MONTHYEARIR 05000317/20230052023-08-31031 August 2023 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2023005 and 05000318/2023005) IR 05000317/20220062023-03-0101 March 2023 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2022006 and 05000318/2022006) ML23047A1022023-02-16016 February 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000317/2023401 and 05000318/2023401 ML23040A0102023-02-0909 February 2023 Notification of Commercial Grade Dedication Inspection (05000317/2023012 and 05000318/2023012) and Request for Information IR 05000317/20220052022-08-31031 August 2022 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2022005 and 05000318/2022005) ML22179A2112022-06-28028 June 2022 Notification of Conduct of a Fire Protection Team Inspection IR 05000317/20210062022-03-0202 March 2022 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2021006 and 05000318/2021006) IR 05000317/20210052021-09-0101 September 2021 Updated Inspection Plan for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2021005 and 05000318/2021005) ML21187A2232021-07-29029 July 2021 Temporary Instruction 2515/194 Inspection Documentation Request IR 05000317/20200062021-03-0303 March 2021 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2020006 and 05000318/2020006) ML21053A3142021-02-22022 February 2021 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000317/2021010 and 05000318/2021010 IR 05000317/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000317/2020005 and 05000318/2020005) ML20154K4602020-06-0202 June 2020 Information Request to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000317/2020011 and 05000318/2020011 IR 05000317/20190062020-03-0303 March 2020 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2019006 and 05000318/2019006) IR 05000317/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Reports 05000317/2019005 and 05000318/2019005) ML19141A1242019-05-21021 May 2019 Notification of Conduct of a Triennial Fire Protection Baseline Inspection and Request for Information IR 05000317/20180062019-03-0404 March 2019 Annual Assessment Letter for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2018006 and 05000318/2018006) ML18348A4812018-12-13013 December 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000317/2019403 and 05000318/2019403 IR 05000317/20180052018-08-28028 August 2018 Updated Inspection Plan: Inspection Report 05000317/2018005 and 05000318/2018005 IR 05000317/20170062018-02-28028 February 2018 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2017006 and 05000318/2017006, Report 05000317/2017402 and 05000318/2017402, Report 05000317/2017501 and 05000318/2017501) IR 05000317/20170052017-08-28028 August 2017 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 - Inspection Report 05000317/2017005 and 05000318/2017005 IR 05000317/20160062017-03-0101 March 2017 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2016006 and 05000318/2016006) IR 05000317/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2, Report 05000317/2016005 and 05000318/2016005 IR 05000317/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2015006 and 05000318/2015006) IR 05000317/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317/2015005 and 05000318/2015005) IR 05000317/20140012015-03-0404 March 2015 2014 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2, (Report 05000317/2014001 and 05000318/2014001)(w/Inspection Plan) IR 05000317/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317-14-006 and 05000318-14-006) ML14206A9932014-07-25025 July 2014 Conrete Bench-Top Autoclave Experiment Test Plan for Calvert Cliffs Nuclear Power Plant. CCNPP-CHLE-010, Revision 1 IR 05000317/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317/2013001 and 05000318/2013001) (W/Inspection Plan) ML13267A0052013-09-23023 September 2013 Requal Program Inspection 60 Day Letter IR 05000317/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317-13-006 and 05000318-13-006) IR 05000317/20120012013-03-0404 March 2013 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 & 2 (Report 05000317-12-001 and 05000318-12-001) ML12244A2032012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 Calvert Cliffs Nuclear Power Plant Units 1 and 2 IR 05000317/20110012012-03-0505 March 2012 Annual Assessment Letter(Report 05000317/2011001 and 05000318/2011001) ML1124208652011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Calvert Cliffs Nuclear Power Plant Units 1 and 2 IR 05000317/20100012011-03-0404 March 2011 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant-05000317/2010001 and 05000318/2010001 ML1031402312010-11-10010 November 2010 Pre-Inspection Cover Sheet and Inspection Plan (12/6/10 - 12/10/10) ML1024402082010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Calvert Cliffs Nuclear Power Plant ML1016600082010-06-15015 June 2010 Pre-Inspection Cover Sheet and Inspection Plan (6/7 - 6/11/10) ML1006208092010-03-0303 March 2010 Annual Assessment Letter ML0924402772009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Calvert Cliffs Nuclear Power Plant, Dated 09/01/2009 IR 05000317/20090012009-03-0404 March 2009 IR 05000317-09-001 and 05000318-09-001, on 01/01/2009 - 12/31/2008, Calvert Cliffs Nuclear Power Plant Annual Assessment Report IR 05000317/20080012008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, Calvert Cliffs, (IR 05000317-08-001 and 05000318-08-001) ML0806100132008-03-0303 March 2008 (05000317-08-001, 05000318-08-001, )Annual Assessment Letter EOC 2007 ROP8 ML0734707242007-12-13013 December 2007 ROP8 - Change to the Inspection Plan for the Calvert Cliffs Nuclear Power Plant ML0724309302007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - Calvert Cliffs Nuclear Power Plant IR 05000317/20070012007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Calvert Cliffs Station (IR 05000317-07-001 and 05000318-07-001) ML0624304482006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan - Calvert Cliffs Nuclear Power Plant ML0606203372006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Calvert Cliffs Nuclear Power Plant (Report 05-317/2006001 and 05-318/2006001) ML0524206942005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Calvert Cliffs 2023-08-31
[Table view] Category:Letter
MONTHYEARIR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000318/LER-2023-004, Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-16016 January 2024 Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-002, Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-0808 January 2024 Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 ML23318A4722023-11-14014 November 2023 Supplement to License Amendment Request to Adopt TSTF-59-A ML23317A1032023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23310A0442023-11-0707 November 2023 Project Manager Assignment IR 05000317/20230402023-11-0202 November 2023 95001 Supplemental Inspection Report 05000317/2023040 and Follow-Up Assessment Letter IR 05000317/20230032023-11-0101 November 2023 Integrated Inspection Report 05000317/2023003 and 05000318/2023003 IR 05000317/20230902023-10-26026 October 2023 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317/2023090 ML23289A1202023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23279A1202023-10-0606 October 2023 Response to NRC Inspection Report and Preliminary White Finding IR 05000317/20230502023-09-29029 September 2023 Special Inspection Report 05000317/2023050 and Preliminary White Finding and Apparent Violation ML23272A1032023-09-29029 September 2023 Condition Prohibited by Technical Specifications Due to Inoperable Nuclear Instrumentation at Very Low Power IR 05000317/20234012023-09-18018 September 2023 Cyber Security Inspection Report 05000317/2023401 and 05000318/2023401 ML23254A0012023-09-0505 September 2023 Registration of Use of Casks to Store Spent Fuel IR 05000317/20230052023-08-31031 August 2023 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2023005 and 05000318/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23241A8412023-08-29029 August 2023 Response to Request for Additional Information - Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping ML23240A3872023-08-28028 August 2023 Senior Reactor and Reactor Operator Initial License Examinations ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration ML23219A1662023-08-16016 August 2023 Request for Additional Information Regarding Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping (EPID: L-2023-LLR-0006) - Non-proprietary ML23228A1002023-08-15015 August 2023 Notification of Readiness for NRC 95001 Inspection ML23188A0402023-08-0808 August 2023 Issuance of Amendment Nos. 346 and 324 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML23214A1572023-08-0707 August 2023 Correction to the Renewed Facility Operating License Page 3 in Amendment No 345 IR 05000317/20230022023-08-0303 August 2023 Integrated Inspection Report 05000317/2023002 ML23188A0512023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 336 and 314 ML23186A0372023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 340 and 318 IR 05000317/20233012023-07-12012 July 2023 Initial Operator Licensing Examination Report 05000317/2023301 and 05000318/2023301 IR 05000317/20230122023-07-10010 July 2023 Commercial Grade Dedication Report 05000317/2023012 and 05000318/2023012 ML23180A2362023-06-29029 June 2023 Correction of Errors on Technical Specification Pages RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators ML23156A6752023-06-20020 June 2023 Request for Withholding Information from Public Disclosure for Proposed Alternative to the Requirements for Repair/Replacement of Saltwater System Buried Piping 2024-02-01
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 September 1, 2009 Mr. James A. Spina, Vice President Calvert Cliffs Nuclear Power Plant, Inc.
Constellation Generation Group, LLC 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - CALVERT CLIFFS NUCLEAR POWER PLANT
Dear Mr. Spina:
On August 12, 2009, the NRC staff completed its performance review of Calvert Cliffs Nuclear Power Plant (CCNPP). Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from July 1, 2008, through June 30, 2009.
The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Information" will include the security cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter at Calvert Cliffs Units 1 and 2 was within the Regulatory Response column of the NRCs Action Matrix, based on one finding having low to moderate safety significance (White). This finding involved CCNPPs emergency action level tables fission product barrier matrix being incorrect resulting in a degraded risk significant planning standard function. In August 2009, we were notified by your staff that you will be ready for the NRC to conduct a supplemental inspection after November 2, 2009, to review the actions taken to address the White finding.
Based on our current assessment of performance for Calvert Cliffs Units 1 and 2, we plan to conduct, in addition to the reactor oversight process (ROP) baseline inspections at your facility, a supplemental inspection using Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area, and will inform you of the inspection dates once it is scheduled.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2010. In addition to the 95001 supplemental inspection and the baseline inspections, we plan on conducting an independent spent fuel storage installation
J. Spina 2 (ISFSI) inspection. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
As you may know, the NRC is currently evaluating the scope and frequency of all the baseline inspection procedures as part of our biennial review of the ROP. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Glenn Dentel at (610) 337-5233 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
James W. Clifford, Acting Director Division of Reactor Projects Docket Nos. 50-317, 50-318 License Nos. DRP-53, DRP-69
Enclosure:
Calvert Cliffs Nuclear Power Plant Inspection/ Activity Plan cc w/ encl.:
M. Wallace, Vice-Chairman, Constellation Energy H. Barron, President, CEO, & Chief Nuclear Officer, Constellation Energy Nuclear Group, LLC W. Parran, President, Calvert County Board of Commissioners C. Fleming, Esquire, Sr. Counsel - Nuclear Generation Group, LLC J. Gaines, Director, Licensing, Calvert Cliffs Nuclear Power Plant S. Gray, Program Manager, Power Plant Assessment Program, Maryland Department of Natural Resources K. Burger, Esquire, Maryland People's Counsel R. Hickok, NRC Technical Training Center L. Larragoite, Manager, Nuclear Safety and Security, Calvert Cliffs Nuclear Power Plant G. Detter, Manager, Nuclear Safety and Security, Constellation Energy M. Griffen, Maryland Department of the Environment Chesapeake Safe Energy Coalition S. Pattison, SLO (2)
J. Spina 2 (ISFSI) inspection. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
As you may know, the NRC is currently evaluating the scope and frequency of all the baseline inspection procedures as part of our biennial review of the ROP. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Glenn Dentel at (610) 337-5233 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
James W. Clifford, Acting Director Division of Reactor Projects Docket Nos. 50-317, 50-318 License Nos. DRP-53, DRP-69 Distribution:
S. Collins, RA D. Screnci, ORA J. Hawkins, DRP M. Dapas, DRA N. Sheehan, ORA S. Kennedy, DRP, SRI D. Lew, DRP R. Barkley, ORA M. Davis, DRP, RI J. Clifford, DRP L. Trocine, RI OEDO C. Newgent, DRP, OA D. Roberts, DRS R. Nelson, NRR D. Bearde, DRP P. Wilson, DRS D V. Pickett, PM, NRR Region I Docket Room DRS Branch Chiefs A. Muniz, PM, NRR ROPreports Resource L. Scholl, DRS G. Dentel, DRP RidsNrrDirsIpab@nrc.gov D. Silk, DRS N. Perry, DRP SUNSI Review Complete: nsp* (Reviewer=s Initials)
DOCUMENT NAME: S:\ROP-10 Mid-Cycle Review\Branch 1\CC MidCycle Ltr 09.doc ML092440277 After declaring this document AAn Official Agency Record@ it will/will not be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP RI/DRP NAME NPerry/nsp* GDentel/gtd* JClifford/jwc DATE 08/21/09 08/24/09 09/01/09
- See prior concurrence OFFICIAL RECORD COPY
J. Spina 2 Page 1 of 2 Calvert Cliffs 09/01/2009 10:39:57 Inspection / Activity Plan Report 22 07/01/2009 - 12/31/2010 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 7111121 - CDBI 6 1, 2 08/03/2009 08/07/2009 IP 7111121 Component Design Bases Inspection 1, 2 08/17/2009 08/21/2009 IP 7111121 Component Design Bases Inspection 1, 2 08/24/2009 08/28/2009 IP 7111121 Component Design Bases Inspection 7112203 - PUB RAD SAFETY - REMP 1 1, 2 08/03/2009 08/07/2009 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 1, 2 08/03/2009 08/07/2009 IP 71151-PR01 RETS/ODCM Radiological Effluent 7111111B - BIENNIAL REQUAL INSP WITH P/F RESULTS 3 1, 2 11/16/2009 11/20/2009 IP 7111111B Licensed Operator Requalification Program EP EXER - EP EXERCISE INSPECTION 3 1, 2 10/18/2009 10/24/2009 IP 7111401 Exercise Evaluation 1, 2 10/18/2009 10/24/2009 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 10/18/2009 10/24/2009 IP 71151-EP01 Drill/Exercise Performance 1, 2 10/18/2009 10/24/2009 IP 71151-EP02 ERO Drill Participation 1, 2 10/18/2009 10/24/2009 IP 71151-EP03 Alert & Notification System 71152B - PI&R BIENNIAL TEAM 4 1, 2 11/02/2009 11/06/2009 IP 71152B Identification and Resolution of Problems 1, 2 11/16/2009 11/20/2009 IP 71152B Identification and Resolution of Problems 71121 - OCC RAD SAFETY 1 1, 2 12/07/2009 12/11/2009 IP 7112101 Access Control to Radiologically Significant Areas 1, 2 12/07/2009 12/11/2009 IP 7112102 ALARA Planning and Controls 1, 2 12/07/2009 12/11/2009 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 1, 2 12/07/2009 12/11/2009 IP 71151-OR01 Occupational Exposure Control Effectiveness TI-177 - MANAGING GAS ACCUMULATION IN ECCS 5 1, 2 01/11/2010 01/15/2010 IP 2515/177 Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 71121 - OCC RADIATION SAFETY 1 1, 2 01/25/2010 01/29/2010 IP 7112101 Access Control to Radiologically Significant Areas 1, 2 01/25/2010 01/29/2010 IP 7112102-7112102R ALARA - Required 71121 - OCC RADIATION SAFETY 1 1, 2 03/01/2010 03/05/2010 IP 7112101 Access Control to Radiologically Significant Areas 1, 2 03/01/2010 03/05/2010 IP 7112102 ALARA Planning and Controls 1, 2 03/01/2010 03/05/2010 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 7111108P - UNIT 1 INSERVICE INSPECTION 1 1 03/01/2010 03/12/2010 IP 7111108P Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Calvert Cliffs 09/01/2009 10:39:57 Inspection / Activity Plan Report 22 07/01/2009 - 12/31/2010 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site TI-172 - U1 TI 2515/172 DISSIMILAR METAL WELDS 1 1 03/01/2010 03/12/2010 IP 2515/172 Reactor Coolant System Dissimiliar Metal Butt Welds 8/2EXAM - OPERATOR LICENSING INITIAL EXAMS 4 1 06/28/2010 07/02/2010 U01770 FY10 - CALVERT CLIFFS UNIT 1&2 INITIAL OPERATOR LICENSING EXAM 1 08/02/2010 08/13/2010 U01770 FY10 - CALVERT CLIFFS UNIT 1&2 INITIAL OPERATOR LICENSING EXAM 71121.03 - RAD MONITORING INSTRUMENTS 1 1, 2 05/03/2010 05/07/2010 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 71122.01 - RAD GAS & LIQ EFFLUENTS SYSTEM 1 1, 2 06/07/2010 06/11/2010 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 2515/173 - INDUSTRY GROUND WATER INITIATIVE 1 1, 2 06/07/2010 06/11/2010 IP 2515/173 Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative ISFSI - ISFSI LOADING CAMPAIGN 1 1, 2 07/12/2010 07/16/2010 IP 60855 Operation Of An ISFSI 1, 2 07/12/2010 07/16/2010 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants EP PROGR - EP PROGRAM INSPECTION 1 1, 2 08/02/2010 08/06/2010 IP 7111402 Alert and Notification System Testing 1, 2 08/02/2010 08/06/2010 IP 7111403 Emergency Response Organization Augmentation Testing 1, 2 08/02/2010 08/06/2010 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 08/02/2010 08/06/2010 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 08/02/2010 08/06/2010 IP 71151 Performance Indicator Verification TRI FIRE - TRIENNIAL FIRE PROTECTION INSPECTION 3 1, 2 11/15/2010 11/19/2010 IP 7111105T Fire Protection [Triennial]
1, 2 11/29/2010 12/03/2010 IP 7111105T Fire Protection [Triennial]
71121 - OCC RAD SAFETY - ACCESS/ALARA & ISFSI 1 1, 2 12/06/2010 12/10/2010 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 1, 2 12/06/2010 12/10/2010 IP 7112101 Access Control to Radiologically Significant Areas 1, 2 12/06/2010 12/10/2010 IP 7112102 ALARA Planning and Controls 1, 2 12/06/2010 12/10/2010 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.