Category:Environmental Assessment
MONTHYEARML21054A3042021-04-22022 April 2021 Final Environmental Assessments and Findings of No Significant Impact of Independent Spent Fuel Storage Facilities Decommissioning Funding Plans Related to Susquehanna ML1008103102010-03-29029 March 2010 ME2839 & ME2840, Correction Letter Correction Fr Notice for EA-FR for Publication in Fr and Corrected Fr Notice for Exemption Prior to Publication in Fr ML1001102532010-03-15015 March 2010 Environmental Assessment and Finding of No Significant Impact Request for Exemption from Implementation Deadline for Physical Security Plans ML0733903062007-12-0707 December 2007 Final Environmental Assessment and Finding of No Significant Impact Related to the Proposed License Amendment to Increase the Maximum Reactor Power Level ML0733204082007-08-15015 August 2007 Draft Environmental Assessment and Finding of No Significant Impact Related to the Proposed License Amendment to Increase the Maximum Reactor Power Level ML0609303652006-03-31031 March 2006 Ltr B Mckinney, PPL Susquehanna, Re Federal Register Notice Publishing an Environmental Assessment and Finding of No Significant Impact for an Exemption from 10 CFR 72.212 and 72.214 (TAC No. L23943) Docket 72-28 2021-04-22
[Table view] Category:Federal Register Notice
MONTHYEARML23073A1192023-03-31031 March 2023 Associated Independent Spent Fuel Storage Installation - Order Approving Indirect Transfer of Licenses & Draft Conforming License Amendments EPID L-2022-LLM-0003 - FRN - Enclosure 5 ML22299A1122022-11-0303 November 2022 Notice of Consideration of Approval of Indirect Transfer of Licenses & Conforming Amendments & Opportunity to Request Hearing - Susquehanna Steam Station, Units 1 & 2 & Associated Independent Spent Fuel Storage Installation (EPID L-2022-LLM ML22299A1132022-11-0303 November 2022 Notice of Consideration of Approval of Indirect Transfer of Licenses and Conforming Amendments & Opportunity to Request Hearing - Susquehanna Steam Station, Units 1 & 2 & Associated Independent Spent Fuel Storage Installation (EPID L-2022-L ML20335A0902020-12-21021 December 2020 Federal Register Notice - November 2020 COVID-19 Exemptions ML20271A0002020-10-13013 October 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for September 2020 ML20035C4082020-02-18018 February 2020 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 02/25/2020 ML19042A3062019-02-15015 February 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 2/26/2019 ML18278A2802018-10-10010 October 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 10/23/2018 NRC-2018-0140, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/20182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML18180A2182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML17213A1842017-08-0404 August 2017 Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 2017 NRC-2017-0175, Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 20172017-08-0404 August 2017 Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 2017 ML16243A3882016-09-28028 September 2016 Federal Register Notice Susquehanna Steam Electric Station, Units 1 and 2, Consideration of Approval of Application Regarding License Transfer of Renewed Facility Operating License Nos. NPF-14 and NPF-22 ML16239A4242016-09-16016 September 2016 Letter with Notice of Consideration of Approval of Transfer of Licenses and Opportunity for a Hearing ML16131A7952016-05-13013 May 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 2016 NRC-2016-0100, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 20162016-05-13013 May 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 2016 ML15218A6252015-08-14014 August 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 14, 2015 ML15202A2252015-07-23023 July 2015 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing ML15202A2292015-07-23023 July 2015 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing (Enclosure) ML15054A0582015-04-10010 April 2015 Letter Forwarding Order Approving Transfer of Licenses and Conforming Amendments Related to Susquehanna Steam Electric Station, Units 1 and 2 (TAC MF4426 and MF4427) NRC-2012-0283, PPL Susquehanna, LLC; Susquehanna Steam Electric Station, Unit Nos. 1 and 2 EDG Amd Frequency Withdraw Federal Register Notice2015-02-0909 February 2015 PPL Susquehanna, LLC; Susquehanna Steam Electric Station, Unit Nos. 1 and 2 EDG Amd Frequency Withdraw Federal Register Notice ML15027A6032015-02-0909 February 2015 PPL Susquehanna, LLC; Susquehanna Steam Electric Station, Unit Nos. 1 and 2 EDG Amd Frequency Withdraw Federal Register Notice ML15027A6052015-02-0909 February 2015 Withdrawal of an Amendment Request ML15027A6112015-02-0909 February 2015 Withdrawal of an Amendment Request ML14149A3102014-05-30030 May 2014 FRN: Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations: Publication Date: June 6, 2014 NRC-2014-0132, FRN: Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations: Publication Date: June 6, 20142014-05-30030 May 2014 FRN: Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations: Publication Date: June 6, 2014 ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit ML13228A3992013-08-12012 August 2013 Letter to Holders of Independent Spent Fuel Storage Installation (ISFSI) Licenses Re Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit - Rin 3150-AI64 (NRC-2009-0163) EA-02-109 NRC-2012-0069, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents - to All Operating Boiling Water Reactor Licensees with Mark I and Mark Ii Containments2012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Hardened Containment Vents - to All Operating Boiling Water Reactor Licensees with Mark I and Mark Ii Containments NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status2012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML12056A0432012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Hardened Containment Vents - to All Operating Boiling Water Reactor Licensees with Mark I and Mark II Containments ML12056A0442012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status NRC-2012-0063, Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing2012-03-0909 March 2012 Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing ML12068A4222012-03-0909 March 2012 Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing ML12068A4192012-03-0909 March 2012 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing ML1126504892011-09-22022 September 2011 FRN: General Notice. Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations NRC-2011-0230, FRN: General Notice. Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations2011-09-22022 September 2011 FRN: General Notice. Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations NRC-2011-0040, Sholly Report for Fr Publication on February 22, 20112011-02-10010 February 2011 Sholly Report for Fr Publication on February 22, 2011 ML1104103732011-02-10010 February 2011 Sholly Report for Fr Publication on February 22, 2011 ML1008103102010-03-29029 March 2010 ME2839 & ME2840, Correction Letter Correction Fr Notice for EA-FR for Publication in Fr and Corrected Fr Notice for Exemption Prior to Publication in Fr ML1001102922010-03-19019 March 2010 ME2839 & ME2840, Transmittal Letter to Licensee for Exemption & Fr Request for Exemption from Part 73 Implementation Date ML1001102532010-03-15015 March 2010 Environmental Assessment and Finding of No Significant Impact Request for Exemption from Implementation Deadline for Physical Security Plans ML0931602812009-11-24024 November 2009 FRN: General Notice. Issuance of Renewed Facility Operating License Nos. NPF-14 and NPF-22 for the Susquehanna Steam Electric Station, Units 1 and 2 NRC-2009-0389, Frn:General Notice, Notice of Withdrawal of Application for Amendment to Facility Operating License2009-08-31031 August 2009 Frn:General Notice, Notice of Withdrawal of Application for Amendment to Facility Operating License ML0924300972009-08-31031 August 2009 Frn:General Notice, Notice of Withdrawal of Application for Amendment to Facility Operating License ML0922300552009-08-31031 August 2009 Letter Regarding Withdrawal of an Amendment Request and FRN ML0911306172009-04-24024 April 2009 Biweekly Notice, Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations ML0908901562009-03-30030 March 2009 Withdrawal of an Amendment Request ML0734404282008-04-25025 April 2008 Notice of Availability of the Draft Supplement 34 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants, and Public Meeting for the Renewal of Plant Name ML0907109672008-03-13013 March 2008 Notice of Availability of the Final Plant-Specific Supplement 35 to the GEIS for License Renewal of Nuclear Plants Regarding Susquehanna Steam Electric Station, Units 1 and 2 (TAC Nos. MD3022, MD3021) FRN 2023-03-31
[Table view] Category:Finding of No Significant Impact
MONTHYEARML21054A3042021-04-22022 April 2021 Final Environmental Assessments and Findings of No Significant Impact of Independent Spent Fuel Storage Facilities Decommissioning Funding Plans Related to Susquehanna ML1008103102010-03-29029 March 2010 ME2839 & ME2840, Correction Letter Correction Fr Notice for EA-FR for Publication in Fr and Corrected Fr Notice for Exemption Prior to Publication in Fr ML1001102532010-03-15015 March 2010 Environmental Assessment and Finding of No Significant Impact Request for Exemption from Implementation Deadline for Physical Security Plans ML0733903062007-12-0707 December 2007 Final Environmental Assessment and Finding of No Significant Impact Related to the Proposed License Amendment to Increase the Maximum Reactor Power Level ML0733204082007-08-15015 August 2007 Draft Environmental Assessment and Finding of No Significant Impact Related to the Proposed License Amendment to Increase the Maximum Reactor Power Level ML0609303652006-03-31031 March 2006 Ltr B Mckinney, PPL Susquehanna, Re Federal Register Notice Publishing an Environmental Assessment and Finding of No Significant Impact for an Exemption from 10 CFR 72.212 and 72.214 (TAC No. L23943) Docket 72-28 2021-04-22
[Table view] Category:Letter
MONTHYEARIR 05000387/20230042024-02-0707 February 2024 Integrated Inspection Report 05000387/2023004 and 05000388/2023004 PLA-8096, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2024-01-0404 January 2024 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8077, Emergency Plan Revision 67 (PLA-8077)2023-12-27027 December 2023 Emergency Plan Revision 67 (PLA-8077) IR 05000387/20230102023-12-11011 December 2023 Fire Protection Team Inspection Report 05000387/2023010 and 05000388/2023010 PLA-8089, Submittal of Revision to Inservice Testing Program Plan2023-12-0505 December 2023 Submittal of Revision to Inservice Testing Program Plan PLA-8084, Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.22023-11-29029 November 2023 Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23345A0682023-11-28028 November 2023 Technical Specification Bases, Manual PLA-8091, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091)2023-11-0808 November 2023 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091) IR 05000387/20230032023-11-0303 November 2023 Integrated Inspection Report 05000387/2023003 and 05000388/2023003 PLA-8082, Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2023-11-0202 November 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML23291A1132023-10-12012 October 2023 Submittal of Revision 71 to Updated Final Safety Analysis Report and Revision 25 to Fire Protection Review Report ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23277A0412023-10-0505 October 2023 Notification of Commercial Grade Dedication Inspection (05000387/2024011 and 05000388/2024011) and Request for Information IR 05000387/20233012023-09-20020 September 2023 Initial Operator Licensing Examination Report 05000387/2023301 and 05000388/2023301 ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) IR 05000387/20230052023-08-31031 August 2023 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2023005 and 05000388/2023005) ML23228A1952023-08-21021 August 2023 Summary of August 10, 2023, Public Observation Meeting Re. Proposed Alternative PLA-8080, Proposed Relief for Valve 251130 (PLA-8080)2023-08-14014 August 2023 Proposed Relief for Valve 251130 (PLA-8080) PLA-8074, Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2023-08-0303 August 2023 Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval IR 05000387/20230022023-08-0101 August 2023 Integrated Inspection Report 05000387/2023002 and 05000388/2023002 ML23195A1852023-07-27027 July 2023 Correction to Technical Specifications Page 3.3-73 in Amendment No. 265 PLA-8076, Unit 2 - 21st Refueling Outage Owner'S Activity Report (PLA-8076)2023-07-20020 July 2023 Unit 2 - 21st Refueling Outage Owner'S Activity Report (PLA-8076) ML23201A0152023-07-20020 July 2023 Operator Licensing Examination Approval ML23200A1012023-07-19019 July 2023 Notification of Conduct of a Fire Protection Team Inspection ML23193A0062023-07-12012 July 2023 Requalification Program Inspection PLA-8078, Submittal of Unit 2 Cycle 22 Core Operating Limits Report, Revision 1, PLA-80782023-07-0505 July 2023 Submittal of Unit 2 Cycle 22 Core Operating Limits Report, Revision 1, PLA-8078 ML23163A1012023-06-12012 June 2023 10 CFR 50.46 Annual Report (Pla 8065) PLA-8054, Proposed Amendment to Licenses NPF-14 and NPF-22: Remove Control Rod Operability Separation Criteria and Replace Reference to Banked Position Withdrawal Sequence with the Analyzed Rod Position Sequence2023-06-0808 June 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Remove Control Rod Operability Separation Criteria and Replace Reference to Banked Position Withdrawal Sequence with the Analyzed Rod Position Sequence IR 05000387/20234012023-06-0707 June 2023 Security Baseline Inspection Report 05000387/2023401 and 05000388/2023401 PLA-8073, Proposed Relief Request for the Fifth 10-Year Inservice Inspection Interval2023-06-0101 June 2023 Proposed Relief Request for the Fifth 10-Year Inservice Inspection Interval PLA-8064, Response to NRC Regulatory Issue Summary 2023-01 (PLA-8064)2023-05-17017 May 2023 Response to NRC Regulatory Issue Summary 2023-01 (PLA-8064) ML23132A3212023-05-17017 May 2023 Associated Independent Spent Fuel Storage Installation - Issuance of Amendment Nos. 285 and 269 Related to Order Approving Transfer of Licenses PLA-8067, Notification of Completion of Emergence from Bankruptcy (PLA-8067)2023-05-17017 May 2023 Notification of Completion of Emergence from Bankruptcy (PLA-8067) IR 05000387/20230012023-05-12012 May 2023 Integrated Inspection Report 05000387/2023001 and 05000388/2023001 PLA-8066, Notification of Planned Closing Date and Information Identified in March 30, 2023 Order, PLA-80662023-05-0808 May 2023 Notification of Planned Closing Date and Information Identified in March 30, 2023 Order, PLA-8066 PLA-8053, Radiation Exposure Information and Reporting System2023-04-27027 April 2023 Radiation Exposure Information and Reporting System PLA-8058, Annual Radiological Environmental Operating Report (PLA-8058)2023-04-26026 April 2023 Annual Radiological Environmental Operating Report (PLA-8058) PLA-8041, Radioactive Effluent Release Report and Offsite Dose Calculation Manual (PLA-8041)2023-04-25025 April 2023 Radioactive Effluent Release Report and Offsite Dose Calculation Manual (PLA-8041) PLA-8047, 2022 Annual Environmental Operating Report (Nonradiological), PLA-80472023-04-19019 April 2023 2022 Annual Environmental Operating Report (Nonradiological), PLA-8047 PLA-8062, Supplement to Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 252F007B, PLA-80622023-04-11011 April 2023 Supplement to Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 252F007B, PLA-8062 PLA-8061, Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 25F007B, PLA-80612023-04-10010 April 2023 Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 25F007B, PLA-8061 ML23090A2302023-03-31031 March 2023 NRC Decommissioning Funding Status Report PLA-8049 PLA-8060, Submittal of Unit 2 Cycle 22 Core Operating Limits Report (PLA-8060)2023-03-30030 March 2023 Submittal of Unit 2 Cycle 22 Core Operating Limits Report (PLA-8060) ML23095A0572023-03-29029 March 2023 NRC Decommissioning Funding Status Report December 31, 2022 PLA-8057, Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments- Supplemental Information, PLA-80572023-03-15015 March 2023 Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments- Supplemental Information, PLA-8057 ML23065A1962023-03-0202 March 2023 EN 56387 Paragon - Part 21 Report Re Defect Identified in Automatic Transfer Switch Pn: NLI-ATS480A400X1 IR 05000387/20220062023-03-0101 March 2023 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2022006 and 05000388/2022006) PLA-8052, (Sses), Proof of Financial Protection and Guarantee of Payment of Deferred Premiums2023-02-13013 February 2023 (Sses), Proof of Financial Protection and Guarantee of Payment of Deferred Premiums IR 05000387/20220042023-02-0808 February 2023 Integrated Inspection Report 05000387/2022004 and 05000388/2022004 ML23010A0882023-01-15015 January 2023 Summary of Regulatory Audit in Support of License Amendment Request to Revise Control Rod Technical Specifications 2024-02-07
[Table view] |
Text
'\,.~p.R REG U/ _ UNITED STATES
.;,V .....".
~ Oil NUCLEAR REGULATORY COMMISSION
~~ ~ WASHINGTON, D.C. 20555-0001
<C
~
~
~
0 tft'lrch 15, 201 ()
V";: ~
+". ~O
Mr. Timothy S. Rausch Senior Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Boulevard Berwick, PA 18603-0467 SUB~IECT: SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT RE: REQUEST FOR EXEMPTION FROM IMPLEMENTATION DEADLINE FOR PHYSICAL SECURITY PLANS (TAC NOS. ME2839 AND ME2840)
Dear Mr. Rausch:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application for exemption dated December 3, 2009, as supplemented by letters dated January 8 and 29, 2010.
PPL Susquehanna, LLC (PPL, or the licensee) requested U.S. Nuclear Regulatory Commission (NRC) approval for an exemption from March 31,2010, implementation date for certain security requirements of Title 10 of the Code of Federal Regulations Part 73, "PHYSICAL PROTECTION OF PLANTS AND MATERIALS," for Susquehanna Steam Electric Station (SSES) Units 1 and 2, issued by NRC in a Final Rule dated March 27, 2009 (74 FR 13926). The proposed exemption would allow an extension from the March 31,2010, implementation date for some specific requirements, until October 29, 2010, for two requirements and until July 31, 2011, for one other requirement.
The environmental assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely, m~~~
Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388
Enclosure:
Environmental Assessment cc w/encl: Distribution via Listserv
7590-01-P UNITED STATES NUCLEAR REGULATORY COMMISSION PPL SUSQUEHANNA, LLC.
DOCKET NOS. 50-387 AND 50-388 SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an Exemption, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 73.5, "Specific exemptions," from the implementation date for certain new requirements of 10 CFR Part 73, "Physical protection of plants and materials," for Renewed Facility Operating License Nos. NPF-14 and NPF-22, issued to PPL Susquehanna, LLC (PPL or the licensee), for operation of the Susquehanna Steam Electric Station (SSES), Units 1 and 2, respectively, located in Luzerne county, Commonwealth of Pennsylvania. Therefore, as required by 10 CFR 51.21, the NRC performed an environmental assessment. Based on the results of the environmental assessment, the NRC is issuing a finding of no significant impact.
ENVIRONMENTAL ASSESSMENT Identification of the Proposed Action:
The proposed action would exempt the licensee from the required implementation date of March 31, 2010, for several new requirements of 10 CFR Part 73. Specifically, the licensee would be granted an exemption from being in full compliance with certain new requirements contained in 10 CFR 73.55 by the March 31,2010, deadline. The licensee has proposed an alternate full compliance implementation date of October 29, 2010, for two requirements and until July 31, 2011, for one other requirement. The proposed action, an extension of the
-2 schedule for completion of certain actions required by the revised 10 CFR Part 73, does not involve any physical changes to the reactor, fuel, plant structures, support structures, water, or land at the SSES Units 1 and 2 site.
The proposed action is in accordance with the licensee's application dated December 3, 2009, as supplemented by letters dated January 8 and 29, 2010.
The Need for the Proposed Action:
The proposed action is needed to provide the licensee with additional time to perform the required upgrades to the SSES Units 1 and 2 security system due to resource and logistical impacts and other factors.
The licensee has requested the proposed exemption from the specific requirements of 10 CFR 73.55, "Requirements for physical protection of licensed activities in nuclear power reactors against radiological sabotage," for SSES Units 1 and 2 by extending the implementation deadline for certain security requirements issued by NRC in a Final Rule dated March 27, 2009 (74 FR 13926).
Pursuant to the Final Rule, the new security requirements must be implemented by March 31, 2010. PPL has evaluated these new requirements and determined that many can be implemented by the required date. PPL has determined, however, that implementation of specific parts of the new requirements will require more time to implement since they are significant physical changes involving or requiring: 1) specific parts that are proving to be long lead time items, 2) specialized industry expertise whose availability is being challenged by the significant demand for a limited resource, or 3) a major interface with the plant for installation that must be carefully planned and implemented to avoid impact to the plant protective strategy.
Specifically, extensions are requested until October 29, 2010, for two requirements and until July 31, 2011, for one other requirement.
-3 Environmental Impacts of the Proposed Action:
The NRC has completed its environmental assessment of the proposed exemption. The staff has concluded that the proposed action to extend the implementation deadline would not significantly affect plant safety and would not have a significant adverse effect on the probability of an accident occurring.
The proposed action would not result in an increased radiological hazard beyond those previously analyzed in the environmental assessment and finding of no significant impact made by the Commission in promulgating its revisions to 10 CFR Part 73 as discussed in a Federal Register notice dated March 27, 2009 (74 FR 13967). There will be no change to radioactive effluents that affect radiation exposures to plant workers and members of the public. Therefore, no changes or different types of radiological impacts are expected as a result of the proposed exemption.
The proposed action does not result in changes to land use or water use, or result in changes to the quality or quantity of non-radiological effluents. No changes to the National Pollution Discharge Elimination System permit are needed. No effects on the aquatic or terrestrial habitat in the vicinity of the plant, or to threatened, endangered, or protected species under the Endangered Species Act, or impacts to essential fish habitat covered by the Magnuson-Steven's Act are expected. There are no impacts to the air or ambient air quality.
There are no impacts to historical and cultural resources. There would be no impact to socioeconomic resources. Therefore, no changes to or different types of non-radiological environmental impacts are expected as a result of the proposed exemption.
Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action. In addition, in promulgating its revisions to 10 CFR Part 73, the Commission prepared an environmental assessment and published a finding of no
-4 significant impact [Part 73, Power Reactor Security Requirements, 74 FR 13926, 13967 (March 27, 2009)].
The licensee currently maintains a security system acceptable to the NRC to provide acceptable physical protection of the SSES, Units 1 and 2 in lieu of the new requirements in 10 CFR Part 73. Therefore, the extension of the implementation date of the new requirements of 10 CFR Part 73 until October 29, 2010, for two requirements and until July 31, 2011, for one other requirement, would not have any significant environmental impacts.
The NRC staff's safety evaluation will be provided in the exemption that will be issued as part of the letter to the licensee approving the exemption to the regulation, if granted.
Environmental Impacts of the Alternatives to the Proposed Action:
As an alternative to the proposed action, the staff considered denial of the proposed action (i.e., the "no-action" alternative). Denial of the application would result in no change in current environmental impacts. If the proposed action was denied, the licensee would have to comply with the March 31, 2010, implementation deadline. The environmental impacts of the proposed action and the alternative action are similar.
Alternative Use of Resources:
The action does not involve the use of any different resources than those previously considered in the Final Environmental Statement for the SSES Units 1 and 2 site, NUREG-0564, dated June 1981 as supplemented through the "Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 35 Regarding Susquehanna Stearn Electric Station, Units 1 and 2 Final Report," dated March 2009.
Agencies and Persons Consulted:
In accordance with its stated policy, on February 17, 2010, the NRC staff consulted with the Commonwealth of Pennsylvania State official, Larry Winker of the Department of
-5 Environmental Protection/Bureau of Radiation Protection, regarding the environmental impact of the proposed action. The State official had no comments.
FINDING OF NO SIGNIFICANT IMPACT On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action.
For further details with respect to the proposed action, see the licensee's letter dated December 3, 2009, as supplemented by letters dated January 8, 2010, and January 29, 2010.
Portions of the letter dated December 3, 2009, as supplemented by letters dated January 8 and January 29, 2010, contain security sensitive information and, accordingly, are withheld from public disclosure in accordance with 10 CFR 2.390. The redacted versions of the December 3, 2009, as supplemented by letters dated January 8 and January 29, 2010, (Agencywide Documents Access and Management System (ADAMS) Accession Number ML093410632, ML100120657, and ML100330085, respectively), may be examined, and/or copied for a fee, at the NRC's Public Document Room (PDR), located at One White Flint North, Public File Area 0 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the ADAMS Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html.
-6 Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1 800-397-4209 or 301-415-4737, or send an e-mail to pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 15th day of MA.rch 2010.
FOR THE NUCLEAR REGULATORY COMMISSION
~'t~.~
Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
' .. ML100110253 OFFICE LPL 1-1/PM LPL 1-1/LA NRR/DLR/RERB/BC NSIR/DSP/RSRLB/BC NAME BVaidya SLittie Almboden DHuyck (wI comments) (wI comments)
DATE 02/24/10 02/24/10 02/25/10 03/01/10 OFFICE OGC LPL 1-1/BC LPL1-1/PM NAME LSubin NSalgado BVaidya DATE 02/09/10 03/10/10 03/15/10