Request for Additional Information for the Review of the Palo Verde Nuclear Generating Station, Units 1, 2, and 3, License Renewal Application
ML093090057
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 11/13/2009
From: Lisa Regner
License Renewal Projects Branch 2
To: Edington R
Arizona Public Service Co
Regner L M, NRR/DLR, 415-1906
References
Download: ML093090057 (5)


Text

November 13, 2009 Mr. Randall K. Edington Executive Vice President, Nuclear Mail Station 7602 Arizona Public Service Company P.O. Box 52034 Phoenix, AZ 85072-2034

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION

Dear Mr. Edington:

By letter dated December 11, 2008, as supplemented by letters dated April 14, 2009 and October 14, 2009, Arizona Public Service Company (APS) submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 to renew Operating License Nos. NPF-41, NPF-51, and NPF-74 for the Palo Verde Nuclear Generating Station, Units 1, 2, and 3. The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review. Further requests for additional information may be issued in the future.

A mutually agreeable date for your response was determined to be 30 calendar days from the date of this letter. If you have any questions, please contact me at 301-415-1906 or by e-mail at Lisa.Regner@nrc.gov.

Sincerely,

/RA/

Lisa M. Regner, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-528, 50-529, and 50-530

Enclosure:

As stated cc w/encl: See next page

ML093090057 OFFICE LA:DLR PM:RPB2:DLR PM:RPB2:DLR BC:RPB2:DLR PM:RPB2:DLR NAME SFigueroa NFerrer LRegner DWrona LRegner (Signature)

DATE 11/5/09 11/10/09 11/12/09 11/12/09 11/13/09

Letter to Randall K. Edington from Lisa M. Regner dated November 13, 2009

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3, LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource RidsOpaMail


L. Regner B. Mizuno R. Treadway, RIV G. Pick, RIV

PALO VERDE NUCLEAR GENERATING STATION LICENSE RENEWAL APPLICATION REQUEST FOR ADDITIONAL INFORMATION RAI 2.3.3.11-1 Drawing LR-PWNGS-HJ-02-M-HJP-001 at zone/location H-16 and LR-PWNGS-HJ-02-M-HJP-002 at zones/locations H-2/16 show fixed louvers in air supply and exhaust flow paths that are not highlighted as being in scope. If these components are excluded from the scope of license renewal, please provide a basis for their exclusion. Please include a discussion on whether deterioration related failure of these components could result in compromised performance of the Control Building Heating, Ventilating, and Air Conditioning (HVAC) System or allow intrusion of missile/debris that could adversely affect in-scope components.

RAI-2.3.3.12-1 Drawing LR-PVNGS-HA-02-M-HAP-001 at locations H-8 and F-6 show fire dampers HAN-M05 and HAN-M29A that are not highlighted. Please provide the basis for excluding these fire dampers from the license renewal scope. Please include in your discussion, a description of the airflow entering into the corridor that then passes through fire damper HAN-M29A into the west piping penetration room.

RAI-2.3.3.15-1 Drawing LR-PVNGS-HD-01-M-HDP-001 shows fixed louver assemblies at drawing zones/locations D-1 and B-3 are not color coded as being in scope. If these components are excluded from the scope of license renewal, please provide a basis for their exclusion. Please include a discussion on whether deterioration related failure of these components could result in compromised performance of the Diesel Generator Building HVAC System or allow intrusion of missile/debris that could adversely affect in-scope components.

RAI-2.3.3.17-1 Drawing LR-PVNGS-HT-01-M-HTP-001 at zone/location B-2 shows fire dampers HTN-M39-S3M and HTN-M40-S3M highlighted as being in scope. Please discuss whether these fire dampers are mounted in the fire barrier boundary (wall) and if the downstream backdraft dampers/ducting should also be shown in scope as needed to maintain the fire barrier boundary integrity. If the downstream backdraft dampers/ducting are excluded from the scope of license renewal, please provide a basis for their exclusion.

ENCLOSURE

Palo Verde Nuclear Generating Station, Units 1, 2, and 3 cc:

Mr. Steve Olea Mr. John C. Taylor, Director, Nuclear Arizona Corporation Commission Generation 1200 W. Washington Street El Paso Electric Company Phoenix, AZ 85007 340 E. Palm Lane, Suite 310 Phoenix, AZ 85004 Mr. Douglas Kent Porter, Senior Counsel Southern California Edison Company Mr. James Ray Law Department, Generation Resources Public Service Company of New Mexico P.O. Box 800 2401 Aztec NE, MS Z110 Rosemead, CA 91770 Albuquerque, NM 87107-4224 Senior Resident Inspector Mr. Geoffrey M. Cook U.S. Nuclear Regulatory Commission Southern California Edison Company P.O. Box 40 5000 Pacific Coast Highway, Bldg. D21 Buckeye, AZ 85326 San Clemente, CA 92672 Regional Administrator, Region IV Mr. Robert Henry U.S. Nuclear Regulatory Commission Salt River Project 612 E. Lamar Blvd., Suite 400 6504 E. Thomas Road Arlington, TX 76011-4125 Scottsdale, AZ 85251 Chairman Mr. Jeffrey T. Weikert Maricopa County Board of Supervisors Assistant General Counsel 301 W. Jefferson, 10th Floor El Paso Electric Company Phoenix, AZ 85003 Mail Location 167 123 W. Mills Mr. Aubrey V. Godwin, Director El Paso, TX 79901 Arizona Radiation Regulatory Agency 4814 S. 40th Street Mr. Eric Tharp Phoenix, AZ 85040 Los Angeles Department of Water & Power Southern California Public Power Authority Mr. Scott Bauer, Director P.O. Box 51111, Room 1255-C Regulatory Affairs Los Angeles, CA 90051-0100 Palo Verde Nuclear Generating Station Mail Station 7636 Mr. Brian Almon P.O. Box 52034 Public Utility Commission Phoenix, AZ 85072-2034 William B. Travis Building P.O. Box 13326 Mr. Dwight C. Mims, Vice President 1701 N. Congress Avenue Regulatory Affairs and Plant Improvement Austin, TX 78701-3326 Palo Verde Nuclear Generating Station Mail Station 7605 P.O. Box 52034 Phoenix, AZ 85072-2034