March 4, 2011

Mr. Tom Vice President Southern Nuclear Operating Company, Inc. Vogtle Electric Generating Plant 7821 River Road Waynesboro, GA 30830

SUBJECT: ANNUAL ASSESSMENT LETTER - VOGTLE ELECTRIC GENERATING PLANT (REPORT 05000424/2011001 AND 05000425/2011001)

Dear Mr. Tynan:

On February 8, 2011, the NRC completed its end-of-cycle performance review of Vogtle Electric Generating Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2010, through December 31, 2010. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRC's assessment of your performance in the Security Cornerstone and its security-related inspection plan. The NRC determined that overall, Vogtle Unit 1 and Unit 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Vogtle Unit 1 and Unit 2 during the most recent quarter was within the Licensee Response column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through June 30, 2012. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. We also plan on conducting Operator Licensing Examinations, Triennial 50.59 Modification Inspection, and TI 2515/177, "Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal, And Containment Spray Systems (NRC Generic Letter 2008-01)."

SNC 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 997-4521 with any questions you may have regarding this letter or the inspection plan.

Sincerely,/RA/ Scott M. Shaeffer, Chief Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-424, 50-425 License Nos.: NPF-68 and NPF-81

Enclosure:

Vogtle Inspection/Activity Plan (01/01/2011 - 06/30/2012) cc w/encl: (See page 3)

SNC 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 997-4521 with any questions you may have regarding this letter or the inspection plan.

Sincerely,/RA/ Scott M. Shaeffer, Chief Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-424, 50-425 License Nos.: NPF-68 and NPF-81

Enclosure:

Vogtle Inspection/Activity Plan (01/01/2011 - 06/30/2012) cc w/encl: (See page 3)

X PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE ADAMS: G Yes ACCESSION NUMBER:__ML110630054 __ G SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE SMS /RA for/ SDR /RA/ SMS /RA/ NAME TLighty SRose SShaeffer DATE 03/02/2011 03/01/2011 03/03/2011 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: G:\DRPII\RPB2\VOGTLE\MID & END CYCLE\2010\EOC 2010\VOGTLE EOC ASSESSMENT LTR 2010.DOC SNC 3 cc w/encl: Managing Attorney and Compliance Officer Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution B. D. McKinney, Jr. Regulatory Response Manager Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Hickox, T. Mark Vogtle Electric Generating Plant Electronic Mail Distribution N. J. Stringfellow Licensing Manager Southern Nuclear Operating Company, Inc. Electronic Mail Distribution T. D. Honeycutt Regulatory Response Supervisor Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc. Electronic Mail Distribution L. Mike Stinson Vice President Fleet Operations Support Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Paula Marino Vice President Engineering Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Bob Masse Resident Manager Vogtle Electric Generating Plant Oglethorpe Power Corporation Electronic Mail Distribution Moanica Caston Vice President and General Counsel Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Chris Clark Commissioner Georgia Department of Natural Resources Electronic Mail Distribution Lee Foley Manager of Contracts Generation Oglethorpe Power Corporation Electronic Mail Distribution F. Allen Barnes Director Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution James A. Sommerville Program Coordination Branch Chief Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Ted V. Jackson Emergency Response and Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution cc w/encl. continued next page

SNC 4 cc w/encl. continued: Mr. Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia Electronic Mail Distribution Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Electronic Mail Distribution Office of the Attorney General Electronic Mail Distribution Office of the County Commissioner Burke County Commission Electronic Mail Distribution Arthur H. Domby, Esq. Troutman Sanders Electronic Mail Distribution Director Consumers' Utility Counsel Division Govenor's Office of Consumer Affairs 2 M. L. King, Jr. Drive Plaza Level East; Suite 356 Atlanta, GA 30334-4600 Susan E. Jenkins Director, Division of Waste Management Bureau of Land and Waste Management S.C. Department of Health and Environmental Control Electronic Mail Distribution SNC 5 Letter to Tom from Scott M. Shaeffer dated March 4, 2011

SUBJECT: ANNUAL ASSESSMENT LETTER - VOGTLE ELECTRIC GENERATING PLANT (NRC INSPECTION REPORT 05000424/2011001 AND 05000425/2011001) Distribution w/encl: C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMVogtle Resource ROP Reports Institute of Nuclear Power Operations (INPO)