Letter Sequence Other |
---|
|
Results
Other: ML090760564, ML090760582, ML090760616, ML090760623, ML090760681, ML090760687, ML092570573, ML092570583, ML092570606, ML092570614, ML092570623, ML092590265, ML092880122, ML092880813, ML093000630, ML093000631, ML093000633, ML093000634, ML093000635, ML093010001, ML093070737, ML093290246, ML093310365, ML093310366, ML103090261
|
MONTHYEARML0902901012009-01-22022 January 2009 Application for an Order Approving License Transfers and Conforming License Amendment Request Project stage: Request ML0906304262009-02-26026 February 2009 R. E. Ginna and Calvert Cliffs, Units 1 & 2 and Independent Spent Fuel Storage Installation - Supplement to Application for an Order Approving License Transfers and Conforming License Amendment Request Project stage: Supplement ML0905703152009-02-26026 February 2009 Acceptance Review Constellation and Edf Development - Application for Approval of License Transfers and Conforming License Amendment Request-Calvert Cliffs Nuclear Power Plant 1 and 2, Nine Mile Point Nuclear Station 1 and 2, and R.E. Ginna Project stage: Acceptance Review ML0910006652009-04-0808 April 2009 ISFSI, Nine Mile Point, Units 1 & 2, and R. E. Ginna, Supplemental Information in Support of Application for an Order Approving License Transfers and Conforming License Amendment Request Project stage: Supplement ML0907605642009-04-28028 April 2009 Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and 10 CFR 50.80 and 72.50 License Transfer and Opportunity for a Hearing - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Project stage: Other ML0907605822009-04-28028 April 2009 FRN: Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and 10 CFR 50.80 and 72.50 License Transfer and Opportunity for a Hearing - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Project stage: Other ML0907606162009-04-28028 April 2009 Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and Opportunity for a Hearing Project stage: Other ML0907606232009-04-28028 April 2009 FRN: Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and Opportunity for a Hearing - Nine Mile Point Nuclear Station, Units 1 and 2 Project stage: Other ML0907606872009-04-28028 April 2009 FRN: Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and Opportunity for a Hearing - R.E. Ginna Nuclear Power Plant Project stage: Other ML0907606812009-04-28028 April 2009 Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and Opportunity for a Hearing - R.E. Ginna Nuclear Power Plant Project stage: Other ML0916007402009-06-10010 June 2009 Request for Additional Information Application for an Order Approving License Transfers and Conforming License Amendment for Calvert Cliffs, Units 1 & 2, ISFSI, Nine Mile, Units 1 & 2, and R.E. Ginna Project stage: RAI ML0918110942009-06-25025 June 2009 ISFSI; Nine Mile Point, Units 1 & 2 and R. E. Ginna - Response to Nrc'S Request for Additional Information Project stage: Request ML0919603652009-07-15015 July 2009 E-mail from R. Guzman to E. Tyler Request for Additional Information - CENG-EDF License Transfer (TAC Nos. ME0443, ME0444, ME0445, ME0446, ME0447) - Non-Proprietary Project stage: RAI ML0921507122009-07-27027 July 2009 and ISFSI, Nine Mile Point Nuclear Station & R. E. Ginna Nuclear Power Plant - Application for an Order Approving License Transfers and Conforming License Amendment Request, Supplemental Information Project stage: Supplement ML0925705732009-10-0909 October 2009 Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0925705942009-10-0909 October 2009 Public - Safety Evaluation Indirect License Transfer - Corporate Restructuring of Constellation Energy Nuclear Group, LLC with Edf Development Project stage: Approval ML0925706062009-10-0909 October 2009 Order Approving License Transfer Constellation Edf Development Project stage: Other ML0925706142009-10-0909 October 2009 Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0925902652009-10-0909 October 2009 Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0926106882009-10-0909 October 2009 Draft Conforming Amendment Constellation Energy Nuclear Group, LLC and Edf License Transfer Project stage: Draft Other ML0925705832009-10-0909 October 2009 Order Approving Application Regarding Proposed Corporate Restructuring and Approving Conforming Amendments Project stage: Other ML0925706232009-10-0909 October 2009 Order Approving License Transfer Constellation Edf Development Project stage: Other ML0929201682009-10-15015 October 2009 Independent Spent Fuel Storage Installation, Notification of Expected Date of Transfer of Name Calvert Cliffs Nuclear Power Plant, Inc. to Calvert Cliffs Nuclear Power Plant, LLC Project stage: Request ML0929901012009-10-19019 October 2009 Units I & 2, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 & 2, R. E. Ginna, Supplemental Information in Support of Orders Approving Application Regarding Proposed Corporate Restructuring Project stage: Request ML0930001412009-10-25025 October 2009 Independent Spent Fuel Storage Installation; Nine Mile Point, Units 1 & 2 and R. E. Ginna - Supplemental Information Requested by NRC Staff on October 23, 2009 Project stage: Request ML0930001272009-10-25025 October 2009 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 & 2, R. E. Ginna, Unit 1, Submittal of Supplemental Information in Support of Orders Approving Application Regarding Proposed Corporate Restructuring Project stage: Request ML0930005062009-10-26026 October 2009 R. E. Ginna Nuclear Power Plant, Supplemental Information in Support of Orders Approving Application Regarding Proposed Corporate Restructuring Project stage: Request ML0930006312009-10-30030 October 2009 Order Superceding October 9, 2009, Order Approving Application Regarding Proposed Corporate Restructuring and Approving Conforming Amendments Project stage: Other ML0930100032009-10-30030 October 2009 Revised Safety Evaluation Public Indirect License Transfer - Corporate Restructuring of Constellation Energy Nuclear Group, LLC with Edf Development Project stage: Approval ML0928801222009-10-30030 October 2009 ISFSI License Pages Amendment No. 8 - Direct Transfer Calvert Cliffs Nuclear Power Plant Inc. to LLC Project stage: Other ML0928808132009-10-30030 October 2009 ISFSI - Conforming Amendment Calvert Cliffs Nuclear Power Plant Inc. to LLC Project stage: Other ML0930006302009-10-30030 October 2009 Revised Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0930006342009-10-30030 October 2009 Revised Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0930100012009-10-30030 October 2009 Revised Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0928808052009-10-30030 October 2009 ISFSI, Issuance of Conforming Amendments Calvert Cliffs Nuclear Power Plant, Inc., to LLC Project stage: Approval ML0930006332009-10-30030 October 2009 Order Superceding October 9, 2009, Order Approving License Transfer Constellation Edf Development Project stage: Other ML0930006352009-10-30030 October 2009 Order Superceding October 9, 2009, Order Approving License Transfer Constellation Edf Development Project stage: Other ML0930707372009-11-12012 November 2009 ISFSI License - Correction Letter for October 30, 2009, Issued Conforming Amendment License Pages Project stage: Other ML0932706122009-11-25025 November 2009 Summary of Closed Meeting Held with Constellation Energy Nuclear Group, LLC to Discuss Joint Venture with Edf Development, Inc Project stage: Meeting ML0932902462009-11-30030 November 2009 Correction Letter to Pages of Enclosure 1 of the October 30, 2009, Order Approving the Transfer of Licenses for Ccnpp and ISFSI Project stage: Other ML0933103652009-11-30030 November 2009 Correction Letter to Pages of Enclosure 1 of the October 30, 2009, Order Approving the Transfer of Licenses for NMPNS, Unit Nos. 1 and 2 Project stage: Other ML0933103662009-11-30030 November 2009 Correction Letter to Pages of Enclosure 1 of the October 30, 2009, Order Approving the Transfer of Licenses for R.E. Ginna Nuclear Power Plant Project stage: Other ML1030902612010-10-25025 October 2010 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 & 2 and R.E. Ginna - Submittal of Securities and Exchange Commission Schedules Project stage: Other 2009-11-25
[Table View] |
Similar Documents at Ginna |
---|
Category:Federal Register Notice
MONTHYEARML21330A0432021-12-15015 December 2021 Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR Part 50, Appendix E, Section IV.F.2.C (EPID L-2021-LLE-0044) (FRN) ML21294A3762021-11-16016 November 2021 Federal Register Notice for Order Approving Indirect Transfer of Licenses ML21277A0772021-10-21021 October 2021 FRN - Notice of Issuance of COVID-19 Exemption Issued in September 2021 ML21145A0142021-05-26026 May 2021 Fleet and the Associated Independent Spent Fuel Storage Installations - Extension of Comment Period for Notice of Consideration of Approval of Transfer of Licenses and Conforming Amendments and Opportunity to Request a Hearing EPID L-2021-L ML21145A0152021-05-26026 May 2021 FRN Exelon License Transfer - Extend Comment Period ML21102A0752021-04-28028 April 2021 Fleet - Notice of Consideration of Approval of Transfer of Licenses and Conforming Amendments and Opportunity for a Hearing (FRN) ML21063A0052021-04-14014 April 2021 Federal Register Notice, Exemption from the Requirements of 10 CFR 2.109(b) Related to Subsequent License Renewal Application ML20269A2002020-09-30030 September 2020 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117 ML20177A6452020-07-15015 July 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for June 2020 ML20119A5242020-05-0707 May 2020 FRN: Notice of Issuance of Multiple Exemptions Regarding 10 CFR Part 26 (COVID-19) ML20055E4282020-02-26026 February 2020 R. E. Ginna Nuclear Power Plant - Cover Letter with Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License and Opportunity for a Hearing ML20055E3922020-02-26026 February 2020 R. E. Ginna Nuclear Power Plant - Individual Federal Register Notice Add a One-Time Note for Use of Alternative Residual Heat Removal Loop ML19238A3692019-09-0303 September 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 09/10/2019 ML19170A3192019-07-23023 July 2019 R. E. Ginna Nuclear Power Plant - Environmental Assessment and Finding of No Significant Impact Related to Changes to Emergency Plan Staffing Requirements ML19162A1642019-07-23023 July 2019 FRN - R. E. Ginna Nuclear Power Plant - Emergency Plan Resource Environmental Assessment-FONSI ML19085A2172019-03-29029 March 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 04/09/2019 ML18180A2182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 NRC-2018-0140, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/20182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML18002A3812018-01-24024 January 2018 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: February 6, NRC-2018-0011, Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: Februar2018-01-24024 January 2018 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: February 6, ML17353A1922017-12-21021 December 2017 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 2018 NRC-2017-0238, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 20182017-12-21021 December 2017 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 2018 ML17248A2262017-09-15015 September 2017 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: October 3, 2017 ML17131A1132017-06-21021 June 2017 R. E. Ginna Nuclear Power Plant - Transmittal Letter Re. Exemption from Requirements of 10 CFR Section 50.46 and Appendix K to 10 CFR Part 50 to Allow the Use of Optimized Zirlo Clad Fuel Rods NRC-2017-0124, FRN: Exemption, Issuance - R. E. Ginna Nuclear Power Plant - Request for Exemption from 10 CFR 50.46 and Appendix K to 10 CFR Part 50 to Allow the Use of Optimized Zirlo Fuel Rod Cladding2017-06-19019 June 2017 FRN: Exemption, Issuance - R. E. Ginna Nuclear Power Plant - Request for Exemption from 10 CFR 50.46 and Appendix K to 10 CFR Part 50 to Allow the Use of Optimized Zirlo Fuel Rod Cladding ML17136A2212017-06-19019 June 2017 FRN: Exemption, Issuance - R. E. Ginna Nuclear Power Plant - Request for Exemption from 10 CFR 50.46 and Appendix K to 10 CFR Part 50 to Allow the Use of Optimized Zirlo Fuel Rod Cladding ML16004A1182016-01-0707 January 2016 FRN, Issuance of Confirmatory Orders, Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended ML15320A0362015-12-0808 December 2015 Cover Letter Transmitting Ginna Fonsi Preemption Authority Request Final EA NRC-2015-0269, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 20152015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 ML15328A5502015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 ML15182A0262015-10-22022 October 2015 Draft Environmental Assessment and Finding of No Significant Impact (MF2618 and MF2623) ML15182A0232015-10-22022 October 2015 Draft Environmental Assessment and Finding of No Significant Impact Related to Preemption Authority Request ML15218A6252015-08-14014 August 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 14, 2015 ML15120A2272015-05-0101 May 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 12, 2015 ML14303A3812014-10-31031 October 2014 Biweekly Sholly FRN - Application and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: November 12, 2014 NRC-2014-0229, Federal Register Notice License Amendment Application, Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Exelon Generation Company, LLC, R. E. Ginna Nuclear Power Plant2014-10-21021 October 2014 Federal Register Notice License Amendment Application, Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Exelon Generation Company, LLC, R. E. Ginna Nuclear Power Plant ML14282A5672014-10-21021 October 2014 Federal Register Notice License Amendment Application, Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Exelon Generation Company, LLC, R. E. Ginna Nuclear Power Plant NRC-2014-0917, Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 16, 20142014-09-0505 September 2014 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 16, 2014 ML14247A1542014-09-0505 September 2014 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 16, 2014 NRC-2013-0252, R.E. Ginna Nuclear Power Plant - Order Approving Direct Transfer of Renewed Operating License and Conforming License Amendment2014-03-25025 March 2014 R.E. Ginna Nuclear Power Plant - Order Approving Direct Transfer of Renewed Operating License and Conforming License Amendment ML14063A2112014-03-25025 March 2014 Order Approving Direct Transfer of Renewed Operating License and Conforming License Amendment ML13294A0702013-12-18018 December 2013 Consideration of Approval of Transfer of Renewed Facility Operating Licenses, Materials Licenses, and Conforming Amendments Containing SUNSI ML13294A0392013-11-0707 November 2013 Notice of Consideration of Approval of Transfer of Renewed Facility Operating Licenses and Conforming Amendments,.. ML13228A3992013-08-12012 August 2013 Letter to Holders of Independent Spent Fuel Storage Installation (ISFSI) Licenses Re Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit - Rin 3150-AI64 (NRC-2009-0163) EA-02-109 ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit NRC-2013-0127, Order Designating an Interim Class of NRC Licensed Facilities That Are Eligible to Apply to the Commission for Authorization to Use the Authority Granted Under the Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended2013-06-0505 June 2013 Order Designating an Interim Class of NRC Licensed Facilities That Are Eligible to Apply to the Commission for Authorization to Use the Authority Granted Under the Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended ML13121A4592013-06-0505 June 2013 Order Designating an Interim Class of NRC Licensed Facilities That Are Eligible to Apply to the Commission for Authorization to Use the Authority Granted Under the Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status2012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML12056A0442012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML1203400102012-02-15015 February 2012 FRN: General Notice. Order Approving Application Regarding Proposed Corporate Merger and Indirect Transfer of License 2021-05-26
[Table view] Category:Letter
MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of B Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23235A1722023-08-23023 August 2023 Re. Ginna Nuclear Power Plant, Transmittal of 2023 Owner'S Activity Report IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 ML23191A0592023-07-21021 July 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 155 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. ML23135A0412023-05-15015 May 2023 2022 Annual Radioactive Effluent Release Report and 2022 Annual Radiological Environmental Operating Report ML23121A0482023-05-0101 May 2023 R. E. Ginna Nuclear Power Plant Core Operating Limits Report Cycle 44, Revision 0 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 ML23100A0302023-04-10010 April 2023 2023 10 CFR 50.46 Annual Report ML23114A1152023-03-29029 March 2023 Electronic Reporting of Exposure Data for 2022 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23075A0872023-03-15015 March 2023 R. E. Ginna Nuclear Power Plant - Project Manager Assignment ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) ML22364A0242023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant Issuance of Amendments Nos. 231, 231, 232, 232, and 154 Regarding Adoption of TSTF-246 ML23060A1622023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23005A1762023-02-23023 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 153 Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes ML23005A1222023-02-22022 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No 152 Adopt TSTF-315-Revise Technical Specification 3.1.8, Physics Tests Exceptions - Mode 2 RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators ML22287A0692023-02-0808 February 2023 R. E. Ginna Station - Forward Fit Analysis (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23031A2992023-02-0707 February 2023 R. E. Ginna Nuclear Power Plant - Withdrawal of an Amendment Request ML23010A0112023-02-0101 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Inservice Testing of Refueling Water Storage Tank Outlet Value RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 ML22362A0382022-12-28028 December 2022 R. E. Ginna Nuclear Power Plant - Letter to Withdraw Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML22348A2062022-12-14014 December 2022 Re. Ginna Nuclear Power Plant - Annual Commitment Change Notification RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator 2024-02-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 November 30, 2009 Mr. Henry B. Barron President, CEO, and Chief Nuclear Officer Constellation Energy Nuclear Group, LLC 100 Constellation Way, Suite 200C Baltimore, MD 21202 SUB~IECT: CORRECTION TO PAGES OF ENCLOSURE 1 OF THE OCTOBER 30, 2009, ORDER SUPERCEDING OCTOBER 9, 2009, ORDER APPROVING THE TRANSFER OF RENEWED FACILITY OPERATING LICENSE NO. DPR-18, FOR THE R.E. GINNA NUCLEAR POWER PLANT (TAC NO. ME0445)
Dear Mr. Barron:
On October 30, 2009, the Nuclear Regulatory Commission (NRC) issued Orders superceding the NRC Orders dated October 9, 2009, approving the direct and indirect transfers of licenses for the Calvert Cliffs Nuclear Power Plant (CCNPP), Nine Mile Point Nuclear Station (NMPNS),
and R.E. Ginna Nuclear Power Plant (Ginna) necessary to implement corporate restructuring activities involving certain subsidiaries of Constellation Energy Group, Inc., and an investment by EDF Development, Inc. (EDF).
On three pages of the October 30, 2009, Order for Ginna, there is a typographical error. On pages 3, 4, and 5, the percentage of EDF's ownership interest in Constellation Energy Nuclear Group, LLC was incorrectly stated as 44.99%. The correct percentage is 49.99%, and was correctly stated on pages 2 and 3 of the Order for Ginna. Enclosed is the revised October 30, 2009, Order to include the corrected pages of Enclosure 1 for the subject license. The corrected pages contain marginal lines indicating the areas of change.
The NRC regrets any inconvenience that this error may have caused. If there are any questions regarding this matter, please contact me at 301-415-1030.
Sincerely, Richard V. Guzman, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244
Enclosure:
As stated cc w/encl: Distribution via Listserv
7590-01-P UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION NRC-2009-0192 In the Matter of ) Docket No. 50-244
)
EDF DEVELOPMENT, INC. ) Renewed License No. DPR-18
)
CONSTELLATION ENERGY NUCLEAR )
GROUP, LLC )
)
RE. GINNA NUCLEAR POWER PLANT, LLC )
)
(RE. Ginna Nuclear Power Plant) )
ORDER SUPERSEDING ORDER OF OCTOBER 9,2009, APPROVING APPLICATION REGARDING PROPOSED CORPORATE RESTRUCTURING I.
RE. Ginna Nuclear Power Plant, LLC (Ginna, LLC or the licensee) is the holder of Renewed Facility Operating License No. DPR-18 which authorizes the possession, use, and operation of the RE. Ginna Nuclear Power Plant (Ginna). The facility is located at the licensee's site in Ontario, New York. The operating license authorizes the licensee to possess, use, and operate Ginna.
II.
By letter dated January 22, 2009, as supplemented on February 26, April 8, June 25, July 27, October 15, October 19, October 25 (two letters), October 26, and October 28, 2009 (together, the Application), Constellation Energy Nuclear Group, LLC (CENG), on behalf of the licensee and EDF Development, Inc. (EDF Development) (together, the applicants), requested that the Nuclear Regulatory Commission (NRC, the Commission), pursuant to Title 10.ofthe Code of Federal Regulations (10 CFR) 50.80, consent to the indirect license transfers that would be effected by the indirect transfer of control of CENG's ownership and operating interests in Ginna. The actions being sought are a result of certain proposed corporate
-2 restructuring actions in connection with a planned investment by EDF Development whereby it would acquire a 49.99% ownership interest in CENG from Constellation Energy Group, Inc.
(CEG), the current 100% owner of CENG. EDF Development is a U.S. corporation organized under the laws of the State of Delaware and a wholly-owned subsidiary of E.D.F. International S.A., a public limited company organized under the laws of France, which is in turn a wholly owned subsidiary of Electricite de France S.A., a French limited company.
Following the closing of the transfer of ownership interests in CENG to EDF Development, EDF Development will hold a 49.99% ownership interest in CENG; CEG will hold a 50.01 % ownership interest in CENG through two new intermediate parent companies, Constellation Nuclear, LLC and CE Nuclear, LLC, formed for non-operational purposes. In addition, Constellation Nuclear Power Plants, Inc., which is currently an intermediate holding company between CENG and Ginna, LLC and Nine Mile Point Nuclear Station, LLC, will convert to a Delaware limited liability company by operation of law and become Constellation Nuclear Power Plants, LLC, and will exist as an intermediate holding company between CENG and Ginna, LLC, Nine Mile Point Nuclear Station, LLC, and Calvert Cliffs Nuclear Power Plant, LLC by merger. No physical changes to the facilities or operational changes are being proposed in the application.
Approval of the transfer of the license is requested by the applicants pursuant to 10 CFR 50.80. Notice of the request for approval and opportunity for a hearing was published in the Federal Register on May 6,2009 (74 FR 21013). No hearing requests or petitions to intervene were received. The NRC received comments from a member of the public in Seattle, Washington, in an e-mail dated May 22,2009. The comments did not provide any information additional to that in the application, nor did they provide any information contradictory to that provided in the Application.
Pursuant to 10 CFR 50.80, no license, or any right thereunder, shall be transferred,
- 3 directly or indirectly, through transfer of control of the license, unless the Commission shall give its consent in writing. Upon review of the information in the application and other information before the Commission, and relying upon the representations and agreements contained in the application, the NRC staff has determined that the proposed indirect license transfer of control of the subject license held by the licensee to the extent such will result from the proposed corporate restructuring actions and the planned investment by EDF Development whereby it will acquire a 49.99% ownership interest in CENG, to the extent affected by the proposed transaction as described in the application, is otherwise consistent with applicable provisions of law, regulations, and Orders issued by the NRC, pursuant thereto, subject to the conditions set forth below. The NRC staff has further found that the application for the proposed license amendment complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; the facility will operate in conformity with the Application, the provisions of the Act, and the rules and regulations of the Commission; there is reasonable assurance that the activities authorized by the proposed license amendment can be conducted without endangering the health and safety of the public and that such activities will be conducted in compliance with the Commission's regulations; the issuance of the proposed license amendment will not be inimical to the common defense and security or to the health and safety of the public; and the issuance of the proposed amendments will be in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
On October 9,2009, the Commission issued, "Order Approving Application Regarding Proposed Corporate Restructuring and Approving Conforming Amendments."
By letter dated October 19, 2009, CENG explained that its January 22, 2009, application for the license transfers had anticipated nearly concurrent completion of the proposed internal corporate restructuring of the CEG subsidiaries and the proposed EDF acquisition of 49.99% of Revised by correction letter dated November 30, 2009
-4 CENG. After it filed its January application, CENG learned that the restructuring activities for the CEG subsidiaries will be completed at least 8 days prior to closing the transaction involving EDF. In letters dated October 25 (two letters), 26, and 28,2009, CENG provided revised financial arrangements that will apply during the period between the completion of the internal restructuring activities and the acquisition of 49.99% of CENG by EDF and a revised operating agreement that will apply after the EDF closing.
The NRC concluded that modifications were needed to the cover letter, the October 9, 2009, Order, and the safety evaluations in light of the new information provided in CENG's letters of October 19 through 28, 2009. This Order contains those modifications and supersedes the Order issued October 9, 2009.
The findings set forth above are supported by a modified NRC safety evaluation (SE) dated the same day as this Order.
III.
Accordingly, pursuant to Sections 161b, 161i, 1610, and 184 of the Act, 42 U.S.C.
Sections 2201 (b), 2201(i), 2201(0), and 2234; and 10 CFR 50.80, IT IS HEREBY ORDERED that the Application regarding the indirect license transfers related to the proposed corporate restructuring actions and the planned investment by EDF Development, as described herein, is approved, subject to the following conditions:
A. With regard to the direct and indirect transfers resulting from the restructuring of the CEG subsidiaries:
(1) The financial arrangements resulting from the corporate restructuring activities of the CEG subsidiaries are subject to the following:
(a) The Inter-Company Credit Agreements (ICA) described in the October 25, 2009, supplement to the Application shall be effective as of the date of the direct and indirect transfers (whichever occurs first) resulting from Revised by correction letter dated November 30, 2009
- 5 the restructuring of CEG subsidiaries and shall be consistent with the representations contained in the Application. CENG and Ginna, LLC shall take no action to cause CEG, or their successors and assigns, to void, cancel or materially modify the ICA as submitted without the prior written consent of the NRC staff. CENG shall inform the Director of the Office of Nuclear Reactor Regulation, in writing, no later than 10 days after any funds are provided to CENG or any of the licensees by CEG or EDF Development under any Support Agreement.
(b) The Master Demand Notes described in the October 26, 2009, supplement to the Application shall be effective as of the date of the direct and indirect transfers (whichever occurs first) resulting from the restructuring of CEG subsidiaries and shall be consistent with the representations contained in the Application. CENG and Ginna, LLC, shall take no action to cause CEG, or their successors and assigns, to void, cancel or materially modify the Master Demand Notes without the prior written consent of the NRC staff.
B. With regard to the indirect transfers resulting from the acquisition of 49.99% of CENG by EDF Development (EDF Closing):
(1) The ownership and governance arrangements in effect as of the date of the indirect transfers to EDF Development are subject to the following:
(a) The Operating Agreement included with the supplement dated October 25, 2009, may not be modified in any material respect concerning decision making authority over "safety issues" as defined therein without the prior written consent of the Director, Office of Nuclear Reactor Regulation.
Revised by correction letter dated November 30, 2009
- 6 (b) At least half the members of CENG's Board of Directors must be U.S.
citizens.
(c) The Chief Executive Officer (CEO), Chief Nuclear Officer (CNO) and Chairman of the Board of Directors of CENG must be U.S. citizens.
These individuals shall have the responsibility and exclusive authority to ensure and shall ensure that the business and activities of CENG with respect to the Calvert Cliffs, Unit Nos. 1 and 2, Calvert Cliffs ISFSI, Nine Mile Point, Unit Nos. 1 and 2, and R.E. Ginna licenses are at all times conducted in a manner consistent with the public health and safety and common defense and security of the United States.
(d) CENG will establish a Nuclear Advisory Committee (NAC) composed of U.S. citizens who are not officers, directors, or employees of CENG, CEG or EDF Development. The NAC will report to and provide transparency to the NRC and other U.S. governmental agencies regarding foreign ownership and control of nuclear operations.
(e) CENG shall cause to be transmitted to the Director, Office of Nuclear Reactor Regulation, within 30 days of knowledge of a filing with the U.S.
Securities and Exchange Commission, any Schedules 13D or 13G filed pursuant to the Securities and Exchange Act of 1934 that disclose beneficial ownership of any registered classes of CEG stock.
(2) The financial arrangements applicable to the indirect transfers resulting from the EDF Closing are subject to the following:
(a) The working capital and cash pooling arrangements described in Article IV of the Operating Agreement included with the October 25, 2009 supplement to the Application, shall be effective as of the date of the
-7 indirect transfers to EDF Development and shall be consistent with the representations contained in the Application. CENG and Ginna, LLC shall take no action to cause CEG and/or EDF Development, or their successors and assigns, to void, cancel or materially modify the working capital and cash pooling arrangements in the Operating Agreement without the prior written consent of the NRC staff.
(b) The Support Agreements described in the February 26,2009 supplement to the Application shall be effective as of the date of the indirect transfers to EDF Development; shall supersede the Inter-Company Credit Agreements provided by CEG, Inc.; and shall be consistent with the representations contained in the Application. CENG and Ginna, LLC shall take no action to cause CEG and/or EDF Development, or their successors and assigns, to void, cancel or materially modify the Support Agreements as submitted without the prior written consent of the NRC staff. CENG shall inform the Director of the Office of Nuclear Reactor Regulation, in writing, no later than 10 days after any funds are provided to CENG or any of the licensees by CEG or EDF Development under any Support Agreement.
(c) The Master Demand Notes described in the October 28,2009 supplement to the Application, shall be effective as of the date of the indirect transfers to EDF Development; shall supersede the Master Demand Notes provided by CEG, Inc.; and shall be consistent with the representations contained in the Application. CENG and Ginna, LLC, shall take no action to cause CEG and/or EDF Development, or their successors and assigns, to void, cancel or materially modify the Master
- 8 Demand Notes without the prior written consent of the NRC staff.
IT IS FURTHER ORDERED that CENG shall inform the Director of the Office of Nuclear Reactor Regulation, in writing, of the date of closing of the transfer of EDF Development's ownership and operating interests in CENG at least 1 business day before the closing. Should the transfer of the license not be completed within 1 year of this Order's date of issuance, this Order shall become null and void, provided, however, that upon written application and for good cause shown, such date may be extended by order.
This Order supersedes the Order issued on October 9,2009, and is effective upon issuance.
For further details with respect to this Order, see the initial application dated January 22, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML090290101), as supplemented by letters dated February 26 (ML090630426), April 8 (ML091000665), June 25 (ML091811094), and July 27,2009 (ML092150712), October 15 (ML092920168), October 19 (ML0929990101), October 25 (ML093000127 and ML093000141),
October 26 (ML093000506), and October 28,2009 (ML092150712), and the SE (ML093010003) with the same date as this Order, which are available for public inspection at the Commission's Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike, Room 0-1 F21 (First Floor), Rockville, Maryland, and accessible electronically from the ADAMS Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS, or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or bye-mail at pdr.resource@nrc.gov.
-9 Dated at Rockville, Maryland, this so" day of October 2009.
FOR THE NUCLEAR REGULATORY COMMISSION IRA!
Eric J. Leeds, Director Office of Nuclear Reactor Regulation
'.. ML093310366 OFFICE LPL1-1/PM LPL 1-1/LA OGC LPL 1-1/BC NAME RGuzman SUttle SUttal NSalgado DATE 11/27/09 11/30/09 11/30/09 11/30/09