Agenda for Forthcoming Meeting with the Technical Specifications Task Force
ML101030660
Person / Time
Site: Technical Specifications Task Force
Issue date: 04/15/2010
From: Michelle Honcharik
NRC/NRR/DPR/PSPB
To: Eric Bowman
NRC/NRR/DPR/PSPB
References
Download: ML101030660 (3)


Text

Agenda for TSTF/NRC Meeting April 28, 2010 8:30 a.m. - 4:00 p.m.

I. Administrative A. Introductions

1. Organizational and Name changes in Special Projects Branch and Tech Spec Branch
2. Temporary membership change in TSTF B. Agenda Review C. Other Administrative Issues II. Future Planning A. Discussion of possible TSTF Traveler to provide a uniform and consistent approach to thermal power limits III. Process Issues A. Status of NRC letter concerning RG 1.174 Tier 2 requirements B. ADAMS posting of TSTF and NRC letters IV. Specific Traveler Review Issues A. Discussion of Status and Outstanding Issues for Travelers Under NRC Review
1. Initiative 1 Travelers (TSTF-422, TSTF-423, TSTF-431, and TSTF-432)
2. TSTF-426, Revise or Add Actions to Preclude Entry into LCO 3.0.3 - RITSTF Initiatives 6b & 6c a) Discuss draft SE of WCAP-16125
3. TSTF-446, Risk Informed Evaluation of Extensions to Containment Isolation Valve Completion Times (WCAP-15791) a) Status of industry comments on the draft Notice of Availability
4. TSTF-493, Clarify Application of Setpoint Methodology for LSSS Functions a) Interest in an NRC/Industry Workshop on TSTF-493
5. TSTF-500, DC Electrical Rewrite - Update to TSTF-360
6. TSTF-501, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control
7. TSTF-508, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation
8. TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection a) TSTF responding to e-mailed RAIs. Includes Traveler revision.
9. TSTF-513, Revise PWR Operability Requirements and Actions for RCS Leakage Instrumentation

a) Industry providing information on gaseous monitor effectiveness

10. TSTF-514, Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation
11. TSTF-515, Revise Post-Accident Monitoring Instrumentation based on Reg Guide 1.97, Rev. 4 and NEDO-33349
12. TSTF-517, Allowance for Non-TS Cooling / Ventilation Systems Degradation on Support System Operability a) Status of acceptance review B. Recent Submittals
1. TSTF-505, "Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b," on 3/29/2010 a) Discussion of design decisions for TSTF-505
2. TSTF-521, "Exclusion of Time Constants from Channel Operation Tests in Specifications 3.3.1 and 3.3.2," on 3/24/2010
3. TSTF-522, "Revise Ventilation System Surveillance Requirements to Operate for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> per Month," on March 30
4. TSTF-523, "Incorporation of Generic Letter 2008-01, Managing Entrained Gas," to be submitted prior to the meeting C. Discussion of Traveler Review Priorities V. Status of Model Applications Published in the Federal Register and CLIIP A. Discussion of Industry review of commitments in Travelers with Model Applications Published in the Federal Register provided to NRC on March 23 B. Discussion of Industry Review of Licensees Issues Experienced During Adoption of Travelers with Model Applications Published in the Federal Register VI. Technical Issues A. Schedule for Traveler submittal to clarify pressure boundary leakage definition and actions B. Discussion of March 31, 2010, TSTF Letter Regarding Required Action Completion VII. Issues with Previously Approved Travelers A. Need for a process to identify, resolve, and communicate resolution of issues with previously approved Travelers B. Discussion of industry white paper provided at the January 28, 2010, public meeting on TSTF-363-A, "Revise Topical Report references in ITS 5.6.5, COLR," TSTF-408-A, "Relocation of LTOP Enable Temperature and PORV Lift Setting to the PTLR (CE NPSD-683)," and TSTF-419-A, "Revise PTLR Definition and References in ISTS 5.6.6, RCS PTLR" C. Discussion on TSTF-400, "Clarify SR on Bypass of DG Automatic Trips
1. NRC staff to discuss an acceptable approach for implementation and recent precedent LAR for Peach Bottom
2. NRC staff to clarify what satisfies TS Section 3.8, Condition B, Required Action B.3.1, "Determine OPERABLE DG(s) is not inoperable due to common [cause or mode]

failure" D. Industry response to NRC questions on TSTF-283, "Modify Section 3.8 Mode restriction Notes," SRs 3.8.4.3 and 3.8.6.6 E. Industry schedule for revising TSTF-490, "Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec" F. Status of publication of revised Notice of Availability for TSTF-475-A, "Control Rod Notch Testing Frequency and SRM Insert Control Rod Action" G. Removal of TSTF-422, 423, 431, and 432 from list of questioned Travelers H. Removal of TSTF-439-A, "Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO," from list of questioned Travelers VIII. Future Planning (continued)

A. NRC feedback on TSTF proposal to Relocate Post Accident Monitoring Instrumentation list to licensee control B. Schedule for submittal of TSTF Traveler to address Use and Application issues regarding SR 3.0.3, LCO 3.0.4, LCO 3.0.5, and Required Action completion C. Consideration of expanding the end-state initiative Travelers to Hot Standby (Mode 3 for PWRs, Mode 2 for BWRs)

IX. Discussion of Development of ISTS Revision 4 A. Discussion of Travelers to be incorporated into Revision 4 B. Identification of Travelers with conditions and limitations that should be captured in Reviewers Notes in Revision 4 C. Revision 4 Schedule X. Future Meetings in 2010

1. July 22, 2010
2. November 3, 2010 - need to reschedule due to NEI Licensing Forum