NRR E-mail Capture - HNP Supplement to Mur Power Uprate LAR
ML11182B053
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 06/29/2011
From: Som S
Electrical Engineering Branch
To: Mozafari B
Division of Operating Reactor Licensing
References
Download: ML11182B053 (3)


Text

NRR-PMDAPEm Resource From: Som, Swagata Sent: Wednesday, June 29, 2011 10:11 AM To: Mozafari, Brenda Cc: Goel, Vijay; Mathew, Roy

Subject:

RE: HNP Supplement to MUR Power Uprate LAR Brenda - As discussed, we can now accept the revised LAR for further review. This is our branch position.

Thanks Swagata From: Mozafari, Brenda Sent: Wednesday, June 29, 2011 9:27 AM To: Som, Swagata

Subject:

FW: HNP Supplement to MUR Power Uprate LAR Can you please send the acceptance review eMail you sent and retracted, I assume that will be the LIC 109 status fir EEEB.

Thanks Brenda 4152020 From: Goel, Vijay Sent: Tuesday, June 28, 2011 6:51 PM To: Mozafari, Brenda; Som, Swagata Cc: Mathew, Roy

Subject:

RE: HNP Supplement to MUR Power Uprate LAR Brenda/Som, I have looked at the revised Electrical Equipment Design descriptions provided in Enclosure 2 of the supplement to the LAR.

Although, the description relating to the iso-phase bus is still somewhat not clear (i.e., further clarifications will be required during RAI process), we can accept the LAR for further review.

Vijay From: Mozafari, Brenda Sent: Monday, June 27, 2011 8:22 AM To: Som, Swagata; Goel, Vijay; Mathew, Roy

Subject:

FW: HNP Supplement to MUR Power Uprate LAR This is the supplemental information for the MUR. Provided the information is robust enough to start your review I will be expecting to be able to send the LIC-109 letter today. Let me know.

Brenda 4152020 1

From: Bass, Kimberly [1]

Sent: Thursday, June 23, 2011 4:56 PM To: Mozafari, Brenda Cc: Caves, John

Subject:

HNP Supplement to MUR Power Uprate LAR

Brenda, I have attached an electronic version of the HNP MUR Power Uprate LAR (Supplement) with the information that was requested during discussions held with the NRC over the last month. The attached version excludes two enclosures (enclosures 5 & 6) because of proprietary information. The original MUR Uprate LAR (submitted April 28, 2011) contains the identical enclosures. No information was changes in those enclosures. A full copy of the revised application has been placed in the mail.

Kim Bass Licensing Engineer Licensing & Regulatory Programs Progress Energy Harris Nuclear Plant 9193622326 kimberly.bass@pgnmail.com 2

Hearing Identifier: NRR_PMDA Email Number: 88 Mail Envelope Properties (AF843158D8D87443918BD3AA953ABF782B68068ED5)

Subject:

RE: HNP Supplement to MUR Power Uprate LAR Sent Date: 6/29/2011 10:10:40 AM Received Date: 6/29/2011 10:10:40 AM From: Som, Swagata Created By: Swagata.Som@nrc.gov Recipients:

"Goel, Vijay" <Vijay.Goel@nrc.gov>

Tracking Status: None "Mathew, Roy" <Roy.Mathew@nrc.gov>

Tracking Status: None "Mozafari, Brenda" <Brenda.Mozafari@nrc.gov>

Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 2264 6/29/2011 10:10:40 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: