Annual Assessment Letter for Surry Power Station, Units 1 and 2 (IR 05000280-11-001 and 05000281-11-001)
ML110630297
Person / Time
Site: Surry  Dominion icon.png
Issue date: 03/04/2011
From: McCoy G J
NRC/RGN-II/DRP/RPB5
To: Heacock D A
Virginia Electric & Power Co (VEPCO)
Shared Package
ML110630293 List:
References
Download: ML110630297 (5)


See also: IR 05000280/2011001

Text

March 4, 2011

Mr. David President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT: ANNUAL ASSESSMENT LETTER FOR SURRY POWER STATION UNITS 1 AND 2 (REPORT 05000280/2011001 AND 05000281/2011001)

Dear Mr. Heacock:

On February 10, 2011, the NRC completed its end-of-cycle performance review of Surry Power Station Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2010 through December 31, 2010. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRC's assessment of your performance in the Security Cornerstone and its security-related inspection plan. The NRC determined that overall, Surry Power Station Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Surry Power Station Units 1 and 2 during the most recent quarter was within the Licensee Response column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2012. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. We also plan on conducting the non-ROP inspection for: TI 2515/177 - Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal & Containment Spray System.

VEPCO 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at 404-997-4551 with any questions you have regarding this letter.

Sincerely,/RA/ Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos. 50-280, 50-281 License Nos. DPR-32, DPR-37

Enclosure:

Surry Inspection/Activity Plan cc w/encl.: (See page 3)

VEPCO 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at 404-997-4551 with any questions you have regarding this letter.

Sincerely,/RA/ Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos. 50-280, 50-281 License Nos. DPR-32, DPR-37

Enclosure:

Surry Inspection/Activity Plan cc w/encl.: (See page 3)

X PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE ADAMS: X Yes ACCESSION NUMBER:_Letter: ML110630297 Pkg.: ML110630293 _____ X SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE JSD RLC4 by email GJM1 NAME JDodson RClagg GMcCoy DATE 03/01/2011 03/02/2011 03/01/2011 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: S:\DRP\PERIODIC ASSESSMENTS & REPORTS\EOC & MID-CYCLE\2010\END OF CYCLE\INPUTS\RPB5\SURRY\SUR 2010 EOC LETTER.DOCX VEPCO 3 cc w/encl: Gerald T. Bischof Site Vice President Surry Power Station Virginia Electric and Power Company Electronic Mail Distribution B. L. (Sonny) Stanley Director, Nuclear Safety and Licensing Virginia Electric and Power Company Electronic Mail Distribution Lillian M. Cuoco, Esq. Senior Counsel Dominion Resources Services, Inc.

Electronic Mail Distribution Chris L. Funderburk Director, Nuclear Licensing & Operations Support Virginia Electric and Power Company Electronic Mail Distribution Ginger L. Melton Virginia Electric and Power Company Electronic Mail Distribution Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197 Richmond, VA 23209 Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219 Senior Resident Inspector Surry Power Station U.S. Nuclear Regulatory Commission 5850 Hog Island Rd Surry, VA 23883 Michael M. Cline Director Virginia Department of Emergency Services Management Electronic Mail Distribution

VEPCO 4 Letter to David from Gerald J. McCoy dated March 4, 2011

SUBJECT: ANNUAL ASSESSMENT LETTER FOR SURRY POWER STATION UNITS 1 AND 2 (REPORT 05000280/2011001 and 05000281/2011001) Distribution w/encl: C. Evans, RII EICS L. Douglas, RII EICS OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMSurry Resource ROP Reports Institute of Nuclear Power Operations (INPO)