MONTHYEARML0923101452009-08-13013 August 2009 Report on the Status of New York State Pollutant Discharge Elimination System Permit - Renewal Project stage: Request ML1009004602010-03-30030 March 2010 Submittal of License Amendment Request, Extension of Completion Time for an Inoperable Diesel Generator - Technical Specification 3.8.1, AC Sources - Operating Project stage: Request ML1011803792010-04-28028 April 2010 Unit No.2 - E-mail from R. Guzman to J. Dosa Acceptance Review for LAR - Inoperable DG 14-Day Completion Time Extension Project stage: Acceptance Review ML1012601662010-05-0606 May 2010 E-mail from R. Guzman to J. Dosa Acceptance Review Revised Questions for License Amendment Requesting 14 Day Completion Time Extension for Inoperable EDG Project stage: Acceptance Review ML1012307272010-05-11011 May 2010 Acceptance Review Determination of License Amendment Request Extension of Completion Time for Inoperable Diesel Generator Project stage: Acceptance Review ML1016004522010-06-0101 June 2010 Submittal of Supplemental Information in Support of License Amendment Extension of Completion Time for an Inoperable Diesel Generator Project stage: Supplement ML1016003832010-06-11011 June 2010 Acceptance Review of License Amendment Request and Supplemental Information Extension of Completion Time for an Inoperable Diesel Generator Project stage: Acceptance Review ML1031302612010-11-0909 November 2010 Request for Additional Information, Extension of Completion Time for Inoperable Diesel Generator, Electrical Engineering Review Project stage: RAI ML1031303272010-12-15015 December 2010 Request for Additional Information Extension of Allowed Outage Time for Inoperable Diesel Generator, Probabilistic Risk Assessment Project stage: RAI ML1101101652010-12-29029 December 2010 Response to NRC Request for Additional Information on License Amendment Request Pursuant to 10 CFR 50.90: Extension of the Completion Time for an Inoperable Diesel Generator Project stage: Response to RAI ML1102502712011-01-14014 January 2011 License Amendment Request Pursuant to 10 CFR 50.90: Extension of the Completion Time for an Inoperable Diesel Generator - Response to NRC Request for Additional Information Project stage: Response to RAI ML1103906562011-02-0808 February 2011 E-mail from R.Guzman to D.Vandeputte - Request for Additional Information Div 3 EDG CT Extension LAR - PRA Review Project stage: RAI ML1105305442011-02-22022 February 2011 E-mail from R. Guzman to D. Vandeputte - Supplemental Request for Additional Information Extension of Completion Time for Inoperable DG Project stage: RAI ML1106704242011-02-25025 February 2011 License Amendment Request Pursuant to 10 CFR 50.90: Extension of the Completion Time for an Inoperable Diesel Generator - Supplemental Information Responding to NRC Follow-up Probabilistic Risk Assessment Review Question Project stage: Supplement ML1107006342011-03-11011 March 2011 E-mail from R. Guzman to S. Som Regarding Supplemental Information from Licensee Regarding License Amendment Request for Completion Time Extension - Division 3 DG Project stage: Other ML1106910202011-03-15015 March 2011 Supplemental Request for Additional Information, Extension of Completion Time for Inoperable Diesel Generator, Electrical Engineering Review Project stage: RAI ML11119A1372011-04-27027 April 2011 License Amendment Request Pursuant to 10 CFR 50.90: Extension of Completion Time for Inoperable Diesel Generator-Supplemental Information Responding to NRC Follow-up Electrical Engineering Branch Review Questions Project stage: Supplement ML1117414582011-06-23023 June 2011 E-mail from R. Guzman to J. Dosa Requesting Supplemental Information Boral Monitoring Program NMP2 Extended Power Uprate LAR Project stage: Approval ML1116603882011-07-11011 July 2011 Request for Additional Information, Extension of Completion Time for Inoperable Diesel Generator, Technical Specifications Review Project stage: RAI ML11214A2142011-07-25025 July 2011 License Amendment Request, Extension of the Completion Time for Inoperable Diesel Generator - Response to NRC Request for Additional Information Project stage: Response to RAI ML1122200812011-08-0909 August 2011 E-mail from Alyse Peterson to Richard Guzman NRC Request for State Consultation for Proposed Amendment Regarding Allowed Outage Time Extension for Division 1 or Division 2 Diesel Generator Inoperable Project stage: Request ML1130400692011-10-31031 October 2011 E-mail from R. Guzman to A. Peterson NRC Response to State Comments for Proposed Amendment Regarding Allowed Outage Time Extension for Division 1 or Division 2 Diesel Generator Inoperable Project stage: Other ML1122001552011-10-31031 October 2011 Issuance of Amendment Regarding Extension of Completion Time for Inoperable Division 1 or Division 2 Diesel Generator Project stage: Approval 2011-01-14
[Table View] |
Text
From:
Guzman, Richard To:
"Dosa, John J"
Subject:
Supplemental information needed for RAI-3 Date:
Thursday, June 23, 2011 11:18:00 PM
- John, The staff has determined that NMPNS has not provided sufficient information to complete its review of the Boral monitoring program (RAI-3). See follow-up question below. If necessary, we can have a call early next week to discuss prior to NMPNS providing its supplemental response on the docket.
- Thanks, Rich Guzman Sr. Project Manager NRR/DORL US NRC 301-415-1030 Richard.Guzman@nrc.gov In its response dated June 13, 2011, the licensee states that, NMPNS will conduct in-situ Boron -10 Areal Density Gauge for Evaluating Racks (BADGER) testing on the Phase 1 Boral Spent fuel racks installed at NMP2 in 2001 on a 10-year frequency, beginning in 2012.
Based on this response, the NRC staff understands that the licensee plans to perform in-situ testing of their Boral spent fuel pool racks installed in 2001; however, the staff notes that NMPNS did not provide information regarding the acceptance criteria for the in-situ test. While the NRC staff views the licensees proposed plan to conduct in-situ testing as acceptable, the staff has determined that the acceptance criteria information is needed to complete its safety evaluation for the Boral monitoring program. Please note that the original RAI-3 in NRC letter dated February 3, 2011, requested the licensee to provide the acceptance criteria for its surveillance/monitoring program. Accordingly, the staff requests NMPNS to provide the acceptance criteria for the in-situ test, including the corrective actions taken if the acceptance criteria is not met.