UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 1, 2010 Mr. Thomas D. Gatlin Vice President South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station P.O. Box 88 Jenkinsville, SC 29065

SUBJECT:

MID-CYCLE ASSESSMENT LETTER AND INSPECTION PLAN - VIRGIL C.

SUMMER NUCLEAR STATION

Dear Mr. Gatlin:

On August 12, 2010, the NRC staff completed its performance review of the Virgil C. Summer Nuclear Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from July 1, 2009, through June 30, 2010. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Information" will include the security cornerstone review and resultant inspection plan.

Plant performance for the most recent quarter at Virgil C. Summer Nuclear Station was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. We also plan on conducting non-ROP inspections which include: TI 2515/179 - National Source Tracking System Verification; TI 2515/177 - Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal & Containment Spray System; and TI 2515/172 - Reactor Coolant System Dissimilar Metal Butt Welds.

The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2011. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of the inspectors arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end of cycle review.

SCE&G 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 404-997-4551 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket No.: 50-395 License No.: NPF-12

Enclosure:

V.C. Summer Inspection / Activity Plan (09/01/2010 - 12/31/2011) cc w/encl: (See next page)

__PKG: ML102440296______________ X SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE JSD GMcCoy for GJM1 NAME JDodson DArnett GMcCoy DATE 08/31/2010 09/01/2010 09/01/2010 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO SCE&G 3 Senior Resident Inspector cc. w/encl. Virgil C. Summer Nuclear Station J. B. Archie U.S. NRC Senior Vice President 576 Stairway Road Nuclear Operations Jenkinsville, SC 29065 South Carolina Electric & Gas Company Electronic Mail Distribution R. J. White Nuclear Coordinator Kathryn M. Sutton, Esq. S.C. Public Service Authority Mail Code 802 Morgan, Lewis & Bockius LLP Electronic Mail Distribution Electronic Mail Distribution Robin R. Haselden Susan E. Jenkins General Manager Director, Division of Waste Management Organizational Development &

Bureau of Land and Waste Management Effectiveness S.C. Department of Health and South Carolina Electric & Gas Company Environmental Control Electronic Mail Distribution Electronic Mail Distribution George A. Lippard, III Mark Yeager General Manager Division of Radioactive Waste Mgmt. Nuclear Plant Operations S.C. Department of Health and South Carolina Electric & Gas Company Environmental Control Electronic Mail Distribution Electronic Mail Distribution Robert L. Justice Andy T. Barbee Manager Director Nuclear Operations Nuclear Training South Carolina Electric & Gas Company South Carolina Electric & Gas Company Electronic Mail Distribution Electronic Mail Distribution Bruce L. Thompson Manager Nuclear Licensing (Mail Code 830)

South Carolina Electric & Gas Company Electronic Mail Distribution Robert M. Fowlkes General Manager Engineering Services South Carolina Electric & Gas Company Electronic Mail Distribution David A. Lavigne General Manager Operational Readiness South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station P.O. Box 88 Jenkinsville, SC 29065

SCE&G 4 Letter to Thomas D. Gatlin from Gerald J. McCoy dated September 1, 2010

SUBJECT:

MID-CYCLE ASSESSMENT LETTER AND INSPECTION PLAN - VIRGIL C.

SUMMER NUCLEAR STATION Distribution w/encl:

C. Evans, RII EICS OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMSummer Resource ROPReports Institute of Nuclear Power Operations (INPO)