Letter Sequence Other |
---|
|
Results
Other: ML090760564, ML090760582, ML090760616, ML090760623, ML090760681, ML090760687, ML092570573, ML092570583, ML092570606, ML092570614, ML092570623, ML092590265, ML092880122, ML092880813, ML093000630, ML093000631, ML093000633, ML093000634, ML093000635, ML093010001, ML093070737, ML093290246, ML093310365, ML093310366, ML103090261
|
MONTHYEARML0902901012009-01-22022 January 2009 Application for an Order Approving License Transfers and Conforming License Amendment Request Project stage: Request ML0906304262009-02-26026 February 2009 R. E. Ginna and Calvert Cliffs, Units 1 & 2 and Independent Spent Fuel Storage Installation - Supplement to Application for an Order Approving License Transfers and Conforming License Amendment Request Project stage: Supplement ML0905703152009-02-26026 February 2009 Acceptance Review Constellation and Edf Development - Application for Approval of License Transfers and Conforming License Amendment Request-Calvert Cliffs Nuclear Power Plant 1 and 2, Nine Mile Point Nuclear Station 1 and 2, and R.E. Ginna Project stage: Acceptance Review ML0910006652009-04-0808 April 2009 ISFSI, Nine Mile Point, Units 1 & 2, and R. E. Ginna, Supplemental Information in Support of Application for an Order Approving License Transfers and Conforming License Amendment Request Project stage: Supplement ML0907605642009-04-28028 April 2009 Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and 10 CFR 50.80 and 72.50 License Transfer and Opportunity for a Hearing - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Project stage: Other ML0907605822009-04-28028 April 2009 FRN: Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and 10 CFR 50.80 and 72.50 License Transfer and Opportunity for a Hearing - Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Project stage: Other ML0907606162009-04-28028 April 2009 Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and Opportunity for a Hearing Project stage: Other ML0907606232009-04-28028 April 2009 FRN: Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and Opportunity for a Hearing - Nine Mile Point Nuclear Station, Units 1 and 2 Project stage: Other ML0907606872009-04-28028 April 2009 FRN: Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and Opportunity for a Hearing - R.E. Ginna Nuclear Power Plant Project stage: Other ML0907606812009-04-28028 April 2009 Notice of Consideration of Approval of Application Proposed Ownership Interest in Ceng by Edf Development and Opportunity for a Hearing - R.E. Ginna Nuclear Power Plant Project stage: Other ML0916007402009-06-10010 June 2009 Request for Additional Information Application for an Order Approving License Transfers and Conforming License Amendment for Calvert Cliffs, Units 1 & 2, ISFSI, Nine Mile, Units 1 & 2, and R.E. Ginna Project stage: RAI ML0918110942009-06-25025 June 2009 ISFSI; Nine Mile Point, Units 1 & 2 and R. E. Ginna - Response to Nrc'S Request for Additional Information Project stage: Request ML0919603652009-07-15015 July 2009 E-mail from R. Guzman to E. Tyler Request for Additional Information - CENG-EDF License Transfer (TAC Nos. ME0443, ME0444, ME0445, ME0446, ME0447) - Non-Proprietary Project stage: RAI ML0921507122009-07-27027 July 2009 and ISFSI, Nine Mile Point Nuclear Station & R. E. Ginna Nuclear Power Plant - Application for an Order Approving License Transfers and Conforming License Amendment Request, Supplemental Information Project stage: Supplement ML0925705732009-10-0909 October 2009 Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0925705942009-10-0909 October 2009 Public - Safety Evaluation Indirect License Transfer - Corporate Restructuring of Constellation Energy Nuclear Group, LLC with Edf Development Project stage: Approval ML0925706062009-10-0909 October 2009 Order Approving License Transfer Constellation Edf Development Project stage: Other ML0925706142009-10-0909 October 2009 Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0925902652009-10-0909 October 2009 Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0926106882009-10-0909 October 2009 Draft Conforming Amendment Constellation Energy Nuclear Group, LLC and Edf License Transfer Project stage: Draft Other ML0925705832009-10-0909 October 2009 Order Approving Application Regarding Proposed Corporate Restructuring and Approving Conforming Amendments Project stage: Other ML0925706232009-10-0909 October 2009 Order Approving License Transfer Constellation Edf Development Project stage: Other ML0929201682009-10-15015 October 2009 Independent Spent Fuel Storage Installation, Notification of Expected Date of Transfer of Name Calvert Cliffs Nuclear Power Plant, Inc. to Calvert Cliffs Nuclear Power Plant, LLC Project stage: Request ML0929901012009-10-19019 October 2009 Units I & 2, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 & 2, R. E. Ginna, Supplemental Information in Support of Orders Approving Application Regarding Proposed Corporate Restructuring Project stage: Request ML0930001412009-10-25025 October 2009 Independent Spent Fuel Storage Installation; Nine Mile Point, Units 1 & 2 and R. E. Ginna - Supplemental Information Requested by NRC Staff on October 23, 2009 Project stage: Request ML0930001272009-10-25025 October 2009 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 & 2, R. E. Ginna, Unit 1, Submittal of Supplemental Information in Support of Orders Approving Application Regarding Proposed Corporate Restructuring Project stage: Request ML0930005062009-10-26026 October 2009 R. E. Ginna Nuclear Power Plant, Supplemental Information in Support of Orders Approving Application Regarding Proposed Corporate Restructuring Project stage: Request ML0930006312009-10-30030 October 2009 Order Superceding October 9, 2009, Order Approving Application Regarding Proposed Corporate Restructuring and Approving Conforming Amendments Project stage: Other ML0930100032009-10-30030 October 2009 Revised Safety Evaluation Public Indirect License Transfer - Corporate Restructuring of Constellation Energy Nuclear Group, LLC with Edf Development Project stage: Approval ML0928801222009-10-30030 October 2009 ISFSI License Pages Amendment No. 8 - Direct Transfer Calvert Cliffs Nuclear Power Plant Inc. to LLC Project stage: Other ML0928808132009-10-30030 October 2009 ISFSI - Conforming Amendment Calvert Cliffs Nuclear Power Plant Inc. to LLC Project stage: Other ML0930006302009-10-30030 October 2009 Revised Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0930006342009-10-30030 October 2009 Revised Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0930100012009-10-30030 October 2009 Revised Letter Approving License Transfer Constellation Edf Development Project stage: Other ML0928808052009-10-30030 October 2009 ISFSI, Issuance of Conforming Amendments Calvert Cliffs Nuclear Power Plant, Inc., to LLC Project stage: Approval ML0930006332009-10-30030 October 2009 Order Superceding October 9, 2009, Order Approving License Transfer Constellation Edf Development Project stage: Other ML0930006352009-10-30030 October 2009 Order Superceding October 9, 2009, Order Approving License Transfer Constellation Edf Development Project stage: Other ML0930707372009-11-12012 November 2009 ISFSI License - Correction Letter for October 30, 2009, Issued Conforming Amendment License Pages Project stage: Other ML0932706122009-11-25025 November 2009 Summary of Closed Meeting Held with Constellation Energy Nuclear Group, LLC to Discuss Joint Venture with Edf Development, Inc Project stage: Meeting ML0932902462009-11-30030 November 2009 Correction Letter to Pages of Enclosure 1 of the October 30, 2009, Order Approving the Transfer of Licenses for Ccnpp and ISFSI Project stage: Other ML0933103652009-11-30030 November 2009 Correction Letter to Pages of Enclosure 1 of the October 30, 2009, Order Approving the Transfer of Licenses for NMPNS, Unit Nos. 1 and 2 Project stage: Other ML0933103662009-11-30030 November 2009 Correction Letter to Pages of Enclosure 1 of the October 30, 2009, Order Approving the Transfer of Licenses for R.E. Ginna Nuclear Power Plant Project stage: Other ML1030902612010-10-25025 October 2010 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 & 2 and R.E. Ginna - Submittal of Securities and Exchange Commission Schedules Project stage: Other 2009-11-25
[Table View] |
|
---|
Category:Federal Register Notice
MONTHYEARML22060A2622022-03-0808 March 2022 FRN - Notice of Issuance of COVID-19 Exemptions Issued in February 2022 ML21294A3762021-11-16016 November 2021 Federal Register Notice for Order Approving Indirect Transfer of Licenses ML21145A0142021-05-26026 May 2021 Fleet and the Associated Independent Spent Fuel Storage Installations - Extension of Comment Period for Notice of Consideration of Approval of Transfer of Licenses and Conforming Amendments and Opportunity to Request a Hearing EPID L-2021-L ML21145A0152021-05-26026 May 2021 FRN Exelon License Transfer - Extend Comment Period ML21102A0752021-04-28028 April 2021 Fleet - Notice of Consideration of Approval of Transfer of Licenses and Conforming Amendments and Opportunity for a Hearing (FRN) ML21060A5962021-03-0909 March 2021 FRN - Notice of Issuance of Multiple COVID-19 Exemptions Regarding 10 CFR Part 26 for February 2021 ML20304A2862020-11-20020 November 2020 Federal Register Notice for COVID-19 October 2020 Group Exemptions ML20269A2002020-09-30030 September 2020 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117 ML20115E3792020-06-10010 June 2020 Independent Spent Fuel Storage Installation Exemption ML19295E7142019-10-28028 October 2019 L-2018-LLA-0222 and L-2018-LLE-0013 -Withdrawal FRN 2019-10-22 ML19238A3692019-09-0303 September 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 09/10/2019 ML19168A0842019-06-26026 June 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 07/02/2019 ML18304A3042018-11-23023 November 2018 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding Exelon Generation Company, LLC License Amendment Request to Change Emergency Plan Staffing NRC-2018-0262, Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding Exelon Generation Company, LLC License Amendment Request to Change Emergency Plan Staffing2018-11-23023 November 2018 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding Exelon Generation Company, LLC License Amendment Request to Change Emergency Plan Staffing ML18278A2802018-10-10010 October 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 10/23/2018 ML18215A0322018-08-16016 August 2018 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information and Order for Fr Publication on 9/4/2 ML18180A2182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 NRC-2018-0140, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/20182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML16257A5172016-09-19019 September 2016 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 2016 NRC-2016-0202, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 20162016-09-19019 September 2016 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 2016 NRC-2016-0181, Exemption Related to the Updated Final Safety Analysis Report 10 CFR 50.71(e)(4) Update Schedule (CAC Nos. MF7340 and MF7341)2016-08-22022 August 2016 Exemption Related to the Updated Final Safety Analysis Report 10 CFR 50.71(e)(4) Update Schedule (CAC Nos. MF7340 and MF7341) ML16075A4082016-08-22022 August 2016 Exemption Related to the Updated Final Safety Analysis Report 10 CFR 50.71(e)(4) Update Schedule ML16075A4062016-08-18018 August 2016 Plants, Units 1 and 2 - Exemption Related to the Updated Final Safety Analysis Report 10 CFR 50.71(e)(4) Update Schedule NRC-2016-0100, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 20162016-05-13013 May 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 2016 ML16131A7952016-05-13013 May 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 2016 ML15356A5992015-12-29029 December 2015 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 5, 2016 NRC-2015-0269, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 20152015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 ML15328A5502015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 NRC-2015-0204, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - September 1, 20152015-08-21021 August 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - September 1, 2015 ML15231A8382015-08-21021 August 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - September 1, 2015 ML15218A6252015-08-14014 August 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 14, 2015 ML15204A2792015-07-27027 July 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 4, 2015 ML15120A2272015-05-0101 May 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 12, 2015 ML13018A2392015-04-0808 April 2015 G20110171 - Letter to Petitioner Saporito on Proposed Director'S Decision Regarding 2.206 Petition Dated: March 12, 2011 ML14303A3812014-10-31031 October 2014 Biweekly Sholly FRN - Application and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: November 12, 2014 ML14189A6652014-07-24024 July 2014 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information - August 5, 2014 ML14063A1252014-03-24024 March 2014 Order Approving Direct Transfer of Licenses and Conforming Amendment, Independent Spent Fuel Storage Installation License, (Tacs. MF2584 and MF2585) NRC-2014-0028, Biweekly Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 18, 20142014-02-10010 February 2014 Biweekly Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 18, 2014 ML14037A4142014-02-10010 February 2014 Biweekly Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 18, 2014 ML13294A0702013-12-18018 December 2013 Consideration of Approval of Transfer of Renewed Facility Operating Licenses, Materials Licenses, and Conforming Amendments Containing SUNSI ML13294A0392013-11-0707 November 2013 Notice of Consideration of Approval of Transfer of Renewed Facility Operating Licenses and Conforming Amendments,.. ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit ML13228A3992013-08-12012 August 2013 Letter to Holders of Independent Spent Fuel Storage Installation (ISFSI) Licenses Re Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit - Rin 3150-AI64 (NRC-2009-0163) EA-02-109 ML13121A4592013-06-0505 June 2013 Order Designating an Interim Class of NRC Licensed Facilities That Are Eligible to Apply to the Commission for Authorization to Use the Authority Granted Under the Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended NRC-2013-0127, Order Designating an Interim Class of NRC Licensed Facilities That Are Eligible to Apply to the Commission for Authorization to Use the Authority Granted Under the Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended2013-06-0505 June 2013 Order Designating an Interim Class of NRC Licensed Facilities That Are Eligible to Apply to the Commission for Authorization to Use the Authority Granted Under the Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended NRC-2012-0183, Exemption from Certain Requirements of 10 CFR Part 26, Fitness for Duty Programs (TAC Nos. ME6738 and ME6739)2012-07-31031 July 2012 Exemption from Certain Requirements of 10 CFR Part 26, Fitness for Duty Programs (TAC Nos. ME6738 and ME6739) ML12198A1232012-07-31031 July 2012 Exemption from Certain Requirements of 10 CFR Part 26, Fitness for Duty Programs ML12198A1382012-07-31031 July 2012 Exemption from Certain Requirements of 10 CFR Part 26, Fitness for Duty Programs NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status2012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML12056A0442012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status 2022-03-08
[Table view] Category:Letter
MONTHYEARIR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000318/LER-2023-004, Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-16016 January 2024 Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-002, Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-0808 January 2024 Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 ML23318A4722023-11-14014 November 2023 Supplement to License Amendment Request to Adopt TSTF-59-A ML23317A1032023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23310A0442023-11-0707 November 2023 Project Manager Assignment IR 05000317/20230402023-11-0202 November 2023 95001 Supplemental Inspection Report 05000317/2023040 and Follow-Up Assessment Letter IR 05000317/20230032023-11-0101 November 2023 Integrated Inspection Report 05000317/2023003 and 05000318/2023003 IR 05000317/20230902023-10-26026 October 2023 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317/2023090 ML23289A1202023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23279A1202023-10-0606 October 2023 Response to NRC Inspection Report and Preliminary White Finding IR 05000317/20230502023-09-29029 September 2023 Special Inspection Report 05000317/2023050 and Preliminary White Finding and Apparent Violation ML23272A1032023-09-29029 September 2023 Condition Prohibited by Technical Specifications Due to Inoperable Nuclear Instrumentation at Very Low Power IR 05000317/20234012023-09-18018 September 2023 Cyber Security Inspection Report 05000317/2023401 and 05000318/2023401 ML23254A0012023-09-0505 September 2023 Registration of Use of Casks to Store Spent Fuel IR 05000317/20230052023-08-31031 August 2023 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2023005 and 05000318/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23241A8412023-08-29029 August 2023 Response to Request for Additional Information - Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping ML23240A3872023-08-28028 August 2023 Senior Reactor and Reactor Operator Initial License Examinations ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration ML23219A1662023-08-16016 August 2023 Request for Additional Information Regarding Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping (EPID: L-2023-LLR-0006) - Non-proprietary ML23228A1002023-08-15015 August 2023 Notification of Readiness for NRC 95001 Inspection ML23188A0402023-08-0808 August 2023 Issuance of Amendment Nos. 346 and 324 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML23214A1572023-08-0707 August 2023 Correction to the Renewed Facility Operating License Page 3 in Amendment No 345 IR 05000317/20230022023-08-0303 August 2023 Integrated Inspection Report 05000317/2023002 ML23188A0512023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 336 and 314 ML23186A0372023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 340 and 318 IR 05000317/20233012023-07-12012 July 2023 Initial Operator Licensing Examination Report 05000317/2023301 and 05000318/2023301 IR 05000317/20230122023-07-10010 July 2023 Commercial Grade Dedication Report 05000317/2023012 and 05000318/2023012 ML23180A2362023-06-29029 June 2023 Correction of Errors on Technical Specification Pages RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators ML23156A6752023-06-20020 June 2023 Request for Withholding Information from Public Disclosure for Proposed Alternative to the Requirements for Repair/Replacement of Saltwater System Buried Piping 2024-02-01
[Table view] Category:Order
MONTHYEARML22021B6602022-02-0101 February 2022 Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000)-Enclosure 1 ML22021B6592022-02-0101 February 2022 Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000) (Letter) ML21277A1922021-11-16016 November 2021 Enclosure 1, Order Approving Transfer of Licenses and Draft Conforming License Amendments ML14105A4722014-03-24024 March 2014 Order Approving Direct Transfer of Renewed Operating Licenses, Independent Spent Fuel Storage Installation License, and Conforming Amendments (TAC Nos. MF2584, MF2585, and L24780) ML13228A3992013-08-12012 August 2013 Letter to Holders of Independent Spent Fuel Storage Installation (ISFSI) Licenses Re Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit - Rin 3150-AI64 (NRC-2009-0163) EA-02-109 ML13038A1142013-06-0505 June 2013 Issuance of Order Designating an Interim Class of NRC Licensed Facilities That Are Eligible to Apply to the Commission for Authorization to Use the Authority Granted Under the Provisions of Section 161A of Atomic Energy Act of 1954, as Amen ML1135603972012-02-15015 February 2012 FRN: General Notice. Order Approving Application Regarding Proposed Corporate Merger and Indirect Transfer of License NRC-2011-0157, FRN: General Notice. Order Approving Application Regarding Proposed Corporate Merger and Indirect Transfer of License2012-02-15015 February 2012 FRN: General Notice. Order Approving Application Regarding Proposed Corporate Merger and Indirect Transfer of License ML0930006312009-10-30030 October 2009 Order Superceding October 9, 2009, Order Approving Application Regarding Proposed Corporate Restructuring and Approving Conforming Amendments ML0930006302009-10-30030 October 2009 Revised Letter Approving License Transfer Constellation Edf Development ML0925705732009-10-0909 October 2009 Letter Approving License Transfer Constellation Edf Development ML0309401982003-04-29029 April 2003 Issuance of Order for Compensatory Measures Related to Fitness-for-Duty Enhancements Applicable to Nuclear Facility Security Force Personnel ML0309106252003-04-29029 April 2003 EA-03-039, Addressee List, (Order Issued by Program Office or OE for Compensatory Measures Related to Training Enhancements on Tactical and Firearms Proficiency and Physical Fitness Applicable to Armed Nuclear Power Plant Security Force Per ML0037286822000-06-30030 June 2000 Safety Evaluation (Non-Proprietary) by the Office of Nuclear Reactor Regulation, Transfer of Renewed Operating Licenses, CC Independent Spent Fuel Storage Installation 2022-02-01
[Table view] |
Text
OFFIOIAL U9E OtdLY PROPRIETARY ItdFORro'ATIOf4 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 30, 2009 Mr. Henry B. Barron President, CEO, and Chief Nuclear Officer Constellation Energy Nuclear Group, LLC 100 Constellation Way, Suite 200C Baltimore, MD 21202
SUBJECT:
ORDER SUPERSEDING OCTOBER 9, 2009, ORDER APPROVING THE TRANSFER OF RENEWED FACILITY OPERATING LICENSE NOS. DPR-53 AND DPR-69 FOR THE CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2, AND MATERIALS LICENSE NO. SNM-2505 FOR THE CALVERT CLIFFS INDEPENDENT SPENT FUEL STORAGE INSTALLATION, AND CONFORMING AMENDMENTS (TAC NOS. ME0443 AND ME0444)
Dear Mr. Barron:
By letter to the Nuclear Regulatory Commission (NRC) dated January 22, 2009, as supplemented by letters dated February 26, April 8, June 25, and July 27, 2009, you requested consent to, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 50.80 and 10 CFR 72.50, the indirect transfer of control of the subject operating licenses and materials license, to the extent such would result from certain proposed restructuring actions in connection with a planned investment by EDF Development Whereby it would acquire a 49.99%
ownership interest in Constellation Energy Nuclear Group, LLC (CENG). The letter also requested consent to, pursuant to 10 CFR 50.90 and 10 CFR 72.56, the direct transfer of licenses held by Calvert Cliffs Nuclear Power Plant, Inc. (CCNPP, Inc.) to a new legal entity, Calvert Cliffs Nuclear Power Plant, LLC (CCNPP, LLC), and approval of conforming license amendments.
On October 9, 2009, the NRC issued Orders approving the direct and indirect transfers of licenses for the Calvert Cliffs Nuclear Power Plant (CCNPP), RE. Ginna Nuclear Power Plant (Ginna), and Nine Mile Point (NMP) necessary to implement corporate restructuring activities involving certain subsidiaries of Constellation Energy Group, Inc, and the acquisition of 49.99%
of CENG by EDF Development, Inc. The Orders also approved the conforming license amendments to be issued at the time the proposed transfers are completed.
By letter dated October 19, 2009, CENG provided new information regarding the timing and sequence of the proposed corporate restructuring of the Constellation Energy Group, Inc. (CEG) subsidiaries and the proposed EDF transaction. By letters dated October 25 (two letters), 26, and 28, 2009, CENG provided revised financial arrangements that will apply during the period between the completion of the restructuring activities and the EDF transaction. The NRC concluded that the October 9, 2009, Order must be modified i!l light of the new information provided in CENG's letters of October 19 through 28, 2009. This letter transmits the revised Order which supersedes the October 9, 2009, Order. The conforming amendment will be issued at the closing of the direct transfer of CCNPP, Inc. to CCNPP, LLC.
Enclosure 3 transmitted herewith contains Official Use Only Proprietary Information. When separated from the Enclosure, this document is decontrolled.
I OFFIOI;9;L UOE OtdLY PROPRIETARY IfdFORPo1JO:TIOt4
OFFlGhA,L elSE O~.LY PPlOPPlIE~AJ~Y INFOPlM;A,TION H. Barron -2 Enclosures 2 and 3 are the non-proprietary and proprietary versions, respectively, of the !\IRC's revised safety evaluation (SE) related to the preceding action. The non-proprietary version of the SE will be placed in the NRC's Public Document Room and added to the Agencywide Documents Access and Management System's Publicly Available Records System Library.
The superseding Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
. hard V. Guzman, Senior Project Manager lant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317,50-318, and 72-8
Enclosures:
- 1. Order Superseding October 9, 2009, Order
- 2. Safety Evaluation (non-proprietary)
- 3. Safety Evaluation (proprietary) cc wlo Enclosure 3: Distribution via Listserv OFFICIAL USE O~.LY PROPRIETARY IPJFORrdl~l'IOrJ
ENCLOSURE 1 ORDER SUPERSEDING OCTOBER 9, 2009. ORDER APPROVING APPLICATION REGARDING PROPOSED CORPORATE RESTRUCTURING AND APPROVING CONFORMING AMENDMENT
7590-01-P UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION NRC-2009-0194 In the Matter of ) Docket Nos. 50-317, 50-318, 72-8
)
CONSTELLATION ENERGY NUCLEAR ) Renewed License No. DPR-53 GROUP, LLC ) Renewed License No. DPR-69
) License No. SNM-2505 EDF DEVELOPMENT, INC. )
)
CALVERT CLIFFS NUCLEAR POWER )
PLANT, INC. )
)
CALVERT CLIFFS NUCLEAR POWER )
PLANT, LLC )
)
(Calvert Cliffs Nuclear Power Plant, )
Unit Nos. 1 and 2, and )
Calvert Cliffs Independent Spent Fuel )
Storage Installation) )
ORDER SUPERSEDING ORDER OF OCTOBER 9,2009, APPROVING APPLICATION REGARDING PROPOSED CORPORATE RESTRUCTURING AND APPROVING CONFORMING AMENDMENTS I.
Calvert Cliffs Nuclear Power Plant, Inc. (CCNPP, Inc. or the licensee) is the holder of Renewed Facility Operating License Nos. DPR-53 and DPR-69, which authorize the possession, use, and operation of Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 (CCNPP 1 and 2), and of Materials License No. SI\lM-2505, which authorizes the possession, use, and operation of the Calvert Cliffs Independent Spent Fuel Storage Installation (Calvert Cliffs ISFSI), and authorizes CCNPP, Inc. to receive, possess, transfer, and store power reactor spent fuel at the Calvert Cliffs ISFSI. The facilities are located at the licensee's site in Calvert County, Maryland.
-2 II.
By letter dated January 22, 2009, as supplemented on February 26, April 8, June 25, July 27, October 15, October 19, October 25 (two letters), October 26, and October 28,2009 (together, the Application), Constellation Energy Nuclear Group, LLC (CENG), on behalf of the licensee and EDF Development, Inc. (EDF Development) (together, the applicants), requested that the Nuclear Regulatory Commission (NRC, the Commission), pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.80, consent to the indirect license transfers that would be effected by the indirect transfer of control of CENG's ownership and operating interests in CCNPP, Inc. The actions being sought are a result of certain proposed corporate restructuring actions in connection with a planned investment by EDF Development whereby it would acquire a 49.99% ownership interest in CENG from Constellation Energy Group, Inc.
(CEG), the current 100% owner of CENG. EDF Development is a U.S. corporation organized under the laws of the State of Delaware and a wholly-owned subsidiary of E.D.F. International S.A., a public limited company organized under the laws of France, which is in turn a wholly owned subsidiary of Electricite de France S.A., a French limited company. The applicants also requested approval of the proposed direct transfer of licenses held under CCI\IPP, Inc. to a new legal entity, Calvert Cliffs Nuclear Power Plant, LLC (CCNPP, LLC) and approval of conforming license amendments that would replace references to CCNPP, Inc. in the license with references to CCNPP, LLC to reflect the transfer of ownership and operating authority, specifically, to possess, use, and operate CCNPP 1 and 2 and to receive, possess, or use related licensed materials under the applicable conditions and authorizations in the CCNPP 1 and 2 licenses and for the ISFSI license.
Following the closing of the transfer of ownership interests in CENG to EDF Development, EDF Development will hold a 49.99% ownership interest in CENG; CEG will hold a 50.01 % ownership interest in CENG through two new intermediate parent companies,
-3 Constellation Nuclear, LLC and CE Nuclear, LLC, formed for non-operational purposes. In addition, Constellation Nuclear Power Plants, Inc., which is currently an intermediate holding company between CENG and Nine Mile Point Nuclear Station, LLC and R.E. Ginna Nuclear Power Plant, LLC, will convert to a Delaware limited liability company by operation of law and become Constellation Nuclear Power Plants, LLC, and will exist as an intermediate holding company between CENG and CCNPP, LLC, Nine Mile Point Nuclear Station, LLC, and R.E.
Ginna Nuclear Power Plant, LLC. CCNPP, Inc. will convert to CCNPP, LLC by merger.
No physical changes to the facilities or operational changes are being proposed in the application. The proposed conforming license amendment would replace references to CCNPP, Inc. in the license with references to CCNPP, LLC to reflect the proposed direct transfer of the licenses.
Approval of the transfer of the license and the conforming license amendment is requested by the applicants pursuant to 10 CFR 50.80, 10 CFR 50.90, and 10 CFR 72.50.
Notice of the request for approval and opportunity for a hearing was published in the Federal Register on May 7, 2009 (74 FR 21413). No hearing requests or petitions to intervene were received. The !\IRC received comments from a member of the public in Seattle, Washington, in an e-mail dated May 22, 2009. The comments did not provide any information additional to that in the application, nor did they provide any information contradictory to that provided in the application.
Pursuant to 10 CFR 50.80 and 10 CFR 72.50, no license, or any right thereunder, shall be transferred, directly or indirectly, through transfer of control of the license, unless the Commission shall give its consent in writing. Upon review of the information in the application and other information before the Commission, and relying upon the representations and agreements contained in the application, the NRC staff has determined that the proposed indirect license transfer of control of the subject licenses held by the licensee to the extent such
- 4 will result from the proposed corporate restructuring actions and the planned investment by EDF Development whereby it will acquire a 49.99% ownership interest in CENG, and that the direct transfer of CCNPP, Inc. to CCNPP, LLC as described in the Application, are otherwise consistent with applicable provisions of law, regulations, and Orders issued by the NRC, pursuant thereto, subject to the conditions set forth below. The NRC staff has further found that the Application for the proposed license amendment complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; the facility will operate in conformity with the Application, the provisions of the Act, and the rules and regulations of the Commission; there is reasonable assurance that the activities authorized by the proposed license amendment can be conducted without endangering the health and safety of the public and that such activities will be conducted in compliance with the Commission's regulations; the issuance of the proposed license amendments will not be inimical to the common defense and security or to the health and safety of the public; and the issuance of the proposed amendments will be in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
On October 9, 2009, the Commission issued, "Order Approving Application Regarding Proposed Corporate Restructuring and Approving Conforming Amendments."
By letter dated October 19, 2009, CENG explained that its January 22, 2009, application for the license transfers had anticipated nearly concurrent completion of the proposed internal corporate restructuring of the CEG subsidiaries and the proposed EDF acquisition of 44.99% of CENG. After it filed its January 22, 2009, application, CENG learned that the restructuring activities for the CEG subsidiaries will be completed at least 8 days prior to closing the transaction involving EDF. In letters dated October 25 (two letters), 26, and 28, 2009, CENG provided revised financial arrangements that will apply during the period between the
-5 completion of the internal restructuring activities and the acquisition of 44.99% of CENG by EDF and a revised operating agreement that will apply after the EDF closing.
The NRC concluded that modifications were needed to the cover letter, the October 9, 2009, Order, and the safety evaluations in light of the new information provided in CENG's letters of October 19 through 28, 2009. This Order contains those modifications and supersedes the Order issued October 9, 2009.
The findings set forth above are supported by a modified NRC safety evaluation (SE) dated the same day as this Order.
III.
Accordingly, pursuant to Sections 161b, 161i, 1610, and 184 of the Act, 42 U.S.C.
Sections 2201(b), 2201(i), 2201(0), and 2234; and 10 CFR 50.80 and 10 CFR 72.50, IT IS HEREBY ORDERED that the Application regarding the indirect license transfers and direct license transfers related to the proposed corporate restructuring actions and the planned investment by EDF Development, as described herein, is approved, subject to the following conditions:
A. With regard to the direct and indirect transfers resulting from the restructuring of the CEG subsidiaries:
(1) Before completion of the direct transfer of the CCNPP license, CENG shall provide the Director of the Office of Nuclear Reactor Regulation satisfactory documentary evidence that CCNPP, LLC has obtained the appropriate amount of insurance required of licensees under 10 CFR Part 140 of the Commission's regulations.
(2) CCNPP, LLC may no longer rely exclusively on an external sinking fund as its decommissioning funding assurance mechanism and will be required to implement an alternate decommissioning funding assurance mechanism,
-6 acceptable per NRC requirements outlined in 10 CFR 50.75( e)( 1), which will be used to provide decommissioning funding assurance.
(3) The financial arrangements resulting from the corporate restructuring activities of the CEG subsidiaries are subject to the following:
(a) The Inter-Company Credit Agreements (ICA) described in the October 25, 2009, supplement to the Application shall be effective as of the date of the direct and indirect transfers (whichever occurs first) resulting from the restructuring of CEG subsidiaries and shall be consistent with the representations contained in the Application. CENG and CCNPP, LLC shall take no action to cause CEG, or their successors and assigns, to void, cancel or materially modify the ICA as submitted without the prior written consent of the NRC staff. CENG shall inform the Director of the Office of Nuclear Reactor Regulation, in writing, no later than 10 days after any funds are provided to CENG or any of the licensees by CEG or EDF Development under any Support Agreement.
(b) The Master Demand Notes described in the October 26,2009, supplement to the Application shall be effective as of the date of the direct and indirect transfers (whichever occurs first) resulting from the restructuring of CEG subsidiaries and shall be consistent with the representations contained in the Application. CENG and CCNPP, LLC, shall take no action to cause CEG, or their successors and assigns, to void, cancel or materially modify the Master Demand Notes without the prior written consent of the NRC staff.
B. With regard to the indirect transfers resulting from the acquisition of 44.99% of CENG by EDF Development (EDF Closing):
-7 (1) Before completion of the EDF Closing, Conditions A.(1) and A.(2) above must be fulfilled.
(2) The ownership and governance arrangements in effect as of the date of the indirect transfers to EDF Development are subject to the following:
(a) The Operating Agreement included with the supplement dated October 25, 2009, may not be modified in any material respect concerning decisionmaking authority over "safety issues" as defined therein without the prior written consent of the Director, Office of Nuclear Reactor Regulation.
(b) At least half the members of CENG's Board of Directors must be U.S.
citizens.
(c) The Chief Executive Officer (CEO), Chief Nuclear Officer (CNO) and Chairman of the Board of Directors of CENG must be U.S. citizens.
These individuals shall have the responsibility and exclusive authority to ensure and shall ensure that the business and activities of CENG with respect to the Calvert Cliffs, Unit Nos. 1 and 2, Calvert Cliffs ISFSI, Nine Mile Point, Unit Nos. 1 and 2, and R.E. Ginna licenses are at all times conducted in a manner consistent with the public health and safety and common defense and security of the United States.
(d) CENG will establish a Nuclear Advisory Committee (NAC) composed of U.S. citizens who are not officers, directors, or employees of CENG, CEG or EDF Development. The NAC will report to and provide transparency to the NRC and other U.S. governmental agencies regarding foreign ownership and control of nuclear operations.
(e) CENG shall cause to be transmitted to the Director, Office of Nuclear
-8 Reactor Regulation, within 30 days of knowledge of a filing with the U.S.
Securities and Exchange Commission, any Schedules 13D or 13G filed pursuant to the Securities and Exchange Act of 1934 that disclose beneficial ownership of any registered classes of CEG stock.
(3) The financial arrangements applicable to the indirect transfers resulting from the EDF Closing are subject to the following:
(a) The working capital and cash pooling arrangements described in Article IV of the Operating Agreement included with the October 25, 2009 supplement to the Application, shall be effective as of the date of the indirect transfers to EDF Development and shall be consistent with the representations contained in the Application. CENG and CCNPP, LLC shall take no action to cause CEG and/or EDF Development, or their successors and assigns, to void, cancel or materially modify the working capital and cash pooling arrangements in the Operating Agreement without the prior written consent of the NRC staff.
(b) The Support Agreements described in the February 26, 2009 supplement to the Application shall be effective as of the date of the indirect transfers to EDF Development; shall supersede the Inter-Company Credit Agreements provided by CEG, Inc.; and shall be consistent with the representations contained in the Application. CENG and CCNPP, LLC shall take no action to cause CEG and/or EDF Development, or their successors and assigns, to void, cancel or materially modify the Support Agreements as submitted without the prior written consent of the NRC staff. CENG shall inform the Director of the Office of Nuclear Reactor Regulation, in writing, no later than 10 days after any funds are provided
-9 to CENG or any of the licensees by CEG or EDF Development under any Support Agreement.
(c) The Master Demand Notes described in the October 28,2009 supplement to the Application, shall be effective as of the date of the indirect transfers to EDF Development; shall supersede the Master Demand Notes provided by CEG, Inc.; and shall be consistent with the representations contained in the Application. CENG and CCNPP, LLC, shall take no action to cause CEG and/or EDF Development, or their successors and assigns, to void, cancel or materially modify the Master Demand Notes without the prior written consent of the NRC staff.
IT IS FURTHER ORDERED that, consistent with 10 CFR 2.1315(b), the license amendment that makes changes to conform the license to reflect the subject direct license transfer is approved. The amendment shall be issued and made effective at the time the proposed direct license transfer is completed.
IT IS FURTHER ORDERED that CENG shall inform the Director of the Office of Nuclear Reactor Regulation, in writing, of the date of closing of the transfer of EDF Development's ownership and operating interests in CENG at least 1 business day before the closing. Should the transfers of the licenses not be completed within 1 year of this Order's date of issuance, this Order shall become null and void, provided, however, that upon written application and for good cause shown, such date may be extended by Order.
This Order supersedes the Order issued on October 9, 2009, and is effective upon issuance.
For further details with respect to this Order, see the initial application dated January 22, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML090290101), as supplemented by letters dated February 26 (ML090630426), April 8
- 10 (ML091000665), June 25 (ML091811094), and July 27,2009 (ML092150712), October 15 (ML092920168), October 19 (ML0929990101), October 25 (ML093000127 and ML093000141),
October 26 (ML093000506), and October 28, and the SE (ML093010003) with the same date as this Order, which are available for public inspection at the Commission's Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike, Room 0-1 F21 (First Floor), Rockville, Maryland, and accessible electronically from the ADAMS Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/readinq-rm/adams.html.
Persons who do not have access to ADAMS, or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1 800-397-4209 or 301-415-4737, or bye-mail at pdr.resource@nrc.qov.
Dated at Rockville, Maryland, this so" day of October 2009.
FOR THE NUCLEAR REGULATORY COMMISSION
~L:
Office of Nuclear Reactor Regulation Michael F. Weber, Director Office of Nuclear Material Safety and Safeguards
OFFIOI,etL UOE m~LV PROPRIETARV IP~FORPo1ATIOP~
- H. Barron -2 Enclosures 2 and 3 are the non-proprietary and proprietary versions, respectively, of the NRC's revised safety evaluation (SE) related to the preceding action. The non-proprietary version of the SE will be placed in the NRC's Public Document Room and added to the Agencywide Documents Access and Management System's PUblicly Available Records System Library.
The superseding Order has been forwarded to the Office of the Federal Register for publication.
Sincerely, IRA!
Richard V. Guzman, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317, 50-318, and 72-8
Enclosures:
- 1. Order Superseding October 9, 2009, Order
- 2. Safety Evaluation (non-proprietary)
- 3. Safety Evaluation (proprietary) cc wlo Enclosure 3: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsRgn1 MallCenter Resouce KMartin, NRR LPL1-1Reading File RidsOgcRp Resource NMSS_DSFT_LB RidsNrrAdes Resource RidsAcrsAcnw_ MailCTRResource E. Benner, NMSS RidsNrrOd Resource RidsSecyMailCenterResource J. Goshen, NMSS RidsNrrAdro Resource RidsOpaMailCenterResource RidsNrrDorlLpl1-1 Resource LTrocine, EDO R-1 RidsNrrPMCalvertCliffs Resource RidsNrrDprPfpb Resource RidsNrrLASLittle Resource RidsNrrDirslolb Resource S. Burnell, OPA ASimmons, NRR RidsNrrAdes Resource RidsNrrPMNineMilePoint Resource Package No.: ML093000625 Letter: ML093000630 Order: ML093000631 SE (Non-proprietary): ML093010003 SE (Pro~ rietarv): ML093010002 "Concurrence via E-mail OFFICE LPL1-1/PM LPL 1-1/PM PFPB/BC* LPL1-1 NAME RGuzman SUttle RCarlson* NSalgado DATE 10/29/09 10/29/09 10/30/09 10/29/09 OFFICE DORL/D OGC NMSSID NRRlD NAME JGiitter SUttal MWeber ELeeds DATE 10/29/09 10/30/09 10/30/09 10/30/09 OFFICIAL RECORD COPY OFFIGhQ,L USE O~dLY PROPRIETARY IP~FORI\1ATIOP~