Report 22, Inspection/Activity Plan
ML102440757
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 09/01/2010
From:
NRC/RGN-II
To:
Duke Energy Carolinas
Shared Package
ML102440748 List:
References
Download: ML102440757 (5)


Text

Inspection / Activity Plan Page 1 of 1 09/01/2010 13:28:31 Report 22 09/01/2010 - 12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site McGuire PB1-SUP

- FOLLOW-UP INSP FOR >3 SL-IV VIOLATIONS 2

1, 2 IP Follow Up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in the S 92723 09/20/2010 09/24/2010 EB1-MODS

- MODIFICATIONS - 10CFR50.59 4

1, 2 IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 08/30/2010 09/03/2010 1, 2 IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 09/13/2010 09/17/2010 PB7-PI&R

- PROBLEM IDENTIFICATION AND RESOLUTION 5

1, 2 IP Identification and Resolution of Problems 71152B 10/04/2010 10/08/2010 1, 2 IP Identification and Resolution of Problems 71152B 10/18/2010 10/22/2010 ISFSI

- ISFSI NAC MAGNASTOR DRY RUN 5

1, 2 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 11/15/2010 11/19/2010 EB3ISI

- UNIT 2 INSERVICE INSPECTION 1

2 IP Inservice Inspection Activities - PWR 7111108P 03/14/2011 03/18/2011 OL EXAM

- INITIAL EXAM PREP 4

1 MCGUIRE/MAY 2011 EXAM AT POWER FACILITIES V23350 05/23/2011 05/27/2011 ISFSI

- ISFSI NAC MAGNASTOR FIRST CAMPAIGN 3

1, 2 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 06/13/2011 06/17/2011 OL EXAM

- INITIAL EXAM - WEEK 1 4

1 MCGUIRE/MAY 2011 EXAM AT POWER FACILITIES V23350 06/13/2011 06/17/2011 OL EXAM

- INITIAL EXAM - WEEK 2 4

1 MCGUIRE/MAY 2011 EXAM AT POWER FACILITIES V23350 06/20/2011 06/24/2011 TI-177

- TI-177 GAS INTRUSION 3

1, 2 IP Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 2515/177 06/27/2011 07/01/2011 PSB1-RP

- RP PUBLIC RADIATION PROTECTION INSP 4

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 06/27/2011 07/01/2011 1, 2 IP Radiation Monitoring Instrumentation 71124.05 06/27/2011 07/01/2011 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 06/27/2011 07/01/2011 1, 2 IP Radiological Environmental Monitoring Program 71124.07 06/27/2011 07/01/2011 1, 2 IP Performance Indicator Verification 71151 06/27/2011 07/01/2011 PSB1-TI

- TI-179 NSTS VERIFICATION 3

1, 2 IP Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 2515/179 06/27/2011 07/01/2011 PSB1EP

- EMERGENCY PREPAREDNESS EXERCISE 3

1, 2 IP Exercise Evaluation 7111401 08/08/2011 08/12/2011 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 08/08/2011 08/12/2011 1, 2 IP Performance Indicator Verification 71151 08/08/2011 08/12/2011 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.