ML101540469
Letter Sequence Request | |
---|---|
TAC:ME1429, (Open) | |
Initiation Administration Questions Answers | |
MONTHYEARW3F1-2009-0026, Request for Relief from ASME Section XI Volumetric Examination Requirements - Second 10-Year Interval2009-06-0101 June 2009
[Table View]Request for Relief from ASME Section XI Volumetric Examination Requirements - Second 10-Year Interval Project stage: Request ML0916602952009-06-15015 June 2009 Acceptance Review Email, Requests for Relief from ASME Section XI Volumetric Examination Requirements - Second 10-Year ISI Interval Project stage: Acceptance Review ML0918300032009-07-23023 July 2009 Request for Additional Information (Rai), Relief Request Nos. WF3-ISI-007 to WF3-ISI-014 from ASME Code, Section XI Volumetric Examination Requirements - Second 10-Year Interval Project stage: RAI ML1015404782009-11-0303 November 2009 Phased Array Ultrasonic Examination Record Project stage: Other W3F1-2009-0061, Response to NRC Request for Additional Information Re Request for Relief from ASME Section XI Volumetric Exam Requirements - Second 10-Year Inservice Inspection Interval2009-11-0606 November 2009 Response to NRC Request for Additional Information Re Request for Relief from ASME Section XI Volumetric Exam Requirements - Second 10-Year Inservice Inspection Interval Project stage: Response to RAI ML1000601722010-01-0606 January 2010 Email, RAI, Relief Request Nos. WF3-ISI-007 to WF3-ISI-014 from ASME Code, Section XI Volumetric Examination Requirements - Second 10-Year Interval (TAC Nos. ME1426 to ME1433) Project stage: RAI W3F1-2010-0014, Response to NRC Request for Additional Information Dated January 6, 2010 Waterford 3 Steam Electric Station, Unit 3 - Requests for Relief from ASME Section XI Volumetric Examination Requirements - Second 10-Year Inservice Inspection I2010-02-0808 February 2010 Response to NRC Request for Additional Information Dated January 6, 2010 Waterford 3 Steam Electric Station, Unit 3 - Requests for Relief from ASME Section XI Volumetric Examination Requirements - Second 10-Year Inservice Inspection Interva Project stage: Response to RAI ML1008203552010-03-23023 March 2010 Request for Additional Information Round 2, Relief Request Nos. WF3-ISI-007 to WF3-ISI-014 from ASME Code, Section XI Volumetric Examination Requirements - Second 10-Year Interval Project stage: RAI W3F1-2010-0033, Response to Request for Additional Information on Relief WF3-ISI-007, 008, 009, 010, 011, 012, 013, and 0142010-04-29029 April 2010 Response to Request for Additional Information on Relief WF3-ISI-007, 008, 009, 010, 011, 012, 013, and 014 Project stage: Response to RAI ML1015404692010-06-0303 June 2010 E-mail, Additional Information on Relief Request WF3-ISI-010 Project stage: Request ML1015905742010-06-30030 June 2010 Relief Request Nos. WF3-ISI-007 to WF3-ISI-014 from ASME Code, Section XI Volumetric Examination Requirements - Second 10-Year Interval Project stage: Other ML13123A4632013-05-0303 May 2013 E-mail from R.Guzman to W.Lobo Acceptance Review Determination - Request for Alternative - Risk Based Inservice Inspection Project stage: Acceptance Review 2010-01-06 |
ML101540469 | |
Person / Time | |
---|---|
Site: | Waterford ![]() |
Issue date: | 06/03/2010 |
From: | Joseph E Pollock Entergy Operations |
To: | Kalyanam K, Carol Nove NRC/NRR/DCI, Plant Licensing Branch IV |
Kalyanam N, NRR/DORL/LPL4, 415-1480 | |
Shared Package | |
ML101540459 | List: |
References | |
TAC ME1429, WF3-ISI-010 | |
Download: ML101540469 (2) | |
Similar Documents at Waterford | |
---|---|
Category:E-Mail
MONTHYEARML23348A1222023-12-14014 December 2023
[Table view]NRR E-mail Capture - Grand Gulf, River Bend, and Waterford, Unit 3 - 2nd Round of Official RAIs for RR EN-RR-22-001, Use ASME Code Case N-752, Risk Informed Categorization for Class 2 and 3 Systems ML23097A0412023-04-0606 April 2023 June 2023 Emergency Preparedness Exercise Inspection - Request for Information ML23076A0552023-03-13013 March 2023 EP Program Inspection RFI Hjs 10132022 ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23052A0882023-02-17017 February 2023 Inspection Request for Information ML22335A4802022-12-0101 December 2022 NRR E-mail Capture - NRC Update Completion Date for Waterford 3 LAR to Adopt TSTF-505 ML22336A0202022-12-0101 December 2022 NRR E-mail Capture - Acceptance Review for Waterford Unit 3 - License Amendment Request to Revise Technical Specification 3/4.3.2 ML22329A0152022-11-0202 November 2022 NRR E-mail Capture - NRC Update Completion Date for Waterford 3 LAR to Adopt TSTF-505 ML22290A0442022-10-13013 October 2022 December 2022 Emergency Preparedness Program Inspection - Request for Information ML22215A2062022-08-0303 August 2022 NRR E-mail Capture - Waterford 3 - LAR to Adopt Title 10 of the Code of Federal Regulations, Section 50.69: Loe and Completion Date Update ML22215A1492022-08-0303 August 2022 NRR E-mail Capture - Waterford 3 - LAR to Permit the Use of Risk-Informed Completion Times in Accordance with Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 2 ML22206A0172022-07-22022 July 2022 NRR E-mail Capture - Request for Additional Information: Waterford 3 - License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-505 ML22206A0152022-07-21021 July 2022 NRR E-mail Capture - Entergy (Grand Gulf, River Bend, and Waterford-3) - Acceptance Review of the RR EN-RR-22-001, Case N-752, Risk-informed Cat & Treatment for Repair/Replacement Activities in Class 2 & 3 Systems ML22209A1082022-07-15015 July 2022 NRR E-mail Capture - Draft RAIs to License Amendment Request for Application to Adopt 10 CFR 50.69 and Revise Technical Specifications to Adopt TSTF-505, Revision 2 ML22144A1662022-05-24024 May 2022 PI&R Request for Information and Transmittal e-mail ML22108A1792022-04-14014 April 2022 WF3 Cpcs Installation Inspection Plan Email ML22209A1062022-01-20020 January 2022 NRR E-mail Capture - (External_Sender) Options Moving Forward Regarding Waterford TSTF-505 and 50.69 ML22209A1052022-01-0606 January 2022 NRR E-mail Capture - Estimate for Completion of 50.69-TSTF-505 Peer Review ML22012A1592022-01-0505 January 2022 WF3 2022 EP Exercise Inspection RFI Sdh 010522 ML21356A5872021-12-22022 December 2021 NRR E-mail Capture - Acceptance for Review: Waterford 3 - Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule ML21349A2242021-12-14014 December 2021 NRR E-mail Capture - (External_Sender) Waterford 3 - Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial EP Exercise ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21280A0812021-10-0505 October 2021 Email 10-5-21 - Request for Information_ Waterford EP Inspection (71114.04 & 71151) - Nov-Dec 2021 ML21285A0242021-10-0505 October 2021 Digital Instrumentation and Control Modification Inspection Request for Information ML22112A1512021-08-0606 August 2021 NRR E-mail Capture - for Review: Draft RAIs to LAR to Relocate Chemical Detection Systems Technical Specifications (TS) to Technical Requirements Manual (TRM) ML21216A4562021-08-0404 August 2021 WF3 2021 EP Exercise Inspection Request for Information (RFI) ML21218A0402021-07-26026 July 2021 NRR E-mail Capture - Final RAIs to Entergy Operations, Waterford Steam Electric Station, Unit 3 LAR to Adopt 10 CFR 50.69 ML21201A0062021-07-19019 July 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21173A1082021-06-22022 June 2021 NRR E-mail Capture - Acceptance Review for Waterford Unit 3 - License Amendment Request to Adopt TSTF-563 ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21160A0852021-06-0404 June 2021 NRR E-mail Capture - (External_Sender) NRC Notification to the State of Louisiana Regarding a Waterford Steam Electric Station, Unit 3 Amendment - Digital Upgrade I&C ML21145A0062021-05-24024 May 2021 NRR E-mail Capture - Supplement Received - Waterford Unit 3 - License Amendment Request for Boration Systems Tech Specs ML21120A1192021-04-30030 April 2021 NRR E-mail Capture - Acceptance Review for Waterford Unit 3 - LAR to Relocate Chemical Detection TSs to TRM ML21105A0512021-04-14014 April 2021 4-14-21 Email - RFI for In-Office Inspection of Recent WF3 Submission of EAL Procedure Revision ML21104A0382021-04-13013 April 2021 NRR E-mail Capture - Acceptance Review for Waterford Unit 3 - License Amendment Request for TSTF-505 ML21084A2552021-03-22022 March 2021 NRR E-mail Capture - Supplement to Audit Plan Dated October 1, 2020 (Waterford 3, L-2020-LLA-0164) ML21088A1512021-03-15015 March 2021 NRR E-mail Capture - Draft Waterford Acceptance Review Letter for TSTF-505 LAR ML21069A1842021-03-0202 March 2021 NRR E-mail Capture - Announcement of QA Inspection ML21040A3892021-02-0808 February 2021 NRR E-mail Capture - Announcement of QA Inspection ML21039A6412021-01-28028 January 2021 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Waterford 3 50.69 LAR ML21022A1692021-01-22022 January 2021 NRR E-mail Capture - Entergy Fleet (ANO, Grand Gulf, River Bend, and Waterford) - Acceptance Review for RR EN-20-RR-003, Proposed Alternative to Use ASME Code Case N-711-2 ML20329A1442020-11-20020 November 2020 Terrapower QAPD Preliminary Questions Email ML20288A2082020-10-0808 October 2020 8Oct2020 Email - Request for Information (RFI) to Support and Prepare for the Emergency Preparedness (EP) Program Inspection at the Waterford 3 Station Scheduled to Occur the Week of December 7, 2020 ML20289A3502020-10-0505 October 2020 NRR E-mail Capture - NRC Request for Additional Information - WF3 EAL Scheme Change - L-2020-LLA-0122 ML20239B0552020-08-26026 August 2020 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Waterford U3 Digital Upgrade LAR ML20197A3122020-07-14014 July 2020 NRR E-mail Capture - NRC Notification of State of Louisiana Re. Waterford Steam Electric Station License Amendments - Changes to Technical Specifications ML20191A0172020-06-26026 June 2020 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Waterford U3 EAL Scheme Change LAR ML20093C3072020-04-0101 April 2020 NRR E-mail Capture - (External_Sender) Entergy Fleet - Performance-Based Cyber Security Testing Plan Fee Waiver Response Letter (EPID P-2020-PRF-0000; CAC No. 001648) 2023-04-06 |
Text
From: POLLOCK, JIM [RPOLLOC@entergy.com]
Sent: Thursday, June 03, 2010 8:01 AM To: Nove, Carol Cc: Kalyanam, Kaly
Subject:
Requested information Attachments: 6-2-2010 info.pdf
- Carol, Please find attached the MRP-139 examination records for welds09-016 and 10-002. Also, the circumferential inspection data sheets for the same welds.
Please let me know if you have any questions.
Jim Pollock (504) 739-6561 E-mail Properties Mail Envelope Properties (6F1B1234E10D174BB87F008116CA63AE03055B52)
Subject:
Requested information Sent Date: 6/3/2010 8:02:23 AM Received Date: 6/3/2010 8:02:24 AM From: POLLOCK, JIM Created By: RPOLLOC@entergy.com Recipients:
Carol.Nove@nrc.gov (Nove, Carol)
Tracking Status: None Kaly.Kalyanam@nrc.gov (Kalyanam, Kaly)
Tracking Status: None Post Office:
CCTEXETSP006.etrsouth.corp.entergy.com Files Size Date & Time MESSAGE 1284393 6/3/2010 6-2-2010 info.pdf 1281706 Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False
Sensitivity: olNormal Recipients received: