ML101450192

From kanterella
Jump to navigation Jump to search
Draft Regulatory Issue Summary 2008-05, Revision 1: Lessons Learned to Improve Inspections, Tests, Analyses, and Acceptance Criteria Submittal
ML101450192
Person / Time
Issue date: 07/20/2010
From: Mcginty T, Tracy G
Division of Construction Inspection and Operational Programs, Division of Policy and Rulemaking
To:
Cheung C, NRO/DCIP, 301-415-2043
References
RIS-08-005, Rev 1
Download: ML101450192 (11)


See also: RIS 2008-05

Text

ML101450192

UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

OFFICE OF NEW REACTORS

WASHINGTON, DC 20555-0001

DRAFT

NRC REGULATORY ISSUE SUMMARY 2008-05, REVISION 1,

LESSONS LEARNED TO IMPROVE INSPECTIONS, TESTS,

ANALYSES, AND ACCEPTANCE CRITERIA SUBMITTAL

ADDRESSEES

All holders of or applicants for a power reactor early site permit (ESP), combined license (COL),

standard design certification (DC), standard design approval, or manufacturing license under

Title 10 of the Code of Federal Regulations (10 CFR) Part 52, Licenses, Certifications, and

Approvals for Nuclear Power Plants.

INTENT

The U.S. Nuclear Regulatory Commission (NRC) is issuing this regulatory issue summary (RIS)

to communicate good practices associated with the quality, clarity, and inspectability of

inspections, tests, analyses, and acceptance criteria (ITAAC) submitted as part of applications

for ESPs, standard DCs, or COLs. This RIS also recommends that applicants, vendors, and the

NRC maintain complete and consistent ITAAC lists. Addressees should consider incorporating

these practices into their applications to provide for a more efficient inspection and ITAAC

closure process. No specific action or written response is required.

RIS 2008-05, Revision 1, expands on issues that were identified in RIS 2008-05, Lessons

Learned to Improve Inspections, Tests, Analyses, and Acceptance Criteria, dated February 27,

2008 (Agencywide Documents Access and Management System (ADAMS) Accession

No. ML073190162), and incorporates several new issues. Additional information appears in

Regulatory Guide (RG) 1.215, Guidance for ITAAC Closure under 10 CFR Part 52 (ADAMS

Accession No. ML091480076), which endorses the methodologies described in the industry

guidance document Nuclear Energy Institute (NEI) 08-01, Industry Guideline for the ITAAC

Closure Process under 10 CFR Part 52, Revision 3, issued January 2009 (ADAMS Accession

No. ML090270415).

BACKGROUND

As required by 10 CFR Part 52, applicants for ESPs, standard DCs, or COLs must submit,

among other information, the proposed ITAAC that are necessary and sufficient to provide

reasonable assurance that, if the inspections, tests, and analyses (ITA) are performed and the

acceptance criteria are met, the facility has been constructed and will be operated in conformity

with the license, the provisions of the Atomic Energy Act of 1954, as amended, and the

Commissions rules and regulations. Following issuance of a COL, a licensee completes the

RIS 2008-05, Rev. 1

Page 2 of 10

ITAAC in the license during construction and submits notification letters to the NRC in

accordance with 10 CFR 52.99, Inspection during Construction. The NRC verifies closure of

all ITAAC through direct inspection or other methods, such as oversight of the licensees ITAAC

completion, closure, and approval processes.

SUMMARY OF ISSUES

On the basis of a review of recent ITAAC submittals to the NRC, the staff has identified five

general categories in which ITAAC submittals could be improved: (1) ITAAC format and

content, (2) ITAAC nomenclature and language, (3) ITAAC focus, logic, and practicality,

(4) ITAAC standardization and consistency, and (5) ITAAC scope.

ITAAC FORMAT AND CONTENT

Applicants should consider using a consistent system to identify and number individual

ITAAC within their applications. Although past submittals have typically used an

alphanumeric system, some submittals used dashes or separate paragraphs with no

labels in the body of the text to specify separate ITAAC requirements. In other

submittals, the alphanumeric designations were not consistently aligned for the

applicable ITAAC tables. Use of a standard and consistent ITAAC identification system

will facilitate ITAAC closure activities.

Applicants should consider a standard methodology for identifying and organizing the

structures, systems, and components (SSCs) associated with an ITAAC to enable a

more efficient inspection and ITAAC closure process. For example, if an applicant

chooses to organize SSCs in a tabular format (as opposed to system drawings), it could

group instrumentation-related components (e.g., sensors) separately from mechanical

components. The applicant could also list mechanical components, or a group of

components that are likely to be close together, in similar categories (e.g., pumps,

valves).

Applicants should avoid the integration of several different engineering or construction

areas into a single ITAAC. For example, one applicant put all of the American Society of

Mechanical Engineers (ASME) Boiler and Pressure Vessel Code requirements and the

pipe break analyses for all of the plants piping into only two ITAAC. In another instance,

an applicants definition for a systems basic configuration included five separate

engineering and construction processes, the applicability of which had to be interpreted

to determine the required ITAAC for each. In both cases, the ITAAC were ill-defined and

unwieldy.

COL applicants should consider aggregating into one complete ITAAC list all of the

ITAAC contained in both the certified design and the COL. Because this complete

ITAAC list would include all ITAAC applicable to a specific COL, it would function as a

master list that could be referenced by both the NRC and the applicant (or licensee)

throughout construction until the Commission makes a 10 CFR 52.103(g) finding.

RIS 2008-05, Rev. 1

Page 3 of 10

As a complementary measure to the development of a consistent ITAAC identification

system and an ITAAC master list, both DC and COL applicants should consider

establishing a logical process for handling, identifying, and referencing ITAAC revisions.

If a design control document (DCD) revision or COL change adds to or renumbers the

existing ITAAC, the applicant should link all new ITAAC to the existing ITAAC they

originated from through their alphanumeric designations. This renumbering protocol

would facilitate the closure of any new ITAAC by correlating available information with

the planned inspection activities for the ITAAC already approved. Both licensee and

NRC inspection processes would then be able to efficiently coordinate existing

inspection results and conclusions with the revised ITAAC.

ITAAC NOMENCLATURE AND LANGUAGE

Applicants should clearly define all terms used in an ITAAC. The following are examples

of confusion caused by undefined terms:

-

It was unclear whether an applicant using the terms design reports and

reports in an ITAAC involving ASME Code piping and welding intended the

ASME Code definition for design report and data report or its own definition

for these terms.

-

An applicant frequently used the term as-installed but did not define it. The

applicant was using this term as a substitute for as-built, which it did define.

Substitution of undefined but similar terms for as-built is not recommended.

Even when the applicable DCD defines ITAAC terms and phrases, applicants should

ensure that such ITAAC word usage is consistent with industry-accepted guidance. For

example, Section 8.6 of NEI 08-01, Guidance for Inspections, Tests or Analyses

Performed at Other Than Final Installed Location, as endorsed by NRC RG 1.215,

discusses several examples of the already defined term, as-built, in the context of how

an as-built condition can be correctly interpreted in various ITAAC applications.

Applicants should specifically consider this guidance (not only in Section 8.6, but also

elsewhere in NEI 08-01) when developing ITAAC to submit for approval.

If applicants use such terms as interfacing systems, control room features, minimum

set, seismic structure, equipment qualification, physical separation, fast-closing

valves, and rapid depressurization, they should clearly define themor at least

quantify the adjectives usedfor inspection purposes. For example, the term

equipment qualification, if not clearly defined, could be associated with the specific

requirements for environmental qualification (EQ) given in 10 CFR 50.49,

Environmental Qualification of Electric Equipment Important to Safety for Nuclear Power

Plants.

Use of the conjunction and/or is never appropriate.

If applicants use the phrase a report exists and concludes that... they should specify

the scope, the type of report and how report generation is controlled. For example, the

RIS 2008-05, Rev. 1

Page 4 of 10

applicant should explain whether the scope of the report includes the design, the as-built

construction (as reconciled with the design), or any other information. This is not

necessary for reports generated in accordance with the ASME Code, as the Code itself

governs the creation of such reports.

Applicants should use specific technical terms consistently. For example, the terms

pressure test and hydrostatic pressure test are often inappropriately interchanged;

similarly, internal pressure and design pressure are used synonymously in the same

ITAAC to mean the same thing. Applicants should also take care not to confuse the

preoperational conditions with the applicable operation modes in situations involving

testing.

Applicants should avoid subjective terms, such as inclined sufficiently, acceptable

level, and adequate thickness. These terms call for interpretation to understand the

ITAAC.

ITAAC INSPECTION FOCUS, LOGIC, AND PRACTICALITY

Applicants should avoid applying a single ITAAC to a large area of construction or to

activities that are likely to be widely separated in time. Large-scoped ITAAC create

problems with verification activities and with the timing of construction and other

requisite inspections.

Applicants should consider breaking ITAAC with a large number of SSCs into areas of

construction. For example, if a single ITAAC includes construction from the basemat to

the top of containment and applies to several different buildings, the large area and

scope create difficulties, not only in tracking the applicable SSCs, but also in connecting

the interdependent nature (e.g., seismic) of the applicable structures. Breaking a large

single ITAAC into several simpler ITAAC will make the ITAAC closure process more

efficient.

Applicants that envision using modular construction should consider the impact of these

activities in developing their ITAAC. For example, the inspection of as-built SSCs

implies that as-built refers to the completion of construction at the final location at the

plant site. However, if a module is fabricated at a remote location (e.g., a shipyard), it

may be possible to justify inspection or testing at the remote location. It may also be

possible for applicants to develop ITA that can be performed at the remote location.

(The industry guidance document, NEI 08-01, discusses modular construction, as well

as a consistent approach to the use of as-built terminology.)

Applicants should consider the timing and sequence of construction activities in the

development of related ITAAC. Breaking an ITAAC into pieces that can be completed in

the early and mid-stages of construction would help alleviate the surge in ITAAC closure

activities at the end of the process.

Applicants should develop ITAAC that require direct inspection of construction as it

occurs, rather than review of postconstruction records. For example, a design

RIS 2008-05, Rev. 1

Page 5 of 10

commitment that indicates certain buildings are constructed of reinforced concrete or are

prestressed is inconsistent with an ITA that specifies an inspection of the construction

records. The ITA should be an inspection of the actual construction to ensure the use of

reinforced concrete or prestressing as required. ITAAC inspections are intended to

physically confirm the attribute being checked. An inspection of documentation is

actually a record check, not a physical verification of the SSC attributes of concern.

Applicants should ensure that design commitments and ITAAC are consistent. It is

important for the language and details of the ITAAC to comport with the language of the

design commitment. In one example, the design commitment indicated that the piping

was designed and constructed in accordance with the ASME Code, but the acceptance

criteria only required the existence of design reports (which would not normally

encompass construction quality) for as-built piping. In another example, the design

commitment indicated that each standby diesel generator was sized to accommodate

expected loads, but the acceptance criteria only required the generator to provide power

at generator terminal rated voltage and frequency when at rated load. To validate the

design commitment, the applicant would first need to determine the electrical loads

presented by equipment credited in the safety analysis (e.g., by analyses or testing) and

then conduct a test to verify that the procured diesel generator could adequately supply

these loads.

Applicants should ensure that the ITA match the associated acceptance criteria. The

NRC staff has observed instances in which the ITA was inappropriate for determining

that the acceptance criteria had been satisfied. In one example, the ITA required an

inspection of a makeup water system. Although three separate acceptance criteria were

associated with this one ITA inspection, only two of the criteria were actually inspections;

the third criterion specified a flow rate, which is a test result and not an inspection

criterion. Below are three additional examples illustrating mismatches between ITA and

acceptance criteria.

- Example 1

Design Commitment

Inspection, Tests,

Analyses

Acceptance Criteria

The XYZ system has an

available volumesized

to contain approximately

400 percent of the full-

core debris.

Inspections of the as-built

system will be conducted.

The as-built XYZ system is

sized to contain 350-450

percent of the full-core

debris.

The inspection is appropriate for determining the volume of the XYZ system.

However, an inspection alone is not capable of determining whether the

measured volume can contain 350-450 percent of full-core debris, because this

amount of material has either not been determined or is not defined for the

inspection.

RIS 2008-05, Rev. 1

Page 6 of 10

- Example 2

Design Commitment

Inspection, Tests,

Analyses

Acceptance Criteria

All low-pressure coolant

injection piping and

componentsare

designed to withstand

full reactor pressure.

Inspection of the as-built

low-pressure coolant

injection pipingwill be

performed.

The as-built low-pressure

coolant injection piping and

componentsare designed

to withstand full reactor

pressure.

The inspection of piping and components can determine whether they were

installed in accordance with design. In addition to the inspection, an analyses or

test would be needed to determine whether the as-built piping and components

meet the approved design. Additionally, the applicant needs to quantify the term

full reactor pressure in the acceptance criteria.

- Example 3

Design Commitment

Inspection, Tests,

Analyses

Acceptance Criteria

Level instruments with

adequate operating

ranges are provided for

the spent fuel pool.

Inspections of the ABC

System will be conducted to

verify that level instruments

with adequate operating

ranges are provided for the

spent fuel pool.

The as-built ABC System

provides spent fuel pool

level instrumentation with

adequate operating ranges.

Pool instruments accurately

indicate pool level over

ranges.

Although an inspection is capable of checking the proper pool level range, an

inspection alone cannot determine the accuracy of the specified instrumentation.

Some form of testing or analyses is likely required to validate the pool instrument

accuracy noted in the acceptance criteria.

ITAAC STANDARDIZATION AND CONSISTENCY

Applicants should ensure consistency in ITAAC designations within their applications.

For example, a count of the ITA designations identified 33 ITAAC, but a count of the

acceptance criteria designations identified 38 ITAAC. Such an inconsistent ITAAC count

could result in problems not only during verification and inspection activities, but also

when the ITAAC are closed and the notification letters are submitted in accordance with

10 CFR 52.99.

Applicants should ensure that ITAAC references exist and provide appropriate

information. For example, a design commitment and acceptance criteria indicated that

controls exist in the main control room, but did not specify nor provide enough

information about what actual controls must exist. Either a list of controls or a reference

RIS 2008-05, Rev. 1

Page 7 of 10

to a list would have provided the necessary information. Applicants should ensure that

the ITAAC verify the design commitment. If the existence and the functionality of the

controls are to be validated, the ITAAC should clearly state that requirement. (However,

functionality can only be verified by a test.)

Applicants should ensure that ITAAC agree with Tier 1 information. For example, the

Tier 1 definition of an EQ required type tests, or type tests and analyses, but the

associated ITA for EQ required type tests, analyses, or a combination of type tests and

analyses. This would appear to inappropriately allow analyses alone to validate the EQ.

Applicants should ensure that ITAAC agree with Tier 2 information. For example, the

acceptance criteria for one ITAAC specified that a certain valve will open within

0.89 seconds, but the Tier 2 design parameter for this valve identified a maximum of

0.7 seconds.

ITAAC SCOPE

Applicants should ensure that ITAAC are written in a clear and objective manner. In

some cases, applicants have expanded the scope of individual ITAAC in a way that

diminished the ITAACs objectivity and promoted a lack of clarity about what the ITAAC

required. Some examples follow that illustrate the generic problem of expanding the

scope of an ITAACs objectivity beyond what was intended.

-

An applicant attempted to expand the ITAAC for functional arrangement of a

system beyond the definition of functional arrangement as a physical

arrangement of SSCs to include several testing, qualification, and analytical

attributes. In this case, an ITAAC intended to be verified by an objective

inspection of the as-built system was inappropriately transformed into a catch-all

for a diverse set of technical attributes. In some cases, these separate attributes

(e.g., separate tests, physical measurements, analytical results) justified their

own unique ITAAC. This was a case where the objectivity of a simple ITAAC

was lost because its scope was inappropriately expanded.

-

Other ITAAC have used terminology that the applicant defined differently than

the NRC, thus expanding the scope of the defined term. For example, the

applicant defined the word exists using part of the definition presented in

Standard Review Plan Section 14.3, Inspections, Tests, Analyses, and

Acceptance Criteria, issued March 2007, of NUREG-0800, Standard Review

Plan for the Review of Safety Analysis Reports for Nuclear Power Plants, which

states, the term exists, when used in the acceptance criteria, means that the

term is present and meets the design description. Unfortunately, the second

part of the section is not quoted by the applicant, which states that, "detailed

supporting information on what should be present is contained in

thestandard safety analysis report. This clarifying sentence implies that what

should be present is something that can be seen to be inspected. Several

criteria described in the design description (e.g., EQ, seismic qualification, design

attributes, and, most importantly, functionality) cannot be seen. Therefore, the

RIS 2008-05, Rev. 1

Page 8 of 10

scope of any ITAAC using the term "exists" might be inappropriately expected to

include attributes (like functionality in accordance with the design) that cannot be

validated by only an inspection that something exists. This is another case in

which an objective ITAAC may be improperly expanded to include the scope of

attributes that cannot be verified by the inspection. Below is an example of an

ITAAC that illustrates improper use of the term exist.

Design Commitment

Inspection, Tests,

Analyses

Acceptance Criteria

Controls exist in the

Main Control Room.

Tests will be performed for

the existence of control

signals from the Main

Control Room.

Controls exist in the Main

Control Room.

The ITAAC should have enough detail to describe what is being verified.

Although the necessary information may be included in the DCD, it is neither

provided in the ITAAC nor provided by reference to any other detailed

information or tables that would adequately support licensee inspection or NRC

verification.

Applicants should ensure that revisions to ITAAC are thoroughly reviewed and the

extent-of-condition fully evaluated and resolved. Applicants should check revisions to

ITAAC for applicability to all related system ITAAC and also for the impact of referenced

SSC table revisions. ITAAC reviews should include verification checks for extent-of-

condition applicability, especially in situations involving ITAAC revisions or ITA activities

that generically apply to similar systems or components.

-

For example, the ITAAC for one system refer to tests of motor-operated valve

(MOV) functions and squib valve functions. The ITAAC references a table

identifying the related valves and their respective functions. However, an ITAAC

for a similar safety-related system that also employs MOVs and squib valves with

active functions refers only to MOV tests and inappropriately neglects the squib

valve tests.

-

In the previous example, the applicant later revised the referenced table to

change the active function of the MOV to none. However, the ITAAC written to

test the operation of the MOV was never deleted. This entire ITAAC was no

longer applicable because there was no active function for the MOVs associated

with this ITAAC.

BACKFIT DISCUSSION

This revised RIS provides addressees information to aid in the submittal of ITAAC as part of

their applications for ESPs, standard DCs, or COLs and does not represent a new or different

NRC staff position on the implementation of 10 CFR Part 52. It does not create or impose any

RIS 2008-05, Rev. 1

Page 9 of 10

new or different applicable NRC staff positions inconsistent with 10 CFR Part 52. It requires no

action or written response beyond what is required in 10 CFR Part 52.

This RIS requires no action or written response and is, therefore, not a backfit under

10 CFR 50.109, Backfitting. Consequently, the NRC staff did not perform a backfit analysis.

FEDERAL REGISTER NOTIFICATION

A notice of opportunity for public comment was not published in the Federal Register because

this RIS is informational and does not represent a departure from current regulatory

requirements. However, the NRC posted this RIS on the NRC Public Web site for comment 30

days. These comments will be considered before the issuance of this RIS.

CONGRESSIONAL REVIEW ACT

This RIS is not a rule as designated by the Congressional Review Act (5 U.S.C. 801-808) and,

therefore, is not subject to the Act.

PAPERWORK REDUCTION ACT STATEMENT

This RIS contains existing information collection requirements that are subject to the Paperwork

Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing requirements were approved by the

Office of Management and Budget, approval number 3150-00151.

Public Protection Notification

The NRC may not conduct or sponsor, and a person is not required to respond to, a request for

information or an information collection requirement unless the requesting document displays a

currently valid Office of Management and Budget control number.

RIS 2008-05, Rev. 1

Page 10 of 10

CONTACT

This RIS requires no specific action or written response. Please direct any questions about this

matter to the technical contact listed below.

Timothy McGinty, Director

Glenn Tracy, Director

Division of Policy and Rulemaking

Division of Construction Inspection and

Office of Nuclear Reactor Regulation

Operational Programs

Office of New Reactors

Technical Contact:

Calvin Cheung

(301) 415-2043

calvin.cheung@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site,

http://www.nrc.gov, under Electronic Reading Room/Document Collections.

RIS 2008-05

Page 10 of 10

CONTACT

This RIS requires no specific action or written response. Please direct any questions about this

matter to the technical contact listed below.

Timothy McGinty, Director

Glenn Tracy, Director

Division of Policy and Rulemaking

Division of Construction Inspection and

Office of Nuclear Reactor Regulation

Operational Programs

Office of New Reactors

Technical Contact:

Calvin Cheung

(301) 415-2043

Calvin.Cheung@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site,

http://www.nrc.gov, under Electronic Reading Room/Document Collections.

ADAMS Accession Number: ML101450192

TAC ME3682

OFFICE

CTSB:DCIP:NRO

Tech Ed.

TL:CTSB:DCIP:NRO

BC:CTSB:DCIP:NRO

OGC (CRA)

NAME

CCheung

KAzasiah

RLaura

MKowal

SCrockett

DATE

5/27/2010

6/18/2010

5/27/2010

5/28/2010

6/17/2010

OFFICE

OE

D:PMDA:NRO

OIS

D:DIRS:NRR

D:DNRL:NRO

NAME

NHilton

BGusack

TDonnell

FBrown

DMatthews

DATE

6/14/2040

5/28/2010

6/7/2010

6/15/2010

6/8/2010

OFFICE

DD:DCI:R-II

D:DORL:NRR

OGC (NLO)

LA:PGCB:NRR

PM:PGCB:NRR

NAME

COgle

JGiitter

MZobler

CHawes CMH

SStuchell

DATE

6/15/2010

6/22/2010

7/19/2010

07/20/2010

/ /

OFFICE

BC:PGCB:NRR

D:DCIP:NRO

D:DPR:NRR

NAME

SRosenberg

GTracy

TMcGinty

DATE

/ /

/ /

/ /