UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 September 1, 2009 Mr. Sam Belcher Vice President Nine Mile Point Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - NINE MILE POINT NUCLEAR STATION
Dear Mr. Belcher:
On August 12, 2009, the NRC staff completed its performance review of Nine Mile Point Nuclear Station (NMPNS). Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from July 1, 2008, through June 30, 2009. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Information" will include the security cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter at Nine Mile Point Unit 1 was within the Licensee Response column of the NRC=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green).
Plant performance for the most recent quarter at Nine Mile Point Unit 2 was within the Regulatory Response Column of the NRCs Action Matrix, based on one PI being classified as having low to moderate safety significance (White). The Mitigating Systems Performance Index (MSPI), Cooling Water Systems crossed the White significance threshold in the 4th quarter 2008 and has remained above the threshold through the first two quarters of 2009. The White PI was due to a combination of high unavailability for service water pump maintenance activities and reliability challenges following introduction of foreign material into the service water pump suctions in November 2008. On July 20, 2009, we were notified by your staff of your readiness for the NRC to conduct a supplemental inspection to review the actions taken to address the degraded SW pumps. Therefore, we conducted a supplemental inspection using Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area, from August 24 to 28, 2009. The results of this inspection will be provided to you in separate correspondence and may result in a change to our assessment of the plants performance and the facility inspection plan.
Based on our current assessment of performance for Nine Mile Point, we plan to conduct, the reactor oversight process (ROP) baseline inspections at Unit 1 and 2, as well as the
S. Belcher 2
supplemental inspection at Unit 2 using Inspection Procedure 95001.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2010. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
As you may know, the NRC is currently evaluating the scope and frequency of all the baseline inspection procedures as part of our biennial review of the ROP. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Glenn Dentel at (610) 337-5233 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
James W. Clifford, Acting Director Division of Reactor Projects Docket Nos. 50-220, 50-410 License Nos. DPR-63, DPR-59
Enclosure:
Nine Mile Point Inspection/Activity Plan cc w/ encl.:
M. Wallace, Vice-Chairman, Constellation Energy H. Barron, President, CEO & Chief Nuclear Officer, Constellation Energy Nuclear Group C. Fleming, Esquire, Senior Counsel, Nuclear Generation, Constellation Energy Group, LLC M. Wetterhahn, Esquire, Winston & Strawn T. Syrell, Director, Licensing, Nine Mile Point Nuclear Station J. Spath, Program Director, New York State Energy Research and Development Authority F. Murray, New York State Energy Research and Development Authority P. Eddy, New York State Department of Public Service C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law Supervisor, Town of Scriba P. Church, Oswego County Administrator T. Judson, Central NY Citizens Awareness Network D. Katz, Citizens Awareness Network J. Evans, LIPA
S. Belcher 2
G. Detter, Manager, Corp Nuclear Safety and Security, Constellation Energy M. Bockstein, Chairman and Executive Director, State Consumer Protection Board R. Thomson, FEMA RII RAC
S. Belcher 2
supplemental inspection at Unit 2 using Inspection Procedure 95001.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2010. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
As you may know, the NRC is currently evaluating the scope and frequency of all the baseline inspection procedures as part of our biennial review of the ROP. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Glenn Dentel at (610) 337-5233 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
James W. Clifford, Acting Director Division of Reactor Projects Docket Nos. 50-220, 50-410 License Nos. DPR-63, DPR-59 SUNSI Review Complete: nsp* (Reviewer=s Initials)
DOCUMENT NAME: S:\\ROP-10 Mid-Cycle Review\\Branch 1\\NMP MidCycle Ltr 09.doc ML092440311 After declaring this document AAn Official Agency Record@ it will/will not be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/ DRP RI/DRP NAME NPerry/nsp*
GDentel/gtd*
JClifford/jwc DATE 08/21/09 08/24/09 09/01/09
S. Belcher 2
Distribution: (via email)
S. Collins, RA M. Dapas, DRA D. Lew, DRP J. Clifford, DRP D. Roberts, DRS P. Wilson, DRS DRS Branch Chiefs L. Scholl, DRS D. Silk, DRS D. Screnci, ORA N. Sheehan, ORA R. Barkley, ORA L. Trocine, RI OEDO R. Nelson, NRR M. Kowal, NRR R. Guzman, NRR D. V. Pickett, NRR G. Dentel, DRP N. Perry, DRP J. Hawkins, DRP E. Knutson, SRI D. Dempsey, RI K. Kolek, DRP, OA D. Bearde, DRP ROPReportsResource Region I Docket Room RidsNrrDirsIpab
Inspection / Activity Plan Page 1 of 3 09/01/2009 10:50:37 Report 22 07/01/2009 - 12/31/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Nine Mile Point 8/31EXAM
- U1 INITIAL OPERATOR LICENSING EXAM 7
1 FY09 - NINE MILE POINT UNIT 1 INTIAL OPERATOR LICENSING EXAM U01782 07/27/2009 07/30/2009 1
FY09 - NINE MILE POINT UNIT 1 INTIAL OPERATOR LICENSING EXAM U01782 08/31/2009 09/04/2009 8/24 EXM
- U2 INITIAL OPERATOR LICENSING EXAM 4
1 FY09 - NINE MILE POINT 2 INITIAL OPERATOR EXAM U01698 07/27/2009 07/31/2009 1
FY09 - NINE MILE POINT 2 INITIAL OPERATOR EXAM U01698 08/24/2009 08/28/2009 71121
- OCC RAD SAFETY 1
1, 2 IP ALARA Planning and Controls 7112102 07/06/2009 07/10/2009 1, 2 IP ALARA Planning and Controls 7112102 07/06/2009 07/10/2009 1, 2 IP Radiation Monitoring Instrumentation and Protective Equipment 7112103 07/06/2009 07/10/2009 92702
- SLIV FOLLOW-UP 1
1 IP Followup On Corrective Actions For Violations And Deviations 92702 07/20/2009 07/24/2009 SUPPL
- 95001 SUPPL INSPECTION - WHITE SW PI 4
2 IP Supplemental Inspection For One Or Two White Inputs In A Strategic Performance Area 95001 08/24/2009 08/28/2009 TI 173
- GROUNDWATER TI 1
1, 2 IP Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 2515/173 08/24/2009 08/28/2009 EP EXER
- EP EXERCISE INSPECTION 5
1, 2 IP Exercise Evaluation 7111401 09/20/2009 09/26/2009 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 09/20/2009 09/26/2009 1, 2 IP Performance Indicator Verification 71151 09/20/2009 09/26/2009 7111111B
- BIENNIAL REQUAL INSP(U2) W P/F RESULTS 3
1, 2 IP Licensed Operator Requalification Program 7111111B 11/30/2009 12/04/2009 71152B
- PI&R BIENNIAL TEAM 4
1, 2 IP Identification and Resolution of Problems 71152B 10/05/2009 10/09/2009 1, 2 IP Identification and Resolution of Problems 71152B 10/19/2009 10/23/2009 71121
- OCC RAD SAFETY 1
1, 2 IP Access Control to Radiologically Significant Areas 7112101 11/09/2009 11/13/2009 1, 2 IP ALARA Planning and Controls 7112102 11/09/2009 11/13/2009 1, 2 IP Radiation Monitoring Instrumentation and Protective Equipment 7112103 11/09/2009 11/13/2009 1, 2 IP Performance Indicator Verification 71151 11/09/2009 11/13/2009 TI-177
- MANAGING GAS ACCUMULATION IN ECCS 5
1, 2 IP Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 2515/177 02/01/2010 02/05/2010 71121
- OCC RAD SAFETY 1
2 IP Access Control to Radiologically Significant Areas 7112101 04/19/2010 04/23/2010 2
IP ALARA - Required 7112102-7112102R 04/19/2010 04/23/2010 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Inspection / Activity Plan Page 2 of 3 09/01/2009 10:50:37 Report 22 07/01/2009 - 12/31/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Nine Mile Point 71121
- OCC RAD SAFETY 1
2 IP Radiation Monitoring Instrumentation and Protective Equipment 7112103 04/19/2010 04/23/2010 7111108G
- U2 INSERVICE INSPECTION 1
2 IP Inservice Inspection Activities - BWR 7111108G 04/26/2010 04/30/2010 7112203
- PUB RAD SAFETY - REMP 1
1, 2 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 7112203 06/28/2010 07/02/2010 EP PROGR
- EP PROGRAM INSPECTION 1
1, 2 IP Alert and Notification System Testing 7111402 07/12/2010 07/16/2010 1, 2 IP Emergency Response Organization Augmentation Testing 7111403 07/12/2010 07/16/2010 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 07/12/2010 07/16/2010 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 07/12/2010 07/16/2010 1, 2 IP Drill/Exercise Performance 71151-EP01 07/12/2010 07/16/2010 1, 2 IP ERO Drill Participation 71151-EP02 07/12/2010 07/16/2010 1, 2 IP Alert & Notification System 71151-EP03 07/12/2010 07/16/2010 11/07EXM
- U2 INITIAL OPERATOR LICENSING EXAM 6
2 FY11 - NINE MILE POINT U2 INITIAL OPERATOR LICENSING EXAM U01790 10/11/2010 10/15/2010 11/14EXM
- U1 OPERATOR LICENSING INITIAL EXAMS 5
1 FY11-NINE MILE POINT U1 INITIAL OPERATOR LICENSING EXAM U01797 10/11/2010 10/15/2010 11/07EXM
- U2 INITIAL OPERATOR LICENSING EXAM 6
2 FY11 - NINE MILE POINT U2 INITIAL OPERATOR LICENSING EXAM U01790 11/08/2010 11/12/2010 11/14EXM
- U1 OPERATOR LICENSING INITIAL EXAMS 5
1 FY11-NINE MILE POINT U1 INITIAL OPERATOR LICENSING EXAM U01797 11/15/2010 11/19/2010 7111107T
- TRIENNIAL HEAT SINK 1
1, 2 IP Heat Sink Performance 7111107T 07/19/2010 07/23/2010 71121
- OCC RAD SAFETY 1
1, 2 IP Access Control to Radiologically Significant Areas 7112101 08/09/2010 08/13/2010 1, 2 IP ALARA - Required 7112102-7112102R 08/09/2010 08/13/2010 1, 2 IP Radiation Monitoring Instrumentation and Protective Equipment 7112103 08/09/2010 08/13/2010 7111111B
- REQUAL INSP (NMP1) WITH P/F RESULTS 3
1, 2 IP Licensed Operator Requalification Program 7111111B 10/25/2010 10/29/2010 MODS
- PERMANENT PLANT MODIFICATIONS 5
1, 2 IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 09/13/2010 09/17/2010 1, 2 IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 09/27/2010 10/01/2010 71121
- OCC RAD SAFETY 1
1, 2 IP Access Control to Radiologically Significant Areas 7112101 11/15/2010 11/19/2010 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Inspection / Activity Plan Page 3 of 3 09/01/2009 10:50:37 Report 22 07/01/2009 - 12/31/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Nine Mile Point 71121
- OCC RAD SAFETY 1
1, 2 IP ALARA - Required 7112102-7112102R 11/15/2010 11/19/2010 1, 2 IP Radiation Monitoring Instrumentation and Protective Equipment 7112103 11/15/2010 11/19/2010 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 11/15/2010 11/19/2010 1, 2 IP RETS/ODCM Radiological Effluent 71151-PR01 11/15/2010 11/19/2010 7112202
- PUB RAD SAFETY - RADWASTE 1
1, 2 IP Radioactive Material Processing and Transportation 7112202 12/13/2010 12/17/2010 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.