ML100490992

From kanterella
Jump to navigation Jump to search
Response to Comanche Peak Disputed Non-Cited Violation 05000445-09-004-05 and 05000446-09-004-05
ML100490992
Person / Time
Site: Comanche Peak  
Issue date: 02/18/2010
From: Caniano R
Division of Reactor Safety IV
To: Flores R
Luminant Generation Co
References
EA 09-306, IR-09-004
Download: ML100490992 (6)


See also: IR 05000445/2009004

Text

February 18, 2010

EA 09-306

Rafael Flores, Senior Vice President

and Chief Nuclear Officer

Attention: Regulatory Affairs

Luminant Generation Company LLC

P.O. Box 1002

Glen Rose, TX 76043

SUBJECT:

RESPONSE TO COMANCHE PEAK DISPUTED NON-CITED VIOLATION 05000445/2009004-05; 00500446/2009004-05

Dear Mr. Flores,

This letter provides the results of Region IV's review of your letter, dated November 23, 2009

(ML093350541), regarding Non-cited Violation 05000445/2009004-05; 00500446/2009004-05,

Failure to Assure that One Train of Equipment is Free from Fire Damage. In your letter, you

denied that a violation had occurred and requested the NRC to further review the issue. The

NRC has reviewed the information provided in your letter and all applicable supporting

documentation, and has concluded that the issue did involve a violation. Specifically, the NRC

did not approve of using operator actions to restore the required functions provided by auxiliary

feedwater or charging in lieu of providing the required separation or protection.

The violation involved the failure to ensure that at least one of the redundant trains needed to

achieve and maintain a safe shutdown condition would be free of fire damage by providing

separation, fire barriers, and/or alternative shutdown capability. The examples cited involved

components from the auxiliary feedwater and the charging and volume control systems that

might not be available to perform the functions credited in your fire safe shutdown analysis

because of potential fire damage. Specifically, the auxiliary feedwater system was credited to

perform the decay heat removal function, and the charging and volume control system was

credited to perform the reactor makeup and reactivity control functions.

The examples described in the violation were recognized as being susceptible to potential fire

damage during the fire safe shutdown analysis. Our reviews indicate that this recognition was

not clearly documented, nor was it identified to the NRC in docketed licensing submittals. The

fire safe shutdown analysis was documented or discussed in seven different documents, only

three of which were submitted for NRC review. The manner in which this susceptibility to fire

damage was documented was inconsistent in the different documents. In particular, the

docketed licensing submittals contained statements that at least one of the redundant trains

needed to achieve and maintain a safe shutdown condition would be free of fire damage by

providing separation, fire barriers, and/or alternative shutdown capability. However, in non-

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

Luminant Generation Company LLC

- 2 -

docketed support documents, it becomes apparent that when the required methods of

protection and separation alternative means were not met, the analysis documented local

alternative acceptance criteria, rather than using an approved method. In the examples cited,

your alternative to separation and protection was to use operator actions to restore the required

functions after fire damage occurred.

Our review has concluded that, for the examples cited, Comanche Peak failed to meet the

requirements for separation and/or protection of the required functions. Your contention that the

NRC approved the use of manual actions in lieu of protection was not supported by the

docketed material that comprises the current licensing basis for your fire protection program.

Your letter contained a position that Comanche Peaks fire protection program was approved to

allow operator actions as a compliance methodology. However, the NRC safety evaluation

reports that document the review and approval of your fire protection program clearly indicate

the criteria used to determine that acceptability of your program, and those criteria did not

include operator actions as an alternative to separation and/or protection. Our review indicated

that Comanche Peak was approved for 30 specific deviations where these criteria were not met.

Each deviation properly identified the requirements that were not met and demonstrated how

the alternative strategy met the underlying intent to the criteria. While some of your approved

deviations involved alternative separation or protection strategies, none involved reliance on

operator actions in lieu of meeting the separation and protection criteria. On the contrary, two

requested deviations that proposed reliance on operator actions were not approved, and the

NRC required modifications to the plant in order to provide the proper equipment protection.

Your letter indicated that in 1987 and 1988, inspectors reviewed the non-docketed calculations

that documented your alternatives to meeting the NRCs separation and protection criteria.

Inspection Reports 87-22 and 88-39, as well as Supplemental Safety Evaluation Report 21

support that claim. These documents reflect an inspection focus on whether manual actions

needed to respond to spurious operation of associated circuits that were taken in the same area

as the postulated fire could be reliably performed. Inspection Report 87-22 contained

comments on the lack of clarity of the intent and timing of the operator actions in the fire safe

shutdown analysis calculation. However, Inspection Reports 87-22 and 88-39, as well as

Supplemental Safety Evaluation Report 21 do not state an approval of the use of operator

actions in lieu of meeting the protection and separation criteria. NRC Management Directive

8.4, "Management of Facility-Specific Backfitting and Information Collection," defines tacit

acceptance/approval as being: "when the NRC's silence to a licensee request is, by rule,

deemed to be approval. Instances of tacit acceptance are rare; silence or lack of comment by

the NRC staff where the NRC's rules do not require an NRC response does NOT constitute tacit

acceptance." Therefore, the review of the non-docketed calculation by inspectors did not

constitute NRC approval of the use of those operator actions.

The operator actions associated with examples in the violation involved locally positioning air-

operated valves. The instrument air system is the support system that provides the air supply to

operate the valves. Our review concluded that your fire safe shutdown analysis failed to identify

that instrument air was required to be available in order to support the charging and auxiliary

feedwater functions, and therefore failed to classify this system as a system needed to achieve

a post-fire safe shutdown condition.

Luminant Generation Company LLC

- 3 -

Your letter indicated that the violation referred to the NRC's approval of the pertinent part of the

fire protection program in Supplemental Safety Evaluation Report 12, which was issued before

you made changes to the fire safe shutdown analysis. Our review indicated that the changes

were reviewed in Supplemental Safety Evaluation Report 21, Section 9.5.1, but this supplement

did not supersede the previous discussion in Supplemental Safety Evaluation Report 12.

Instead, it treated the revision to the program as an update. Although the Fire Hazards Analysis

Report conclusions and the staff's conclusions were the same after the changes, it would have

been more appropriate to refer to the staff's conclusions in both Supplemental Safety Evaluation

Reports 12 and 21 in the statement of the violation.

Your letter stated that the NRC's contention in the violation is different from what was approved

during licensing, and if the NRC maintains this position, this may constitute a backfit. In a

conversation with Mr. Neil O'Keefe on February 1, 2010, Mr. F. Madden, Director of Regulatory

Affairs, stated that it was not Luminant's intention to claim a backfit or request an NRC review of

whether the violation involved a backfit. Mr. Madden stated that the intention was to mention

the possibility that a backfit might be involved. Therefore, no backfit review was performed as

part of this enforcement review.

In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of the

NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Roy J. Caniano, Director

Division of Reactor Safety

Dockets: 50-445; 50-446

Licenses: NPF-87; NPF-89

Luminant Generation Company LLC

- 4 -

Mike Blevins, Chief Operating Officer

Luminant Generation Company LLC

Comanche Peak Steam Electric Station

P.O. Box 1002

Glen Rose, TX 76043

Mr. Fred W. Madden, Director

Oversight and Regulatory Affairs

Luminant Generation Company LLC

P.O. Box 1002

Glen Rose, TX 76043

Timothy P. Matthews, Esq.

Morgan Lewis

1111 Pennsylvania Avenue, NW

Washington, DC 20004

County Judge

P.O. Box 851

Glen Rose, TX 76043

Mr. Richard A. Ratliff, Chief

Bureau of Radiation Control

Texas Department of Health

P.O. Box 149347, Mail Code 2835

Austin, TX 78714-9347

Environmental and Natural

Resources Policy Director

Office of the Governor

P.O. Box 12428

Austin, TX 78711-3189

Honorable Walter Maynard

County Judge

P.O. Box 851

Glen Rose, TX 76043

Mr. Brian Almon

Public Utility Commission

William B. Travis Building

P.O. Box 13326

Austin, TX 78711-3326

Luminant Generation Company LLC

- 5 -

Ms. Susan M. Jablonski

Office of Permitting, Remediation

and Registration

Texas Commission on

Environmental Quality

MC-122

P.O. Box 13087

Austin, TX 78711-3087

Anthony Jones

Chief Boiler Inspector

Texas Department of Licensing

And Regulation

Boiler Division

E.O. Thompson State Office Building

P.O. Box 12157

Austin, TX 78711

Chief, Technological Hazards

Branch

FEMA Region VI

800 North Loop 288

Federal Regional Center

Denton, TX 76209

Luminant Generation Company LLC

- 6 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Chuck.Casto@nrc.gov)

DRS Director (Roy.Caniano@nrc.gov)

DRS Deputy Director (Troy.Pruett@nrc.gov)

DRP Director (Dwight.Chamberlain@nrc.gov)

DRP Deputy Director (Anton.Vegel@nrc.gov)

Branch Chief, ACES (William.Jone@nrc.gov)

Senior Enforcement Specialist (Mark.Haire@nrc.gov)

Senior Resident Inspector (John.Kramer@nrc.gov)

Resident Inspector (Brian.Tindell@nrc.gov)

Senior Project Engineer (David. Proulx@nrc.gov)

Branch Chief, DRP/A (Wayne.Walker@nrc.gov)

CP Site Secretary (Sue.Sanner@nrc.gov)

Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

OEMail.Resource (OEMail.Resource@nrc.gov)

OEDO RIV Coordinator (Leigh.Trocine@nrc.gov)

OE Director (Roy.Zimmerman@nrc.gov)

OE Deputy Director (Belkys.Sosa@nrc.gov)

Branch Chief, Enforcement Branch, OE (Nick.Hilton@nrc.gov)

G. Gulla (Gerry.Gulla@nrc.gov)

Branch Chief, Fire Protection Branch, NRR (Alex.Klein@nrc.gov)

Team Leader, Fire Protection Branch, NRR (Dan.Frumkin@nrc.gov)

P. Qualls (Phil.Qualls@nrc.gov)

M. Ashley (MaryAnn.Ashley@nrc.gov)

J. Mateychick (John.Mateychick@nrc.gov)

R:\\Reactors\\CP Response-disputed NCV - NFO

ADAMS ML

ADAMS: No  ; Yes

NFOSUNSI Review Complete

Reviewer Initials: NFO

Publicly Available
Non-Sensitive

Category A.

Non-publicly Available

Sensitive

KEYWORD:

EB 2

C:EB2

SEC: ACES

C: PBA

D: DRS

J. Mateychick N. O'Keefe

R. Kellar

W. Walker

R. Caniano

/RA/

/RA/

/RA/

/RA/

/RA/

2/11 /2010

2/ 16 /2010

2/ 17 /2010

2/ 16 /2010

2/ 18 /2010

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax