Regulatory Guide 1.215

From kanterella
(Redirected from ML091480076)
Jump to navigation Jump to search
Guidance for ITAAC Closure Under 10 CFR Part 52
ML091480076
Person / Time
Issue date: 10/31/2009
From:
Office of Nuclear Regulatory Research
To:
Jervey, Richard 301-251-7404
Shared Package
ML091480069 List:
References
DG-1204 RG-1.215
Download: ML091480076 (27)


The NRC issues regulatory guides to describe and make available to the public methods that the NRC staff considers acceptable for use in implementing specific parts of the agency=s regulations, techniques that the staff uses in evaluating specific problems or postulated accidents, and data that the staff needs in reviewing applications for permits and licenses. Regulatory guides are not substitutes for regulations, and compliance with them is not required. Methods and solutions that differ from those set forth in regulatory guides will be deemed acceptable if they provide a basis for the findings required for the issuance or continuance of a permit or license by the Commission.

This guide was issued after consideration of comments received from the public.

Regulatory guides are issued in 10 broad divisionsC1, Power Reactors; 2, Research and Test Reactors; 3, Fuels and Materials Facilities; 4, Environmental and Siting; 5, Materials and Plant Protection; 6, Products; 7, Transportation; 8, Occupational Health;

9, Antitrust and Financial Review; and 10, General.

Electronic copies of this guide and other recently issued guides are available through the NRC=s public Web site under the Regulatory Guides document collection of the NRC=s Electronic Reading Room at http://www.nrc.gov/reading-rm/doc-collections/ and through the NRC=s Agencywide Documents Access and Management System (ADAMS) at http://www.nrc.gov/reading-rm/adams.html, under Accession No. ML091480076.

U.S. NUCLEAR REGULATORY COMMISSION

October 2009 OFFICE OF NUCLEAR REGULATORY RESEARCH

Revision 0

REGULATORY GUIDE

REGULATORY GUIDE 1.215 (Draft was issued as DG-1204, dated March 2009)

GUIDANCE FOR ITAAC CLOSURE UNDER 10 CFR PART 52

A. INTRODUCTION

This guide describes a method that the staff of the U.S. Nuclear Regulatory Commission (NRC)

considers acceptable for use in satisfying the requirements for documenting the completion of inspections, tests, analyses, and acceptance criteria (ITAAC). In particular, this guide endorses the methodologies described in the industry guidance document Nuclear Energy Institute (NEI) 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, Revision 3, issued January 2009 (Ref. 1), for the implementation of Title 10, Section 52.99, Inspection during construction, of the Code of Federal Regulations (10 CFR 52.99) (Ref. 2).

The NRC issues regulatory guides to describe to the public methods that the staff considers acceptable for use in implementing specific parts of the agencys regulations, to explain techniques that the staff uses in evaluating specific problems or postulated accidents, and to provide guidance to applicants. Regulatory guides are not substitutes for regulations and compliance with them is not required.

This regulatory guide contains information collection requirements covered by 10 CFR Part 52 that the Office of Management and Budget (OMB) approved under OMB control number 3150-0151.

The NRC may neither conduct nor sponsor, and a person is not required to respond to, an information collection request or requirement unless the requesting document displays a currently valid OMB control number.

RG 1.215, Page 2

B. DISCUSSION

Background

10 CFR 52.99 includes requirements for documenting and reporting the satisfaction of the acceptance criteria for each ITAAC in the combined license (COL).

This guide provides guidance on licensee notifications to the NRC for completed and uncompleted ITAAC. The NRC uses these notifications to determine whether ITAAC have been successfully completed, to facilitate public participation in the ITAAC hearing process, and for inspection planning. This regulatory guide describes methods that the NRC staff considers acceptable for licensees to use for documenting and reporting the satisfactory completion of the acceptance criteria for each ITAAC in the COL. This regulatory guide, through its endorsement of an industry guidance document for licensees, provides guidance on complying with the requirements of 10 CFR 52.99.

1.

Development of Industry Guideline Document NEI 08-01

In accordance with 10 CFR 52.97(b), COLs must contain ITAAC that are necessary and sufficient to provide reasonable assurance that the facility has been constructed and will operate in accordance with the license, the Atomic Energy Act, and NRC regulations. After issuance of a COL, a licensee completes all the ITAAC contained in the COL during construction and then submits closure notification letters to the NRC pursuant to 10 CFR 52.99.

Two types of ITAAC notifications from licensees are required by 10 CFR 52.99. The first type of ITAAC notification (ITAAC closure letter) is submitted under 10 CFR 52.99(c)(1) and informs the NRC of the basis for the licensees determination that an ITAAC has been successfully completed.

ITAAC closure letters must be submitted for all ITAAC, with the exception of ITAAC resolved at COL

issuance under 10 CFR 52.97(a)(2). The second type of ITAAC notification (uncomplete ITAAC

notification letter) is submitted under 10 CFR 52.99(c)(2) at least 225 days before scheduled initial fuel load and describes how all uncompleted ITAAC will be successfully completed prior to fuel load.

Operation (which includes loading fuel) cannot commence until the Commission finds under 10

CFR 52.103(g) that all acceptance criteria in the ITAAC are met. To provide a basis for the Commissions finding and to ensure that ITAAC closure notifications contain sufficient information to satisfy 10 CFR 52.99, the licensee can follow industry guideline NEI 08-01.

NEI 08-01 provides guidance for licensees on major aspects of the ITAAC closure process in the following sections:

Introduction

Definitions

General Description of 10 CFR Part 52 and ITAAC Processes

Role of ITAAC in 10 CFR Part 52 Process

ITAAC Closure Process

General Description of Public Hearing Opportunity

RG 1.215, Page 3

Summary Description of 10 CFR 52.103 Process and Fuel Load Authorization Process

Schedule Considerations for ITAAC-Related Activities and Coordination to Support NRC Inspection Planning

Proprietary Construction Schedule Information

Licensee Schedule Coordination

Licensee Process for Review and Preparation of ITAAC Closure Letters

Guidance for Oversight of ITAAC Closure Activities and Maintenance of Records

Standard Format for ITAAC Closure Packages

Licensee Problem Identification and Resolution Program

Guidance on Sufficient Information for ITAAC Closure Letters

Guidance on Sufficient Information for 225-Day Notification of Uncompleted ITAAC

Special Topics

Maintaining the Validity of ITAAC Conclusions Post-ITAAC Completion

Criteria/Process for Withdrawal or Update of 10 CFR 52.99 ITAAC Completion Notices

Design Acceptance Criteria

Subsequent COL ITAAC Closure

Non-ITAAC Systems

Acronyms

Appendix AExcerpts from 10 CFR Part 52

Appendix BReserved

Appendix CGeneral Description of Common ITAAC Acceptance Criteria Categories

Appendix DList of ITAAC Closure Letter Examples

Appendix EList of 225-Day Notification Examples

2.

Guidelines on ITAAC Closure Development and Documentation in NEI 08-01

The staff endorses NEI 08-01, Revision 3, as an acceptable method of complying with the requirements of 10 CFR 52.99, subject to the comments below. NEI 08-01 provides guidance for licensees on major aspects of the ITAAC closure process in the following sections:

Section 1 of NEI 08-01 provides an introduction to the document, a description and purpose of ITAAC, and the scope of topics that it will cover.

Section 2 of NEI 08-01 provides a list of definitions for terminology used in the guide. Some of these definitions will reappear in other documents such as combined license applications, design

RG 1.215, Page 4 certification applications, and other supporting documents. Currently certified designs have the following definition for as-built:

As-built means the physical properties of the structure, system, or component following the

completion of its installation or construction activities at its final location at the plant site.

NEI 08-01 defines as-built as follows:

As-built means the physical properties of a structure, system, or component following the completion of its installation or construction activities at its final location at the plant site. Determination of physical properties of the as-built structure, system, or component may be based on measurements, inspections, or tests that occur prior to installation, provided that subsequent fabrication, handling, installation, and testing do not alter the properties.

COL licensees referencing already-certified designs are, of course, bound by the definitions in the design certification rather than the definitions in NEI 08-01, but the NRC staff believes that the NEI 08-

01 definition of as-built could form part of the basis for a DCD definition of as-built in future design certifications and design certification amendments. Any such DCD definition, however, should also reflect the additional discussion in NEI 08-01 Section 3.1.4. The second paragraph of NEI 08-01 Section

3.1.4 states:

Many ITAAC require verification of as-built SSCs. However, some of these ITAAC will involve measurements and/or testing that can only be conducted at the vendor site due to the configuration of equipment or modules or the nature of the test (e.g., measurements of reactor vessel internals). For these specific items where access to the component for inspection or test is impractical after installation in the plant, the ITAAC closure documentation (e.g., test or inspection record) will be generated at the vendor site and provided to the licensee.

As-built inspections, tests, and analyses of ITAAC SSCs should ordinarily be performed after installation and construction activities at the final location at the plant site. Section 3.1.4 of NEI 08-01 acknowledges that it may be impractical to perform some inspections and testing after installation in the plant. In those cases, it may be appropriate to perform inspections or tests prior to final installation (e.g.,

measuring an interior dimension prior to final assembly of a valve).

Section 3 of NEI 08-01 provides a general description of the role of the ITAAC process in Subpart A, Early Site Permits; Subpart B, Standard Design Certifications; and Subpart C, Combined Licenses, of 10 CFR Part 52. The ITAAC closure process described in NEI 08-01 is consistent with

10 CFR 52.99 requirements for verifying that the construction of a new nuclear plant matches the certified design and the additional criteria listed in the combined license. The discussion on sufficient information further describes the notification letters as required by 10 CFR 52.99(c)(1) and

10 CFR 52.99(c)(2). Section 3 also discusses public hearing opportunities during construction and provides a summary description of the process under 10 CFR 52.103, Operation under a Combined License and its associated fuel load authorization process.

Section 4 of NEI 08-01 provides information on schedule considerations for ITAAC-related activities and coordination to support NRC inspection planning. In accordance with 10 CFR 52.99, the licensee is required to submit an ITAAC closure schedule at 6-month intervals during plant construction.

RG 1.215, Page 5 Within 1 year of fuel load, that interval will decrease to 30 days. The licensees ITAAC closure schedule will allow the NRC staff to plan its oversight activities of onsite and offsite construction inspections. The NRC will consider any licensee claims that the submitted schedule is proprietary and should be withheld from public release under the Freedom of Information Act and 10 CFR 2.390 (Ref. 4).

Section 5 of NEI 08-01 provides guidance on the licensee process for preparation and review of ITAAC closure letters. This section also provides guidance for licensee oversight of ITAAC closure activities and the maintenance of records referenced by the ITAAC closure packages. Section 5 also provides an outline of closure letters. This outline is further detailed in the templates contained in Appendix D to NEI 08-01. Section 5 includes a discussion of a licensees problem identification and resolution (PI&R) program addressing the identification and correction of deficiencies and the prevention of their recurrence as they relate to ITAAC completion.

Section 6 of NEI 08-01 provides guidance on the amount of information that must be contained in ITAAC closure letters. ITAAC closure letters must contain sufficient information to allow the NRC to determine whether the ITAAC have been successfully completed. According to the SOC for the 2007 Part 52 Rule, the closure letters mandated by 10 CFR 52.99(c)(1) must also include sufficient information so that interested persons will have access to information on completed ITAAC at a level of detail sufficient to address the Atomic Energy Act of 1954, Section 189.a(1)(B), threshold for requesting a hearing on whether the acceptance criteria have been, or will be, met. (Ref. 3).

The NRC expects the notification of ITAAC completion to contain more information than just a simple statement that the licensee has completed the ITAAC and has met the acceptance criteria. The NRC expects the notification to be sufficiently complete and detailed for a reasonable person to understand the bases for the licensees representation that it has successfully completed the inspections, tests, and analyses and has met the acceptance criteria. The term sufficient information requires, at a minimum, a summary description of the bases for the licensees conclusion that it has performed the inspections, tests, or analyses and that it has met the prescribed acceptance criteria (Ref. 3).

Each 10 CFR 52.99(c)(1) submittal should include sufficient information on the attributes that validate that the licensee has satisfied the acceptance criteria. The licensee should copy the ITAAC

directly from the certified design and COL to the ITAAC statement. The ITAAC determination basis should include a clearly written, detailed process for how the licensee completed the inspections, tests, or analyses and should explain how the acceptance criteria have been met. Each inspection, test, or analysis should be detailed to clearly indicate how it was completed and should state its results. The results should then be compared to the acceptance criteria and should include the bases for the licensees conclusion that the acceptance criteria have been met. The submittal should also include ITAAC-related construction findings related to the ITAAC and their closure status, confirmation from the licensees official representative that the licensee has met the acceptance criteria, and a list of references applicable to the ITAAC and available for NRC review. Appendix D to NEI 08-01 presents examples of ITAAC closure letters.

Section 7 of NEI 08-01 provides guidance on sufficient information for the 225-day notification of uncompleted ITAAC. The 225-day notification mandated by 10 CFR 52.99(c)(2) must include sufficient information so that interested persons will have access to information on uncompleted ITAAC

at a level of detail sufficient to address the Atomic Energy Act of 1954, Section 189.a(1)(B), threshold for requesting a hearing on whether the acceptance criteria have been, or will be, met (Ref.3). In addition, this requirement will aid the staff in determining if the licensee will be able to satisfy the acceptance

RG 1.215, Page 6 criteria for a given ITAAC. The uncomplete notification will be a predictive summary for how the licensee plans to complete the ITAAC if that ITAAC is not completed by 225 days before scheduled fuel load.

The licensee must demonstrate that it will comply with the ITAAC, and it must provide sufficient information to demonstrate that it will perform the prescribed inspections, tests, or analyses and will meet the prescribed acceptance criteria for the uncompleted ITAAC. The term sufficient information requires, at a minimum, a summary description of the bases for the licensees conclusion that it will perform the inspections, tests, or analyses and that it will meet the prescribed acceptance criteria (Ref. 3).

In addition, sufficient information includes, but is not limited to, a description of the specific procedures and analytical methods that the licensee will use to perform the inspections, tests, and analyses and to determine that it has met the acceptance criteria (Ref. 2).

Each 10 CFR 52.99(c)(2) notification should include sufficient information for both the completed and uncompleted elements of the ITAAC. The licensee should copy the ITAAC directly from the certified design and COL to the ITAAC statement. Items that the licensee has completed toward ITAAC closure should be accompanied by a clearly written, detailed process for how the licensee completed those portions of the inspections, tests, or analyses. Items that remain uncomplete for ITAAC

closure should be accompanied by a clearly written, detailed process for how the licensee expects to complete those portions of the inspections, tests, or analyses and subsequently conclude that the acceptance criteria will be met. Each inspection, test, or analysis for both completed and uncompleted portions should be detailed to clearly indicate how it was, or will be, completed. The submittal should also include a schedule for completing the ITAAC and a list of references applicable to the ITAAC and available for NRC review. Appendix E to NEI 08-01 presents examples of uncomplete notifications.

Section 8 of NEI 08-01 provides a discussion on special topics, including acceptance criteria preservation for closed ITAAC, withdrawals or updates to 10 CFR 52.99 completion notices, design acceptance criteria (DAC) procedures, subsequent COL ITAAC closure, and non-ITAAC systems.

Section 52.103(g) states, The licensee shall not operate the facility until the Commission makes a finding that the acceptance criteria in the combined license are met. Following the completion of any ITAAC,

the licensee must maintain the validity of the acceptance criteria of the closed ITAAC to demonstrate that this requirement is met. One proposed method that the licensee can use to meet this requirement is to include provisions in approved programs such as the quality assurance program, the maintenance program, the problem identification and resolution program, and the design and configuration control program. These provisions should include licensee plans and programs to ensure that the maintenance of items such as structures, systems, or components that are included in ITAAC does not invalidate the conclusion that the acceptance criteria are met.

Withdrawals or updates to a 10 CFR 52.99(e)(1) Federal Register posting are possible if a material error or omission is found to affect the validity of a licensees 10 CFR 52.99(c)(1) notification after it has made the notification.

DAC are a subset and special type of ITAAC. In SECY-92-053 (Ref. 5), Use of Design Acceptance Criteria During 10 CFR Part 52 Design Certification Reviews, DAC were defined by the staff to address design areas that rapidly change or for which sufficient as-built (or, as procured) information is unavailable to support design analysis. For example, digital instrumentation and control (I&C) is a rapidly changing design area and freezing its associated design details early in a design certification stage

RG 1.215, Page 7 could make implementation of the certified design impractical for holders of a combined license, as the final I&C design and installation would be completed years after the design certification was completed.

DAC set forth the processes and acceptance criteria for completing design detail. DAC can be resolved through three different options: (1) an amendment to the design certification (generic), (2) a submittal as part of the combined license application (plant-specific), and (3) closure of the DAC during construction (plant-specific). The NRC staff prefers to resolve DAC through the amendment of the design certification rule or resolve DAC through the COL application review process, because these two scenarios would be completed before construction begins.

As-built ITAAC will be used to demonstrate that the as-built facility conforms to the completed DAC. As-built ITAAC will be resolved as part of the ITAAC closure process. The successful completion of the as-built ITAAC will be documented through the ITAAC completion documentation process described in NEI 08-01.

The DAC review and inspection process is currently being developed. Detailed guidance on NRC review and inspection of DAC will be documented as appropriate when complete. Types of documents being considered include an inspection manual chapter, the standard review plan, or other suitable guidance.

ITAAC closure might involve closure letters that are common to each licensee of a particular design. After the initial closure letter on a common issue is submitted, subsequent licensees could submit letters referencing identical information, but this would not apply to acceptance criteria that require field activities.

Non-ITAAC systems might not have design commitments specifically listed under its system title but, in some cases, have design commitments listed under another system title.

Section 9 of NEI 08-01 provides a list of acronyms used in the guide.

Appendix A to NEI 08-01 provides excerpts from 10 CFR Part 52 that are applicable to the guidelines areas of discussion.

Appendix B to NEI 08-01 is reserved for future use.

Appendix C to NEI 08-01 provides a general description of common ITAAC categories and includes discussions of categories such as calculations and analyses, test procedures, special processes, inspection program, American Society of Mechanical Engineers code design reports, existing reports that conclude that acceptance criteria are met, procurement, material control, and training and qualification.

These discussions are intended to assist the licensee in preparing closure letters or uncomplete notifications for each type of ITAAC category.

Appendix D to NEI 08-01 provides the set of ITAAC closure letters that were prepared during the workshops and public meetings in 2007 and 2008.

Appendix E to NEI 08-01 provides the set of 225-day notifications that were also prepared during the workshops and public meetings in 2007 and 2008. Licensees can use these templates to submit

10 CFR 52.99(c)(1) and 10 CFR 52.99(c)(2) letters. Each template contains a statement of the full

RG 1.215, Page 8 ITAAC as it is included in the COL or certified reactor design, a section describing the bases for considering the ITAAC complete, a section for an ITAAC-related construction finding review, and a closure statement followed by a licensee representative signature for each submittal. Licensees must submit a 10 CFR 52.99(c)(2) notification for each uncompleted ITAAC by the 225-day milestone before scheduled fuel load. The 225-day notification requires additional detail on items completed toward ITAAC closure and on items that must be completed in the time before the 10 CFR 52.103(g) finding.

The staff considers these letters to be examples and anticipates that differing or additional information, consistent with Section 6 of NEI 08-01 (Guidance on Sufficient Information for ITAAC Closure Letters),

may be necessary for individual ITAAC letters. Licensees should review the criteria of Sections 6 and 7 of NEI 08-01 to determine the appropriate content.

3.

Appendices to This Regulatory Guide

Appendix A to this regulatory guide contains the text of 10 CFR 52.99.

Appendix B to this regulatory guide contains the flowchart and description for the implementation of 10 CFR 52.99 and 10 CFR 52.103(g), which the staff developed for use in public workshops, as described in SECY-08-0117. (Ref. 6) The process flowchart blocks include numbered descriptions to further delineate each major milestone in the regulatory process of ITAAC closure and verification up to and including the 10 CFR 52.103(g) finding.

C. REGULATORY POSITION

1.

NEI 08-01

The NRC staff considers the methods discussed in NEI 08-01, Revision 3, to be acceptable for complying with the provisions of 10 CFR 52.99

2.

Other Documents Referenced in NEI 08-01 NEI 08-01 references other documents, but this regulatory guide does not endorse any of the referenced documents.

3.

Use of Examples in NEI 08-01 NEI 08-01 includes examples for ITAAC closure letter submittals and uncomplete notifications for ITAAC. Although these examples are appropriate as general templates for illustrating and reinforcing the guidance in NEI 08-01, the NRCs endorsement of this industry guideline document should not be considered a determination that each example applies to all licensees as it is presented and written in the guide. A licensee should ensure that an example applies to its particular circumstances before implementing the guidance, or template, as described.

4.

Guidance for Site-Specific ITAAC

For licensees who have site-specific ITAAC in their COL, the guidance in NEI 08-01 applies to both design certification and site-specific ITAAC closure notification development.

RG 1.215, Page 9

5.

Use of Other Methods Licensees may use methods other than those provided in NEI 08-01 to meet the requirements of

10 CFR 52.99. The staff will review such methods and determine the acceptability of other methods on a case-by-case basis.

D. IMPLEMENTATION

The purpose of this section is to provide information to applicants and licensees regarding the NRCs plans for using this regulatory guide. The NRC does not intend or approve any imposition or backfit in connection with its issuance.

In some cases, applicants or licensees may propose or use a previously established acceptable alternative method for complying with specified portions of the NRCs regulations. Otherwise, the methods described in this guide will be used in evaluating compliance with the applicable regulations for ITAAC closure.

REGULATORY ANALYSIS / BACKFIT ANALYSIS

The NRC published a regulatory analysis and a backfit analysis with the draft of this guide when it was originally issued for public comment as Draft Regulatory Guide DG-1204, Guidance for ITAAC

Closure Under 10 CFR Part 52. The NRC issued DG-1204 in March 2009 to solicit public comment on the draft of this new Regulatory Guide 1.215, but received no comments on the regulatory analysis or backfit analysis.

RG 1.215, Page 10

REFERENCES1

1.

NEI 08-01, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52, Revision 3, January 2009, Nuclear Energy Institute, Washington, DC. ADAMS Accession No. ML090270415

2.

10 CFR Part 52.99, Inspection during construction, U.S. Nuclear Regulatory Commission, Washington, DC.

3.

Final Rule for 10 CFR Part 52 Licenses, Certifications, and Approvals for Nuclear Power Plants, August 28, 2007, 72 FR 49352, U.S. Nuclear Regulatory Commission, Washington, DC.

4.

10 CFR Part 2.390, Public inspections, exemptions, requests for withholding, U.S. Nuclear Regulatory Commission, Washington, DC.

5.

SECY-92-053, Use of Design Acceptance Criteria During 10 CFR Part 52 Design Certification Reviews, U.S. Nuclear Regulatory Commission, Washington, DC.

6.

SECY-08-0117, Staff Approach to Verify Closure of Inspections, Tests, Analyses, and Acceptance Criteria and to Implement Title 10 CFR 52.99, Inspection During Construction, and Related Portion of 10 CFR 52.103(g) on the Commission Finding, Enclosure 3, Flowchart and Description of Implementation under 10 CFR 52.99 and 10 CFR 52.103(g),

U.S. Nuclear Regulatory Commission, Washington, DC.

1 Publicly available NRC published documents such as Regulations, Regulatory Guides, NUREGs, and Generic Letters

listed herein are available electronically through the Electronic Reading room on the NRCs public Web site at:

http://www.nrc.gov/reading-rm/doc-collections/. Copies are also available for inspection or copying for a fee from the

NRCs Public Document Room (PDR) at 11555 Rockville Pike, Rockville, MD; the mailing address is USNRC PDR,

Washington, DC 20555; telephone 301-415-4737 or (800) 397-4209; fax (301) 415-3548; and e-mail

PDR.Resource@nrc.gov.

Appendix A to RG 1.215, Page A-1 APPENDIX A

TEXT OF 10 CFR 52.99

§ 52.99 Inspection during construction.

(a) The licensee shall submit to the NRC, no later than 1 year after issuance of the combined license or at the start of construction as defined in 10 CFR 50.10(a), whichever is later, its schedule for completing the inspections, tests, or analyses in the ITAAC. The licensee shall submit updates to the ITAAC schedules every 6 months thereafter and, within 1 year of its scheduled date for initial loading of fuel, the licensee shall submit updates to the ITAAC schedule every 30 days until the final notification is provided to the NRC under paragraph (c)(1) of this section.

(b) With respect to activities subject to an ITAAC, an applicant for a combined license may proceed at its own risk with design and procurement activities, and a licensee may proceed at its own risk with design, procurement, construction, and pre-operational activities, even though the NRC may not have found that any one of the prescribed acceptance criteria have been met.

(c)(1) The licensee shall notify the NRC that the prescribed inspections, tests, and analyses have been performed and that the prescribed acceptance criteria have been met. The notification must contain sufficient information to demonstrate that the prescribed inspections, tests, and analyses have been performed and that the prescribed acceptance criteria have been met.

(2) If the licensee has not provided, by the date 225 days before the scheduled date for initial loading of fuel, the notification required by paragraph (c)(1) of this section for all ITAAC, then the licensee shall notify the NRC that the prescribed inspections, tests, or analyses for all uncompleted ITAAC will be performed and that the prescribed acceptance criteria will be met prior to operation. The notification must be provided no later than the date 225 days before the scheduled date for initial loading of fuel, and must provide sufficient information to demonstrate that the prescribed inspections, tests, or analyses will be performed and the prescribed acceptance criteria for the uncompleted ITAAC will be met, including, but not limited to, a description of the specific procedures and analytical methods to be used for performing the prescribed inspections, tests, and analyses and determining that the prescribed acceptance criteria have been met.

(d)(1) In the event that an activity is subject to an ITAAC derived from a referenced standard design certification and the licensee has not demonstrated that the ITAAC has been met, the licensee may take corrective actions to successfully complete that ITAAC or request an exemption from the standard design certification ITAAC, as applicable. A request for an exemption must also be accompanied by a request for a license amendment under § 52.98(f).

(2) In the event that an activity is subject to an ITAAC not derived from a referenced standard design certification and the licensee has not demonstrated that the ITAAC has been met, the licensee may take corrective actions to successfully complete that ITAAC or request a license amendment under § 52.98(f).

Appendix A to RG 1.215, Page A-2 (e) The NRC shall ensure that the prescribed inspections, tests, and analyses in the ITAAC are performed.

(1) At appropriate intervals until the last date for submission of requests for hearing under § 52.103(a),

the NRC shall publish notices in the Federal Register of the NRC staffs determination of the successful completion of inspections, tests, and analyses.

(2) The NRC shall make publicly available the licensee notifications under paragraph (c)(1), and, no later than the date of publication of the notice of intended operation required by § 52.103(a), make available all licensee notifications under paragraphs (c)(1) and (c)(2) of this section.

[57 FR 60978, Dec. 23, 1992; 72 FR 49536, Aug. 28, 2007; 72 FR 57447, Oct. 9, 2007]

Appendix B to RG 1.215, Page B-1 APPENDIX B

Flowchart and Description of Implementation Under 10 CFR 52.99 and 10 CFR 52.103(g)

No Yes No Yes No No Yes Yes No MC2504 MC2503

52.99(c)(1) submittal

(9)

52.99(c)(2)

Uncomplete ITAAC

notification

(7)

Is the ITAAC

complete?

(1)

Did NRC

determine ITAAC

successfully completed?

(10)

More than

225 days until fuel load? (5)

52.99(c)(1)

submittal

(2)

Yes Tech Specs No ITAAC to be completed by licensee (8)

Fuel load and mode change

(19)

Did NRC

determine ITAAC

successfully completed?

(3)

Licensee needs to complete all ITAAC and submit closure letters for each ITAAC

(17)

10 CFR 52.103(a) Commission must publish notice of intended operation

180 days before scheduled fuel load

10 CFR 52.99(c)(2) Uncomplete ITAAC notification requirement

225 days before scheduled fuel load

52.103(g)

Fuel Load Start construction

(4 to 5 years duration)

For a given ITAAC, ITAAC is considered closed

(11)

FRN of staff determination for individual ITAAC or ITAAC

family, as required

(12)

ITAAC considered to be work-in- progress and closure letter not submitted

(6)

Operation ROP

Yes Substantiated information received that invalidates the closed status of any ITAAC (14)

Update FRN for affected ITAAC as appropriate (15)

ITAAC to be reworked and/or closure letter resubmitted by licensee

(4)

Each ITAAC

listed in the combined license Hearing contentions addressed Timeline of Major Milestones (not to scale)

Licensee use of developed programs to preserve the satisfaction of acceptance criteria of completed ITAAC

(13)

All acceptance criteria are met? (16)

52.103(g)

finding

(18)

Appendix B to RG 1.215, Page B-2 Process block descriptions:

(1)

This is the first decision block for any given inspection, test, analysis, and acceptance criterion (ITAAC), and the licensee needs to assess each ITAAC from the license. Each ITAAC can enter this block at any time during construction regardless of its completed or uncompleted status for processing through this flowchart.

(2)

If (1) is yes, then the licensee must submit a closure letter pursuant to 10 CFR 52.99(c)(1).

(3)

The U.S. Nuclear Regulatory Commission (NRC) will perform ITAAC closure verification activities, including direct inspection, engineering reviews, and consideration of licensee performance within an ITAAC family. Licensee performance within an ITAAC family is taken into consideration for determination of subsequent licensee ITAAC submittals. Yes indicates that the staff has determined that the ITAAC was successfully completed and is closed. No indicates that the ITAAC is not closed and remains uncomplete.

(4)

If (3) is no, the NRC has determined that either the 10 CFR 52.99(c)(1) closure letter information is insufficient or that the licensee has not met the acceptance criteria for the given ITAAC. The licensee will either need to resubmit a closure letter that contains sufficient information demonstrating that it has completed the ITAAC, or the licensee will need to rework the ITAAC and redo the inspections, tests, and analyses. In either case, the licensee will need to resubmit the 10 CFR 52.99(c)(1) closure letter.

(5)

If (1) is no, the licensee needs to identify if the time to scheduled fuel load is greater than 225 days. At the 225-day milestone, the licensee is required to submit 10 CFR 52.99(c)(2)

uncomplete ITAAC notifications for those ITAAC not yet completed and the 10 CFR 52.99(c)(1) closure letter not yet submitted.

(6)

If (5) is yes, there is no 10 CFR 52.99(c)(2) uncomplete notification required for this ITAAC, and the ITAAC under consideration is in the work-in-progress population.

(7)

If (5) is no, the licensee needs to submit to the NRC a 10 CFR 52.99(c)(2) uncomplete ITAAC notification. This notification needs to contain sufficient information to demonstrate that the licensee will perform the ITAAC.

(8)

Entry here indicates that an individual ITAAC remains in the uncomplete population. Once the licensee concludes that it has met the acceptance criteria, process block (9) is entered.

(9)

Upon successfully meeting the acceptance criteria for a given ITAAC, the licensee can submit the 10 CFR 52.99(c)(1) closure letter to the NRC.

(10)

The NRC will perform ITAAC closure verification activities. This decision block is identical to block (3).

(11)

If (10) is yes, the NRC staff has determined that the licensee has met the acceptance criteria.

(12)

The NRC determination that the licensee has successfully completed an ITAAC is published in the Federal Register until the last date for submission of requests for hearings under

10 CFR 52.103(a). The NRC can publish a Federal Register notice (FRN) for individual ITAAC (if needed) or multiple ITAAC (such as an entire family). The NRC is not required to publish an FRN after the last date for submission of requests for hearings under 10 CFR 52.103(a).

(13)

The licensee will apply developed programs such as quality assurance and maintenance to preserve the satisfaction of acceptance criteria for completed ITAAC of applicable structures, systems, and components.

(14)

Any substantiated information received by the NRC, including allegations, can invalidate the closed status of any ITAAC.

(15)

If (14) is yes, then, depending on the severity of the substantiated allegation or information received, the FRN for each affected ITAAC could be updated accordingly. Also depending on the severity of the situation, the licensee may or may not have options available to act accordingly to preserve the FRN for the affected ITAAC.

(16)

This process block collectively considers if the licensee has met all ITAAC acceptance criteria.

(17)

If (16) is no, then the licensee needs to complete all ITAAC and ensure that it meets, and continues to meet, all the acceptance criteria for the 10 CFR 52.103(g) finding.

(18)

At the time of the 10 CFR 52.103(g) finding, all acceptance criteria must be met, such as when (16) is yes. Also, this timeline and flowchart do not contemplate an interim operation scenario whereby the Commission could authorize a period of interim operation that would allow the licensee to load fuel before making the 10 CFR 52.103(g) finding, per 10 CFR

52.103(c).

(19)

With an affirmative Commission 10 CFR 52.103(g) finding, the licensee will be authorized to load fuel and enter operational status.