TAC:ME3949, (Open) | |
MONTHYEARML1016803832010-06-25025 June 2010
[Table View]Summary of Public Meeting with Progress Energy to Discuss Their Proposed Digital Modifications in Support of Fast Cooldown System for Extended Power Uprate Project stage: Meeting ML1109005982011-03-30030 March 2011 Input for Confirmatory LOCA and non-LOCA Models for CR-3 Upcoming EPU Project stage: Other ML1107405412011-03-31031 March 2011 4/21/11 Notice of Forthcoming Meeting with Progress Energy, Crystal River, Unit 3, to Discuss Licensee'S Overall Plans Associated with an EPU Application Project stage: Request ML1107701322011-03-31031 March 2011 Request for Withholding Proprietary Information from Public Disclosure Related to Pre-Extended Power Uprate for the Development of Confirmatory Loss-Of-Coolant (LOCA) and Non-LOCA Models Project stage: Other ML11123A0422011-04-21021 April 2011 4/21/11 Crystal River Unit 3 Meeting Slides Regarding EPU Pre-Application Project stage: Meeting ML11167A1072011-05-0606 May 2011 Request for Additional Information Required for the Development of Confirmatory LOCA and non-LOCA Models for the CR-3 Extended Power Uprate Project stage: Request 3F0511-02, Response to Request for Additional Information Required for the Development of the Confirmatory LOCA and Non-LOCA Models2011-05-0606 May 2011 Response to Request for Additional Information Required for the Development of the Confirmatory LOCA and Non-LOCA Models Project stage: Response to RAI ML11123A0472011-05-12012 May 2011 April 21, 2011, Summary of Public Meeting with Progress Energy on Their Final Pre-Application for Extended Power Uprate Project stage: Meeting ML11172A3432011-06-22022 June 2011 Request for Withholding Proprietary Information from Public Disclosure Related to the Development of Confirmatory Loss-of-Coolant and Non-LOCA Models in Support of Its Upcoming Extended Power Uprate Project stage: Other 2011-04-21 |
ML110900598 | |
Person / Time | |
---|---|
Site: | Crystal River |
Issue date: | 03/30/2011 |
From: | Ken Wilson Progress Energy Florida |
To: | Siva Lingam Plant Licensing Branch II |
Lingam, S NRR/DORL 415-1564 | |
References | |
TAC ME3949 | |
Download: ML110900598 (1) | |
Similar Documents at Crystal River | |
---|---|
Category:E-Mail
MONTHYEARML24191A4232024-07-0303 July 2024
[Table view]RAI2 NRC Response to Fws ESA Crystal River Unit 3 LTP ML24190A1382024-06-18018 June 2024 Supplement to NRC Request for Concurrence with ESA Determinations for Crystal River Unit 3 LTP ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24143A0242024-05-20020 May 2024 Draft EA for Crystal River Unit 3 Opportunity for Flhealth Review and Comment ML24143A0132024-05-20020 May 2024 Achp Response for Crystal River Unit 3 (Achp Project No. 020794) ML24143A0212024-05-20020 May 2024 SHPO Response to Initiate Section 106 Consultation for Crystal River Unit 3 ML24120A3312024-04-24024 April 2024 Seminole Tribe of Florida Email - Initiation ML24054A6462024-02-29029 February 2024 Request for RAI Extension Related to the Crystal River License Termination Plan ML24060A0862024-02-29029 February 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Crystal River Unit 3 Nuclear Generating Plant License Termination Plan (Consultation Code: 2024-0023697) ML24025A0952024-01-24024 January 2024 Clarifications Related to the NRC Staffs EA for Crystal River ML23180A0562023-06-13013 June 2023 ADP-CR3, Crystal River Unit 3 Email from J. Jernigan to Tim Barvitskie Confirmation That Enclosure 22 Radiological Groundwater Characterization Report ML21117A2902021-04-26026 April 2021 Acceptance of License Amendment Request Related to the ISFSI-Only Physical Securityplan ML21096A0432021-04-0505 April 2021 Acceptance of License Amendment Request Related to the ISFSI-Only Emergency Plan ML19344C8052019-11-12012 November 2019 Response from NEIMA Local Community Advisory Board Questionnaire 11-12-2019 H Danenhower ML19310D8602019-10-24024 October 2019 E-Mail Dated October 24, 2019, from Mark Vansicklen, Duke Energy Florida, to John Hickman, NRC, Providing Background Information for the Crystal River Partial Site Release Request ML19344C7872019-10-0303 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-03-2019 D Taylor ML19310D8212019-09-13013 September 2019 E-Mail Dated September 13, 2019, from John Hickman, NRC, to Mark Vansicklen, Duke Energy Florida, Requesting Background Information for the Crystal River Partial Site Release Request ML19130A2082019-05-0808 May 2019 Email - NRC Email to FEMA Dated May 8, 2019: NRC Response to Comment on FEMA Review of Proposed Changes to DBNPS Emergency Plan for Permanently Defueled Condition ML19071A0662019-03-0606 March 2019 E-Mail Dated 3/6/2019 from John Hickman, NRC, to Phyllis Dixon, Duke Energy Florida, LLC, Regarding NRC Acceptance Review of a Request to Revise the ISFSI Only Emergency Plan for Crystal River Unit 3 ML19070A3112019-03-0606 March 2019 Document Title or Accession No. E-Mail Dated 3/6/2019 from John Hickman, NRC, to Phyllis Dixon, Duke Energy Florida, LLC, Regarding NRC Acceptance Review of Partial Site Release Request for Crystal River Unit 3 ML18263A1462018-09-11011 September 2018 NRR E-mail Capture - Logbook Entry: 09/11/2018 a Kemp'S Ridley Sea Turtle (Federal Endangered Species) Carcass Was Recovered from the Crystal River Energy Complex Unit 2 Fossil Unit ML16054A2402015-12-10010 December 2015 E-44108 Attachment 10 E-mail from Steven Edwards (Due Energy) to Don Shaw (Areva) for Brunswick Nuclear Plant, Oconee Nuclear Station, and Robinson Nuclear Plant ML15176A2692015-06-25025 June 2015 NRR E-mail Capture - NRC Acceptance Review for LAR #317 Regarding Changes in Managment Titles ML15043A1042015-02-0505 February 2015 NRR E-mail Capture - Mf Crystal River TAC ML15015A6722015-01-15015 January 2015 NRR E-mail Capture - NRC Acceptance Review for LAR - Application for Order Approving Transfer of License and for Conforming License Amendment ML14344A9992014-12-0909 December 2014 NRR E-mail Capture - Severe Weather Exemption ML14258A7432014-09-0505 September 2014 NRR E-mail Capture - FW: Comparison of Crystal River'S Exemption Secy Paper with Kewaunee'S ML14290A1992014-08-27027 August 2014 NRR E-mail Capture - Draft RAIs for Ep/Eal LAR ML14163A2512014-06-0303 June 2014 NRR E-mail Capture - Request for Additional Information - Exemption for Conducting Annual force-on-force Exercises ML14153A0842014-05-29029 May 2014 NRR E-mail Capture - Logbook Entry: 05/29/2014 ML14153A6912014-05-21021 May 2014 NRR E-mail Capture - Request for Additional Information - Decommissionign Trust Fund Exemption Request ML14132A2052014-05-0909 May 2014 NRR E-mail Capture - MF3089 - Defueled TS Amendment Request for Additrional Information ML14114A2792014-04-10010 April 2014 NRR E-mail Capture - MF3089 Defueled TS Request for Additional Information ML14113A3632014-04-10010 April 2014 NRR E-mail Capture - MF3415/MF2981 RAI on EP Exemptions, EAL Scheme Change and E Plan Amendment ML14118A2872014-02-20020 February 2014 NRR E-mail Capture - Request for Additional Information: Exemptions to the Radiological Emergency Plan Requirements ML14045A0012014-02-12012 February 2014 NRR E-mail Capture - RAI: Adminstrative Controls ML14031A1752014-01-27027 January 2014 NRR E-mail Capture - CR3 Certified Fuel Handler Training and Retraining Program Approval - RAI Request ML14017A0772014-01-16016 January 2014 NRR E-mail Capture - Brunswick 1 and 2, Crystal River Unit 3, Harris Unit 1, and Robinson Unit 2 - Acceptance for Review of License Amendment Request for Cyber Security Plan Implementaion Milestone 8 (TAC Nos. MF3263 - MF3267) ML14027A0332013-12-16016 December 2013 NRR E-mail Capture - Eplan and EAL Scheme Change Request for Additional Information (LAR #315) ML13336A9112013-12-0202 December 2013 NRR E-mail Capture - Periodic Update to the Crystal River 3 Containment Petition ML13198A1422013-07-17017 July 2013 NRR E-mail Capture - Draft RAI - Request to Amend Section 5.0 of the CR-3 Technical Specifications (MF1504) ML13157A2062013-05-31031 May 2013 NRR E-mail Capture - Logbook Entry: 5/31/2013 ML13155A2062013-05-29029 May 2013 NRR E-mail Capture - Petition Status Update - Containment for Crystal River ML13120A0412013-04-29029 April 2013 NRR E-mail Capture - Status Update for Petition on Crystal River 3 ML13095A4002013-04-0505 April 2013 E-mail - Acceptance of Requested Licensing Action Change of Licensee Name ML13052A2402013-02-0808 February 2013 LTR-13-0131 - E-mail Tom Gurdziel Concerns Crystal River, Unit 3 ML13015A2832013-01-14014 January 2013 NRR E-mail Capture - Status of 10 CFR 2.206 Petition Related to Crystal River 3 ML13011A1482013-01-10010 January 2013 NRR E-mail Capture - CR-3 EPU LAR - Additional RAI from Eeeb (ME6527) ML12304A0682012-10-26026 October 2012 NRR E-mail Capture - RAIs Regarding Crystal River 30-day Report for ECCS Model Changes Pursuant to 10 CFR 50.46 Requirements (ME8408) ML12297A3922012-10-23023 October 2012 NRR E-mail Capture - Draft Bypass Test Plan 2024-07-03 |
Text
From: Wilson, Kenneth R [Kenneth.Wilson@pgnmail.com]
Sent: Wednesday, March 30, 2011 12:29 PM To: Lingam, Siva Cc: Thatipamala, Ramakrishna; Herrin, Dennis W.
Subject:
Good Afternoon I re-reviewed the transmittal letter for the confirmatory calc inputs. You are quite correct. The data on the CD is proprietary NOT the list/explanations in Attachment B. Feel free to make it publically available.
Ken
(
Reference:
Progress Energy Letter 3F0311-07, Dated March 15, 2011 - Development of Confirmatory LOCA and non-LOCA Models for the CR-3 Upcoming EPU)
(NRC ADAMS Accession No. ML110900598)