NRC-10-0018, Scheduling of Initial Operator Licensing Examinations
ML100750517 | |
Person / Time | |
---|---|
Site: | Fermi |
Issue date: | 03/10/2010 |
From: | Rachel Johnson Detroit Edison |
To: | Office of Nuclear Reactor Regulation, NRC/RGN-III |
References | |
NRC-10-0018 | |
Download: ML100750517 (1) | |
Similar Documents at Fermi | |
---|---|
Category:Letter type:NRC
MONTHYEARNRC-24-0058, Status of License Renewal Commitments2024-10-0303 October 2024
[Table view]Status of License Renewal Commitments NRC-24-0057, Update to NRC 24-0041: Technical Specification (TS) 5.6.7 – Post Accident Monitoring Report2024-09-0303 September 2024 Update to NRC 24-0041: Technical Specification (TS) 5.6.7 – Post Accident Monitoring Report NRC-24-0053, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 20242024-08-30030 August 2024 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 2024 NRC-24-0050, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2024-08-12012 August 2024 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-24-0048, Submittal of Inservice Inspection Summary Report2024-08-0606 August 2024 Submittal of Inservice Inspection Summary Report NRC-24-0046, Fenni 2 Power Plant - Approval of the National Pollutant Discharge Elimination System Permit Application for Reissuance2024-07-25025 July 2024 Fenni 2 Power Plant - Approval of the National Pollutant Discharge Elimination System Permit Application for Reissuance NRC-24-0020, Submittal of Revision 51 to the Fermi 2 Radiological Emergency Response Preparedness Plan2024-07-24024 July 2024 Submittal of Revision 51 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-24-0044, Enrico Fermi 1 License Expiration - 10 CFR 50.51 (Continuation of License)2024-07-10010 July 2024 Enrico Fermi 1 License Expiration - 10 CFR 50.51 (Continuation of License) NRC-24-0041, Technical Specification (TS) 5.6.7 - Post Accident Monitoring Report2024-06-21021 June 2024 Technical Specification (TS) 5.6.7 - Post Accident Monitoring Report NRC-24-0042, Regulat01y Issues Summaty (RIS) 24-01 Preparation and Scheduling of Operator Licensing Examinations to Submit Fonn 536, Operator Licensing Examination Data2024-06-18018 June 2024 Regulat01y Issues Summaty (RIS) 24-01 Preparation and Scheduling of Operator Licensing Examinations to Submit Fonn 536, Operator Licensing Examination Data NRC-24-0040, Verification of No Significant Hazards Considerations for License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance Supplement Provided in NRC-24-00332024-06-0606 June 2024 Verification of No Significant Hazards Considerations for License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance Supplement Provided in NRC-24-0033 NRC-24-0033, DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-05-30030 May 2024 DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0017, 2023 Annual Radioactive Effluent Release Report and 2023 Radiological Environmental Operating Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report and 2023 Radiological Environmental Operating Report NRC-24-0032, Transmittal of the Core Operating Limits Report for Cycle 232024-04-25025 April 2024 Transmittal of the Core Operating Limits Report for Cycle 23 NRC-24-0027, Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-04-24024 April 2024 Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0031, Retake Exam Outline Submittal Letter2024-04-22022 April 2024 Retake Exam Outline Submittal Letter NRC-24-0018, 2023 Annual Non-Radiological Environmental Operating Report2024-04-0909 April 2024 2023 Annual Non-Radiological Environmental Operating Report NRC-24-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2024-03-31031 March 2024 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-24-0001, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, TSTF-439, Rev. 2, Eliminate Second Completion2024-03-21021 March 2024 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, TSTF-439, Rev. 2, Eliminate Second Completion NRC-24-0019, Submittal of 2023 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2024-03-14014 March 2024 Submittal of 2023 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-24-0023, NRC-24-0023, Post Exam Package Submittal Letter to NRC2024-03-0707 March 2024 NRC-24-0023, Post Exam Package Submittal Letter to NRC NRC-24-0008, Levels and Sources of Property Insurance Coverage2024-02-15015 February 2024 Levels and Sources of Property Insurance Coverage NRC-24-0009, Request for NRC to Suspend Regulatory Audit of License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance for Fermi Unit 22024-02-0606 February 2024 Request for NRC to Suspend Regulatory Audit of License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance for Fermi Unit 2 NRC-24-0007, Report of Changes to Quality Assurance Program for Radioactive Material Packages2024-01-12012 January 2024 Report of Changes to Quality Assurance Program for Radioactive Material Packages NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0079, Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 222023-12-14014 December 2023 Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 22 NRC-23-0077, Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan2023-12-0404 December 2023 Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-23-0075, Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notification Implementation2023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notification Implementation NRC-23-0073, Guarantee of Payment of Deferred Premiums2023-11-29029 November 2023 Guarantee of Payment of Deferred Premiums NRC-23-0071, Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-10-13013 October 2023 Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0064, Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-09-11011 September 2023 Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0057, Independent Spent Fuel Storage Installation Cask Registration2023-08-31031 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0054, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 20232023-08-31031 August 2023 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 2023 NRC-23-0056, Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval2023-08-31031 August 2023 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. NRC-23-0059, Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0060, Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0053, Independent Spent Fuel Storage Installation Cask Registration2023-08-23023 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0050, Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-10010 August 2023 Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0048, Independent Spent Fuel Storage Installation Cask Registration2023-08-0101 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0049, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-07-24024 July 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0043, Independent Spent Fuel Storage Installation, Cask Registration2023-06-27027 June 2023 Independent Spent Fuel Storage Installation, Cask Registration NRC-23-0020, License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2023-06-13013 June 2023 License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-23-0039, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-06-0606 June 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0029, Snubber Program for the Fourth 10-Year Testing Interval2023-06-0505 June 2023 Snubber Program for the Fourth 10-Year Testing Interval NRC-23-0030, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2023-06-0505 June 2023 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi NRC-23-0031, Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2023-05-16016 May 2023 Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements 2024-09-03 |
Text
Fermi 2 6400 North Dixie Hwy., Newport, M1 48166 Detroit Edison March 10, 2010 NRC- 10-0018 Regional Administrator Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, Illinois 60532-4352
Reference:
Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
Subject:
Scheduling of Initial Operator Licensing Examinations In a telephone conversation on January 21, 2010, Mr. Dell McNeil requested that Fermi 2 transmit the preliminary dates for the Fermi 2 initial operator licensing examinations in 2015 and 2016. For the year 2015 the proposed primary dates are the weeks of February 23 and March 2. For the year 2016 the proposed primary dates
'are the weeks, of September 5 and September 12. No alternate dates are proposed at this time.
No new commitments are made in this letter.
Should you have any questions in this matter, please contact Mr. David Coseo, General Supervisor, Operations Training at (734) 586-4055.
Sincerely, Rodney Wohnson Manager, Nuclear Licensing cc: NRC Project Manager Document Control Desk, Washington D C Reactor Projects Chief, Branch 4, Region III NRC Resident Office:
Janet R. Kweiser, DRS, Operations Branch, Region III Y A DTE Energy Company