January 27, 2010 Summary of Pre-Application Meeting with Maine Yankee to Discuss Proposed Security Fence Relocations at the Maine Yankee Independent Spent Fuel Storage Installation. (TAC No. L24402) (W/Enclosure 1: Attendance List)
ML100500823
Person / Time
Site: Maine Yankee
Issue date: 02/19/2010
From: Goshen J
NRC/NMSS/SFST/LID/LB
To: Weaver D
NRC/NMSS/SFST/LID
Goshen, JM, NNSS/SFST, 492-3325
Shared Package
ML100500811 List:
References
TAC L24402
Download: ML100500823 (5)


Text

February 19, 2010 MEMORANDUM TO: Doug Weaver, Deputy Director Licensing and Inspection Directorate Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards FROM: John Goshen, Project Manager /RA/

Licensing Branch Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards

SUBJECT:

SUMMARY

OF JANUARY 27, 2010, PRE-APPLICATION MEETING WITH MAINE YANKEE TO DISCUSS PROPOSED SECURITY FENCE RELOCATIONS AT THE MAINE YANKEE INDEPENDENT SPENT FUEL STORAGE INSTALLATION. (TAC NO. L24402)

PURPOSE:

To provide Maine Yankee the opportunity to discuss their proposed application to relocate part of the security fence at the Maine Yankee Independent Spent Fuel Storage Installation (ISFSI) with NRC staff.

MEETING

SUMMARY

The meeting took place on January 27, 2010, from 10:00 a.m. to 11:30 a.m., at the NRCs Two White Flint Building in Rockville, MD. Attendees included Maine Yankee staff, NRCs Nuclear Security and Incident Response (NSIR) staff, and NRC Region I (RI) staff. The attendance list is enclosed (Enclosure 1). The meeting discussed Safeguards information, and the public was excluded. The meeting began with introductions, introductory remarks by Maine Yankee staff, and then Maine Yankees presentation (Enclosure 2) of the proposed protected area fence system.

Maine Yankee provided the presentation to allow the NRC staff to provide feedback on Maine Yankees intent to implement the change without prior NRC approval under 10 CFR 50.54. It is Maine Yankees intent to commence work on the project on May 1, 2010. The NRC staff indicated that due to their lack of familiarity with the details of the Maine Yankee ISFSI site and the current security provisions they would need to perform an on-site review of the specific details in order to provide feedback to Maine Yankee on the proposed change. NSIR and RI staff will coordinate the site visit with Maine Yankee staff to be held in late February or early March 2010.

No regulatory decisions were made at the meeting.

D. Weaver If you have any questions or comments, please contact me at (301) 492-3325 or John.goshen@nrc.gov.

Docket Nos. 72-30, 50-309 TAC No. L24402

Enclosures:

As stated

D. Weaver If you have any questions or comments, please contact me at (301) 492-3325 or John.goshen@nrc.gov.

Docket Nos. 72-30, 50-309 TAC No. L24402

Enclosures:

As stated DISTRIBUTION:

NRC attendees jconnell@3yankees.com BWhite File Location: G:\SFST\Maine Yankee\01 27 10 meeting\MY 01 27 10 Mtg Summary.doc G:\SFST\Maine Yankee\01 27 10 meeting\MY Enclosure 2.pdf ADAMS Accession/Package No.: ML100500811 OFC: SFST SFST SFST NAME: JGoshen WWheatley EBenner DATE: 2/17/2010 2/ 18 /2010 2/19/2010 OFFICIAL RECORD COPY

ENCLOSURE 1 January 27, 2010 ATTENDANCE LIST Name Affiliation Sandra Wastler NSIR/DSP/DDMS/MWISB John Goshen NMSS/SFST/LB Rupert Rockhill NSIR/DSP/DDMS/MWIS James Connell Maine Yankee Mark Roberts R-I/DNMS/DB John Nicholson R-I/DNMS/DB

ENCLOSURE 2 MAINE YANKEE ISFSI REVIEW OF REGULATORY ISSUES ASSOCIATED WITH PROTECTED AREA FENCE RECONSTRUCTION