MONTHYEARTMI-10-079, Submittal of Relief Requests Associated with the Fourth Inservice Inspection Interval2010-08-10010 August 2010 Submittal of Relief Requests Associated with the Fourth Inservice Inspection Interval Project stage: Request ML1026402792010-09-21021 September 2010 Non-Acceptance, with Opportunity to Supplement, for TMI-1 RR-I4R-02, TAC No. ME4519 Project stage: Other ML1026406132010-09-23023 September 2010 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Relief l4R-02, Fourth Inservice Inspection Interval, Alternate Risk Informed Selection and Examination Criteria for Project stage: Acceptance Review TMI-10-101, Three Mile, Unit 1, Supplemental Information Request - Fourth Inservice Inspection (ISI) Interval Relief Request I4R-022010-10-0808 October 2010 Three Mile, Unit 1, Supplemental Information Request - Fourth Inservice Inspection (ISI) Interval Relief Request I4R-02 Project stage: Supplement ML1029303472010-10-21021 October 2010 Acceptance of Requested Licensing Action Request for Relief l4R-02, Fourth Inservice Inspection Interval, Alternate Risk Informed Selection and Examination Criteria for Pressure Retaining Welds Project stage: Acceptance Review TMI-10-111, Submittal of Relief Requests Associated with the Fourth Inservice Inspection (ISI) Interval - Relief Request I4R-012010-10-29029 October 2010 Submittal of Relief Requests Associated with the Fourth Inservice Inspection (ISI) Interval - Relief Request I4R-01 Project stage: Request ML1034405552010-12-10010 December 2010 Electronic Transmission, Draft Request for Additional Information Regarding Relief Request 14R-02 Project stage: Draft RAI ML1034001582010-12-20020 December 2010 Request for Additional Information Regarding Fourth Inservice Inspection Interval Relief Requests l4R-02 and l4R-04 Project stage: RAI TMI-11-007, Response to Request for Additional Information Concerning Relief Requests Associated with the Fourth Inservice Inspection Interval2011-01-25025 January 2011 Response to Request for Additional Information Concerning Relief Requests Associated with the Fourth Inservice Inspection Interval Project stage: Response to RAI ML1111804942011-04-28028 April 2011 Electronic Transmission, Draft Request for Additional Information Regarding Fourth Interval Inservice Inspection Relief Request I4R-04 Project stage: Draft RAI ML1111806402011-05-0606 May 2011 Request for Additional Information Regarding Fourth Inservice Inspection Interval Relief Request I4R-04 Project stage: RAI TMI-11-084, Response to Request for Additional Information Concerning Relief Requests Associated with the Fourth Inservice Inspection (ISI) Interval2011-05-11011 May 2011 Response to Request for Additional Information Concerning Relief Requests Associated with the Fourth Inservice Inspection (ISI) Interval Project stage: Response to RAI ML1117304752011-07-20020 July 2011 Fourth Inservice Inspection Interval Relief Requests I4R-02, I 4R-03, I4R-04, I4R-05, and I4R-06 Project stage: Other 2010-09-21
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24011A2332024-01-11011 January 2024 Request for Additional Information - License Amendment Request (ML23058A064) (EPID L-2023-LLA-0026 - Three Mile Island, U2: Amendment Historic and Cultural Resources) ML23187A0202023-06-29029 June 2023 TMI Unit 2 RAI Related to the Amended Post-Shutdown Decommissioning Activities Report ML23135A3992023-05-12012 May 2023 (External_Sender) Section 106 Consultation - NRC NHPA for Three Mile Island Unit 2 ML23159A1642023-05-11011 May 2023 Email TMI-2 Pol Am. 67 SE Minor Discrepancies ML23107A2232023-04-14014 April 2023 Response Re State Consultation-TMI-2 Solutions - Draft EA Fonsi Criticality Exemption Request ML23094A1482023-03-30030 March 2023 TMI-2 TS 6.0 Draft Wording Agreement ML23090A2142023-03-30030 March 2023 Asnyder, NRC Email from Tdevik, Energysolutions, Three Mile Island, Unit 2 -Response Regarding MC&A TS Change, Modification ML23094A0602023-03-30030 March 2023 TMI-2 Response on Draft TS Wording ML23068A4682023-03-0909 March 2023 Response Re State Consultation - License Amendment Request TMI-2 Solutions - Update Technical Specifications and Remove Certain License Conditions Applicable to Pdms ML23057A0062023-02-24024 February 2023 State Consultation - License Amendment Request TMI-2 Solutions - Update Technical Specifications and Remove Certain License Conditions Applicable to Pdms ML23051A0412023-02-15015 February 2023 Email from TMI-2 Solutions Regarding Commitment Date, Dated 02/15/2023 ML22364A1942022-12-30030 December 2022 Email Mitigation for Hydrogen Concerns Commitment, Dated December 30, 2022 ML22357A0142022-12-22022 December 2022 NRC Request for Additional Information Related to the TMI-2 Pdms Transition License Amendment Request ML22321A0072022-11-16016 November 2022 Material Control and Accounting RAI Response Clarification Call Docket No 50-320 ML23069A1582022-09-22022 September 2022 NRC Response TMI-2 Solutions Exemption Question ML22214A0482022-08-0101 August 2022 TMI-2 Response: License Amendment Request TMI-2 Solutions Physical Materials Security Plan - Revised Modified License Condition 2.C(2) ML22208A0492022-07-21021 July 2022 State Consultation Response: License Amendment Request TMI-2 Solutions Physical Materials Security Plan ML22199A2762022-07-18018 July 2022 E-mail from A. Snyder, NRC, to B. Werner, PDEP, Regarding State Consultation Proposed Conforming Amendment Related to Proposed Exemption Request from Certain Record Retention Requirements ML22199A2772022-07-15015 July 2022 E-mail Attachment: Federal Register Notice - Volume 87 ML22189A2032022-07-0808 July 2022 E-mail from A. Snyder, NRC, to B. Werner, PA Department of Environment Protection - Three Mile Island, Unit 2 - State Consultation - License Amendment Request TMI-2 Solutions Physical Materials Security Plan ML22189A2042022-06-28028 June 2022 NRC-2022-0131-0001_Content - Federal Register Vol. 87, No. 123 ML22143A8902022-05-23023 May 2022 Request for Additional information- TMI-1 ISFSI Only Physical Security License Amendment Request ML22131A1382022-05-10010 May 2022 E-mail from T. Devik, Energysolutions TMI-2, to A. Snyder, NRC, Physical Security Plan May 9 Submittal Typo Correction ML22125A0162022-05-0303 May 2022 Email from T Devik to a Snyder: Three Mile Island 2 - Security Plan Proposed Revision License Condition 2.C.(2) (EPID: L-2021-LLA-0103) Proposed License Condition - May 3, 2022 Response Courtesy Copy ML22125A0102022-05-0303 May 2022 Proposed Action- Proposed Fonsi for TMI-1 Exemption Request from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) Notification of Commonwealth of Pennsylvania Response ML22125A0092022-05-0303 May 2022 Proposed Action- Proposed Fonsi for TMI-1 Exemption Request from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) Notification of Commonwealth of Pennsylvania ML22125A0132022-04-28028 April 2022 Security Plan Proposed Revision License Condition 2.C.(2) (EPID: L-2021-LLA-0103) Proposed License Condition - Partial Response ML22125A0122022-04-28028 April 2022 Clarification RAI Partial Response Email from C Smith to a Snyder ML22110A0212022-04-19019 April 2022 Security Plan Proposed Revision License Condition 2.C.(2) (EPID: L-2021-LLA-0103) Proposed License Condition ML22110A0202022-04-19019 April 2022 Unit 1 Request for Additional Information ML22108A1762022-04-14014 April 2022 E-mail: Proposed Order Conditions for In-Direct Transfer of Licenses Held by Energysolutions, LLC (Zion, TMI Unit-2, La Crosse Boiling Water Reactor, Kewaunee, Energysolutions Radioactive Materials License, and Energysolutions Export Licens ML22102A3062022-03-31031 March 2022 Email from T. Divik, Energy Solutions, to A. Snyder Clarification of Security License Condition Amendment Request ML22094A1812022-03-22022 March 2022 Licensee High Confidence Dates for Submittals ML22108A1022022-03-18018 March 2022 Email from A. Snyder, NRC to G. Van Noordennen, Energy Solutions, Clarification Request - September 21, 2021 Supplement- TMI-2 Physical Security Plan LAR ML22090A0142022-03-17017 March 2022 TMI, Unit 1 - Commonwealth of PA Response to Request for Consultation on the Proposed Revision to the License and the Permanently Defueled Technical Specifications to Align to the Requirements for Permanent Removal of Spent Fuel from the Sp ML22070A1202022-03-10010 March 2022 E-mail from S. Acker, PADEP, to A. Snyder, NRC - Three Mile Island Unit 1, State Consultation - License Amendment Request TMI-1 in Support of the ISFSI Only Security Plan License Amendment Request ML22068A1792022-03-0909 March 2022 Email from a Snyder to Acker State Consultation- License Amendment Request TMI-1 in Support of the ISFSI Only Emergency Plan and Emergency Action Level Scheme ML22068A1672022-03-0909 March 2022 Email from a Snyder to Acker State Consultation - License Amendment Request TMI-1 in Support of the ISFSI Only Security Plan License ML22068A1462022-03-0909 March 2022 Email from a Snyder to Acker Three Mile Island Unit 1, State Consultation- License Amendment Request TMI-1 in Support of the ISFSI Only Tech Spec License Amendment Request ML22090A0232022-03-0909 March 2022 Email from A. Snyder, NRC to Craig Smith, Constellation Energy Generation, License Amendment Request - Proposed ISFSI-Only Technical Specifications, Dated March 9, 2022 ML22047A2392022-02-16016 February 2022 E-mail from D. Kenney to A. Snyder Dated 2/16/2022 TMI Unit 1 Typo Correction to February 8, 2022 Submittal ML22038A9352022-02-0707 February 2022 TMI-2 Pdms LAR Email Dated 2/7/2022 from T. Smith, NRC to G. Van Noordennen ML22034A6702022-02-0303 February 2022 LTR-22-0020 Eric Epstein, E-mail Follow-up on Decommissioning and Tax Question from December 8, 2021 on TMI Cleanup Funding, Docket Id NRC-2021-0230 - Region I Response ML22343A1612021-11-0909 November 2021 Shpo Email 11-9-2021 Alowery to Gvannoordennen and Hpell ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21230A3812021-08-18018 August 2021 TMI-1 ISFSI-Only Security Plan License Amendment Request ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application 2024-01-11
[Table view] |
Text
From: Bamford, Peter Sent: Tuesday, September 21, 2010 11:09 AM To: 'thomas.loomis@exeloncorp.com' Cc: 'david.helker@exeloncorp.com'
Subject:
Non-Acceptance, With Oppoutunity to Supplement, for TMI-1 RR-I4R-02, TAC ME4519 By letter dated August 10, 2010, (Agencywide Documents Access and Management System (ADAMS) Accession Number ML102290162), Exelon Generation Company, LLC (Exelon) submitted a package of six relief requests associated with the fourth inservice inspection (ISI) interval for Three Mile Island Nuclear Station, Unit 1 (TMI-1). Relief Request I4R-02 requests approval for alternate risk-informed selection and examination criteria for certain pressure retaining piping welds in lieu of meeting requirements specified in the code of record for the TMI-1 fourth ISI interval. The fourth interval program is based on the American Society of Mechanical Engineers, Boiler and Pressure Vessel Code,Section XI, 2004 Edition, no Addenda. The purpose of this email is to provide the draft results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the request has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your submittal and concluded that the following information is necessary to enable the staff to make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment.
Relief Request I4R-02 neither discusses the technical adequacy of its fire, seismic, and external events probabilistic risk assessment (PRA) nor provides a justification that these hazard groups are insignificant to the applications risk-informed decision making, and therefore is not demonstrated to be consistent with Regulatory Guide (RG) 1.200, revision 2 and RG 1.174, revision 1, both of which are referenced in the application.
Without this information, the NRC staff does not have sufficient information to begin its review.
Relief Request I4R-02 must be modified to provide a discussion confirming that either RG 1.200, revision 2, guidelines on the technical adequacy have been evaluated and satisfied, or provide a justification that these hazard groups are insignificant to the applications risk-informed decision making consistent with RG 1.174, revision 1, guidelines.
In order to make the submittal complete, the NRC staff requests that Exelon supplement the submittal by providing the information requested above. This will enable the NRC staff to begin its detailed technical review. If information responsive to the NRC staffs request is not received by October 13, 2010, the request will not be accepted for review pursuant to 10 CFR 2.101, and the NRC will cease its review activities associated with Relief Request I4R-02. Please note that the acceptance review status of the relief requests other than I4R-02, contained in the August 10, 2010, submittal, have been communicated to you separately.
Please confirm your availability for a teleconference to discuss this issue on the afternoon of Thursday, September 23, 2010. Please call me at the number listed below with that information and/or if you have any questions regarding this matter.
The image cannot be display ed. Your computer may not hav e enough memory to open the image, or the image may hav e been corrupted. Restart y our computer, and then open the file again. If the red x still appears, y ou may hav e to delete the image and then insert it again.
Peter Bamford NRR/DORL/LPL 1-2 Limerick & TMI-1 Project Manager 301-415-2833