Revised Review Schedule Regarding the Application from Prairie Island Nuclear Generating Plant, Units 1 and 2
ML101480951
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 09/01/2010
From: David Wrona
License Renewal Projects Branch 2
To: Schimmel M
Northern States Power Co
Keegan E NMSS/SFPO (301) 415-8517
References
TAC MD8528, TAC MD8529
Download: ML101480951 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 1, 2010 Mr. Mark A. Schimmel Site Vice President Prairie Island Nuclear Generating Plant Northem States Power - Minnesota 1717 Wakonade Drive East Welch, MN 55089

SUBJECT:

REVISED REVIEW SCHEDULE REGARDING THE APPLICATION FROM PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 (TAC NOS. MD8528 AND MD8529)

Dear Mr. Schimmel:

By letter dated April 11, 2008, Nuclear Management Company, LLC, now known as Northem States Power Company, Minnesota, submitted an application pursuant to Title 10 of the Code of the Federal Regulations Part 54, to renew the operating license for Prairie Island Nuclear Generating Plant, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff).

The schedule for publishing the final Supplemental Environmental Impact Statement (SEIS) is being extended from September 24, 2010 to October 22, 2010. During staff's review of public comments of the draft SEIS, an issue was identified which resulted in a request for additional information.

The schedule in the enclosure was discussed with Mr. Gene Eckholt of your staff. If you have any questions, contact Ms. Elaine Keegan by telephone at 301-415-8517 or by email at Elaine.Keegan@nrc.gov.

Sincerely,

() J 9-ttl------

David J. Wrona, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306

Enclosure:

As stated cc w/encl: Distribution via Listserv

Prairie Island Nuclear Generating Plant LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestones Schedule Actual SER-Issued 10/22/2009 10/16/2009 Draft Supplemental Environmental Impact Statement (SEIS)

Issued 11/16/2009 11/16/2009 EPA FRN Published - Availability / Comment on draft SEIS 11/27/2009 11/27/2009 Public Meeting - draft SEIS 12/16/2009 12/16/2009 ACRS Full Committee Meeting on SER 12/03/2009 12/03/2009 End of draft SEIS Comment Period 01/30/2010 01/30/2010 Final SEIS - Issued 10/22/2010 EPA FRN Published - Availability of Final SEIS 10/29/2010 Commission Decision (Hearing Pending)

TBD ENCLOSURE

M L 101480951 OFFICE PM:DLR:RPB2 LA:DLR BC:DLR:RPB2 NAME EKeegan IKing DWrona DATE 08/31/10 08/18/10 09/01/10

Letter to Mark A. Schimmel from David J. Wrona dated September 1, 2010

SUBJECT:

REVISED REVIEW SCHEDULE REGARDING THE APPLICATION FROM PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 (TAC NOS. MD8528 AND MD8529)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RidsOpaMailResource RPlasse EKeegan TWengert VMitlyng, Rill KStoedter, Rill PZurawski, Rill ICouret,OPA BMizuno, OGC RShaneOCA