MONTHYEARML0816801502008-08-21021 August 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Hear Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other ML0930202052009-10-29029 October 2009 Email, Request for Additional Information, Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: RAI ML1113800612011-05-25025 May 2011 Closeout of Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Other 2009-10-29
[Table View] |
|
---|
Category:Letter
MONTHYEARGO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report ML23288A0002023-12-0707 December 2023 Issuance of Amendment No. 272 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000397/20230122023-11-20020 November 2023 Commercial Grade Dedication Inspection Report 05000397/2023012 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000397/20230102023-11-0909 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000397/2023010 IR 05000397/20230932023-11-0101 November 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023093 ML23299A2072023-10-26026 October 2023 Biennial Requalification Inspection Request for Information IR 05000397/20230032023-10-25025 October 2023 Integrated Inspection Report 05000397/2023003 IR 05000397/20230112023-10-0404 October 2023 License Renewal Phase 2 Report 05000397/2023011 IR 05000397/20234012023-09-11011 September 2023 Security Baseline Inspection Report 05000397/2023401 GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) ML24032A2182023-09-0101 September 2023 Information Request, Security IR 2024401 GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000397/20230052023-08-22022 August 2023 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2023005) - Mid Year Letter IR 05000397/20230022023-08-0101 August 2023 Integrated Inspection Report 05000397/2023002 GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 ML23206A2442023-07-25025 July 2023 Energy Northwest Columbia Generating Station, Response to Apparent Violation in NRC Inspection Report 05000397/2023092; EA-23-054 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation ML23143A1202023-06-27027 June 2023 Request Number 4ISI-11 to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Regarding Alternate Examination of Reactor Vessel Welds GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance ML23163A2502023-06-12012 June 2023 Summary of Changes and Analysis for Revision 41 of Plant Procedures Manual 13.8.1 Emergency Dose Projection System Operations GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report ML23157A2702023-06-0101 June 2023 4-2022-011 -022 Letter - OI Closure to Licensee IR 05000397/20230922023-06-0101 June 2023 NRC Inspection Report 05000397/2023092 and Preliminary White Finding IR 05000397/20230902023-06-0101 June 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023090 GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report IR 05000397/20230012023-05-0505 May 2023 Integrated Inspection Report 05000397/2023001 - April 26, 2023 GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications IR 05000397/20233012023-05-0101 May 2023 NRC Examination Report 05000397/2023301 GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report ML23110A2642023-04-20020 April 2023 Request for Information License Renewal Phase 2 Inspection GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report ML23013A0812023-03-15015 March 2023 Issuance of Amendment No. 270 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times-RITSTF Initiative 4B GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 2024-01-08
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 25, 2011 Mr. Mark E. Reddemann Chief Executive Officer Energy Northwest P.O. Box 968 (Mail Drop 1023)
Richland, WA 99352-0968
SUBJECT:
COLUMBIA GENERATING STATION - CLOSEOUT OF GENERIC LETTER 2008-01, "MANAGING GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS" (TAC NO. MD7812)
Dear Mr. Reddemann:
On January 11,2008, the U.S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2008-01, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML072910759). The stated purpose of GL 2008-01 was (a) to request addressees to submit information to demonstrate that the subject systems are in compliance with the current licensing and design bases and applicable regulatory requirements, and that suitable design, operational, and testing control measures are in place for maintaining this compliance; and, (b) to collect the requested information to determine if additional regulatory action is required.
In GL 2008-01, the NRC staff requested that licensees provide the following information within 9 months of the date of the GL 2008-01:
(a) A description of the results of evaluations that were performed pursuant to requested actions [specified in the GL 2008-011. This description should provide sufficient information to demonstrate that you are or will be in compliance with the quality assurance criteria in Sections III, V, XI, XVI, and XVII of Appendix B to 10 CFR Part 50 and the licensing basis and operating license as those requirements apply to the subject systems; (b) A description of all corrective actions, including plant, programmatic, procedure, and licensing basis modifications that you determined were necessary to assure compliance with these regulations; and (c) A statement regarding which corrective actions were completed, the schedule for completing the remaining corrective actions, and the basis for that schedule.
By letters dated April 10 and October 8, 2008, and September 21 and December 9, 2009 (ADAMS Accession Nos. ML081080115, ML083010333, ML092730359, and ML093520382, respectively), Energy Northwest, the licensee for Columbia Generating Station, provided its responses to GL 2008-01.
M. Reddemann 2 The NRC staff has reviewed the submitted information and has concluded that the licensee has acceptably addressed each of the NRC staff's request.
Consequently, your GL 2008-01 response is considered closed and no further information or action is requested of you with the exception of any commitments you have made with respect to the GL 2008-01 responses. The NRC staff expects that those associated commitments will be entered into the licensee's tracking system, and controlled consistent with the Nuclear Energy Institute (NEI) guidance document NEI 99-04, "Guidelines for Managing NRC Commitment Changes." In addition, NRC's Region IV staff may decide to perform (and would contact you to schedule) an inspection using Temporary Instruction (TI) 2515/177, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems (NRC Generic Letter 2008-01)" (ADAMS Accession No. ML082950666). The TI 2515/177 is confirmatory in nature in that it directs NRC inspectors to selectively verify that the licensee has implemented or is in the process of acceptably implementing the commitments, modifications, and programmatically controlled actions described in the licensee's responses to GL 2008-01 and the plant-specific information supports a conclusion that subject systems operability is reasonably ensured.
If you have any questions regarding this letter, please feel free to contact me at (301) 415-1476 or e-mail at mohan.thadani@nrc.gov Sincerely, Mohan Thadani, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-397 cc: Distribution via Listserv
M. Reddemann -2 The NRC staff has reviewed the submitted information and has concluded that the licensee has acceptably addressed each of the NRC staff's request.
Consequently, your GL 2008-01 response is considered closed and no further information or action is requested of you with the exception of any commitments you have made with respect to the GL 2008-01 responses. The NRC staff expects that those associated commitments will be entered into the licensee's tracking system, and controlled consistent with the Nuclear Energy Institute (NEI) guidance document NEI 99-04, "Guidelines for Managing NRC Commitment Changes." In addition, NRC's Region IV staff may decide to perform (and would contact you to schedule) an inspection using Temporary Instruction (TI) 2515/177, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems (NRC Generic Letter 2008-01)" (ADAMS Accession No. ML082950666). The TI 2515/177 is confirmatory in nature in that it directs NRC inspectors to selectively verify that the licensee has implemented or is in the process of acceptably implementing the commitments, modifications, and programmatically controlisd actions described in the licensee's responses to GL 2008-01 and the plant-specific information supports a conclusion that subject systems operability is reasonably ensured.
If you have any questions regarding this letter, please feel free to contact me at (301) 415-1476 or e-mail at mohan.thadani@nrc.gov Sincerely, IRA!
Mohan Thadani, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-397 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrLAJBurkhardt Resource LPLIV r/f RidsNrrPMColumbia Resource RidsAcrsAcnw_MaiICTR Resource RidsOgcRp Resource RidsNrrDorlLpl4 Resource RidsRgn4MailCenter Resource RidsNrrDssSrxb Resource ..IMiller, NRR/DSS/SRXB ADAMS Accession No. ML111380061 I OFFICE DORULPL4/PM DORULPL4/LA NRR/DSS/SRXB/BC DORULPL4/BC DORULPL4/PM
- NAME MThadani JBurkhardt AUlses MMarkley MThadani I DATE 5/20/11 5/20/11 5/24/11 5/25/11 5/25/11
=
OFFICIAL RECORD