MONTHYEARML23342A0942024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commission'S Analysis of ADP CR3, Llc'S Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan ML21238A0952021-10-13013 October 2021 Issuance of Amendment No. 259 Approving the ISFSI-Only Emergency Plan, Revision Draft a IR 05000302/20210012021-08-12012 August 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021001 and 05000302/2021002 ML21182A1032021-07-0606 July 2021 Request for Additional Information (RAI) Related to the ISFSI-Only Emergency Plan ML21159A0422021-06-28028 June 2021 VY and CR Indirect License Transfer Package ML21060B4142021-04-12012 April 2021 U.S. Nuclear Regulatory Commission Analysis of Duke Energy Florida, Llc'S Initial Decommissioning Funding Plan for the Crystal River Independent Spent Fuel Storage Installation ML21028A5912021-03-0202 March 2021 Letter to Reid Forwarding Exemption from 10 CFR Part 20, Appendix G, Section Iii.E ML21055A7832021-02-25025 February 2021 Letter to Reid, Change in NRC Staff Project Management for Crystal River Unit 3 Nuclear Generating Plant ML21012A3142021-01-13013 January 2021 Independent Spent Fuel Storage Installation Security Inspection Plan IR 05000302/20200012020-11-19019 November 2020 NRC Inspection Report No. 05000302/2020001, Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, Crystal River, Florida ML20269A2922020-10-0707 October 2020 NRC Form 311 QA Program Approval Revision 10 Related to Crystal River 3 ML20101G5822020-04-10010 April 2020 CR-3 License Transfer SE Corrected Cover Letter ML20069A0232020-04-0101 April 2020 Order Approving Transfer of Licensed Authority from Duke Energy Florida, LLC, to ADP CR3, LLC, and Draft Conforming Administrative License Amendment ML20050D0142020-02-19019 February 2020 NRC Independent Spent Fuel Storage Installation Inspection Report No. 07201035/2020001, Duke Energy Florida, LLC, Crystal River Unit 3, Crystal River, Florida ML20050F7702020-02-14014 February 2020 30-Day Notice of Payment from the City of Tallahassee Trust Fund Non-Qualified Nuclear Decommissioning Trust Fund for Crystal River Unit 3 ML20015A5672020-01-15015 January 2020 Independent Spent Fuel Storage Installation Security Inspection Plan ML20009D0432020-01-10010 January 2020 Letter to Hobbs, Crystal River Unit 3 Nuclear Generating Plant - Corrected Safety Evaluation for Approval of Partial Site Release for Facility Operating License No. DPR-72 ML19339G5092020-01-0202 January 2020 Letter to Hobbs, Crystal River Unit 3 Nuclear Generating Plant - Approval of Partial Site Release for Facility Operating License No. DPR-72 ML19343A8252019-12-0606 December 2019 Letter from Erika Bailey, Oak Ridge Institute for Science and Education, to John Hickman, NRC, Forwarding Independent Confirmatory Survey Summary and Results for the 3,854-Acre Area Partial Site Release at the Crystal River Energy Complex IR 05000302/20190022019-11-20020 November 2019 NRC Inspection Report No. 05000302/2019002 and Independent Spent Fuel Storage Installation Inspection Report No. 07201035/2019002, Duke Energy Florida, LLC, Crystal River Unit 3, Crystal River, Florida ML19317D0932019-10-25025 October 2019 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10 CFR21-0127, Rev. 0, Emd Fuel Injectors - Seized Plunger and Bushing ML19261A0702019-09-19019 September 2019 VEGP U3 Proficiency Watches Prior to Fuel Load ML19177A0802019-06-26026 June 2019 Nuclear Generating Plant (CR-3) - Notification of Revised Post-Shutdown Decommissioning Activities Report (Revised PSDAR) ML19170A1942019-06-14014 June 2019 Application for Order Consenting to Direct Transfer of Control of Licenses and Approving Conforming License Amendment ML19129A1402019-05-15015 May 2019 Letter to Hobbs, Correction to Amendment No. 257 Approving Independent Spent Fuel Storage Installation (ISFSI)-Only Emergency Plan, Revision 1 2024-01-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 May 31,2011 Mr. Frederick Gaske, SHPO & Division Director State Historic Preservation Officer Division of Historical Resources, Department of State 500 South Bronough Street Room 305 Tallahassee, FL 32399-0250
SUBJECT:
CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT LICENSE RENEWAL ENVIRONMENTAL REVIEW (DHR NO. 2009-2164)
Dear Mr. Gaske:
The U.S. Nuclear Regulatory Commission (NRC) is conducting an environmental review of the effects of renewing the Crystal River Unit 3 Nuclear Generating Plant (CR-3) operating license.
CR-3, located in Citrus County, Florida, approximately 80 miles north of Tampa, is operated by Florida Power Corporation. As part of the environmental review, the NRC has prepared a draft Supplemental Environmental Impact Statement (SE/S) to NRC's "Generic Environmental Impact Statement for License Renewal of Nuclear Plants," NUREG-1437. The SEIS includes the results of a site-specific analysis of environmental impacts of license renewal at CR-3, including potential impacts to historic properties. A copy of the draft SEIS is enclosed. Pursuant to 36 CFR 800.8(c), we are requesting your comments on the draft SEIS and on our preliminary conclusions regarding potential impacts to historic properties.
As explained in our letter dated April 10, 2009, the NRC determined that the area of potential effect (APE) for this license renewal action (the undertaking) is the CR-3 power plant site, transmission lines, and immediate environs. This determination is made irrespective of ownership or control of the lands of interest.
NRC technical staff toured the CR-3 site and reviewed historic and archaeological records. The NRC also contacted three Native American Tribes identified as having potential interest in the proposed undertaking. To date, no comments have been received.
In the context of the National Environmental Policy Act of 1969, under which the draft SEIS was prepared, the NRC's preliminary determination is that any impact from continued power plant operations and maintenance activities during the license renewal term on historical and archaeological resources located in the APE would be small. Under the provisions of the National Historic Preservation Act of 1966, the NRC also determined that historic properties would not be adversely affected by this undertaking (the renewal of the CR-3 operating license).
The justification for this conclusion is explained in Section 4.9.6 which begins on page 4-53 in the draft SEIS.
F. Gaske -2 Please note that the period for public comment expires on July 25, 2011. If your office requires additional time, or if there are any other questions regarding this correspondence, please have your representative contact the Environmental Project Manager, Mr. Daniel Doyle, at 301-415-3748 or bye-mail at DanieLDoyle@nrc.gov.
ham, Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302
Enclosure:
As stated cc w/encl: Listserv
F. Gaske - 2 Please note that the period for public comment expires on July 25, 2011. If your office requires additional time, or if there are any other questions regarding this correspondence, please have your representative contact the Environmental Project Manager, Mr. Daniel Doyle, at 301-415-3748 or bye-mail at DanieI.Doyle@nrc.gov.
Sincerely, IRA!
Bo M. Pham, Chief Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302
Enclosure:
As stated cc w/encl: Listserv DISTRIBUTION:
E-MAIL:
PUBLIC BPham RidsNrrDlr Resource RKuntz RidsNrrDlrRpb1 Resource EKeegan RidsNrrDlrRpb2 Resource FSaba RidsNrrDlrRarb Resource ICouret, OPA RidsNrrDlrRasb Resource AJones,OGC RidsNrrDlrRapb Resource MFranke, RII RidsNrrDlrRerb Resource LLake, RII RidsNrrDlrRpob Resource DRich, RII RidsOgcMailCenter Resource TMorrissey, RII RidsOpaMail Resource RReyes, RII RTrojanowski, RII RHannah, RII ADAMS Accession Nos.:
- 1. Letter: ML11140A151