ML100321543
From kanterella
Jump to navigation
Jump to search
ML100321543 | |
Person / Time | |
---|---|
Site: | Indian Point, Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png |
Issue date: | 11/24/1981 |
From: | Soutar C Consolidated Edison Co of New York |
To: | Haynes R NRC/OE, NRC/OI/RGN-I/FO |
Shared Package | |
ML093430786 | List: |
References | |
NUDOCS 8112170097 | |
Download: ML100321543 (1) | |
Similar Documents at Indian Point, Haddam Neck | |
---|---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217K3161999-10-19019 October 1999
[Table view]Forwards Amend 195 to License DPR-61 & Safety Evaluation. Amend Deletes Certain TSs Either No Longer Applicable to Permanently Shutdown & Defueled State of Reactor or Duplicate Regulatory Requirements CY-99-137, Notifies NRC of Intent to Apply Haddam Neck Plant 10CFR50 App B,Qa Program to Activities Related to Development of ISFSI at Haddam1999-10-12012 October 1999 Notifies NRC of Intent to Apply Haddam Neck Plant 10CFR50 App B,Qa Program to Activities Related to Development of ISFSI at Haddam DD-99-11, Informs That Time Provided by NRC Regulation within Which Commission May Act to Review Director'S Decision (DD-99-11) Expired & That Commission Declined Any Review.Decision Became Final Action on 9910041999-10-0808 October 1999 Informs That Time Provided by NRC Regulation within Which Commission May Act to Review Director'S Decision (DD-99-11) Expired & That Commission Declined Any Review.Decision Became Final Action on 991004 ML20217B3331999-10-0707 October 1999 Responds to 990825 Telephone Call Re Presense of Polychlorinated Biphenyl Wastes at Plant,Unit 1 ML20212L1261999-10-0404 October 1999 Forwards Viewgraphs Presented by Licensee at 990923 Meeting with Nrc,In Response to Request ML20212D0341999-09-20020 September 1999 Expresses Appreciation for Accepting NRC Request for Tour of Haddam Neck Facility During on 991014.Invites R Mellor to Participate in NRC 1999 Decommissioninng Power Reactor Work- Shop:Nrc Insp Program at Decommissioning Power Reactors ML20212F4481999-09-17017 September 1999 Forwards NRC Form 536 Containing Currently Proposed Site Specific Operator Licensing Exam Schedule & Estimates of Number of Applicants for Generic Fundamentals Exams Through Cy 2003 ML20212F7051999-09-14014 September 1999 Forwards Rev 19 to Ipn,Units 1 & 2 Physical Security Plan. Plan Withheld,Per 10CFR2.790(d) & 73.21 ML20211N0681999-09-0202 September 1999 Informs That Commission Requested Publication of Notice of Consideration of Issuance of Amend to Fol,Proposed NSHC Determination & Opportunity for Hearing. Amend Changes Senior Reactor License Requirement for Operations Manager CY-99-111, Submits Clarification of Changes Made to Connecticut Yankee QA Program,Per Util 990810 Submittal.Change Will Be Submitted to NRC in Dec 1999 as Part of Annual Update1999-09-0202 September 1999 Submits Clarification of Changes Made to Connecticut Yankee QA Program,Per Util 990810 Submittal.Change Will Be Submitted to NRC in Dec 1999 as Part of Annual Update ML20211H6291999-08-26026 August 1999 Forwards NPDES Discharge Monitoring Rept for July 1999 for Indian Point,Units 1,2 & 3. Rept of Noncompliance Is Attached for Noncompliance Which Occurred at Unit 3 ML20211E8051999-08-20020 August 1999 Forwards Insp Rept 50-213/99-02 on 990420-0719.No Violations Noted.Completion of Corrective Actions for Spent Fuel Bldg Ventilation Issues Adequate ML20211H6051999-08-18018 August 1999 Forwards Rev 8 to Security Force Training & Qualification Plan, for Indian Point 3 Nuclear Power Plant.Rev Facilitates Transition of Duty Weapons Carried by Security Force Members from Revolvers to Semiautomatic Pistols ML20211E1531999-08-18018 August 1999 Forwards Semi Annual fitness-for-duty Program Performance Data for 990101-990630,IAW 10CFR26.71(d) ML20211A9241999-08-11011 August 1999 Informs That IPS Currently Estimates,That Approx Two Licensing Actions Will Be Submitted to NRC During Remainder of 1999 NRC Fiscal Yr & Approx Ten Will Be Submitted During 2000 NRC Fiscal Yr ML20210J6021999-08-0202 August 1999 Informs That Info Re Orise Technical Survey Assistance to NRC at CT Yankee Is to Include Copies of Listed Documents CY-99-048, Forwards Cyap Rept CY-HP-0031,Rev 0, Bounding Dose Assessment for Offsite Radioactive Matls1999-07-29029 July 1999 Forwards Cyap Rept CY-HP-0031,Rev 0, Bounding Dose Assessment for Offsite Radioactive Matls ML20210M7251999-07-26026 July 1999 Forwards Projection of Ability to Pay Retrospective Premium Adjustment for Period of Aug 1999 to 000731, Which Demonstrates That Ceny Will Have Sufficient Cash Flow &/Or Cash Reserve Available Throughout Period to Pay Premium ML20210G8911999-07-20020 July 1999 Forwards Application for Amend to License DPR-5 for Proposed New TS 3.2.1.i,revising Senior Reactor License Requirement for Operations Manager CY-99-066, Forwards Revised Plan for Recovery of Licensed Matl from Offsite Locations.Completion of Implementation of Plan During Summer of 1999 Is Planned,Contingent on Support Extended by Property Owners,Weather & Uncontrolled Factors1999-07-20020 July 1999 Forwards Revised Plan for Recovery of Licensed Matl from Offsite Locations.Completion of Implementation of Plan During Summer of 1999 Is Planned,Contingent on Support Extended by Property Owners,Weather & Uncontrolled Factors ML20210C1491999-07-0101 July 1999 Responds to ,Which Responded to NRC Ltr & NOV & Informs That Engagement in Any Similar Wrongdoing in Future May Result in More Significant Enforcement Action. No Further Action Will Be Taken at This Time ML20209C3911999-06-30030 June 1999 Forwards TS Page 6-3 for Haddam Neck Plant ML20209B6611999-06-29029 June 1999 Returns Recently Submitted Renewal Applications,Nrc Form 398,for Three Reactor Operators,As They Are Not Completed Properly.List of Docket Numbers & Block Numbers That Contain Incorrect Info & Block Numbers Not Completed.Without Encls ML20195H1741999-06-15015 June 1999 Forwards Original & Copy of Request for Approval of Certain Indirect & Direct Transfer of License & Ownership Interests of Montaup Electric Co (Montaup) with Respect to Nuclear Facilities Described as Listed ML20196A6371999-06-15015 June 1999 Forwards Rev 19 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(d) & 73.21 ML20195F9011999-06-0909 June 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp 50-213/98-06 on 990226. Util Did Not Agree with Disposition of Issue Cited as Severity Level IV Violation.Violation Will Be Noncited ML20195H3591999-06-0202 June 1999 Responds to NRC Re Violations Noted in Insp of License DPR-61.Corrective Actions:Disciplinary Actions Were Taken by Util Against Jm Foley & Individual & Departmental Emphasis Is Placed on New HP Stds & Expectations ML20207E9031999-06-0202 June 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Mt Masnik Will Be Section Chief for Haddam Neck.Organization Chart Encl ML20207D1861999-05-27027 May 1999 Informs That Effective 990328,NRC Office of NRR Underwent Reorganization.Mt Masnik Section Chief for Indian Point Station,Unit 1.JL Minns Remains Primary Contact for All Routine Licensing & Administrative Matters.Chart Encl ML20207B9301999-05-25025 May 1999 Responds to 990114 Correspondence Re Changes to Plant Defueled Physical Security Plan Rev 1 Submitted Under 10CFR50.54(p).Implementation of Changes Subj to Insp to Confirm Changes Have Not Decreased Security Plan ML20207G1761999-05-21021 May 1999 Forwards Insp Rept 50-213/99-01 on 980119-990419 & Closure of CAL 1-97-010.No Violations Noted.Conduct of Activities Associated with Control of Radiological Work at Haddam Neck Generally Characterized as Careful & Thorough ML20206R7021999-05-12012 May 1999 Refers to Investigation 1-97-008 Conducted by Region I & Forwards Notice of Violation.Investigation Found That Recipient Deliberately Attempted to Conceal Release of Contaminated Video Equipment ML20206R8051999-05-12012 May 1999 Responds to 3 Investigations,Repts 1-97-031,008 & 1-98-008 Between 970314 & 980722 as Well as Insp Conducted Between 980720 & 1102.Forwards Synopsis of 3rd OI Investigation ML20206R7221999-05-12012 May 1999 Refers to Investigation 1-97-031 on 970616-0718 & Forwards Nov.Investigation Found That Recipient Deliberately Did Not Follow Radiation Protection Procedures,Falsified Documents & Provided Incomplete & Inaccurate Info to NRC CY-99-057, Forwards 1998 Annual Radioactive Effluent Rept for HNP, & Rev 10 to Remodcm. with Summary of Quantities of Solid Radwaste & Liquid & Gaseous Effluents,As Well as Summary of Assessment of Max Individual Dose1999-04-30030 April 1999 Forwards 1998 Annual Radioactive Effluent Rept for HNP, & Rev 10 to Remodcm. with Summary of Quantities of Solid Radwaste & Liquid & Gaseous Effluents,As Well as Summary of Assessment of Max Individual Dose ML20206J2801999-04-30030 April 1999 Forwards 1998 Annual Financial Repts for CT Light & Power Co,Western Ma Electric Co,Public Svc Co of Nh,North Atlantic Energy Corp,Northeast Nuclear Energy Co & North Atlantic Energy Svc Corp,License Holders ML20206C8631999-04-28028 April 1999 Forwards Amend 194 to License DPR-61 & Safety Evaluation. Amend Authorizes Relocation of Requirements Related to Seismic Monitoring Instrumentation from TSs to Technical Requirements Manual ML20206A6871999-04-22022 April 1999 Informs of Completion of Review of Re Nepco in Capacity as Minority Shareholder in Vermont Yankee Nuclear Power Corp,Yaec,Myap & Connecticut Yankee Atomic Power Co ML20205R1981999-04-15015 April 1999 Requests That Dept of Environ Conservation Modify SPDES Permit for IPS IAW Proposed Rev Attached & Described as Listed ML20205R2961999-04-15015 April 1999 Forwards Copy of Proposed Change to Indian Point SPDES Permit NY0004472.Proposed Change Requests Permission to Add Permitted Outfall to Plant as Well as Change Character of Existing Outfall.Without Encl ML20210V5221999-04-0808 April 1999 Discusses Continued Performance of Technical Assistance Activities for NRC & Environ Survey & Site Assessment Program (Essap) Survey Assistance at Cy IR 05000213/19960121999-04-0505 April 1999 Discusses NRC Insp Repts 50-213/96-12 & 50-213/98-04 on 961102-27 Re Airborne Radioactivity Contamination Event That Occurred in Fuel Transfer Canal & Reactor Cavity in Nov 1996.Notice of Violation Encl ML20205J7931999-04-0505 April 1999 Discusses NRC Insp Repts 50-213/96-12 & 50-213/98-04 on 961102-27 Re Airborne Radioactivity Contamination Event That Occurred in Fuel Transfer Canal & Reactor Cavity in Nov 1996.Notice of Violation Encl ML20196K8111999-03-31031 March 1999 Forwards Decommissioning Funding Status Rept for Indian Point,Units 1 & 2 Through 981231 CY-99-042, Provides Info on Status of Decommissioning Funding for Haddam Neck Plant1999-03-31031 March 1999 Provides Info on Status of Decommissioning Funding for Haddam Neck Plant CY-99-024, Responds to Violations Noted in Insp Rept 50-213/98-06. Corrective Actions:Meetings Were Held with Contractor Mgt, Disciplinary Action Against Worker Was Taken & Notices Alerting Workers to HRA Controls Were Posted1999-03-29029 March 1999 Responds to Violations Noted in Insp Rept 50-213/98-06. Corrective Actions:Meetings Were Held with Contractor Mgt, Disciplinary Action Against Worker Was Taken & Notices Alerting Workers to HRA Controls Were Posted ML20206A6951999-03-29029 March 1999 Request Confirmation That No NRC Action or Approval,Required Relative to Proposed Change in Upstream Economic Ownership of New England Power Co,Minority Shareholder in Vermont Yankee Nuclear Power Corp,Yaec,Myap & Connecticut Yankee ML20205F9711999-03-25025 March 1999 Informs That Under Separate Cover,Licensee Transmitted to Ofc of Nuclear Regulatory Research Annual Rept of Results of Individual Monitoring at Indian Point,Units 1 & 2,for CY98 ML20204F7931999-03-17017 March 1999 Forwards Table Outlining Nuclear Property Insurance Which Has Been Placed on Behalf of Consolidated Edison Co of Ny, Inc.Insurance Covers Indian Point,Units 1 & 2 B17697, Notifies NRC of Amount of Property Insurance Coverage, Effective 990401,for HNP & Mnps,Units 1,2 & 3,per Provisions of 10CFR50.54(w)1999-03-12012 March 1999 Notifies NRC of Amount of Property Insurance Coverage, Effective 990401,for HNP & Mnps,Units 1,2 & 3,per Provisions of 10CFR50.54(w) 1999-09-20 Category:INCOMING CORRESPONDENCE MONTHYEARCY-99-137, Notifies NRC of Intent to Apply Haddam Neck Plant 10CFR50 App B,Qa Program to Activities Related to Development of ISFSI at Haddam1999-10-12012 October 1999
[Table view]Notifies NRC of Intent to Apply Haddam Neck Plant 10CFR50 App B,Qa Program to Activities Related to Development of ISFSI at Haddam ML20212F4481999-09-17017 September 1999 Forwards NRC Form 536 Containing Currently Proposed Site Specific Operator Licensing Exam Schedule & Estimates of Number of Applicants for Generic Fundamentals Exams Through Cy 2003 ML20212F7051999-09-14014 September 1999 Forwards Rev 19 to Ipn,Units 1 & 2 Physical Security Plan. Plan Withheld,Per 10CFR2.790(d) & 73.21 CY-99-111, Submits Clarification of Changes Made to Connecticut Yankee QA Program,Per Util 990810 Submittal.Change Will Be Submitted to NRC in Dec 1999 as Part of Annual Update1999-09-0202 September 1999 Submits Clarification of Changes Made to Connecticut Yankee QA Program,Per Util 990810 Submittal.Change Will Be Submitted to NRC in Dec 1999 as Part of Annual Update ML20211E1531999-08-18018 August 1999 Forwards Semi Annual fitness-for-duty Program Performance Data for 990101-990630,IAW 10CFR26.71(d) ML20211H6051999-08-18018 August 1999 Forwards Rev 8 to Security Force Training & Qualification Plan, for Indian Point 3 Nuclear Power Plant.Rev Facilitates Transition of Duty Weapons Carried by Security Force Members from Revolvers to Semiautomatic Pistols ML20211A9241999-08-11011 August 1999 Informs That IPS Currently Estimates,That Approx Two Licensing Actions Will Be Submitted to NRC During Remainder of 1999 NRC Fiscal Yr & Approx Ten Will Be Submitted During 2000 NRC Fiscal Yr CY-99-048, Forwards Cyap Rept CY-HP-0031,Rev 0, Bounding Dose Assessment for Offsite Radioactive Matls1999-07-29029 July 1999 Forwards Cyap Rept CY-HP-0031,Rev 0, Bounding Dose Assessment for Offsite Radioactive Matls ML20210M7251999-07-26026 July 1999 Forwards Projection of Ability to Pay Retrospective Premium Adjustment for Period of Aug 1999 to 000731, Which Demonstrates That Ceny Will Have Sufficient Cash Flow &/Or Cash Reserve Available Throughout Period to Pay Premium ML20210G8911999-07-20020 July 1999 Forwards Application for Amend to License DPR-5 for Proposed New TS 3.2.1.i,revising Senior Reactor License Requirement for Operations Manager CY-99-066, Forwards Revised Plan for Recovery of Licensed Matl from Offsite Locations.Completion of Implementation of Plan During Summer of 1999 Is Planned,Contingent on Support Extended by Property Owners,Weather & Uncontrolled Factors1999-07-20020 July 1999 Forwards Revised Plan for Recovery of Licensed Matl from Offsite Locations.Completion of Implementation of Plan During Summer of 1999 Is Planned,Contingent on Support Extended by Property Owners,Weather & Uncontrolled Factors ML20209C3911999-06-30030 June 1999 Forwards TS Page 6-3 for Haddam Neck Plant ML20196A6371999-06-15015 June 1999 Forwards Rev 19 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(d) & 73.21 ML20195H1741999-06-15015 June 1999 Forwards Original & Copy of Request for Approval of Certain Indirect & Direct Transfer of License & Ownership Interests of Montaup Electric Co (Montaup) with Respect to Nuclear Facilities Described as Listed ML20195H3591999-06-0202 June 1999 Responds to NRC Re Violations Noted in Insp of License DPR-61.Corrective Actions:Disciplinary Actions Were Taken by Util Against Jm Foley & Individual & Departmental Emphasis Is Placed on New HP Stds & Expectations CY-99-057, Forwards 1998 Annual Radioactive Effluent Rept for HNP, & Rev 10 to Remodcm. with Summary of Quantities of Solid Radwaste & Liquid & Gaseous Effluents,As Well as Summary of Assessment of Max Individual Dose1999-04-30030 April 1999 Forwards 1998 Annual Radioactive Effluent Rept for HNP, & Rev 10 to Remodcm. with Summary of Quantities of Solid Radwaste & Liquid & Gaseous Effluents,As Well as Summary of Assessment of Max Individual Dose ML20206J2801999-04-30030 April 1999 Forwards 1998 Annual Financial Repts for CT Light & Power Co,Western Ma Electric Co,Public Svc Co of Nh,North Atlantic Energy Corp,Northeast Nuclear Energy Co & North Atlantic Energy Svc Corp,License Holders ML20205R2961999-04-15015 April 1999 Forwards Copy of Proposed Change to Indian Point SPDES Permit NY0004472.Proposed Change Requests Permission to Add Permitted Outfall to Plant as Well as Change Character of Existing Outfall.Without Encl ML20210V5221999-04-0808 April 1999 Discusses Continued Performance of Technical Assistance Activities for NRC & Environ Survey & Site Assessment Program (Essap) Survey Assistance at Cy ML20196K8111999-03-31031 March 1999 Forwards Decommissioning Funding Status Rept for Indian Point,Units 1 & 2 Through 981231 CY-99-042, Provides Info on Status of Decommissioning Funding for Haddam Neck Plant1999-03-31031 March 1999 Provides Info on Status of Decommissioning Funding for Haddam Neck Plant ML20206A6951999-03-29029 March 1999 Request Confirmation That No NRC Action or Approval,Required Relative to Proposed Change in Upstream Economic Ownership of New England Power Co,Minority Shareholder in Vermont Yankee Nuclear Power Corp,Yaec,Myap & Connecticut Yankee CY-99-024, Responds to Violations Noted in Insp Rept 50-213/98-06. Corrective Actions:Meetings Were Held with Contractor Mgt, Disciplinary Action Against Worker Was Taken & Notices Alerting Workers to HRA Controls Were Posted1999-03-29029 March 1999 Responds to Violations Noted in Insp Rept 50-213/98-06. Corrective Actions:Meetings Were Held with Contractor Mgt, Disciplinary Action Against Worker Was Taken & Notices Alerting Workers to HRA Controls Were Posted ML20205F9711999-03-25025 March 1999 Informs That Under Separate Cover,Licensee Transmitted to Ofc of Nuclear Regulatory Research Annual Rept of Results of Individual Monitoring at Indian Point,Units 1 & 2,for CY98 ML20204F7931999-03-17017 March 1999 Forwards Table Outlining Nuclear Property Insurance Which Has Been Placed on Behalf of Consolidated Edison Co of Ny, Inc.Insurance Covers Indian Point,Units 1 & 2 B17697, Notifies NRC of Amount of Property Insurance Coverage, Effective 990401,for HNP & Mnps,Units 1,2 & 3,per Provisions of 10CFR50.54(w)1999-03-12012 March 1999 Notifies NRC of Amount of Property Insurance Coverage, Effective 990401,for HNP & Mnps,Units 1,2 & 3,per Provisions of 10CFR50.54(w) CY-99-032, Clarifies Info Re TRM Change Submitted with Re Proposed Rev to TSs on Seismic Monitoring1999-03-0909 March 1999 Clarifies Info Re TRM Change Submitted with Re Proposed Rev to TSs on Seismic Monitoring ML20204C6901999-02-22022 February 1999 Informs That Public Citizen Waives Copyright for 5th Edition of Nuclear Lemon So NRC May Reproduce for Purpose of Contributing to NRC Recommended Improvements to Oversight Process for Nuclear Power Reactors CY-99-005, Responds to NRC 981221 RAI Re Amend 193 to License to Reflect Permanent Shutdown Condition of Plant.Licensee Withdrawing 981030 (CY-98-199) Request & Will Submit Corrections in Future Proposed Rev to TS1999-01-29029 January 1999 Responds to NRC 981221 RAI Re Amend 193 to License to Reflect Permanent Shutdown Condition of Plant.Licensee Withdrawing 981030 (CY-98-199) Request & Will Submit Corrections in Future Proposed Rev to TS ML20203H9711999-01-21021 January 1999 Requests Response to Concerns Raised by Constitutent M Marucci Re Spent Fuel at Decommissioned Nuclear Plants CY-99-002, Forwards Response to NRC 981203 RAI Re Proposed License Amend to Relocate Requirements for Seismic Monitoring Instrumentation from Section 3/4.3.3.3 of TS to Trm. Supporting TSs Encl1999-01-18018 January 1999 Forwards Response to NRC 981203 RAI Re Proposed License Amend to Relocate Requirements for Seismic Monitoring Instrumentation from Section 3/4.3.3.3 of TS to Trm. Supporting TSs Encl CY-99-010, Provides Special Rept Concerning Potential of Radiation Exposure Due to Hypothetical Explosive Attack to Facility. Without Encl1999-01-14014 January 1999 Provides Special Rept Concerning Potential of Radiation Exposure Due to Hypothetical Explosive Attack to Facility. Without Encl CY-99-009, Forwards Rev 1 to Haddam Neck Plant Defueled Physical Security Plan,Per 10CFR50.54(p).Rev Does Not Decrease Effectiveness of Plan.Encl Withheld,Per 10CFR73.21 & 2.7901999-01-14014 January 1999 Forwards Rev 1 to Haddam Neck Plant Defueled Physical Security Plan,Per 10CFR50.54(p).Rev Does Not Decrease Effectiveness of Plan.Encl Withheld,Per 10CFR73.21 & 2.790 ML20199H3731999-01-11011 January 1999 Informs That T Schmeiser,Con Ed Plant Manager for Plant Is Retiring,Effective 990111.AA Blind Will Assume Duties & Responsibilities of Plant Manager Until Replacement Named CY-98-142, Forwards Proposed Rev 2 of Cyap QAP for Info & Approval of Exception Number 8 of App E of Cy Qap.Copy of Rev 2 Showing Changes from Rev 1 Also Included1998-12-22022 December 1998 Forwards Proposed Rev 2 of Cyap QAP for Info & Approval of Exception Number 8 of App E of Cy Qap.Copy of Rev 2 Showing Changes from Rev 1 Also Included ML20198C4911998-12-11011 December 1998 Forwards Rev 18 to Physical Security Plan,Reflecting Organizational Changes & Incorporating Administrative Corrections & Clarifications.Encl Withheld CY-98-201, Provides Clarification of NRC Staff SE for Amend 193 Which Approved HNP Defueled TSs1998-12-0303 December 1998 Provides Clarification of NRC Staff SE for Amend 193 Which Approved HNP Defueled TSs CY-98-191, Provides Notification That Util Implemented Defueled Emergency Plan for HNP on 981001.Util Completed Annual Exercise Required by Subj Plan & 10CFR50.471998-11-0505 November 1998 Provides Notification That Util Implemented Defueled Emergency Plan for HNP on 981001.Util Completed Annual Exercise Required by Subj Plan & 10CFR50.47 CY-98-140, Provides Commitment to Maintain Water Chemistry Requirements in HNP Technical Requirements Manual1998-11-0202 November 1998 Provides Commitment to Maintain Water Chemistry Requirements in HNP Technical Requirements Manual CY-98-183, Forwards Revised License Amend 193 TS Pages to Correct Amend Number on Pages Not Changed by Amend 193.No Commitments Contained within Ltr1998-10-30030 October 1998 Forwards Revised License Amend 193 TS Pages to Correct Amend Number on Pages Not Changed by Amend 193.No Commitments Contained within Ltr CY-98-199, Forwards Listing of Corrections Made & Revised Pages for Proposed License Amend 193.Ltr Also Transmits Repaginated Pages for TS Index & Section 1,per Request of NRC Project Manager1998-10-30030 October 1998 Forwards Listing of Corrections Made & Revised Pages for Proposed License Amend 193.Ltr Also Transmits Repaginated Pages for TS Index & Section 1,per Request of NRC Project Manager CY-98-154, Forwards Sf Mgt Plan for Haddam Neck Plant.Plan Submits Info on Mgt & Funding for Program to Safely Store Sf Following Permanent Cessation of Power Operations Until Title Is Transferred to DOE1998-10-28028 October 1998 Forwards Sf Mgt Plan for Haddam Neck Plant.Plan Submits Info on Mgt & Funding for Program to Safely Store Sf Following Permanent Cessation of Power Operations Until Title Is Transferred to DOE CY-98-062, Updates Info of Historical Nature in Response to Both NRC Historical Review Rept & NRC Insp Rept 50-213/97-11 Open Items1998-10-28028 October 1998 Updates Info of Historical Nature in Response to Both NRC Historical Review Rept & NRC Insp Rept 50-213/97-11 Open Items ML20155F9181998-10-28028 October 1998 Forwards Changes to SPDES Permit,Removing Requirement to Monitor Svc Boiler Blowdown for Phosphates,Eliminate Redundant Sampling of Oil or Grease Entering Flow Tributary to Floor Drains,Per Ts,App B,Section 3.2 ML20155D2791998-10-23023 October 1998 Forwards Corrected Pages for Indian Point Annual Radiological Environ Operating Rept for 1997 CY-98-129, Provides Supplemental Info to 980629 Response to 2.206 Petition Questions on Spent Fuel Cooling Methods.Util Pending Commitment Made within Ltr Stated1998-10-14014 October 1998 Provides Supplemental Info to 980629 Response to 2.206 Petition Questions on Spent Fuel Cooling Methods.Util Pending Commitment Made within Ltr Stated CY-98-186, Provides Notification of Organizational Changes Which Affect Cyap.Organization Chart,Biographical Profile of K Heider & Revised Distribution List for NRC Correspondence,Encl1998-10-0202 October 1998 Provides Notification of Organizational Changes Which Affect Cyap.Organization Chart,Biographical Profile of K Heider & Revised Distribution List for NRC Correspondence,Encl CY-98-153, Forwards Final Response to NRC 961009 RAI Re Configuration Mgt Project at Plant.No New Commitments Made within Ltr or Attachment1998-09-30030 September 1998 Forwards Final Response to NRC 961009 RAI Re Configuration Mgt Project at Plant.No New Commitments Made within Ltr or Attachment CY-98-157, Responds to NRC Request That Cyap Submit Proposed License Amend to Include Fuel Storage Pool Water Chemistry Program within Haddam Neck Plant Ts.Cyap Considers That Amend Is Not Necessary for Listed Reasons.Procedure Encl1998-09-28028 September 1998 Responds to NRC Request That Cyap Submit Proposed License Amend to Include Fuel Storage Pool Water Chemistry Program within Haddam Neck Plant Ts.Cyap Considers That Amend Is Not Necessary for Listed Reasons.Procedure Encl B17440, Corrects Errors in Ltrs & 980225 Re semi-annual Fitness for Duty Performance Data for Jan-June 1998 & July-Dec 19971998-09-24024 September 1998 Corrects Errors in Ltrs & 980225 Re semi-annual Fitness for Duty Performance Data for Jan-June 1998 & July-Dec 1997 1999-09-02 Category:UTILITY TO NRC MONTHYEARML0934410661990-09-0606 September 1990
[Table view]Forwards Rev 20 to Vol I Emergency Plan Index,Rev 35 to Vol II, Emergency Response Activation, Rev 60 to Vol III EPIP Index & Rev 12 to IP-1011, Offsite Monitoring/Site Perimeter Surveys. B13622, Forwards Crdr Human Engineering Discrepancy Info for Plant1990-08-30030 August 1990 Forwards Crdr Human Engineering Discrepancy Info for Plant B13617, Requests NRC Revise Confirmatory Order for Plant to Specify New Completion Date of Cycle 16 Refueling Outage for Item II.E.1.2.Util Intends to Implement Design Change During Next Refueling Outage to Resolve Listed Issues1990-08-22022 August 1990 Requests NRC Revise Confirmatory Order for Plant to Specify New Completion Date of Cycle 16 Refueling Outage for Item II.E.1.2.Util Intends to Implement Design Change During Next Refueling Outage to Resolve Listed Issues B13615, Requests That 900705 Request for Amend to License DPR-61 Be Approved on Emergency Basis & That Temporary Waiver of Compliance from Tech Spec 4.4.6.2.1.g Be Given Until NRC Acts on Emergency Amend1990-08-20020 August 1990 Requests That 900705 Request for Amend to License DPR-61 Be Approved on Emergency Basis & That Temporary Waiver of Compliance from Tech Spec 4.4.6.2.1.g Be Given Until NRC Acts on Emergency Amend B13611, Forwards, Semiannual Radioactive Effluents Release Rept for Jan-June 19901990-08-16016 August 1990 Forwards, Semiannual Radioactive Effluents Release Rept for Jan-June 1990 B13595, Notifies NRC That Utils Volunteer to Participate in Emergency Response Data Sys Project for All Four Nuclear Units,Per Generic Ltr 89-15 & NUREG-13941990-08-14014 August 1990 Notifies NRC That Utils Volunteer to Participate in Emergency Response Data Sys Project for All Four Nuclear Units,Per Generic Ltr 89-15 & NUREG-1394 B13602, Submits Addendum to Plant Control Room Design Review Summary Rept,Per .Lists 10CFR50 App R-related Mods Outside Control Room That Could Not Be Reviewed Until After Final Implementation of Changes1990-08-14014 August 1990 Submits Addendum to Plant Control Room Design Review Summary Rept,Per .Lists 10CFR50 App R-related Mods Outside Control Room That Could Not Be Reviewed Until After Final Implementation of Changes B13580, Discusses Revised Tech Spec Conversion Program,Reflecting Conversion of Tech Spec to Westinghouse Sts.Future Upgrade of Tech Specs Should Be Conducted on Voluntary Basis Consistent W/Nrc Policy Statement1990-08-10010 August 1990 Discusses Revised Tech Spec Conversion Program,Reflecting Conversion of Tech Spec to Westinghouse Sts.Future Upgrade of Tech Specs Should Be Conducted on Voluntary Basis Consistent W/Nrc Policy Statement ML1003314851990-08-0707 August 1990 Forwards Proprietary WCAP-12687 & Nonproprietary WCAP-12688, Indian Point Unit 2 Tube Fatigue Reevaluation, Rev 2,per NRC Request.Proprietary Rept Withheld (Ref 10CFR2.790) B13603, Withdraws 900731 Request for Temporary Waiver of Compliance W/Tech Spec 3.7.1.2 Re Inoperability of Auxiliary Feedwater Pumps1990-08-0202 August 1990 Withdraws 900731 Request for Temporary Waiver of Compliance W/Tech Spec 3.7.1.2 Re Inoperability of Auxiliary Feedwater Pumps ML1003314901990-08-0101 August 1990 Forwards Proprietary WCAP-12670 & Nonproprietary WCAP-12671, Indian Point Unit 2 - Final Rept on Steam Generator Insp, Repair & Restoration Efforts During 1990 Midcycle Insp. Proprietary Rept Withheld (Ref 10CFR2.790(b)(4)) B13601, Requests Temporary Waiver of Compliance from Tech Spec 3.7.1.2,allowing Plant to Remain in Mode 3 for Addl 14 Days Beyond Current Action Statement Limits W/One or of Two Auxiliary Feedwater Pumps Inoperable1990-07-31031 July 1990 Requests Temporary Waiver of Compliance from Tech Spec 3.7.1.2,allowing Plant to Remain in Mode 3 for Addl 14 Days Beyond Current Action Statement Limits W/One or of Two Auxiliary Feedwater Pumps Inoperable ML20058L4741990-07-31031 July 1990 Forwards 900713 Projection for Aug 1990 - Jul 1991 Guaranteeing Payment of Deferred Premiums ML20056A7181990-07-27027 July 1990 Forwards Corrected Page 3.10-9 Inadvertently Omitted from 900621 Application for Amend to License DPR-64 Re Removal of cycle-specific Parameter Limits Per Generic Ltr 88-16 B13585, Provides Supplemental Response to Generic Ltr 89-19 Re Request for Action Concerning Resolution of Unresolved Safety Issue A-47.Plant Procedures Modified to Provide Operability Verification of Steam Generator Protection Sys1990-07-26026 July 1990 Provides Supplemental Response to Generic Ltr 89-19 Re Request for Action Concerning Resolution of Unresolved Safety Issue A-47.Plant Procedures Modified to Provide Operability Verification of Steam Generator Protection Sys B13571, Clarifies 900625 Tech Spec Change Request Re Limit of 160 Failed Fuel Rods for Cycle 16 Operation1990-07-19019 July 1990 Clarifies 900625 Tech Spec Change Request Re Limit of 160 Failed Fuel Rods for Cycle 16 Operation B13569, Forwards, Haddam Neck Plant Decommissioning Financial Assurance Certification Rept1990-07-18018 July 1990 Forwards, Haddam Neck Plant Decommissioning Financial Assurance Certification Rept ML20055G9971990-07-17017 July 1990 Forwards Decommissioning Financial Assurance Certification Rept for Facilities,Per 10CFR50.33(K)(2) ML0934410591990-07-16016 July 1990 Forwards Rev 34 to Vol II, Emergency Response Activation, & Revised Epips,Including Rev 11 to IP-1038,Rev 16 to IP-1050,Rev 6 to IP-1054 & Rev 12 to IP-1076 ML20055E6791990-07-0606 July 1990 Responds to NRC Bulletin 88-008, Thermal Stresses in Piping Connected to Rcs. All Socket Welded Joints from Header Isolation motor-operated Valves to RCS for All 4 Loops Examined.No Recordable Indications Found ML20055D3461990-07-0303 July 1990 Responds to NRC Bulletin 90-001 Re Loss of Fill Oil Transmitters Mfg by Rosemount.Operability Determinations Performed & Documented for All Rosemount 1153 & 1154 Transmitters at Facility ML20055D7191990-06-29029 June 1990 Amends 900604 Rev 13 to QA Program B13564, Provides NRC W/Info Re Plant Pressurizer as follow-up to 900607 Meeting.Info Particularly Concerns Disposition of Three Indications on Pressurizer Inner Surface & Discussion of Resolution of Previous Indication1990-06-29029 June 1990 Provides NRC W/Info Re Plant Pressurizer as follow-up to 900607 Meeting.Info Particularly Concerns Disposition of Three Indications on Pressurizer Inner Surface & Discussion of Resolution of Previous Indication B13550, Responds to Generic Ltr 90-04, Request for Info on Status of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions. Implementation & Completion Tables for staff-imposed Requirements Encl1990-06-27027 June 1990 Responds to Generic Ltr 90-04, Request for Info on Status of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions. Implementation & Completion Tables for staff-imposed Requirements Encl ML1003314461990-06-27027 June 1990 Forwards Proprietary & Nonproprietary WCAP-12625 & WCAP-12626, Status Rept Indian Point Unit 2 Mid-Cycle Steam Generator Insp Presentation to NRC & WCAP-12627 & WCAP-12628, Indian Point Unit 2 Steam Generator Insp.... ML20043H9981990-06-21021 June 1990 Forwards Application for Amend to License DPR-64,proposing Removal of cycle-specific Parameters from Tech Specs,Per Generic Ltr 88-16 ML20043G2971990-06-11011 June 1990 Submits Supplemental Info Re New Temp Sensors Installed in Primary Auxiliary Bldg & Revised Safety Evaluation,To Support 900412 Request for Tech Spec Changes.New Temp Sensors in Piping Penetration Have Setpoints of 140 F ML0934410501990-05-18018 May 1990 Forwards Rev 20 to Emergency Plan,Rev 33 to Emergency Response Activation & Revised Epips,Including IP-1011 ML1003312261990-05-16016 May 1990 Forwards Proprietary WCAP 12573 & Nonproprietary WCAP 12574, Indian Point Unit 2 Steam Generator Insp,Repair & Restoration Program Per NRC 900314 Request.Proprietary Rept Withheld ML20012F4791990-04-0303 April 1990 Informs That Current Revs to Emergency Plan Sent to NRC Document Control Desk ML1003312131990-03-0505 March 1990 Forwards Rev 5 to Fire Protection Program Plan. ML1003311891990-01-19019 January 1990 Forwards Nonproprietary WCAP-11812 & Proprietary WCAP-11811, Indian Point Unit 2 Evaluation for Tube Vibration Induced Fatigue, Per Request for Addl Info Re Implementation of NRC Bulletin 88-002.Proprietary Rept Withheld (Ref 10CFR2.790) ML1003311711989-11-20020 November 1989 Forwards Public Version of Revised Emergency Procedures Document,Including Rev 4 to IAP-7,Revs 2 to IP-1008 to IP-1014,Rev 6 to IP-1016,Rev 4 to IP-1019,Rev 5 to IP-1029 & Revs 3 to IP-1033 & IP-1039 ML1003311581989-11-20020 November 1989 Forwards Rev 2 to WCAP-12294 & Proprietary Rev 2 to WCAP-12293, Indian Point Unit 2 Steam Generator Girth Weld/ Feedwater Nozzles Rept,Spring,1989 Outage. Proprietary Rept Withheld (Ref 10CFR2.790) ML1003311541989-11-14014 November 1989 Forwards Nonproprietary WCAP-12443 & Proprietary WCAP-12442, Info Presented to NRC Re Indian Point Unit 2 Steam Generator Loose Objects, Per 891102 Meeting Concerning 1989 Inservice Insp.Proprietary Rept Withheld (Ref 10CFR2.790) ML1003311731989-11-13013 November 1989 Forwards Public Version of Revised EPIPs Including Rev 9 to IP-1002 & Rev 5 to IP-1007.W/DH Grimsley 891211 Release Memo ML1003311491989-10-24024 October 1989 Forwards Public Version of Books 1 & 2 of Emergency Procedures Document,Including Rev 4 to IP-1029, Emergency Closeout/Class Reduction Written Summary to Authorities. B13364, Forwards Rev 19 to Modified Amended Security Plan.Rev Withheld (Ref 10CFR2.790(a))1989-10-0505 October 1989 Forwards Rev 19 to Modified Amended Security Plan.Rev Withheld (Ref 10CFR2.790(a)) A08598, Provides Clarification of Util Position Re Emergency Notification Sys (ENS) & Health Physics Network (Hpn).Util Intends to Provide Two Separate Qualified Individuals for ENS & HPN Communications During Exercise Drills1989-10-0202 October 1989 Provides Clarification of Util Position Re Emergency Notification Sys (ENS) & Health Physics Network (Hpn).Util Intends to Provide Two Separate Qualified Individuals for ENS & HPN Communications During Exercise Drills B13376, Forwards Util Response to Generic Ltr 89-04 Re Guidance on Developing Acceptable Inservice Test Programs1989-10-0202 October 1989 Forwards Util Response to Generic Ltr 89-04 Re Guidance on Developing Acceptable Inservice Test Programs ML20248E4521989-09-29029 September 1989 Forwards Proposed Tech Spec Pages Omitted from 890728 Application for Amend to License DPR-61 Re Cycle 16 Reload B13375, Responds to Request for Addl Info Re Electrical Distribution Sys Design Associated W/New Switchgear Bldg.New Switchgear Bldg Provides Opportunity to Minimize Dependence on Motor Control Ctr 5 & Further Reduce Level of Risk1989-09-29029 September 1989 Responds to Request for Addl Info Re Electrical Distribution Sys Design Associated W/New Switchgear Bldg.New Switchgear Bldg Provides Opportunity to Minimize Dependence on Motor Control Ctr 5 & Further Reduce Level of Risk B13374, Forwards Bimonthly Progress Rept 18 Re New Switchgear Bldg Const1989-09-27027 September 1989 Forwards Bimonthly Progress Rept 18 Re New Switchgear Bldg Const ML20248B2671989-09-25025 September 1989 Forwards Cycle 7 Startup Physics Test Rept,Indian Point Unit 3 B13352, Requests Exemption from Certain Requirements of 10CFR50,App J to Assure That Containment Leakage During Design Basis Event Will Not Exceed Applicable Leakage Limits. Justification Encl1989-09-0808 September 1989 Requests Exemption from Certain Requirements of 10CFR50,App J to Assure That Containment Leakage During Design Basis Event Will Not Exceed Applicable Leakage Limits. Justification Encl B13346, Forwards Tornado Missile Risk Analysis of Bleed & Feed & Auxiliary Feedwater Safe Shutdown Sys at Connecticut Yankee Atomic Power Station, Per SEP Topics III-2 & III-4.A1989-08-30030 August 1989 Forwards Tornado Missile Risk Analysis of Bleed & Feed & Auxiliary Feedwater Safe Shutdown Sys at Connecticut Yankee Atomic Power Station, Per SEP Topics III-2 & III-4.A A08170, Forwards Updated Schedules for Operator Licensing & Requalification Exams for Plants,Per Generic Ltrs 89-12 & 89-031989-08-30030 August 1989 Forwards Updated Schedules for Operator Licensing & Requalification Exams for Plants,Per Generic Ltrs 89-12 & 89-03 A08237, Confirms Receipt of Listed Invoices for Costs Incurred During Routine Insps1989-08-28028 August 1989 Confirms Receipt of Listed Invoices for Costs Incurred During Routine Insps B13351, Provides Clarifications of Util & NRC 890525 Insp Rept 50-213/89-200.Util Proposes to Extend Schedule for Completion of Sampling and Evaluation Program to 900930 & Valves That Fail Systematic Testing Will Be Replaced1989-08-28028 August 1989 Provides Clarifications of Util & NRC 890525 Insp Rept 50-213/89-200.Util Proposes to Extend Schedule for Completion of Sampling and Evaluation Program to 900930 & Valves That Fail Systematic Testing Will Be Replaced B13340, Submits Results of Svc Water & Primary Auxiliary Bldg Equipment Operability Analyses Not Provided in 890428 Submittal of Results of ECCS Single Failure Analysis1989-08-24024 August 1989 Submits Results of Svc Water & Primary Auxiliary Bldg Equipment Operability Analyses Not Provided in 890428 Submittal of Results of ECCS Single Failure Analysis 1990-09-06 |
Text
Charles F. Soutar Senor Vice Prew-oent
- a. 0 Consolidated Edison Company of New York, Inc.
4 Irving P'ace, New York, NY 10003 Telephone (212) 460-4696 November 24, 1981 Re: Indian Point Unit No. 2 Docket No. 50-247 Mr. Ronald C. Haynes, Director Office of Inspection and Enforcement Region I U. S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pa. 19406
Dear Mr. Haynes:
Please find attached INPO report, "Evaluation of Indian Point Station Unit No. 2", October 1981. A copy of the attached has already been provided to the resident inspector.
Should you or your staff have any questions, please contact us.
Very truly yours, Attachment cc: Mr. T. Rebelowski, Senior Resident Inspector w/o Attach U. S. Nuclear Regulatory Commission P. 0. Box 38 Buchanan, New York 10511 i\ef
'~