails to Adequately Consider

Licensing Basis Variability in the Area of

Degraded Grid Voltage Protection

The only generic obligation or legally binding

Agree in part.

As a general matter, NRC staff positions are

guidance, as are, among other things,

30

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

requirement mentioned in the Discussion section of

the draft RIS is GDC 17.

regulatory guides and Interim Staff Guidance

(ISG). As guidance, NRC staff positions, like

regulatory guides, are not legally binding

unless the NRC legally imposes them on a

licensee or the licensee binds itself to

complying with them in a document subject

to NRC-mandated controls. In other words,

for any particular nuclear power plant,

guidance may be part of the licensing basis

for that plant because of past NRC or

licensee actions. For instance, guidance

may be legally imposed upon a plant by

virtue of the issuance of an order or through

a license condition that imposes the

guidance on that particular plant. As another

example, a licensee may have committed to

compliance with the guidance in the plants

final safety analysis report (FSAR) or other

document subject to NRC controls (e.g., the

description of the plants quality assurance

program, an emergency plant, or a security

plan). The NRC resolutions for all the public

comments received on this RIS should be

understood in light of this explanation.

.

89

General

NEI 3/2/11

Letter

Page 3, Paragraph 2, Comment I (Cont.)

The Draft RIS Fails to Adequately Consider

Licensing Basis Variability in the Area of

Degraded Grid Voltage Protection

Although these letters resulted in changes to the

licensing bases of the nuclear power plants that

received them, they do not function the same way

as generally applicable regulatory requirements.

That is, these generic communications were only

received by plants that were licensed at the time

the communications were issued. Operating

licenses for the current fleet were issued during a

period that ranged from the late 1960s through the

1990s. Thus, not all operating plants received and

responded to the generic communications issued in

1977 and 1979.

Disagree.

The 77 Letter is a staff position which applies

to all operating reactors at that time and

plants licensed since, on how to comply with

the requirements in 10 CFR Part 50, General

Design Criteria 17 (GDC 17).The 1977 letter,

as well as other staff guidance, were made

available or sent to all operating plants at

that time. In addition, the NRCs regulatory

practice-which has been understood by the

industry-is that staff guidance represents the

staff position until subsequently modified or

withdrawn. While the staff recognizes that

there is variability among plants licensing

bases with respect to degraded voltage

protection, the NRC believes (with one

exception identified elsewhwere) that the

overall licensing basis provisions with

respect to degraded voltage protection are

consistent with the staffs position.

90

General

NEI 3/2/11

Letter

Page 3, Paragraph 2, Comment I (Cont.)

The Draft RIS Fails to Adequately Consider

Licensing Basis Variability in the Area of

Degraded Grid Voltage Protection

Further, the Branch Technical Position (BTP)

described in the draft RIS BTP PSB-1, Rev. 0,

"Adequacy of Station Electric Distribution System

Voltages"--was issued in 1981. BTP PSB-1 and the

Standard Review Plan in which it is included were

"prepared for the guidance of the Office of Nuclear

Reactor Regulation staff responsible for the review

of applications to construct and operate nuclear

power plants.... Standard review plans are not

substitutes for regulatory guides or the

Commission's regulations and compliance with

them is not required." Thus, BTP PSB-1 would

have been directly relevant to plants licensed after

its issuance, but not before. Further, the specific

details in the information provided in the 1977

letters, Generic Letter 79-36, and BTP PSB-I are

not identical.

Disagree.

The 1977 Letter is a staff positionguidance

which applies to all operating reactors at that

time and plants licensed since, on how to

comply with the requirements in 10 CFR

Part 50, General Design Criteria 17 (GDC

17).

31

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

91

General

NEI 3/2/11

Letter

Page 3, Paragraph 3, Comment I (Cont.)

The Draft RIS Fails to Adequately Consider

Licensing Basis Variability in the Area of

Degraded Grid Voltage Protection

For example, the draft RIS makes several

recommendations that may be inconsistent with the

approved licensing bases for operating plants,

including:

The draft RIS proposes "Degraded

voltage conditions coincident with a

postulated design basis accident." BTP

PSB-1 says "subsequent occurrence."

Disagree.

NRC Staff asserts that coincident degraded

grid and accident is specified in the 77 Letter

and the BTP approach supports that

position.

See also staff response to Comment No. 36.

92

General

NEI 3/2/11

Letter

Page 4, First Bullet, Comment I (Cont.)

The Draft RIS Fails to Adequately Consider

Licensing Basis Variability in the Area of

Degraded Grid Voltage Protection

The draft RIS proposes "DVR Dropout setting

based on starting and running voltage." BTP PSB-1

says "sustained," implying a steady state voltage

condition and not a transient voltage condition that

exists during a motor starting event.

Disagree.

The staff position is consistent with 1977

letter and BTP PSB-1.

93

General

NEI 3/2/11

Letter

Page 4, Second Bullet, Comment I (Cont.)

The Draft RIS Fails to Adequately Consider

Licensing Basis Variability in the Area of

Degraded Grid Voltage Protection

The draft RIS proposes "separate analysis should

be performed for each unit assuming (1) an

accident in the unit being analyzed and

simultaneous shutdown of all other units at the

station."

GDC 5 says:

"... in the event of an accident in one unit, an

orderly shutdown and cooldown of the remaining

units."

Disagree

This statement is consistent with GDC 17,

GL 79-36, and IEEE Standard 308-1971,

Class IE Electrical Systems, Section 8,

Multi-Unit Station Considerations.

94

General

NEI 3/2/11

Letter

Page 4, Third Bullet, Comment I (Cont.)

The Draft RIS Fails to Adequately Consider

Licensing Basis Variability in the Area of

Degraded Grid Voltage Protection

The draft RIS proposes "During normal plant

operation, the Class 1E safety related buses

should automatically separate from the power

supply within a short interval (typically less than 60

seconds) if sustained degraded voltage conditions

are detected." BTP PSB-1 clause B.1.b.2 included

provisions for operator manual actions to restore

bus voltage on the Class 1 E distribution system.

BTP PSB-1 B.1.b.2 says:

"The second time delay should be of a limited

duration such that the permanently connected

Class 1E loads will not be damaged. Following this

delay, if the operator has failed to restore adequate

voltages, the Class 1E distribution system should

be automatically separated from the offsite power

system. Bases and justification must be provided in

support of the actual delay chosen."

The draft RIS specifically excludes manual load

shedding under the Offsite/Onsite Design Interface

Calculations whereas the BTP PSB-1 allows for

manual actions to avoid separation from offsite

power.

The sixty second time delay would not allow

operator actions. This appears to be a new NRC

position.

Disagree

See staffs response to Comment No. 37.

Manual actions for the purposes of reducing

load for the design of the plant electrical

distribution system should not be assumed.

This is not precluding load shedding as part

of normal operation when there is sufficient

time to do so to support adequate voltage.

See GL 79-36 for more details.

32

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

95

General

NEI 3/2/11

Letter

Page 5, Paragraph 2, Comment I (Cont.)

The Draft RIS Fails to Adequately Consider

Licensing Basis Variability in the Area of

Degraded Grid Voltage Protection

In addition to the specific examples provided

above, the draft RIS states "[t]he staff considers

degraded voltage conditions coincident with a

postulated design basis accident to be a credible

event." It is unclear what exactly the staff intended

with this statement.

Disagree

.

The 77 Letter indicates that the DVR circuits

should be designed assuming coincident

sustained degraded grid voltage and

accident events. Upon the onset of the

coincident accident and degraded grid event,

the time delay for the DVR circuit should

allow for separation of the 1E buses from the

offsite circuit(s) and connection to the 1E

onsite supplies in time to support safety

system functions to mitigate the accident in

accordance with the FSAR accident

analyses.

96

General

NEI 3/2/11

Letter

Page 6-7, Comment II

The Backfit Discussion Provided in the Draft

RIS is Inadequate

Given the complex regulatory and licensing history

associated with providing degraded grid voltage

protection, the backfitting discussion included in the

draft RIS is inadequate. Despite the fact that

facility-specific backfits were required as a result of

several recent inspection findings on degraded

voltage protection,1 8 the entire backfitting

discussion included in the draft RIS consists of

three sentences. Of those three sentences, only

one provides any analysis:

Specifically, NRC Staff technical

positions outlined in this draft RIS are

consistent with the aforementioned

regulations [GDC 17] and generic

communications [1977 letter, Generic

Letter 79-36, BTP PSB-1], while

providing more detailed discussion

concerning the necessary voltage

calculations supporting DVR settings

based only on voltage requirements of

Class 1E components and the Class 1E

distribution system design.19

This analysis misses the point. First, GDC 17 (like

most GDC) is cast in broad, general terms;

therefore, the fact that the specific positions

discussed in the draft RIS are "consistent with" the

design criteria does not necessarily mean that they

escape the definition of a backfit. Specifically, there

are any number of staff positions that are

"consistent with" a broad design principle, but the

relevant inquiry when examining the backfit

definition is whether the staff position being

articulated is new or different from a previously

applicable staff position. The draft RIS does not

address this issue. Further, as discussed above,

the generic communications and guidance

discussed in the draft RIS are not completely

consistent with one another and were not equally

relevant in developing the licensing bases for all

reactor licensees. Given the variability in the

protection schemes approved by the NRC, merely

concluding that the positions provided in the draft

RIS are "consistent with" one or more of these

documents, does not address the obvious fact that

"providing more detailed discussion" on how to

demonstrate compliance with GDC 17 could

Disagree

The details of the inspection findings and

enforcement actions are discussed in detail

in the applicable inspection reports and TIAs,

if applicable referenced in the RIS.

NRC staff asserts that the regulations and

staff positions articulated in the RIS are

consistent with the regulations and existing

guidance documents and therefore do not

constitute new or different positions with

respect to the backfit rule (50.109).

See the supplemental response attached at

the end of this Comment/Response Table.

33

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

constitute a staff position that is new or different

from a previously approved protection scheme.

97

General

PPL

Page 1-2, First Bullet

Contrary to the stated intent, PPL believes that the

RIS does transmit new requirements and staff

positions. Specific comments applicable to

Susquehanna Steam Electric Station (SSES) are

as follows:

The RIS introduces the need to consider

both "starting and running" conditions

during all operating configurations while

maintaining the offsite power supply

connected to the plant electrical

distribution system. The establishment of

a degraded voltage relay (DVR) to detect

a "sustained" degraded voltage condition

challenges the relay's basis for

"protection" if its actuation (dropout)

setpoint must accommodate both starting

and running voltage conditions. The term

"sustained degraded voltage" implies a

steady state degraded voltage condition,

and excludes starting voltage

consideration

Disagree

The NRC 1977 letter states that voltage and

time setpoints shall be determined from an

analysis of the voltage requirements of the

safety related loads. Safety related

equipment, particularly large motors, have

starting and running voltage requirements.

This second level of protection should

address these voltage requirements.

Sustained degraded voltage, as discussed in

the 1977 letter, refers to grid voltage below

the expected low value given normal grid

operation and grid post contingency. Thus,

when grid voltages are degraded (such as

resulting in SR bus voltages down close to

where DVRs are set based on SR equipment

requirements), separation from the grid is

appropriate. The design of the plant electrical

distribution system and setting of the DVRs,

based on the grid voltage range (described

above) should provide proper margin such

that spurious separation from the grid should

not occur due to sequencing or block loading

of loads during a design basis events.

98

Page 6, Section 1

PPL

Page 2, Paragraph 2

RIS 201 1-XX, Page 6, Section 1. "Degraded

Voltage Relaying Design Calculations" contains the

statement "staff considers degraded voltage

condition coincident with a postulated design basis

accident to be a credible event." This statement

implies a requirement to demonstrate capability of

connected loads to start and run at the degraded

voltage relay dropout setting. For Susquehanna,

sequencing of loads from the offsite power source

cannot be demonstrated at the relay dropout

setpoint because operation at this voltage level

would result in separation from the offsite

transmission system. Furthermore, the statement

on page 6 of the RIS is not in agreement with other

regulatory position documents such as GSI 171,

"Engineered Safety Features Failure (ESF) from a

Loss of Offsite Power (LOOP) subsequent to a

Loss of Coolant Accident (LOCA)," which

concluded a degraded voltage condition coincident

with a postulated design basis accident is not a

credible event.

Disagree

NRC Staff asserts that this statement means

that while the events are coincident (which is

important from the standpoint that the time

delay chosen for the DVR must support the

accident analysis), it does not mean that

connected loads must start and run at the

dropout setting. The dropout setting should

be developed based on the voltage

requirements (starting and running) and

therefore to develop values which are

bounding, the studies should be done under

worst starting and loading conditions, which

means the required voltage at the 1E bus

prior to the start or run case would have to

be higher than the setpoint. The main point is

that the setpoint should equate to the limiting

voltage at the limiting component during the

bounding starting or running scenario to

protect the 1E equipment.

99

Page 6, Section 1

PPL

Page 2, Paragraph 3

Additional clarification is necessary if starting

transients must be included when determining the

degraded voltage relay (DVR) dropout setpoint.

This condition will increase the probability of

separating from the offsite transmission system

and increase the likelihood of a double sequencing

event, which is a potential nuclear safety concern.

Disagree.

Proper design of the plant electrical

distribution system, given the operating

range of the grid and the proper selection of

DVR settings (based on the voltage

requirements of the 1E equipment), should

provide more than adequate operating

margin, preventing unnecessary separation

from offsite power.

100

Page 8, Section c)

PPL

Page 2, Paragraph 3

The RIS requires performance of analyses for an

accident in the unit being analyzed and

simultaneous shutdown of all other units at the

station. This is not consistent with the present

Susquehanna design and licensing basis, which is

an accident on one unit followed by the safe

shutdown of the second (non-accident) unit. The

safe shutdown of the non-accident unit is

Disagree.

This statement in the RIS is consistent with

GDC 17, GL 79-36, and IEEE Standard

308-1971, Class IE Electrical Systems,

Section 8, Multi-Unit Station Considerations.

34

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

considered a controlled shutdown, which follows

automatic operation of the safety related loads on

the accident unit. This accident response is also

consistent with the NERC requirements for the

design of the transmission system. The RIS should

be revised to be in agreement with the current

NERC requirements.

101

General

PPL

Page 2-3, First Bullet

The draft RIS attempts to clarify the requirements

for setting the DVRs based on the criteria

established in the following three main documents:

1) NRC letters to licensees dated June 2 & 3, 1977,

2) Branch Technical Position (BTP), PSB-1

Revision 0,

3) Generic Letter 79-36, "Adequacy of Station

Electric Distribution Systems Voltages"

The guidance listed in the draft RIS is not

consistent with all the requirements listed in these

three documents and a new interpretation is

provided in some cases.

It should be generally recognized that a nuclear

plant operating license may not have been issued

based on the above documents. For example, the

1977 letters discussed above are not applicable to

SSES.

Disagree.

The 1977 Letter is a staff positionguidance

which applies to all operating reactors at that

time and plants licensed since, on how to

comply with the requirements in 10 CFR

Part 50, General Design Criteria 17 (GDC

17). In addition, NRCs staff position is that

while the BTPs go into some more detail,

they are consistent with the 77 Letter.

102

General

PPL

Page 3, First Bullet

The lack of regulatory clarity in the RIS could result

in revising the degraded voltage setpoint for a

plant's DVR thus increasing the possibility of

premature separation from the offsite circuit (i.e.,

undervoltage relay actuation). This relay operation

could lead to an increase in the likelihood of a

double sequencing event, which has the potential

to create a nuclear safety concern.

Disagree.

Proper design of the plant electrical

distribution system, given the operating

range of the grid and the proper selection of

DVR settings (based on the voltage

requirements of the 1E equipment), should

provide more than adequate operating

margin, preventing unnecessary separation

from offsite power.

103

General

PPL

Page 3, Second Bullet

The RIS introduces the need for two sets of

calculations, one to establish the DVR relay

setpoint and one for the interface with the offsite

transmission system. The RIS should not specify

the number of calculations that are necessary for a

plant to meet a regulatory requirement.

Disagree.

The RIS is primarily identifying that different

types of calculations are necessary to

address different requirements. DVR setting

calculations consider the voltage of the 1E

equipment while the plant design is more

about the operating range of the grid and the

resulting voltages in the plant system (which

should be well above the DVR voltages)

104

General

PPL

Page 3, Third Bullet

The condition the DVR is required to "protect"

needs to be specifically defined along with the

applicable relay setting, (i.e., relay minimum

dropout, maximum dropout, or reset). If the DVR is

installed to provide a level of protection then the

analysis must demonstrate that the safety related

equipment is capable of performing its required

safety function. An example of this would be the

case where the DVR analysis would need to

demonstrate acceptable operation at both the

starting and running equipment ratings when at the

DVR dropout setting.

Disagree.

The DVRs function is specified in that it

ensures that 1E equipment is supplied with

adequate voltage in accordance with its

design requirements.

105

General

PPL

Page 3, Fourth Bullet

A clarification of the term "sustained" is needed to

determine if "sustained" refers to a steady state

voltage condition (i.e., no equipment starting

voltage effects) for which the DVR setting is to be

established.

Disagree.

Sustained degraded voltage, as discussed in

the NRC 1977 letter as well, refers to grid

voltage below the expected low value given

35

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

normal grid operation.

106

General

PPL

Page 3, Fifth Bullet

The guidance in the RIS is too general when

referring to operating voltages. The specific voltage

requirements need to be specified instead of

implied by a general term. The RIS needs to clarify

that the impact of the nuclear unit trip on the

transmission system voltage must be considered in

the plants voltage analysis.

Disagree.

The term voltage requirements used in the

RIS is defined in terms of equipment

manufacturer design requirements. NRC

Staff feels that this terminology is sufficiently

specific. Additional wording has been added

to the RIS to clarify that unit trip voltage

impact should be factored into the accident

analysis cases.

107

General

PPL

Page 3, Sixth Bullet

The time delays suggested are not consistent with

PSB-l. The PSB established one time delay to

allow for operator action. The RIS does not

address this requirement.

Disagree.

While there may be differences, the BTPs

are guidance documents and represent an

approach but not necessarily the only

approach. In addition, following the guidance

documents approach will satisfy the GDC 17

requirements.

108

General

PPL

Page 4, First Bullet

The RIS also lacks any acknowledgement of

preventative measures the licensees have taken to

minimize the potential for a degraded voltage

condition. Advancements in plant Ioadflow

analyses and measures to increase the reliability of

the offsite transmission system are industry

improvements that have occurred since the

degraded voltage events that occurred 35 years

ago.

Disagree.

Regardless of improvements made in terms

of grid operation and understanding of grid

operations impact on plant voltages, the

plant design has always had to properly

address grid operating parameters and their

impact on plant voltages in all modes of

operation. This point was properly

emphasized in the RIS as was in the original

regulations and guidance.

109

General

APS

Page 2, 1.

The draft RIS asserts that there is a simple and

singular set of design criteria that have been

applied universally to the industry. Over the years

the degraded voltage performance requirements

have changed, as a specific issue, and on a

component basis (e.g., motor operated valves and

contactors), for individual nuclear power plants. As

a result, each nuclear power plant has specific

licensing bases, and there is no singular set of

requirements that have been applied universally to

the industry.

Disagree.

The 77 Letter provides staff positions on the

design criteria in that the voltage

requirements for the 1E equipment has to be

ensured by the DVR circuits by automatic

separation from offsite and transfer to the

onsite sources.

110

General

APS

Page 2, 2.

The draft RIS asserts that the guidance provided to

the industry to address the Millstone and other

degraded voltage events adequately addresses

this potential common mode failure. The common

mode failure potential is that multiple trains of

safety equipment could be simultaneously

negatively impacted if off-site power is degraded.

The deterministic guidance provided does not

appear to effectively address integrated plant

response nor preclude a Millstone type event. The

use of degraded voltage relays to address this

potential failure mode is not consistent with

operating experience and lacks adequate technical

basis as described in the detailed technical

comments that follow.

Disagree.

The DVR circuits will automatically separate

the 1E circuits from offsite power when

voltage requirements are not met which will

prevent the Millstone type event

automatically.

111

Page 6

APS

Page 2, 3.

The draft RIS (page 6 of 10) states:

"The staff considers degraded voltage conditions

coincident with a postulated design basis accident

to be a credible event."

Disagree

The point being made in the RIS is that

setting of the DVR should include

consideration of a coincident accident signal

in that the time delay chosen for the DVR

36

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

It is our understanding that the established staff

interpretation is that this is not a credible event, as

discussed and supported by analysis in NUREG-

0933, Supplement 33, dated August 2010,

Resolution of Generic Safety Issues, Issue 171,

ESF Failure from LOOP Subsequent to a LOCA,

and Brookhaven National Laboratory NUREG/CR-

6538 (BNL-NUREG-52528), Evaluation of LOCA

With Delayed Loop and Loop With Delayed LOCA

Accident Scenarios, Technical Findings Related to

GSI-1 71, 'ESF Failure from LOOP Subsequent to

LOCA' published July 1997. This appears to be a

new staff interpretation and no documented

analysis is provided to support it. Therefore, if the

scenario is credible, as the draft RIS asserts, then

GSI-171 is not adequately resolved and should be

reevaluated.

should support the accident analysis

assumptions consistent with the NRC1977

letter.

112

General

APS

Page 5, 4.

The recent licensing actions in the industry which

have mandated setpoint changes for the degraded

voltage relays (DVRs) and loss of voltage relays

(such as the one cited in the draft RIS for Fermi-2)

only serve to increase the probability of the 'ESF

Failure from LOOP Subsequent to a LOCA' event

discussed in NUREG/CR-6538 without providing

an advantage for any credible scenario. As such,

these changes may increase core damage

frequency (CDF).

It is APS's understanding that a comprehensive

review of guidance related to degraded grid voltage

has not been performed using the cost-benefit and

risk criteria of 10 CFR 50.109 (backfit rule), nor is it

apparent that risk insights have been used to

inform this guidance.

Disagree

Setting the DVRs in accordance with the

voltage requirements of the 1E equipment

coupled with a properly designed plant

electrical distribution system (and based on

the grids allowable voltage range) must

provide adequate voltage margin to preclude

offsite separation.

Disagree

NRC staff asserts that the regulations and

positions guidance articulated in the RIS are

consistent with the existing regulatory

requirements and NRC staff positions

guidance therefore do not constitute new or

different positions with respect to the backfit

rule (50.109).

113

General

APS

Page 5, 5.

The draft RIS does not address the implication of

the Branch Technical Position (BTP) PSB-1

requirement that "The Class 1 E bus load shedding

scheme should automatically prevent shedding-

during sequencing of the emergency loads to the

bus." A large variety of voltage conditions could

exist during the sequencing period while the

shedding is blocked, and no analytical methods are

discussed that could demonstrate that equipment

damage or malfunction would not occur.

Disagree.

The design of the plant electrical distribution

system and the onsite sources should

provide for adequate voltage to all 1E

equipment in all normal, abnormal and

accident conditions.

Typical designs do not block the DVR or the

LOV relay when sequencing loads on the

offsite source. Hence load shedding in the

event of a loss of offsite power should be

part of the design basis. A large variation of

voltage conditions can occur during various

operating modes of a nuclear plant. The

DVR setpoint should be based on limiting

conditions. If the recommendations of BTP

PSB-1 are followed, the probability of events

such as double sequencing is minimized.

114

Page 7

APS

Page 5-7, 6.

In light of the summary of the resolution of GSI-

171, the draft RIS statement (page 7 of 10) that

"the time-delays(s) chosen for DVRs during

accident conditions should meet the accident

analysis assumptions..." does not seem

appropriate. The degraded voltage condition could

occur at various times during the initial energization

of the accident mitigation equipment, and the relay

time delay value only affects the additional time

Disagree.

Degraded voltage conditions can be

postulated to occur at anytime. The DVR

setpoint should accommodate the limiting

case for equipment protection. If the

recommendations of BTP PSB-1 are

followed, then a separation from the

degraded grid coupled with accident signal is

37

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

until the subsequent LOOP occurs.

the preferred approach to resolve the issue

and satisfy accident analyses.

115

Page 8

APS

Page 7-8, 7.

It is not feasible for multi-unit nuclear plants to

successfully demonstrate that voltage from the

offsite circuits would be adequate, as described in

the draft RIS (page 8 of 10), for:

"(1) an accident in the unit being analyzed and

simultaneous shutdown of all other units at the

station; or (2) an anticipated transient (anticipated

operation occurrence) in the unit being analyzed

(e.g., unit trip) and simultaneous shutdown of all

other units at that station."

North American Electric Reliability Corporation

(NERC) Standard TPL-004 recognizes that the

design and operating constraints of the

transmission network are such that the loss of all

generating units at a station could result in portions

or all of the interconnected system not achieving a

new, stable operating point.

It is beyond the nuclear plant operators authority or

capability to ensure otherwise.

Disagree

This wording in the RIS is the same as was

used in GL 79-36.

TPL-004 requires transmission planning to

address simultaneous multiple transmission

contingencies.

The requirements of TPL-004 are not within

the scope of RIS.

116

Page 6

APS

Page 8, 8.

The draft RIS (page 6 of 10) contains the following

statement:

"The Class I E buses should separate

from the offsite power system within a

few seconds if an accident occurs

coincident with sustained degraded

voltage conditions."

This statement appears to reflect the position of

Revision 3 of BTP 8-6, which states, in part:

"The first time delay should be long

enough to establish the existence of a

sustained degraded voltage condition

(i.e., something longer than a motor-

starting transient). Following this delay,

an alarm in the control room should alert

the operator to the degraded condition.

The subsequent occurrence of a safety

injection actuation signal (SIAS) should

immediately separate the Class 1 E

distribution system from the offsite power

system. In addition, the degraded voltage

relay logic should appropriately function

during the occurrence of an SIAS

followed by a degraded voltage

condition."

This is not currently a design or licensing

requirement for all existing plants. As such the RIS

process would not be the appropriate method to

communicate a new regulatory position.

Disagree.

As a result of these Millstone events, the

NRC requested that all licensees implement

degraded protection as described in the

1977 Letter to ensure automatic protection of

safety buses and loads. This Letter provides

staff positionguidance, which applies to all

operating reactors at that time and plants

licensed since, on how to comply with the

requirements in 10 CFR Part 50, General

Design Criteria 17 (GDC 17).

38

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

117

Page 6

APS

Page 8-9, 9.

The draft RIS (page 6 of 10) contains the following

statement:

"The time delay chosen should be optimized to

ensure that permanently connected Class 1 E

loads are not damaged under sustained degraded

voltage conditions (such as sustained degraded

voltage just above the LVR voltage setting for the

duration of the DVR time delay setting)."

This deterministic approach, while appearing

conservative, has the net effect of increasing the

frequency of delayed LOOP events during

transients, even when the subsequent sustained

voltage condition is not degraded (see Comment

4), with resulting adverse effects as discussed in

the resolution of GSI-171. It also neglects

consideration of the voltage levels that must be

maintained in the event of a unit trip and coincident

accident to prevent delayed LOOP events. Finally,

the draft RIS is silent on the particulars of the

voltage studies that would be acceptable to use to

determine the optimum time delay (such as the

plant operating conditions and voltage profile).

Disagree

The voltage studies done for evaluating

offsite power/onsite power interface should

use minimum expected voltage at the

plant/grid interface node, demonstrating

adequate voltage for starting and running of

plant components during normal, abnormal

and accident conditions. The voltage studies

for the DVR setpoints should require

plant/grid interface node voltages well below

the minimum expected values (including post

grid contingency).

118

Page 6

APS

Page 9, 10.

The DVR Setting Design Calculations section

(page 6 of 10) indicates that:

"models would allow calculation of voltages at

terminals or contacts of all safety related

equipment with the voltage of the DVR monitored

bus at the DVR dropout setting, providing the

necessary design basis for the DVR voltage

settings. In this manner, the DVR ensures

adequate operational (starting and running) voltage

to all safety related equipment, independent of

voltage controlling equipment external to the plant

safety related electrical distribution system."

This seems to impose a new requirement. Further,

the described model is of a nondegraded voltage

scenario that does not result in DVR actuation.

Therefore, it does not demonstrate that "required

safety related components are provided adequate

voltage" for accidents with degraded voltage

scenarios. That conclusion could only be

demonstrated by modeling degraded voltage

scenarios that involve DVR actuation. However, in

all cases involving degraded voltage coincident

with postulated accidents, such models would

result in delayed LOOP scenarios as discussed in

GSI-171.

Also, it reflects a non-conservative voltage profile.

If the voltage at the DVR monitored bus was at the

DVR dropout setting prior to starting a motor, it

would be lower than that during and after starting

the motor, and the voltage at the motor terminals

would be correspondingly lower, as well, compared

to the results using the constant bus voltage

methodology described in the draft RIS.

Disagree

The DVR dropout setting should be

developed based on the voltage

requirements (starting and running) and

therefore to develop values which are

bounding, the studies should be done under

worst starting and loading conditions which

means the required voltage at the 1E bus

prior to the start or run case would have to

be higher than the setpoint. The main point is

that the setpoint should equate to the limiting

voltage at the limiting component during the

bounding starting or running scenario to

protect the 1E equipment.

The RIS does not impose any new

requirements. It provides clarification on

existing requirements.

The DVR setpoint should be optimized for

motor starting transient and protection of

safety related equipment.

119

Page 5

APS

Page 10, 11.

The draft RIS discussion asserts that the NRC

Office of Nuclear Reactor Regulation (NRR) Task

Disagree

39

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

Interface Agreement (TIA) response (TIA 2010-05)

"concluded ... the time delay to transfer from a

degraded offsite source to the standby power

source to support the emergency core cooling

equipment operation must be consistent with

accident analysis time assumptions, as required by

BTP PSB-1 (NUREG 0800)." This statement is not

included in the TIA response. The TIA response

(pages 4 and 5) quotes the Palo Verde UFSAR

description for the design requirements of the

degraded voltage relays, and this specific time

delay provision is not included in the PVNGS

UFSAR.

This specific time delay provision was removed as

part of the PVNGS license amendment 123

process and was specifically addressed in the NRC

and APS correspondence (NRC Letter dated June

14, 1999, and APS letter dated July 16, 1999,

Question 13). The subject matter of the TIA did not

include the time delay element of the design, with

regard to the accident analysis time assumptions,

but rather was focused upon whether license

amendment 123 bounded the need to perform

design basis electrical calculations for the

degraded voltage relay low setpoint value of 3697

volts or below.

The point being made in the RIS is that

setting of the DVR should include

consideration of a coincident degraded grid

and accident in that the time delay chosen

for the DVR should support the accident

analysis assumptions consistent with the

NRC1977 letter.

Task Interface Agreement 2010-005

(ADAMS Accession No. ML102800340)

provides more details regarding Palo Verde

degraded voltage inspection finding.

Plant specific findings are not in the scope of

the RIS.

120

Page 5

APS

Page 10-11, 12.

The draft RIS asserts that PVNGS erroneously

maintains that a degraded voltage condition

concurrent with a design basis accident is not

credible. PVNGS had originally implemented the

design approach included in the NRC letter

Qualification Review of the PVNGS Units 1,2 and

3, dated December 12, 1977. Based on operating

experience (LER 50-528/529/530-93-011)-and site

specific license amendment 123, PVNGS took

action to preclude such an event, by implementing

new TS LCO 3.8.1, Condition G. This approach

was consistent with the resolution of GS1-171,

alternative 3, and was approved.

The prevention strategy was implemented to

preclude a concurrent degraded voltage condition

and design basis accident because the PSB-1 type

design is not capable of adequately coping with

such an event. All such events would result in

delayed LOOP/double sequencing scenarios, as

described in GSI-171, for which there is no viable

analytical approach.

Disagree.

The point being made in the RIS is that

setting of the DVR should include

consideration of a coincident degraded grid

and accident in that the time delay chosen

for the DVR should support the accident

analysis assumptions consistent with the

NRC1977 letter.

The licensee should ensure that SI actuation

at a point just above the DVR set point

should not cause double sequencing.

See staff response to Task Interface

Agreement 2010-005 (ADAMS Accession

No. ML102800340) for more details

regarding Palo Verde degraded voltage

inspection finding.

121

Page 5

APS

Page 11, 13.

PVNGS originally implemented the second level

degraded voltage protection design consistent with

NRC letter Qualification Review of the PVNGS

Disagree

40

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

Units 1, 2 and 3, dated December 12, 1977. As a

result, reference to PSB-1 in the draft RIS for

PVNGS does not reflect the historic licensing basis

for PVNGS.

The licensees analysis must show that

degraded voltage trip setpoint adequately

protects the equipment powered by the 4.16

kV ESF bus from a potentially damaging

degraded voltage condition.

The NRC regulatory requirement is Criterion

17 of Appendix A to 10 CFR Part 50. The

NRC staff guidance and positions are

described in PSB-1.

See staff response to Task Interface

Agreement 2010-005 (ADAMS Accession

No. ML102800340) for more details

regarding Palo Verde degraded voltage

inspection finding.

122

Page 5

APS

Page 11, 14.

Inspection Report 2009-008 is described in the

draft RIS. The specific elements of the inspection

report that require response are next described.

The inspection report states:

"the time delay of 35 seconds for transfer of safety

buses to the onsite power supplies may be too long

to prevent core damage in case of a sustained

degraded voltage condition concurrent with an

accident. This time delay could result in a delay in

supplying water to the core in case of an accident

concurrent with degraded voltage, due to the

inability of electrical equipment to respond as

required during the timeout period."

APS Response: This is a double sequencing

scenario, which is a malfunction of an SSC with a

different result than previously evaluated pursuant

to 10 CFR 50.59, for PVNGS. It could result in core

damage regardless of the time delay value at which

the DVR actuation (delayed LOOP) occurs. This is

the reason APS precludes such an event by

establishing appropriate initial conditions, with TS

LCO 3.8.1, Condition G, through license

amendment 123.

Disagree.

The point being made in the RIS is that

setting of the DVR should include

consideration of a coincident degraded grid

and accident in that the time delay chosen

for the DVR should support the accident

analysis assumptions consistent with the

NRC1977 letter.

The focus of the RIS is to clarify regulatory

requirements.

See staff response to Task Interface

Agreement 2010-005 (ADAMS Accession

No. ML102800340) for more details

regarding Palo Verde degraded voltage

inspection finding.

The double sequencing issue is a plant-

specific issue. The staff determined that the

amendment that addressed the specific

design issue (double sequencing) at PVNGS

did not change the licensing requirements for

the degraded voltage protection at PVNGS.

123

Page 5

APS

Page 11-12, 15.

The inspection report states:

"A shorter time delay will not delay the time

required to provide water to the core, but will

actually improve it."

APS Response: APS is not aware of any analysis

in the GSI-171 resolution document to suggest that

Disagree

41

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

a shorter time delay (e.g., delayed LOOP occurring

sooner) would be of any benefit in preventing the

failure mechanisms associated with a delayed

LOOP or assuring that water would be successfully

provided to the core. See Technical Comment 6 for

further discussion on the lack of correlation

between the DVR time delay setting, accident

analysis time, and core damage.

The PVNGS current licensing basis for the DVR

time delay is > 28.6 seconds. During the review

that led to issuance of PVNGS license amendment

123, the staff expressed a concern that a minimum

allowable time delay be specified to assure that

unnecessary separation from offsite power would

not occur. The safety evaluation for license

amendment 123 states:

"APS responded by adding a lower limit (> 28.6

seconds) to the time delay allowable value

specified for the degraded voltage function in its

revised submittal dated September 29, 1999. This

change resolves the staffs concern on this matter."

The NRC staff was aware and approved the

existing time delay values for the DVRs and the

staff considered a shorter time delay to be a

concern. The inspection report is inconsistent with

the current safety evaluation.

This is a plant specific issue. The issue will

be reviewed through the ROP.

124

Page 5

APS

Page 12, 16.

The inspection report states:

"The licensee had offered the proposition that

degraded voltage concurrent with an accident was

not credible, but the team could not find evidence

that the NRC had accepted this position, or that the

degraded voltage relays were no longer required to

perform a protective function during accidents."

APS Response: The PVNGS current licensing

basis is documented in the safety evaluation for

PVNGS license amendment 123, which states:

"The licensee's proposed revision to TS 3.8.1,

Condition G is designed to preclude a degraded

voltage/double sequencing scenario from occurring

at the Palo Verde site. The staff finds this approach

acceptable...."

The safety evaluation recognizes that the

prevention strategy precludes degraded voltage

conditions from occurring. All scenarios involving

degraded voltage concurrent with an accident are

delayed LOOP/double-sequencing scenarios. The

purpose for PVNGS license amendment 123 was

to implement a method to prevent this degraded

voltage concurrent with an accident (which would

always result in a delayed LOOP and double

sequencing). APS is not aware of an accepted

method to ensure that core damage will not result,

if such an event were to occur. Design basis

calculations to justify the function of the degraded

voltage relays during accidents are not feasible,

because they would be unable to justify the

delayed LOOP/double sequencing effects

discussed in GSI-171.

Disagree.

See staffs response to Comment No. 123

125

Page 6

Nextera 1

This paragraph could be interpreted to require the

LOCA sequence to be modeled at the DVR dropout

setting. LOCA sequencing modeled at the DVR

Disagree

42

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

dropout setting would result in separation of the

buses from the Preferred Power Source (off-site

power) as the voltage would not recover above the

DVR reset value.

Clarify the intent is to show safety related

equipment will function at the selected DVR

dropout setting voltage and that it is not expected

to start the LOCA sequence from this voltage level.

Clarify that LOCA sequencing is evaluated using

minimum switchyard voltage as starting point.

The dropout setting should be developed

based on the voltage requirements (starting

and running) and therefore to develop values

which are bounding, the studies should be

done under worst starting and loading

conditions which means the required voltage

at the 1E bus prior to the start or run case

would have to be higher than the setpoint.

The main point is that the setpoint should

equate to the limiting voltage at the limiting

component during the bounding starting or

running scenario to protect the 1E

equipment.

126

Page 6

Nextera 2

Having a sustained degraded voltage just above

the LVR voltage setting (70%) is not practical

without grid collapse and does not exist in Branch

Technical Position #1 (PSB-1).

Clarify degraded voltages to be analyzed to a

credible level.

Agree.

The DVR setpoints are calculated based only

on the voltage requirements of the 1E

equipment, not based on whether the grid

can sustain voltage at levels that result in

such conditions.

127

Page 6

Nextera 3

The statement that the DVR ensures adequate

operational (starting and running) is the first time in

NRC correspondence that starting equipment at

the DVR setpoint is expected. The example letter

sent to Peach Bottom in June 1977 did not require

starting of equipment at the DVR setpoint. This

requirement should be removed from the RIS since

it is not possible to start equipment at the DVR

setpoint and not subsequently separate from offsite

power. If the equipment starts at the DVR setpoint,

the voltage will dip during the transient and must

then recover above the reset point to avoid

separation from offsite power. Since the reset point

will always be above the DVR dropout point it will

be impossible to reset the relay.

Remove starting of equipment at the DVR setpoint

as a requirement.

Disagree

The dropout setting should be developed

based on the voltage requirements (starting

and running) and therefore to develop values

that are bounding, the studies should be

done under worst starting and loading

conditions, which means the required voltage

at the 1E bus prior to the start or run case

would have to be higher than the setpoint.

The main point is that the setpoint should

equate to the limiting voltage at the limiting

component during the bounding starting or

running scenario to protect the 1E

equipment.

128

Page 7

Nextera 4

It is agreed that no credit is to be taken for voltage

controlling equipment external to the Class 1 E

distribution system for the establishing the

degraded voltage relay (DVR) settings; however, it

should be clarified that for credit may be taken for

minimum switchyard voltage/voltage drop

calculations (or the Offsite/Onsite Design Interface

Calculations).

Clarify that credit may be taken for automatic load

tap changers and/or capacitor banks for minimum

switchyard voltage/voltage drop calculations (or the

Offsite/Onsite Design Interface Calculations).

Agree

Additional wording has been added to the

Offsite/Plant distribution discussion to make

it more clear that equipment like automatic

load tap changers can be credited if the

response time will support normal operation.

129

Page 8

Nextera 5

NRC Generic Letter 79-36, Enclosure 2, Item 2

states that It is recommended that "For multi-unit

stations a separate analysis should be performed

for each unit assuming (1) an accident in the unit

being analyzed and simultaneous shutdown of all

other units "Offsite/Onsite at the station; or (2) an

anticipated transient in the unit being Design

analyzed (e.g., unit trip) and simultaneous

43

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

shutdown of all Interface other units at that station,

whichever presents the largest Calculations", load

situation."

Comment:

NRC Draft RIS re-states NRC GL 79-36 verbatim,

with an attempt to clarify "anticipated transient' by

adding in parenthesis "(anticipated operational

occurrence)" immediately afterwards. It is not clear

what the added parenthetical statement is meant to

convey, other than unit trip (which already exists in

GL 79-36).

It is recommended that this either be removed, or

stated "anticipated transient per station licensing

basis".

Disagree

The reference added is the wording used in

GDC 17 (for consistency).

130

Page 8

Nextera 6

NRC should clarify "simultaneous shutdown" with

consideration to:

Most multi-unit station's Licensing Basis consider

an "orderly or controlled safe shutdown" of the

other unit(s) not being analyzed.

NERC Std TPL-004-0; particularly Category D

events per Table 1, where a "loss of all generating

units at a station" may result in "portions or all of

the interconnected systems may or may not

achieve a new, stable operating point'.

IEEE Std 308-1974, Clause 8, subclause 8.1.1

"Capacity' describes this as a "concurrent safe

shutdown on the remaining units".

The wording for the proposed RIS, subclause 2.c

should be revised to indicate "orderly or controlled

safe shutdown of the remaining units, as per the

station's licensing basis" instead of "simultaneous

shutdown". Alternatively, the wording "shutdown

consistent with the station licensing basis" could be

used instead of "simultaneous shutdown".

Disagree

This wording in the RIS is the same as was

used in GL 79-36.

TPL-004 requires transmission planning to

address simultaneous multiple transmission

contingencies.

The plant licensing basis provides basis for

analyses related to multi unit sites.

131

Page 8

Nextera 7

These guidelines ( e) and f) )seem contradictory

that you cannot credit procedurally controlled

operator actions to reduce load but you have to

assume the actions will be carried out when load is

added.

Delete "e) Manual load shedding should not be

assumed" or add allowance to credit procedurally

controlled operator actions to decrease load.

Disagree.

These guidelines are not contradictory in that

one is considering load shedding (not

conservative) for design of system based on

maximum load, while the other is about load

additions that occur per procedure

(conservative for maximum loading design).

132

General

TVA

Comment: The RIS suggests that demonstrating

adequate motor starting voltage is a reasonable

objective or outcome of a setpoint calculation for a

Degraded Voltage Relay whose purpose is to

protect Class 1 E equipment.

TVA's position is that such an objective or outcome

is not technically achievable for the reasons

discussed below:

1) A Voltage Relay is not a Predictive Device

Voltage sensing equipment cannot provide a

predictive function without crediting the capacity or

capability of the upstream system, since it cannot

determine the capacity or capability provided

during a transient condition such as a motor start.

Since the existing regulatory framework for

Disagree

The DVR dropout setting should be

developed based on the voltage

requirements (starting and running) and

therefore to develop values that are

bounding, the studies should be done under

worst starting and loading conditions, which

means the required voltage at the 1E bus

44

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

degraded voltage protection was based on use of

voltage relaying, it is not clear how the existing

relaying equipment could be used to demonstrate

compliance with an adequate motor starting

demonstration requirement.

2) A Degraded Voltage Relay Protection Setpoint

Based on Starting Voltage Does Not Provide Motor

Protection

This method could potentially be calculated but

would mean that the DVR setpoint would have

been determined during the starting of the most

limiting Class-I E motor. A degraded voltage relay

setpoint based on a motor starting would not

protect the motor from damage (required by

regulations) or preclude tripping of the motor's

over-current device(s) prior to transferring to the

onsite power supply (required by regulations). This

is because the DVR time delays are (by definition)

required to be longer than a motor starting transient

(1st time delay) and long enough to allow operator

intervention (2nd time delay). If starting of the

limiting (worst-case) motor was attempted in a true

degraded voltage situation (even slightly below the

DVR setpoint), the DVR scheme could not perform

either of these protective functions prior to tripping

the normal overcurrent relays. Therefore, this

would not provide any additional protection for the

Class-1 E loads.

prior to the start or run case would have to

be higher than the setpoint. The main point is

that the setpoint should equate to the limiting

voltage at the limiting component during the

bounding starting or running scenario to

protect the 1E equipment. In addition, the

time delay would be determined based on

the limiting starting transient duration only

(not based on allowing time for operator

action). In this manner, if the voltage drops

below expected values during starting

(based on the 1E equipment limits) and

prolongs the start transient, then the DVR

will timeout and separation will occur

(providing low starting voltage protection).

133

General

Progress

Energy 1

Background: The draft NRC Regulatory Issue

Summary, 2011 -xx, Adequacy of Station Electric

Distribution System Voltages, describes a

methodology of implementation for degraded

voltage relay schemes that would impose

"Additional Conservatisms" into the settings and

time delays in an effort to further reduce the risk of

degraded voltage operation on nuclear plant safety

related / accident mitigating electrical equipment.

"Additional Conservatisms" from this point of view

tends to mean that the degraded voltage relaying

will actuate earlier in a degraded voltage event time

line - meaning it would be set to actuate at a higher

degraded voltage and/or with a shorter time delay.

In conflict with the NRC's desire to impose

additional conservatisms on degraded voltage

protection at nuclear power plants, the North

American Electric Reliability Corporation (NERC),

is developing a national standard for Frequency

and Voltage Excursion Ride- Through Performance

(PRC-024) for all generating stations in North

America. The Voltage Excursion Ride-Through

Time Duration Curves currently proposed by the

NERC Standards Drafting Team shows the

competing desire for nuclear power plants to be

capable of riding through a grid induced voltage

transient without tripping.

Actuation of the degraded voltage relaying in a

nuclear power plant during a grid induced voltage

transient results in a temporary loss of power to the

safety related loads powered from the plant buses

until the loads are realigned to an emergency

power source and reenergized. This temporary loss

of power will result in a trip of the nuclear plant in

many cases and a significant challenge to

Disagree.

Additional conservatism should not be added

for the sake of adding conservatism.

Conservatism is typically added to

compensate for assumptions that cannot be

accurately verified or proven (e.g. cable

impedances when actual pull lengths are not

known).

.

NERC and FERC guidelines are reviewed by

NRC staff for applicability to nuclear plant

operation.

The DVR and loss of voltage relay settings

should not be in conflict with NERC or FERC

recommended guidelines for grid operations.

45

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

continued operation of the plant in all cases.

An analysis of current settings and time delays for

several nuclear plant loss-of-voltage and degraded

voltage relay schemes against the proposed NERC

ride through criteria shows that existing settings are

already in conflict with the proposed ride-through

criteria.

Imposition of additional conservatisms into the

relay settings and time delays for nuclear

plant equipment degraded voltage protection will

further complicate efforts to coordinate

NRC required degraded voltage protection

schemes with NERC voltage transient ridethrough

capability needs.

Comment: Please coordinate NRC Staff proposed

degraded voltage relay setting

methodology changes with NERC proposed

voltage transient ride-through capability

standard (PRC-024) by engaging with NERC under

the current NRC - NERC Memorandum of

Agreement (MOA).

134

General

Progress

Energy 2

Background: The use of on-load automatic load tap

changing transformers for nuclear plant offsite

power supplies would aid in minimizing auxiliary

bus under voltage or degraded voltage transients

of concern to the NRC while also improving the

voltage transient ride through capability of the

nuclear plants that is of concern to NERC.

Comment: Please revise the RIS to allow the

nuclear plants to use and take credit for on load

automatic load tap changing transformers for

nuclear plant offsite power supplies to prevent

degraded voltage events and improve the voltage

transient ride through capability of the nuclear

plants.

Agree

Load tap changers help improve voltage

regulation for normal plant operation. Load

tap changers do not help protect safety

related equipment during degraded grid

conditions.

Additional wording has been added to the

Offsite/Plant distribution discussion to make

it more clear that equipment like automatic

load tap changers can be credited for normal

plant operation.

135

General

Progress

Energy 3

Comment: Please also consider the italicized

changes below:

DVR Setting Design Calculations

Licensee voltage calculations should provide the

basis for their DVR settings, ensuring safety related

equipment is supplied with adequate operating

voltage (typically a minimum of 0.9 per unit voltage

at the terminals of the safety related equipment per

equipment manufacturers requirements), based on

bounding conditions for the most limiting safety

related load (in terms of voltage) in the plant.

These voltage calculations should model the plant

safety related electrical distribution system such

that the limiting voltage at the bus monitored by the

DVR can be calculated in terms of the voltage at

the terminals of the most limiting safety related

component in the plant. These models would allow

calculation of voltages at terminals (delete "or

contacts ") of all safety related equipment with the

voltage at the DVR monitored bus at the DVR

dropout setting, providing the necessary design

Agree

Italicized changes suggested were

considered along with other similar

comments received from other stakeholders

and clarified in the RIS revision.Italicized

changes were not incorporated in the RIS

since the comments were not consistent with

the staffs existing guidance for DVR

settings.

46

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

basis for the DVR voltage settings.

In this manner, independent of voltage controlling

equipment external to the plant safety related

electrical distribution system, the DVR ensures that

all safety related equipment can continue to

operate at the degraded voltage relay drop out

setting if previously in service, small loads will not

be damaged if successfully started at the degraded

voltage without DVR time out (the DVR either does

not drop out or resets before time out because the

started load is small), and larger loads will not be

damaged or trip on overload /protective relaying if

starting the equipment results in sustained

degraded voltage for the duration of the DVR time

delay (the DVR drops out and does not reset

because the load is large but the DVR timer times

out and sheds the load from the degraded voltage

source before the overloads and/or protective

relaying actuates).

For the purposes of this DVR Setting Design

calculation, no credit should be taken for voltage

controlling equipment external to the Class 1 E

distribution system such as automatic load tap

changers and capacitor banks because these

devices normally prevent degraded voltage from

occurring and thus, by definition, should not be

included in a bottom up analysis to determine

minimum voltage requirements for the safety

related loads. Voltage time settings for DVRs

should be selected so as to avoid spurious

separation of safety buses from the offsite power

system during unit startup, normal operation and

shutdown. These DVRs should disconnect the

Class 1 E buses from any power source other than

the emergency diesel generators (onsite sources) if

the degraded voltage condition exists for a time

interval that could prevent the Class 1 E safety

related loads from achieving their safety function.

The DVRs should also protect the Class 1 E safety

related loads from prolonged operation below

sustained degraded voltage which could result in

equipment damage.

The licensees should demonstrate that the existing

DVR settings including allowable values and time

delays are adequate so that safety related loads

can continue to operate at the degraded voltage

relay drop out setting if previously in service, small

loads will not be damaged if successfully started at

the degraded voltage without DVR time out, and

larger loads will not be damaged or trip on

overload/protective relaying if starting the

equipment results in sustained degraded voltage

for the duration of the DVR time delay resulting in

separation from offsite power and realignment to

the emergency onsite power supply. The time-

delay(s) chosen for DVRs during accident

conditions should be short enough to meet the

accident analyses assumptions and allow for

proper starting of all Class 1E safety related

equipment assuming that the DVR time delay times

out and the accident mitigating loads realign to the

onsite emergency power supply. Also, the time

delay chosen for DVRs during non-accident

condition must be short enough to not cause any

degradation of the safety related components,

including actuation of their protective devices.

Contacts was deleted.

47

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

136

General

Progress

Energy 3

Comment: Please also consider the italicized

changes below:

Offsite/Onsite Design Interface Calculations

The offsite power source is the preferred source of

power to safely shut down the plant during design

basis accidents, abnormal operational occurrence,

and reactor trips. The licensee's voltage

calculations should provide the basis for proper

operation of the plant safety related electrical

distribution system, when supplied from the offsite

circuit (from the transmission network). These

calculations should demonstrate that the voltage

requirements (both starting and operational

voltages) of all plant safety related systems and

components are satisfied based on operation of the

transmission system and the plant onsite electric

power system during normal, startup, shutdown,

accident mitigation, and alternate authorized

operating configurations of transmission network

and plant systems. In this way, all safety related

systems and components will function as designed

with proper starting and running voltages during all

plant conditions and the DVRs will not actuate

(separating the transmission network supply).

Following are guidelines for voltage drop

calculations derived from Generic Letter 79-36,

which have been supplemented to add clarifying

information. They do not represent new NRC staff

positions.

Agree

Italicized changes suggested were

considered along with other similar

comments received from other stakeholders

and clarified in the RIS revision.Italicized

changes were not incorporated in the RIS

since the comments were not consistent with

staffs existing guidance for offsite/onsite

design interface calculations.

137

General

Progress

Energy 3

Comment: Please also consider the italicized

changes below:

Guidelines for voltage drop calculations

a) The plant voltage analysis, while supplied from

the transmission network, should be based on the

operating voltage range of the transmission

network connection. This transmission

owner/operator supplied voltage range should

address normal, startup, shutdown, accident

mitigation, and alternate authorized transmission

network and plant system operating configurations

and should also include voltage drop due to the

bounding worst case transmission system single

contingency (transmission system contingencies

include trip of the nuclear power unit). Normally in-

service and periodically tested non-safety related

equipment (such as automatic load tap changing

transformers that regulate voltage during changing

conditions) are to be included in the analysis.

b)

Separate analyses should be

performed assuming the power

source to the safety buses is (1) the

unit auxiliary transformer; (2) the

startup transformer; and (3) other

available connections (e.g., from all

available connections) to the offsite

network one by one assuming the

need for electric power is initiated

by (1) an anticipated transient such

as a unit trip (e.g., anticipated

operational occurrence), or (2) an

accident, whichever presents the

bounding load demand on the

power source.

Agree

Italicized changes suggested were

considered along with other similar

comments received from other stakeholders

and clarified in the RIS revision.Italicized

changes were not incorporated in the RIS

since the comments were not consistent with

staffs guidance provided in Generic Letter 79-36.

48

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

138

General

STARS

"Statement of Staff Positions Relative to

Emergency Power Systems for Operating

Reactors"

RIS 201 1-XX states that "the NRC required

licensees to install degraded voltage protection

schemes ... as described in NRC Letters dated

June 2 & 3, 1977, 'Statement of Staff Positions

Relative to Emergency Power Systems for

Operating Reactors,' which were sent to all

licensees of all operating nuclear power plants. As

an example, see the NRC letter dated June 2,

1977, ADAMS Accession No. ML100610489, sent

to the licensee for Peach Bottom Atomic Power

Station." (Ref. 2) However, the RIS does not

recognize the latitude in response allowed to each

Licensee:

"We request that you compare the current design

of the emergency power systems at your

facility(ies) with the Staff Positions stated in the

enclosure and:

(1) propose plant modifications as necessary to

meet the Staff Positions, or

(2) provide a detailed analysis which shows your

facility design has equivalent capabilities and

protective features.

Additionally, we require that certain technical

specifications be incorporated into all facility

operating licenses."

Observations:

1. The NRC letters request some actions and

require some actions - specifically - a technical

specification change.

2. The response makes allowance for varied

responses that account for "equivalent capabilities

and protective features." These varied responses

become part of the licensees' Current Licensing

Basis.

3. Licensees were required to change their

operating license because the staff position.

However, this in and of itself, does not change the

licensees' Current Licensing Basis.

4. The "1977" letters apply only to addressees, i.e.,

plants licensed before 1977.

Adequacy of Station Electric Distribution System

Voltages

The technical content, with some modifications, of

the "Statement of Staff Positions Relative to

Emergency Power Systems for Operating

Reactors" was put in the Branch Technical Position

(BTP) of the Standard Review Plan (SRP/NUREG-

0800), PSB-1, Revision 0, "Adequacy of

Station Electric Distribution System Voltages,"

dated July 1981, and in the current BTP 8-6 of

the SRP, Revision 3, "Adequacy of Station Electric

Distribution System Voltages," dated March

2007.

Disagree

NRC staff does not agree with this position.

As a result of these Millstone events, the

NRC requested that all licensees implement

degraded protection as described in the

1977 Letter to ensure automatic protection of

safety buses and loads. This Letter provides

staff positionguidance, which applies to all

operating reactors at that time and plants

licensed since, on how to comply with the

requirements in 10 CFR Part 50, General

Design Criteria 17 (GDC 17).

49

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

1.

Branch Technical Positions of NUREG-

0800 are not requirements but:

"represent guidelines intended to supplement the

acceptance criteria established in

Commission Regulations, guidelines presented in

Regulatory Guides, and recommendations

presented in applicable IEEE standards."

2.

PSB-1 and BTP 8-6 provide subtle but

significant changes to each other and to

the original "Statement of Staff Positions

Relative to Emergency Power Systems

for Operating Reactors" (Note: these

differences will be provided in a

comment letter from the Nuclear Energy

Institute). If the original statement of staff

positions is considered a requirement,

then it is contradictory to subsequent

NRC guidance.

3. PSB-1 and BTP 8-6 represent guidance as

committed to in a licensees' Current

Licensing Basis - which, with plant specific

justification, may depart from NRC

guidelines, but are reviewed and approved by the

NRC.

139

General

STARS

By characterizing the new contents of RIS 2011 -

XX as clarifications to "the NRC staff's technical

position on existing regulatory requirements," the

RIS seeks to supersede the NRC reviewed and

approved Current Licensing Basis for many

licensees.

Disagree

The purpose of the RIS is to clarify the NRC

staffs technical position on existing

regulatory requirements and voltage studies

necessary for Degraded Voltage Relay

(second level undervoltage protection)

setting bases and Transmission

Network/Offsite/Onsite station electric power

system design bases. This RIS does not

transmit any new requirements or staff

positions.

A RIS is an appropriate document for NRC

staff to provide clarification on existing

Regulatory Requirements and existing NRC

Staff Positions.

140

General

Greg

Reimers

(DCCP)

The issue I am concerned about is the regulatory

conflict created by requiring the DVR setpoint to

preclude spurious actuation of the undervoltage

protection function.

The NRC draft RIS 2011-XXX discusses spurious

separation at least three times.

1.

The first occurrence is an accurate

restatement of the 1977 NRC position

that "The voltage protection shall include

coincidence logic to preclude spurious

trips of the offsite power source" (See

RIS Page 2, Item (b)).

2.

The second occurrence is in the

"Degraded Voltage Relay Design

Calculations" section. Specifically, the

second sentence of the first paragraph

on Page 7 reads "Voltage-time settings

for DVRs should be selected so as to

avoid spurious separation of safety

buses from the offsite power system

during unit startup, normal operation and

shutdown." This introduces the DVR

Agree

NRC Staff agrees with commenters position

on use of the term spurious with respect to

the design of the DVR scheme to prevent

false actuations due to DVR component

failures or miss-operations

The RIS will be revised to remove spurious

from this section. The NRC Staff position is

that the settings are to be selected based on

the voltage requirements of the 1E

equipment such that when compared with

the minimum expected grid voltages, there

should be sufficient margin ensure that

separation from the grid would not be

expected during normal, abnormal or

50

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

voltage and time setpoint interaction with

the offsite power circuits as a factor in

the setpoint determination. I believe a

conclusion of the workshop was a

common understanding that the

functional requirement of the DVR

protection is to prevent common mode

equipment failure during a sustained

degraded voltage condition. As

discussed, this can best be achieved via

a "bottom up" analysis without

consideration of offsite power capacity

and capability.

3.

The third occurrence is in the

"Offsite/Onsite Design Interface

Calculation" Section. Page 8, Item (i)

reads "For each case evaluated, the

calculated voltages on each safety bus

should demonstrate adequate voltage at

the component level without separation

from the offsite circuit due to DVR

actuation."

Points #2&3 above introduce a contradiction for

those stations whose current license basis is

consistent with the Standard Technical

Specifications. Referring to NUREG-1431,

Standard Technical Specifications Westinghouse

Plants (typical TS), the degraded voltage TS bases

read "The Allowable Value is considered a limiting

value such that a [DVR] channel is OPERABLE."

Thus, at the Allowable Value lower limit, the Class

1E electrical distribution system is capable of

fulfilling its ESF supporting design function. The

offsite power LCO reads "Each offsite circuit must

be capable of maintaining rated frequency and

voltage, and accepting required loads during an

accident, while connected to the ESF buses." No

voltage values are defined for the offsite power TS

LCO. Therefore, if the offsite power circuit can

maintain the bus voltage such that the DVR lower

Allowable Limit is satisfied, then the offsite power

circuit would also be operable.

The DVR dropout and reset setpoints must be

greater than the TS lower Allowable Value due to

instrument tolerances and uncertainty. Given the

DVR favors the DGs, does not mean bus voltages

between the DVR setpoint and the TS lower

Allowable Value reduce the capability of the offsite

power circuit. Consequently, the DVR setpoint

cannot completely preclude spurious separation.

As discussed in the workshop, a voltage relay

cannot predict future operating conditions.

Consequently, the DVR can't distinguish between

voltage transients that are expected to recover and

those that are not. Therefore, in the context of the

original NRC position (i.e. Point #1), I believe the

term spurious was in the context of false signals

from within the DVR instrumentation and not any

group of bus voltage transients. The IEEE 308

requirement that RIS Page 8, Item (i) is trying to

convey is "The preferred power supply shall be

capable of starting and operating all required

loads."

accident conditions.

NRC Staff agrees with commenters position

on use of the term spurious with respect to

the design of the DVR scheme to prevent

false actuations due to DVR component

failures of miss-operations

NRC Staff agrees with the commenters

position that the intent of item i) is to specify

that the preferred power supply is able to

start and run all required 1E equipment in

accordance with its voltage requirements

while not separating

141

Backup power

options

Brian Wilson,

CA

Why are there not back-up power sources located

on the roof of the fuel cell tanks with electric lines

Disagree

51

No.

Section of RIS

Originator

Specific Comment

NRC Resolution

connected directly to the pumps that cool the fuel

rods back-up power sources run on both methane

or propane and Ipg. A remote control panel from a

distant site would provide a safe environment to

control a dangerous situation safely.

This comment is not related to the RIS

regarding Adequacy of Station Electric

Distribution System Voltage. Therefore,

staff did not address the comment.

52

Supplemental Response to NEI Comment No. 96 in Comment/Resolution Table (corrected)

RESPONSES TO NEI 3-2-2-11 BACKFITTING COMMENTS

RIS On Adequacy of Station Electric Distribution Voltages

Comment: The RIS represents an NRC attempt to standardize varied approaches to providing protection during

degraded grid voltage conditions, as currently memorialized in the licensing bases of individual plants. However,

given the complex regulatory and licensing history associated with providing degraded grid voltage protection at each

plant, a conclusion that the guidance in the proposed RIS is consistent with prior NRC guidance is insufficient to

meet the requirements of the Backfit Rule. (NEI - pp.2-7)

NRC Response: The NRC interprets the comment as stating a general principle: if the NRC proposes to issue

generic guidance applicable to several plants - each of which has a complex regulatory and licensing history, then the

NRC complies with the Backfit Rule only if its backfitting discussion for the proposed generic guidance considers and

addresses the licensing basis for each affected plant.

The NRC disagrees with the comment, and does not believe that the NRC should, as a matter of policy, adopt such a

principle to guide the agencys implementation of the Backfit Rule. Application of such a principle would oftentimes

impose substantial resource burdens on the NRC, inasmuch as the NRC currently has no efficient way of easily

compiling and reviewingas it is difficult for the NRC to efficiently compile and review the licenses bases of selected

plants on a comparative basis. The more complex the regulatory licensing history for each licensees plant, the more

resource intensive it would be for the NRC to prepare a generic backfitting discussion that essentially constitutes a

collection of plant-specific licensing basis reviews. Upon completing the licensing basis review for each plant to which

the generic guidance is applicable, the NRC (and licensee) may well conclude that imposition of the guidance would

not represent backfitting. In that situation, the review would constitute an arguably unnecessary expenditure of NRC

(and licensee1) resources.

The NRC believes a more sensical approach is: if the NRC has generally maintained a consistent position (or at least

expressed no contrary position) and has implemented that position in a consistent manner, then the NRC may issue

guidance as a statement of position, and prepare any necessary backfit discussion in connection with any NRC

action which imposes the guidance on a licensee who claims that the imposition constitutes backfitting. The NRC

action may be, among other things, a NRC determination of a license amendment application, the issuance of a

notice of violation, or issuance of an order directing the licensee to comply with the guidance. In this manner, the

specific regulatory and licensing history for that plant can be compiled and evaluated by the NRC as part of the

NRCs mandated backfitting consideration.

Consistent with this general principle, the NRC has (as part of the backfitting consideration of this RIS) reviewed its

records with respect to generic guidance on GDC017 and degraded voltage protection. Based upon that review, the

NRC believes its generic guidance on GDC-17 and degraded voltage protection has been consistent over time.

Thus, the positions presented in the degraded voltage RIS do not constitute generic backfitting. In addition, the NRC

has reviewed its records and believes that (with one exception which is being dealt with in a plant-specific manner2 ),

the NRC has taken a consistent position on a plant-specific basis. The NRC is currently in the process of applying

the guidance to a specific plant, and is preparing the appropriate documentation required by the Backfit Rule. Hence,

the NRC concludes that plant-specific evaluation of the backfitting implications of this RIS is not appropriate.

Therefore, the NRC believes it makes more sense, that if the NRC has generally maintained a consistent position (or

at least expressed no contrary position) and has implemented that position in a consistent manner, then the NRC

may issue guidance as a statement of position, and prepare any necessary backfit discussion in connection with any

NRC action imposing the guidance on each licensee. The NRC action may be, among other things, a NRC

determination of a license amendment application, the issuance of a notice of violation, or issuance of an order

directing the licensee to comply with the guidance. In this manner, the specific regulatory and licensing history for that

plant can be compiled and evaluated by the NRC as part of the NRCs mandated backfitting consideration.

For this RIS, the NRC reviewed the regulatory guidance and NRC practice in this area, and concluded that the

guidance in the RIS is consistent with the NRCs regulations and staff guidance, as well as the NRCs approval of

1 If the NRC prepared a detailed discussion of a plants licensing bases to support the issuance of guidance, then it

would be likely that the licensee would be required to verify the NRCs discussion.

2 This involves the Edwin C. Hatch (Hatch) Plant, for which the NRC staff has prepared a documented evaluation

supporting the invocation of the compliance exception (included in NRC Inspection Report 05000321 and

366/2011009, ML1114507930). The NRCs reliance on the compliance exception is the subject of a backfit appeal by

Southern Nuclear Operating Company, the licensee of the Hatch Plant (ML111680360). The NRC has denied the

backfit appeal (ML112730194).

Formatted: Font: Italic, Underline

Formatted: Centered

Formatted: Centered

Formatted: Font: 9 pt

Formatted: Font: Italic

Formatted: Font color: Auto

Formatted: Font: 9 pt

Formatted: Font: (Default) Arial, 9 pt

Formatted: Font: (Default) Arial, 9 pt, Not

Superscript/ Subscript

Formatted: Font: (Default) Arial, 9 pt

Formatted: Font: (Default) Arial, 9 pt, Not

Superscript/ Subscript

Formatted: Font: (Default) Arial, 9 pt, Font

color: Auto, Not Superscript/ Subscript

Formatted: Font: (Default) Arial, 9 pt, Not

Superscript/ Subscript

Formatted: Font: (Default) Arial, 9 pt, Font

color: Auto, Not Superscript/ Subscript

53

electrical systems in various licensing actions (with one exception which is being dealt with in a plant-specific

manner3). Hence, the NRC concludes that plant-specific evaluation of the backfitting implications of this RIS is not

appropriate.

The NRC emphasizes that this approach to addressing backfitting in connection with the issuance of guidance (such

as this RIS) would not be appropriate if the NRC does not have reasonable certainty that it has articulated (or at least

expressed no contrary position) and implemented a consistent position over time. However, as stated above, such is

not the case with the guidance on degraded grid voltage protection contained in this RIS. Thus, the degraded voltage

RIS does not constitute generic backfitting because it does not constitute a new or different generic NRC staff

position. If there is plant-specific backfit when applying the guidance to a specific plant, then the staff will address

backfitting in the context of that staff action (and prepare the necessary documentation to support the staffs

backfitting action). Accordingly, the NRC declines, as a matter of discretion, to prepare a plant-specific backfitting

discussions for each of the plants that may be affected by the RIS. No change was made to the RIS as a result of this

comment.

Comment: The NRC should not rely upon GDC-17 to conclude that the proposed RIS does not represent backfitting.

GDCs are cast in broad, general terms and are non-specific nature. Thus, the relevant backfitting inquiry should be

whether the proposed RISs guidance differs from any individual plants NRC-approved voltage protection scheme.

(NEI - pp.6-7) (See NRC Comment/Resolution table item No. 96)

NRC Response: In general, the NRC agrees with the comment that many (but not all) of the GDC are cast in broad,

general, performance-based language. However, the NRC disagrees with the comments implicit assertion that any

GDC which is expressed in broad, general terms or is non-specific in nature, or is expressed in performance-based

language, may not be relied upon when the NRC invokes the compliance exception under § 50.109(a)(4)(i). Nothing

in the history of the Backfit Rule suggests that the Commission intended to adopt such an interpretation of the Backfit

Rule.

Furthermore, if the NRC were to adopt the position that NRC issuance of changed or new guidance for performance-

based regulations must always be accompanied by plant-specific licensing basis analyses for all potentially-affected

plants, this would likely inhibit the adoption of performance-based rules. If the NRC must take into account the plant-

specific licensing basis considerations whenever it proposes to take generic regulatory action through the issuance of

rules and regulations, then this effectively converts the administrative process of rulemaking under the Administrative

Procedures Act (APA) to the administrative process of issuance of orders under the APA. The NRC does not see why

it must limit itself, in light of the several and broadly-worded rulemaking authorities accorded the NRC under various

provisions of the Atomic Energy Act of 1954, as amended. These rulemaking provisions include, among others,

Sections 103.a, 103.b, 161.i, 161.p, 182.a, and 183.

Moreover, the GDCs are just one NRC position for which a licensee is protected from backfitting. If there is a more

specific requirement in a plants licensing basis representing the NRC position on an acceptable way of compliance

with the performance-based requirement (e.g., a GDC), then that position is a separate and independent basis for

that licensee to invoke backfitting protection when the NRC proposes to impose that NRC position on that licensee.3

More importantly, the NRC disagrees with the comments implicit assertion that GDC-17 is a broad, general, and

nonspecific GDC. A brief review of GDC-17 shows that its regulatory text is among the most lengthy of the GDCs,

consisting of three paragraphs. The requirements are stated in relatively specific terms using performance-based

regulatory language, but also setting forth very specific conceptual requirements, e.g., the need for electric power

from the transmission network to the onsite electrical distribution system to be supplied by two physically

independent circuits (not necessarily on separate rights of way).

For these reasons, the NRC disagrees that the relevant inquiry for GDC-17 is whether the proposed RIS differs from

any individual plants licensing and regulatory bases. No change was made to the RIS as a result of this comment.

backfit appeal by Southern Nuclear Operating Company, the licensee of the Hatch Plant (ML111680360).

3 The situation involving the imposition of a new NRC position on an acceptable way of complying with GDC-17 is

an example where the NRC acknowledges that the NRC approval of the licensees specific undervoltage protection

scheme) in a license amendment constitutes an applicable staff position for purposes of the Backfit Rule. Thus, the

NRC has acknowledged that the proposed new staff position on the Hatch Plants undervoltage protection scheme

constitutes backfitting. Thus, the issue which is the subject of the licensees backfit appeal, is whether the NRC may

rely upon the compliance exception under 10 CFR 50.109(a)(4)(i).

54

Comment: The NRCs generic communications and guidance identified in the draft RIS are not completely consistent

with one another and were not equally relevant in developing the licensing bases for all reactor licensees, citing to

various statements in the BTP PSB-1. (NEI - pp. 4-5) (See NRC Comment/Resolution table item No. 96)

NRC Response: The NRC agrees that there is some variability between the scope of depth of information presented

in the NRCs generic communications and guidance on the subject of degraded voltage protection. However, the

NRC disagrees with the comments implicit assertion that there is no consistent NRC staff position. As discussed in

response to the prior comment, there is some variability among the NRC generic communications and guidance

documents in terms of the scope of issues relating to electrical system design, as well as the detail provided. The

comment provided four bulleted examples purporting to describe inconsistent or contradictory NRC guidance.

However, none of the identified examples set forth statements which are clearly contradictory or implicitly inconsistent

with one another.

The first example identifies an apparent conflict between a draft RIS statement that degraded voltage conditions

[must be] coincident with a postulated design basis accident, and a statement for Branch Technical Position (BTP)

PSB-1 which states that The subsequent occurrence of a safety injection signalshould immediately separate the

Class 1E distribution system from the offsite power system (emphasis added). There is no conflict or inconsistency

between these two statements, when the BTP (which precedes the RIS) is read in full context. The full text of the

relevant portion of the BTP is:

Two separate time delays shall be selected for the second level of undervoltage

protection based upon the following conditions:

1)

The first time delay should be of a duration that established the

existence of a sustained degraded voltage condition (i.e.,

something longer than a motor starting transient). Following this

delay, an alarm in the control room should alert the operator to the

degraded condition. The subsequent occurrence of a safety

injection actuation signal (SIAS) should immediately separate the

Class 1E distribution system from the offsite system (emphasis

added).

Coincident means, happening at the same time, and coinciding. The Random House College Dictionary,

Revised Edition (1980). Coincide means, among other things, to come to occupy the same period in time

(emphasis added). Id. Subsequent means either occurring or coming later or after, or, following in order of

succession, succeeding. Id. Coincidence simply requires that the two events or conditions happen at the same time,

or come to occupy the same period in time. It is clear that this is what the RIS was addressing - that the postulated

design basis accident must be assumed to occur at the same time as the degraded voltage (undervoltage) condition.

By contrast, the BTP addresses the order or sequence of occurrence of the two events or conditions which must,

despite the order or sequence, must also happen at the same time. The BTP states that the staff will accept a design

in which the undervoltage condition occurs first, and then (while the undervoltage condition is still present), the design

basis event occurs (and thereby draws a load on the electrical system). In either case, the result is the same in that

separation from the grid occurs and the 1E systems are powered from the onsite sources during design basis event

mitigation. The only difference is that in the case of the subsequent design basis event, the actual start of the 1E

equipment will be later than when the two events occur coincidently. Either way the design basis event assumptions

are satisfied.

Figure 1 illustrates the difference. There is no conflict or inconsistency between the RIS and the BTP.

55

Alarm setpoint

significantly

higher than DVR

setpoint

100%

DVR set point based on minimum

voltage required at equipment terminal

to operate all safety related equipment

(BTP PSB-1) DVR-2 Protection with short time

delay to rideout the motor starting transients.

Ensures minimum voltage required for all

equipment to prevent control fuse blowing, relay

lockout, contactor opening etc ., concurrent DVR-

2 condition SI signal causes relay to time out if

the voltage doesnt within the time delay and

bus transfers to onsite power system.

OR

Follow 1977 letter staff position

The selection of voltage and time

delay setpoints shall be determined from an

analysis of the operating voltage requirements of

the safety related loads at all onsite system

distribution levels;

Degraded Voltage Set Points

Figure 1

(BTP PSB-1) DVR -1 Protection - Existence of a sustained degraded

voltage condition

To account for ECCS motor starting, running of all 1E loads and time for

grid recovery (Long time Delay.) Causes alarm and Time delay is

bypassed on SI signal if a subsequent SI occurs. Provide adequate time

for plant or grid operator to take manual actions.

The second example identifies an apparent conflict between the RIS and BTP PSB-1. The draft RIS proposes "DVR

Dropout setting based on starting and running voltage." BTP PSB-1 says "sustained degraded voltage condition,"

during the discussion concerning selection of time delays for the DVR, implying a degraded voltage condition lasting

more than a few seconds and not a transient voltage condition that exists during a motor starting event or during a

momentary grid perturbation such a lightning strike that may be cleared by automatic actions of protection schemes

and automatic breaker open/reclosure cycle. Specifically, BTP PSB-1 states: 'Two separate time delays shall be

selected for the second level of undervoltage protection based on the following conditions: 1) The first time delay

should be of a duration that established the existence of a sustained degraded voltage condition (i.e., something

longer than a motor starting transient)."

It is clear in the context of the 1977 Letter that the phrase sustained degraded voltage is referring to the grid event

and not voltage scenarios in plant electrical system operation (see fig 1). In addition, when selecting an appropriate

time delay for the DVR (which is what the RIS is referring to), one must consider the voltage drop due to large motor

starts in the plant since they can depress voltage momentarily by design and such voltage drops should therefore be

overridden by the time delay since they would mask detection of the sustained degraded grid voltage event. Also, it is

also clear that the 1977 Letter language refers to the DVR voltage setting(s) being based on the voltage requirements

of the 1E equipment. Large 1E motors, for example, have starting and running voltage requirements by design which

must be met to ensure proper operation during accident conditions. Thus, the statement that the BTP implies only

running voltage requirements are required be enforced is not correct. No change was made to the RIS as a result of

this comment. There is no conflict between the RIS and BTP PSB-1.

The third example juxtaposes: (i) the proposed RIS guidance indicating that each unit must have analysis that

assumes an accident in the unit being analyzed and simultaneous shutdown for all other units (emphasis in

original), with language in GDC 5 which states, in the event of an accident in one unit, an orderly shutdown and

cooldown of the remaining units. The language of GDC 5 concerns sharing of SSCs rather than electrical systems,

56

and the language quoted in the comment represents a criterion for allowing sharing of important to safety SSCs

among nuclear power units. This is not the same subject as the determination of how to analyze whether GDC-17s

requirements are being met. Moreover, there is no direct contradiction between simultaneous shutdown in the

proposed RIS, and orderly shutdown and cooldown in GDC 5: an orderly shutdown under GDC-5 could also be

simultaneous for purposes of GDC-17.

The fourth example identifies an apparent conflict between the RIS and BTP PSB-1. The draft RIS proposes "During

normal plant operation, the Class 1E safety related buses should automatically separate from the power supply within

a short interval (typically less than 60 seconds) if sustained degraded voltage conditions are detected." (emphasis

added). The comment suggests that a sixty second time delay would not allow operator actions, and appears to be a

new NRC position.

BTP PSB-1 clause B.1.b.2 included provisions for operator manual actions to restore bus voltage on the Class 1E

distribution system. BTP PSB-1 B.1.b.2 says: "The second time delay should be of a limited duration such that the

permanently connected Class 1E loads will not be damaged. Following this delay, if the operator has failed to restore

adequate voltages, the Class 1E distribution system should be automatically separated from the offsite power

system. Bases and justification must be provided in support of the actual delay chosen." The draft RIS specifically

excludes manual load shedding under the Offsite/Onsite Design Interface Calculations whereas the BTP PSB-1

allows for manual actions to avoid separation from offsite power. The sixty second time delay would not allow

operator actions. This appears to be a new NRC position.

The reference to 60 seconds has been removed in the revised RIS, however, the time delay chosen still has to be

justified in terms of providing automatic protection of the Class 1E equipment in addition to allowing time for operator

actions (if possible). See DVR1 and DVR2 relay and time delays depicted in Figure 1. This is in accordance with BTP

PSB-1 staff position and is an acceptable design to meet the staff position in the 1977 letter, staff position i.e., the

selection of voltage and time delay setpoints shall be determined from an analysis of the operating voltage

requirements of the safety related loads at all onsite system distribution levels. BTP PSB-1 clause B.1.b.2 included

provisions for operator manual actions to restore bus voltage on the Class 1E distribution system. BTP PSB-1 B.1.b.2

says: "The second time delay should be of a limited duration such that the permanently connected Class 1E loads will

not be damaged. Following this delay, if the operator has failed to restore adequate voltages, the Class 1E

distribution system should be automatically separated from the offsite power system. Bases and justification must be

provided in support of the actual delay chosen." The draft RIS specifically excludes manual load shedding under the

Offsite/Onsite Design Interface Calculations whereas the BTP PSB-1 allows for manual actions to avoid separation

from offsite power. Therefore, there is no conflict between the RIS and BTP PSB-1.

Comment: Given the variability in NRCs generic communications and guidance, the draft RIS statement that the

positions in the RIS are consistent with the RIS-identified NRC documents, does not address the possibility that the

RIS is new or different from a previously-approved protection scheme (and thereby constitute backfitting). (NEI - p.7)

NRC Response: As discussed above in response to NEI- pp.4-5, while the NRC agrees that there is some

variability in NRCs communications and guidance on degraded voltage protection, the NRC does not agree that

this variability is of any significance from a backfitting standpoint because there is no contradiction or material

inconsistency between the various NRC communications and guidance documents. Thus, such variability does not

provide a sufficient basis for the NRC to perform plant-specific determination on whether imposition of the RIS

constitutes backfitting. No change was made to the RIS as a result of this comment.