Revised Review Schedule Regarding the Application from Prairie Island Nuclear Generating Plant, Units 1 and 2
ML102940375
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 10/22/2010
From: David Wrona
License Renewal Projects Branch 2
To: Schimmel M
Northern States Power Co
Elaine Keegan (301) 415-8517
References
TAC MD8528, TAC MD8529
Download: ML102940375 (5)


Text

Mr. Mark A. Schimmel Site Vice President UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 22, 2010 Prairie Island Nuclear Generating Plant Northern States Power - Minnesota 1717 Wakonade Drive East Welch, MN 55089

SUBJECT:

REVISED REVIEW SCHEDULE REGARDING THE APPLICATION FROM PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 (TAC NOS. MD8528 AND MD8529)

Dear Mr. Schimmel:

By letter dated April 11,2008, Nuclear Management Company, LLC, now known as Northern States Power Company, Minnesota, submitted an application pursuant to Title 10 of the Code of the Federal Regulations Part 54, to renew the operating license for Prairie Island Nuclear Generating Plant, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff).

The schedule for publishing the final Supplemental Environmental Impact Statement is being extended from October 22, 2010, to February 4, 2011. The NRC has several ongoing license renewal reviews on similar schedules, and any delay in resolving technical issues in one project affects review schedules of other projects. Therefore, the schedule is being extended due to staff scheduling conflicts and to allow sufficient time to fully meet the terms of the Memorandum of Understanding with the Prairie Island Indian Community.

The extension on the environment review is not expected to adversely impact the schedule for a decision on license renewal since the staff is evaluating the effect of recent operating experience issues as part of the safety review. Staff is currently reviewing your annual update to the license renewal application which included additional information on the Buried Piping and Tank Inspection Program, and Class 1 Small-Bore Piping Program.

The schedule in the enclosure was discussed with Mr. Gene Eckholt of your staff. If you have any questions, contact Ms. Elaine Keegan by telephone at 301-415-8517 or by email at Elaine.Keegan@nrc.gov.

Docket Nos. 50-282 and 50-306

Enclosure:

As stated cc w/encl: Distribution via Listserv Sincerely, David J. Wron,Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation

Prairie Island Nuclear Generating Plant LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestones Schedule SER -Issued 10/22/2009 Draft Supplemental Environmental Impact Statement (SEIS) 11/1 6/2009 Issued EPA FRN Published - Availability 1 Comment on draft SEIS 11/27/2009 Public Meeting - draft SEIS 12/16/2009 ACRS Full Committee Meeting on SER 12/03/2009 End of draft SEIS Comment Period 01/30/2010 Send Letter to Prairie Island Indian Community (PIIC) per MOU 10/29/2010 Receive comments from PIIC 11/23/2010 Final SEIS - Issued 02/04/2011 EPA FRN Published - Availability of Final SEIS 02/11/2011 Receive Input on Unresolved Technical Issues TBD Supplemental Safety Evaluation Report TBD Commission Decision TBD Actual 10/16/2009 11/16/2009 11/27/2009 12/16/2009 12/03/2009 01/30/2010 ENCLOSURE

ML102940375 OFFICE LADLR PM:DLR:RPB2 NAME IKing EKeegan DATE 10/21/10 10/22/10 Sincerely, IRAJ David J. Wrona, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation BC:DLR:RPB2 DD:DLR BC:DLR:RPB2 DWrona BHolian DWrona 10/22/10 10/22/10 10/22/10

Letter to Mark A. Schimmel from David J. Wrona dated October 22, 2010

SUBJECT:

REVISED REVIEW SCHEDULE REGARDING THE APPLICATION FROM PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 (TAC NOS. MD8528 AND MD8529)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RidsOpaMailResource RPlasse EKeegan TWengert VMitlyng, Rill KStoedter, Rill PZurawski, Rill ICouret, OPA BMizuno, OGC RShane OCA